Computer-Aided Facilities Management - A Logical Trend
|
|
- Ross May
- 8 years ago
- Views:
Transcription
1 Computer-Aided Facilities Management - A Logical Trend Two major organisational changes are part of the modern pharmaceutical industry scene. Firstly, mergers as companies seek to consolidate resources to get best returns on their R&D budgets. Secondly, a re-focusing on what is considered to be "core business". This may be Marketing, Research, Development, Manufacturing or any combination. For sure companies no longer wish to do everything in-house and contract manufacture, sub-contracting of QC analytical services, development services, and so on, is becoming the norm. If we look at the "Value Chain", the core competence of a pharmaceutical company will lie along the path: Research Develop Manufacture Distribute Core competence can be broadly described as: Research: Development: Identify potential drugs and therapeutic opportunities. Ensure patient safety. Develop reliable processes Establish QA standards Ensure process safety Manufacturing: Cost-effective in accordance with GMPs and Regulatory requirements Distribution: Effective, controlled delivery to the customer. Pharmaceutical companies require skill-sets to work within and across the functional boundaries. Maximum benefits to the business are achieved when new products reach the market place in the shortest time possible. Even a few weeks' delay can mean the loss of millions of pounds in revenue. Why then, with so much at stake, are those managers who are so crucial to the value chain so often distracted by a myriad of important but relatively peripheral issues which are part and parcel of the infrastructure of any large enterprise? In the engineering field we have already seen the reduction in in-house resources as pharmaceutical companies acknowledge that project and construction management is definitely not a core competence requirement. More and more engineering houses
2 are negotiating "term-contracts" with their customers for the provision of small projects and maintenance services. Manufacturing sites routinely outsource services such as catering, security and laundry. Many items of process and utility equipment are now serviced by the original or other suitably qualified vendor. However, the consequence of this evolutionary rather than structural change is that outsourcing of services to manufacturing is often piecemeal and uncoordinated. Responsibilities can be split across the site management team. Scope of work is often based on vendor recommendations rather than client needs. Commercial terms are often general rather than focused on a quality of services and not always monitored to demonstrate true value for money. Professional Facilities Management service providers take full responsibility for all non-core activities, naturally allowing clients to focus their resources where most value can be added. The essential objective of Facilities Management is to systematically allocate the infrastructural activities to those for whom it is a speciality or their "core competence". (These include site security, maintenance services, laundry, catering, gardening, cleaning and a host of others.) In doing so, the pharmaceutical company concentrates its resources where it gives the greatest benefit to the business. Figure 1 A + B demand mainly for core business C demand for support services C activities are the A business of the service provider "Services" are core business of the service provider Service Provider CAFM provider Efficient management and document control for Technical Services! Cost reduction! Performance improvement! Flexibility Client Concentration on core business of the company
3 As with anything new, there is a range of interpretations around the basic Facilities Management concept. Early versions of Facilities Management were basically office services: reception, cleaning and elementary maintenance. Later developments were driven by equipment and control system vendors who added routine servicing to their scope of supply. The added dimension of modern Facilities Management is to have systems and procedures which not only ensure that the service is provided but also that the quality and cost of that service is regularly monitored and reviewed. In the pharmaceutical manufacturing industry, there is the added dimension that work must be implemented and administered in a GMP-controlled manner. The broad scope for Facilities Management can be defined as: # The development and continuous execution of the PPM (Planned Preventative maintenance) regimes for all M&E elements, production equipment, building fabric, external hard-standing and roads. # Developing jointly with the Client the contractual strategy with the identified maintenance suppliers. # Maintaining all records in accordance with the pharmaceutical industry standards and the expectations of the MCA and FDA. # Monitoring and maintaining essential spares and developing strategies for procurement. # Formulating strategies for remedial action following a breakdown in any service. The key to successful Facilities Management lies in robust management systems to control these activities. In order to cope with the quantities of information, an essential pre-requisite is tried and tested CAFM (Computer-Aided Facilities Management) systems. CAFM systems enable the Facilities Manager to develop and issue work programmes, monitor all activities and prepare meaningful management reports.
4 The overview of a CAFM system is given below in Figure 2. FM Activities Maintenance and Service expenditure Material and goods expenditure Service contracts Services with third parties Projects, remodelling reinvestments Energy and utilities Statistical analysis Graphical representation Special occurrences with comments Creation of necessary reports! Monthly! Quarterly! Yearly From the analysis determine required actions and improvements Report for the Client Structured to suit Client requirements Report for the Facilities Manager For controlling and supervising and identifying required actions
5 For any Facilities Management system to be effective there needs to be two phases of activity: Step 1. Setting up the Facilities Management systems Step 2. Operational Phase. The Set-Up phase requires a careful analysis of all the relevant activities. For each service area the Set-Up team will need to identify the tasks to be undertaken, the specification of each task and the performance expectation of the relevant system. For example, a service contract may be required for a number of Chiller Units. During the Set-Up phase all relevant documentation for the units will be assembled and reviewed. If not already detailed, the PPM requirements will be identified including tasks, materials SOPs and frequencies. (Initially, vendor data may be used but over time the Facilities Management provider will constantly challenge and review these requirements). A performance measure will then be allocated such as the percentage operational availability of the equipment. It has to be said that 100% targets across the board will be both unrealistic and prohibitively expensive. Again, over time, results will be monitored and evaluated so that the actual service level can be optimised for cost-effective performance. This detailed analysis enables a realistic performance-based contract for the Operational Phase to be established between the client and the service provider. Typically, such an evaluation will take a team of Facilities Management specialists about 6 to 8 weeks to complete. At the end of the evaluation, Facilities Management contracts can be drawn up to include activities such as: Ensuring adequate supply of quality-compliant utilities. Ensuring secure operation of HVAC systems. Ensuring secure energy supply. Ability to respond rapidly to a problem (recognising that a substantial portion of the workload is reactive). Promptly responding to and repairing minor discrepancies in the facility. Developing and executing a system of regularly scheduled maintenance actions to prevent premature failure of the facility and its systems and components. Completing major repairs based on lowest life-cycle cost. Operating the facility utilities in the most economical manner while providing necessary reliability. Providing for easy and complete reporting and identification of necessary repair and maintenance work. Performing accurate cost estimating to ensure lowest cost solutions to maintenance problems. Accurately tracking the costs of all maintenance work. Scheduling all planned work in advance, and allocating and anticipating staff requirements to meet planned and, as far as possible, unplanned events. Monitoring the progress of all maintenance work. Maintaining complete historical data concerning the facility in general, and equipment and components in particular. Continually seeking workable engineering solutions to maintenance problems. Identifying design and complete improvement projects to reduce and minimise total operating and maintenance costs. Maintaining a proper level of material and spare parts to support timely repairs.
6 Although many Facilities Management activities do not have a regulatory dimension it is of paramount importance that those that do are managed in a GMP-compliant manner. Pharmaceutical clients are understandably concerned and cautious about any activity carried out by third parties on GMP-sensitive systems. This includes Purified Water and WFI Systems, Clean Steam, HVAC and Sterile Compressed Air. It can also include standard process equipment such as Washers and Autoclaves. Given the principle of the client concentrating on core activities, it is less usual for specialist process equipment to be included in the Facilities Management contract. In the case of GMP-significant equipment, the performance criteria are necessarily more stringent and will have been established for the Performance Qualification of each system. All work carried out on such systems will be in accordance with clientapproved SOPs and any system modifications will be subject to rigid Change Control procedures. The CAFM system will need to embrace requirements such as: Installation Qualification Operational Qualification Performance Qualification Standard Operating Procedures Change Control Training Records Calibration Good Automated Manufacturing Practice Equipment History Files Equipment Log Books
7 The requirement for integrating these activities within a CAFM system is illustrated in Figure 3. Integrated Documentation Systems system logs log books certificates maintenance records activity records reports daily reports regulatory aspects correspondence maintenance instructions warranty management equipment deficiency list tracking of damages order handling requests for material delivery notes Change control documentation Projects Modifications Improvements In consideration for: FM Internal Reporting: Documentation of the facilities activities Comprehensive documentation processes In consideration for: Systems documentation Regulatory compliance Documentation Responsibilities Structure of personnel Maintenance plan Supplementary services Inventory list Regulatory authority: Relevant to inspections, Manufacturing approvals Product release Continuous documented proof of Personnel activities Equipment status Fault Analysis, etc
8 Ultimately, the major benefit stems from the business opportunity given to clients to focus their staff where they add most value. However, a commercial justification can be made for Facilities Management in isolation. By monitoring key operational parameters such as equipment availability and performance criteria, the quality of maintenance service can be judged. This can lead to review of activities, procedures, maintenance frequency, suppliers, etc. Ultimately, this will result in a reduction in the overall cost for a table or improved level of service. Figure 4. Reduction in maintenance hours through improvements to maintenance process 99.7% 99.7% 99.8% 99.8% 99.8% 99.8% 99.8% Preventative maintenance Number of Faults Availability In summary, the benefits of CAFM are: # Efficient maintenance service. # Optimisation and control of overall maintenance costs. # Meaningful reporting of all Facility Management activities. # Control of small works projects. # All activities in a GMP-controlled environment. # Proper application of Change Control procedures. # Permitting company management to concentrate on core business activities
1 The quality management system (QMS) is the corner stone of compliance to GMP. The QMS is made up of several documents, that when followed ensures the GMP compliance of the process, facility and company.
More informationA Guide to Efficient MRO Procurement & Management White Paper
A Guide to Efficient MRO Procurement & Management White Paper Brammer 117554 WhitePaper_V5_SP.indd 1 19/04/2010 15:19 Executive summary The purchasing of spares for the daily maintenance, repair and overhaul
More informationPlanon Maintenance Management. For maintaining the value of real estate and corporate assets
Planon Maintenance Management For maintaining the value of real estate and corporate assets Planon s Maintenance Management solution includes: Building Asset Management Reactive Maintenance Planned Preventive
More informationASSESSMENT OF QUALITY RISK MANAGEMENT IMPLEMENTATION
PHARMACEUTICAL INSPECTION CONVENTION PHARMACEUTICAL INSPECTION CO-OPERATION SCHEME PI 038-1 26 March 2012 AIDE-MEMOIRE ASSESSMENT OF QUALITY RISK MANAGEMENT IMPLEMENTATION PIC/S March 2012 Reproduction
More informationOptimizing Quality Control / Quality Assurance Agents of a Global Sourcing / Procurement Strategy
Optimizing Quality Control / Quality Assurance Agents of a Global Sourcing / Procurement Strategy Global Pharma Sourcing Conference December 6-7, 2011 Philadelphia, USA Nigel J. Smart, Ph.D. Smart Consulting
More informationConducting a Gap Analysis on your Change Control System. Presented By Miguel Montalvo, President, Expert Validation Consulting, Inc.
Conducting a Gap Analysis on your Change Control System Presented By Miguel Montalvo, President, Expert Validation Consulting, Inc. Standards, Regulations, Guidelines related to Change Control Management
More informationAn Assessment of The South African Facilities Management Industry. March 2012 Final Deliverable
An Assessment of The South African Facilities Management Industry March 2012 Final Deliverable 1 Project Background, Methodology and Definitions Project Background The South African Facilities Management
More informationRelease: 1. AURT575393A Analyse and evaluate electrical and electronic faults in transmission/driveline systems
Release: 1 AURT575393A Analyse and evaluate electrical and electronic faults in transmission/driveline systems AURT575393A Analyse and evaluate electrical and electronic faults in transmission/driveline
More informationMaking Business Mobile. Enterprise Mobile Apps. Facilities Management Framework. www.commontime.com
Enterprise Mobile Apps Facilities Management Framework www.commontime.com Facilities Management At The Heart Of An Efficient Organisation Companies of all sizes are recognising the financial and operational
More informationJOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning
JOB DESCRIPTION Position Title and Number: Senior Procurement Officer (100618) Grade: Department: Section: Responsible to: Responsible for: SO2 People Directorate Health, Wellbeing & Commissioning Team
More informationProject Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
More informationCommercial Manufacturing - Qualification & Validation-related GMP Deficiencies and Other Lifecycle Considerations
Commercial Manufacturing - Qualification & Validation-related GMP Deficiencies and Other Lifecycle Considerations Kevin O Donnell PhD Market Compliance Manager, IMB PDA / FDA Conference Pharmaceutical
More information2012 Americas School of Mines
www.pwc.com 2012 Americas School of Mines Maximizing Asset Management From Work Plan to Financial Performance Doug Stretton, Paul Ingram May 17, 2012 Presentation Summary Maximizing mining assets is often
More informationPORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
More informationGuidance for Industry: Starting Material Supplier Management
Guidance for Industry: Starting Material Supplier Management Version 1.0 Drug Office Department of Health. Contents 1. Introduction... 3 2. Purpose of this document... 3 3. Scope... 3 4. Selecting and
More informationArrangements for the Maintenance and Testing of Laboratory Autoclaves
Arrangements for the Maintenance and Testing of Laboratory Autoclaves Royal Free NHS Trust & Royal Free and UC Medical School (Hampstead Campus) This document has been produced by the Safety Office, Royal
More informationPHARMACEUTICAL QUALITY SYSTEM Q10
INTERNATIONAL CONFERENCE ON HARMONISATION OF TECHNICAL REQUIREMENTS FOR REGISTRATION OF PHARMACEUTICALS FOR HUMAN USE ICH HARMONISED TRIPARTITE GUIDELINE PHARMACEUTICAL QUALITY SYSTEM Q10 Current Step
More informationRail Asset Management. Rail
Rail Asset Management Rail Rail Asset Management Calibre Global understands the key drivers facing rail owners and operators are both financial and operational performance. The end objective for any company
More informationOECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT
GENERAL DISTRIBUTION OCDE/GD(95)115 OECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT THE APPLICATION OF THE PRINCIPLES OF GLP TO COMPUTERISED
More informationJOB DESCRIPTION. Manager Mechanical (Fleet, Workshop & Recycling)
JOB DESCRIPTION JOB TITLE: REPORTS TO: Manager Mechanical (Fleet, Workshop & Recycling) Director of Municipal Services PURPOSE OF THE JOB Organise, control, manage and develop staff and services of the
More informationGuidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables
(1987) Guidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables 1. General 1.1 Introduction 1.1.1 The present guidelines are to serve as a supplement to the IACS
More informationHow CMOs are Turning Their Training Programs into Market Differentiators
How CMOs are Turning Their Training Programs into Market Differentiators How CMOs are Turning Their Training Programs into Market Differentiators A Contract Manufacturing Organization (CMO) has as much
More informationCustomer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy
Section 8 Output monitoring Inputs Customer requirements Safety standards Outputs and funding SRA and Government Policy Network stewardship strategy Asset and operational policies Maintenance & renewal
More informationLHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home
LHT S ASSET MANAGEMENT STRATEGY 2015-20 It s My Home 0 ASSET MANAGEMENT STRATEGY 2015-20 It s My Home Contents Page No 1. WHAT DOES OUR ASSET MANAGEMENT STRATEGY AIM TO DO? 2 2. WHY IS ASSET MANAGEMENT
More informationWORLD CLASS CUSTOMER SERVICE
SMART SERVICES WORLD CLASS CUSTOMER SERVICE Whether you run one trailer, or operate a large fleet located across multiple European countries, the ability to plan and control your operating costs is essential
More informationPrinciples. of Pharmaceutical Facility Design. Full Time Part Time Online. www.dpseng.com.sg
Principles of Pharmaceutical Facility Design Full Time Part Time Online www.dpseng.com.sg Contents 1. Welcome 2. Programme Overview 3. Programme Content www.dpseng.com.sg 2 Welcome Transition into a new
More informationProject success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
More informationProgramme Delivery & Performance Management
Chapter 13 Programme Delivery & Performance Management Chapter Overview This chapter explains how the County Council will ensure that its transport investment programme is delivered in a cost-effective
More informationPublic Cord Blood Bank
The The Public Cord Blood Bank Page 1 of 21 TABLE OF CONTENTS INTRODUCTION... 3 WHAT ARE GOOD MANUFACTURING PRACTICES?... 5 1 TOTAL QUALITY... 7 2 PREMISES... 8 3 EQUIPMENT AND MATERIAL... 9 4 PERSONNEL...
More information12 Tips for Successful Medical Equipment Outsourcing
REPRINTED FROM MD&DI APRIL 2009 12 Tips for Successful Medical Equipment Outsourcing Successful outsourcing is contingent upon knowing your company s needs and carefully selecting a supplier. Milton Frank
More informationTelecom Expense Management
Telecom Expense Professional Cost Group Ltd. Control your costs Manage your assets Transform your business Visit us online: www.pcmg.co.uk/tem Your Challenges. For most companies, fixed and mobile communications
More informationCONFORMED COPY. Method Statement Helpdesk Services. Revision History. Revision Date Reviewer Status. 23 March 2007 Project Co Final Version
CONFORMED COPY Method Statement Revision History Revision Date Reviewer Status 23 March 2007 Project Co Final Version Table of Contents 1 Objectives... 3 2 Management Supervision and Organisation Structure...
More informationProcurement driving better value for money. Guide 7 to Sustainable Procurement. Manage the contract and disposal route
Procurement driving better value for money Guide 7 to Sustainable Procurement Manage the contract and disposal route A guide for agencies July 2010 This guide is part of a series of documents focussed
More informationA Perspective on Draft Embedded Digital RIS. Ron Jarrett Tennessee Valley Authority Embedded Digital Devices Workshop October 9, 2014 NRC
A Perspective on Draft Embedded Digital RIS Ron Jarrett Tennessee Valley Authority Embedded Digital Devices Workshop October 9, 2014 NRC What does the RIS mean to a Utility? This is an important RIS from
More informationAchieving the Next Level of Component & Supplier Management: Integral Design and Procurement
Achieving the Next Level of Component & Supplier Management: Integral Design and Procurement Why CSM is Vital to Success Today Global outsourcing, competition, price erosion, environmental regulations,
More informationQuality Risk Management The Pharmaceutical Experience Ann O Mahony Quality Assurance Specialist Pfizer Biotech Grange Castle
Quality Risk Management 11 November 2011 Galway, Ireland Quality Risk Management The Pharmaceutical Experience Ann O Mahony Quality Assurance Specialist Pfizer Biotech Grange Castle Overview Regulatory
More informationPredictive Maintenance for Government
Predictive Maintenance for How to prevent asset failure, control maintenance costs and anticipate budget needs Highlights Predictive maintenance helps government agencies automatically detect equipment
More informationProcurement & Supply Chain Management
New Skills. New Thinking Procurement & Supply Chain Management Supply Chain Effectiveness Audit - Implementing lean processes in your supply chain 20 September 2012 Auckland 24 September 2012 Wellington
More informationOMCL Network of the Council of Europe QUALITY ASSURANCE DOCUMENT
OMCL Network of the Council of Europe QUALITY ASSURANCE DOCUMENT PA/PH/OMCL (08) 69 3R Full document title and reference Document type VALIDATION OF COMPUTERISED SYSTEMS Legislative basis - CORE DOCUMENT
More informationSpecialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services
Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4
More informationDuke University Health System
Duke University Health System Job Description Job Title: Biomedical Equipment Technician Job Code: FLSA: Pay Band: 4D Date: Job Level: Level 1 General Description of the Job Class: Perform a variety of
More informationSpecialist Cloud Services Lot 4 Cloud EDRM Consultancy Services
Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4 3.2 Service description...
More informationPROPOSED UPDATED TEXT FOR WHO GOOD MANUFACTURING PRACTICES FOR PHARMACEUTICAL PRODUCTS: MAIN PRINCIPLES (JANUARY 2013)
January 2013 RESTRICTED PROPOSED UPDATED TEXT FOR WHO GOOD MANUFACTURING PRACTICES FOR PHARMACEUTICAL PRODUCTS: MAIN PRINCIPLES (JANUARY 2013) DRAFT FOR COMMENTS Please address any comments on this proposal
More informationOECD Series on Principles of GLP and Compliance Monitoring Number 8 (Revised)
Unclassified ENV/JM/MONO(99)24 ENV/JM/MONO(99)24 Or. Eng. Unclassified Organisation de Coopération et de Développement Economiques OLIS : 14-Sep-1999 Organisation for Economic Co-operation and Development
More information«COSWIN 7i helps you increase your return on assets while boosting their productivity.»
COSWIN 7i is the new generation asset and facilities management software developed by SIVECO GROUP. COSWIN 7i helps companies to increase their profitability - by improving the management of corporate
More informationLABORATORY OUTSOURCING
June 2009 LABORATORY OUTSOURCING Intertek s EVP of Analytical Services, Dr. Andrew Swift, discusses laboratory outsourcing and explains how dedicated analytical service providers are stepping up to support
More informationQuality Assurance Policy And Project Organisation Plan
Quality Assurance Policy Quality Assurance Policy And Project Organisation Plan This document defines the general policy for Quality Assurance to be used for the whole project. It gives the project organisation,
More informationMedical Equipment Management Policy. Procedure No. 114
Medical Equipment Management Policy Page 1 of 18 Medical Equipment Management Policy Procedure No. 114 Print Name Title Date Prepared by Clinical Engineering 1 st June 08 Reviewed by Bernard Ryan Clinical
More informationRegulatory Asset Management: Harmonizing Calibration, Maintenance & Validation Systems
Regulatory Asset Management: Harmonizing Calibration, Maintenance & Validation Systems 800.982.2388 1 Introduction Calibration, maintenance and validation activity, despite operating within the same department
More informationThe FDA recently announced a significant
This article illustrates the risk analysis guidance discussed in GAMP 4. 5 By applying GAMP s risk analysis method to three generic classes of software systems, this article acts as both an introduction
More informationM&LE17 Outsource business processes 1
M&LE17 Overview Outsource business processes What this Unit is about This Unit is about outsourcing business processes which are not part of your organisation s core competencies. It covers the outsourcing
More informationAIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
More informationPlease Note: Temporary Graduate 485 skills assessments applicants should only apply for ANZSCO codes listed in the Skilled Occupation List above.
ANZSCO Descriptions This ANZSCO description document has been created to assist applicants in nominating an occupation for an ICT skill assessment application. The document lists all the ANZSCO codes that
More informationThe Asset Information Model using BIM
AIM - PAS 1192:3:2014 The Asset Information Model using BIM Figure 1 PAS1192-2 and PAS1192-3 by: Rob Manning BIS BIM Task Group Introduction In this article we look at how the approach outlined in document
More informationPerformance Improvement Consulting. What would you like to change? Outsourcing
Performance Improvement Consulting What would you like to change? Outsourcing What makes us different? By making change personal to those it affects, starting with asking them What would you like to change?,
More informationThe Prophotonix (UK) Ltd Quality manual
The Prophotonix (UK) Ltd Quality manual Date: March 2014 Revision: D Sparrow lane, Hatfield Broad Oak, Herts, UK, CM22 7BA Tel: +44 (0)1279 717170 Fax: +44 (0)1279 717171 e-mail: info@prophotonix.com Page
More informationINTERNAL AUDIT DIVISION AUDIT REPORT 2013/073
INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073 Audit of maintenance and building services provided by the Office of Central Support Services at Headquarters Overall results relating to the Office of Central
More informationOptimization of Clinical Engineering in Private Healthcare
Optimization of Clinical Engineering in Private Healthcare Speaker: James Herbert Organisation: Medi-Clinic Southern Africa Job Title: Technical Specialist - Clinical Engineering About the Speaker: James
More information10.0 ASSET MANAGEMENT PRACTICES
10.0 ASSET MANAGEMENT PRACTICES 10.1 Current Asset Management Practices This section outlines the decision making tools Taupō District Council (TDC) currently uses to determine long term maintenance, renewal
More informationRelease: 1. BSBPMG510A Manage projects
Release: 1 BSBPMG510A Manage projects BSBPMG510A Manage projects Modification History Not applicable. Unit Descriptor Unit descriptor This unit describes the performance outcomes, skills and knowledge
More informationGMP Pharma BV. Netherlands
GMP Pharma BV Netherlands Connecting the European & Indian Pharmaceutical, Biotechnology and Biopharmaceutical Industry for parallel growth and solicitation. About Us: GMP Pharma BV is a multisource organization
More informationGUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement
More informationInformation Security Policies. Version 6.1
Information Security Policies Version 6.1 Information Security Policies Contents: 1. Information Security page 3 2. Business Continuity page 5 3. Compliance page 6 4. Outsourcing and Third Party Access
More informationSolution Architecture Overview. Submission Management. 2015 The Value Enablement Group, LLC. All rights reserved.
Solution Architecture Overview Submission Management 1 Submission Management Overview Sources of Record MDM Manually Captured Lifecycle Events PLM Repository Data Domain Objects supporting Submission Process
More informationInside Track Research Note. In association with. Enterprise Storage Architectures. Is it only about scale up or scale out?
Research Note In association with Enterprise Storage Architectures Is it only about scale up or scale out? August 2015 About this The insights presented in this document are derived from independent research
More informationHow To Host An Incompany Project For An Msc Student At Cranfield
The Cranfield Project an opportunity for your business Applying learning to real business issues At Cranfield School of Management we believe that Logistics and Supply Chain excellence is both a desirable
More informationUNICEF s Quality Assurance System for Procurement of Micronutrient Powders (MNP)
UNICEF s Quality Assurance System for Procurement of Micronutrient Powders (MNP) Nutrition Supplier Meeting, June 30, 2015 Dimitris Catsoulacos Quality Assurance Specialist PRESENTATION OVERVIEW Quality
More informationOutsourcing Risk Guidance Note for Banks
Outsourcing Risk Guidance Note for Banks Part 1: Definitions Guideline 1 For the purposes of these guidelines, the following is meant by: a) outsourcing: an authorised entity s use of a third party (the
More informationISSUES AND CHALLENGES OF FACILITIES MANAGEMENT (FM) IN BUSINESS ENVIRONMENT FOR HEALTH CARE SECTORS
ISSUES AND CHALLENGES OF FACILITIES MANAGEMENT (FM) IN BUSINESS ENVIRONMENT FOR HEALTH CARE SECTORS Zuhairi Abd. Hamid 1, Mohd Khairolden Ghani 2, Syahrul-Nizam Kamaruzzaman 3,Kamarul Anuar Mohamad Kamar
More informationA risky business. Why you can t afford to gamble on the resilience of business-critical infrastructure
A risky business Why you can t afford to gamble on the resilience of business-critical infrastructure Banking on a computer system that never fails? Recent failures in the retail banking system show how
More informationSoftware. Strategic Maintenance Planning Ltd CMMS. www.smpltd.co.uk
Strategic Maintenance Planning Ltd CMMS www.smpltd.co.uk The Company 3 Maintenance, Implementation & Consultancy are the three core themes to our business. Our Maintenance Management HolisTech Horizon
More informationFleet Strategy 2015-2018
Fleet Strategy 2015-2018 Foreword I am pleased to introduce the Fleet Strategy for Cheshire Constabulary, with its focus very firmly upon supporting frontline operations in the most cost efficient way.
More information10.0 ASSET MANAGEMENT PRACTICES
10.0 ASSET MANAGEMENT PRACTICES 10.1 Current Asset Management Practices This section outlines the decision making tools Taupō District Council (TDC) currently uses to determine long term maintenance, renewal
More informationFleet Management Services
Fleet Management Services Welcome to Smartfleet What is Smartfleet? Overview Managed Services Powerful Modules Reporting Overview Smartfleet is a leading Australian fleet management company, helping organisations
More informationJOB DESCRIPTION. Facilities Management PARTICIPATING JOB HOLDER(S): APPROVED BY: JOB HOLDERS: HEAD OF DEPARTMENT OR DIRECTOR: Zoological Director
JOB DESCRIPTION JOB TITLE: SECTION: DIVISION: RESPONSIBLE TO: PARTICIPATING JOB HOLDER(S): Head of FM Facilities Management LONDON ZOO ZOOLOGICAL DIRECTOR VACANT APPROVED BY: JOB HOLDERS: HEAD OF DEPARTMENT
More informationVendor Relationship Management
Vendor Relationship Management Getting What You Paid For (and More) Stephen Guth VP, Vendor Management Thursday, February 26 th, 2015, 8:00 9:00 a.m. Topics Case Study Company Intro Begin with the End
More informationQuality Management Plan
6500m HOV Project Stage 1: A-4500 HOV Document Control No.: 0000000 3-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control Sheet Date Originator Description 07-28-09
More informationMapping of outsourcing requirements
Mapping of outsourcing requirements Following comments received during the first round of consultation, CEBS and the Committee of European Securities Regulators (CESR) have worked closely together to ensure
More informationA Framework for Developing and Evaluating Data Center Maintenance Programs
A Framework for Developing and Evaluating Data Center Maintenance Programs White Paper 178 Revision 0 by Bob Woolley > Executive summary Inadequate maintenance and risk mitigation processes can quickly
More informationCOMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited
PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date
More informationIsolating the real merits of fully outsourced hosting and FX connectivity services
Isolating the real merits of fully outsourced hosting and FX connectivity services Opportunities in FX trading are enormous, but the risks are also considerable. In the current low volatility environment,
More informationAsbestos Management Policy
Asbestos Management Policy Originator: Approval date: Policy and Strategy Team Sovini Board PCHA Board OVH Board/EMT 3 rd December 2012 22 nd November 2012 25 th September 2012 Review date: December 2013
More informationGuidance for Industry. Q10 Pharmaceutical Quality System
Guidance for Industry Q10 Pharmaceutical Quality System U.S. Department of Health and Human Services Food and Drug Administration Center for Drug Evaluation and Research (CDER) Center for Biologics Evaluation
More informationModule 1 Study Guide Introduction to PPO. ITIL Capability Courses - Planning, Protection and Optimization
Module 1 Study Guide Introduction to PPO ITIL Capability Courses - Planning, Protection and Optimization Introducing PPO Welcome to your Study Guide. This document is supplementary to the information available
More informationHighly challenged environment
Highly challenged environment Navigating the maze of healthcare compliance requirements in healthcare facilities The world s population is both growing and aging. Healthcare costs are escalating. Workplace
More informationGap Analysis of ISO 15189:2012 and ISO 15189:2007 in the field of Medical Testing
Gap Analysis May 2013 Issued: May 2013 Gap Analysis of and in the field of Medical Testing Copyright National Association of Testing Authorities, Australia 2013 This publication is protected by copyright
More informationSUPPORTING PATIENT CENTRIC CARE WITH INTEGRATED ASSET & SERVICE MANAGEMENT
TRUSTED ADVISORS TO HEALTHCARE AND LIFE SCIENCE EXECUTIVES SUPPORTING PATIENT CENTRIC CARE WITH EXECUTIVE SUMMARY Healthcare providers are under increased pressures to enhance patient care and improve
More informationImproving Offshore Supply Chain by Predictive Asset Management Making Smarter Business Decisions
Improving Offshore Supply Chain by Predictive Asset Management Making Smarter Business Decisions Aberdeen, 28 November 2013 Agenda: Asset Management as the front office of the offshore supply chain Impact
More informationA Guide to Reviewing Outsourced Contracts. By James Milner - Ember Public Sector Solutions
A Guide to Reviewing Outsourced Contracts By James Milner - Ember Public Sector Solutions Introduction from James Milner, Director EPSS Outsourced contracts in the public sector are now commonplace. Unfortunately
More informationJOB DESCRIPTION. Application Support Analyst
JOB DESCRIPTION JOB TITLE: Application Support SECTION: DEPARTMENT: DIVISION: RESPONSIBLE TO: ICT ICT Finance Head of ICT PARTICIPATING JOB HOLDER(S): APPROVED BY: JOB HOLDER(S): Nick Napier tbc HEAD OF
More informationIMP management at site. Dmitry Semenyuta
IMP management at site Dmitry Semenyuta TOP 5 FDA inspections finding 1999-2009 Center of Drug Evaluation and Research (CDER) Failure to follow the protocol Failure to keep adequate and accurate records
More informationUtilizing Real-Time Information in Enterprise Asset Management Systems
Utilizing Real-Time Information in Enterprise Asset Management Systems Jason Barath Matrikon Inc. December 2006 Utilizing Real-Time Information in Enterprise Asset Management Systems Today, industries
More informationThe Quality Opportunities & Challenges in the Implementation of Managed Service Contracts
The Quality Opportunities & Challenges in the Implementation of Managed Service Contracts Ian Rothnie BMS4/Laboratory Manager Clinical Biochemistry NHS Grampian 1. NHS Finances 2. Budgets 3. Managed Service
More informationClient Study Portfolio
Client Study Portfolio Client Study 1: UK District Council A re-architecture of the client s RAC Environment and full 24/7 support of the client s database systems thereafter has eliminated the risk of
More informationSUPPORTING THE RAIL INDUSTRY UNIQUE SOLUTIONS FOR UNIQUE SITUATIONS WWW.SGS.COM/RAIL
SUPPORTING THE RAIL INDUSTRY UNIQUE SOLUTIONS FOR UNIQUE SITUATIONS WWW.SGS.COM/RAIL OUR UNIQUE SOLUTION TO YOUR UNIQUE SITUATION SGS is recognised as the global benchmark for quality and integrity. We
More informationStreamline your Purchase to Pay (P2P) functions within your business
Streamline your Purchase to Pay (P2P) functions within your business Have you thought about the amount of effort it takes your organisations to procure goods and services? The number of steps and processes
More informationContact Centre. National Occupational Standards May 2011
Contact Centre National Occupational Standards May 2011 Skills CFA 6 Graphite Square, Vauxhall Walk, London SE11 5EE T: 0207 0919620 F: 0207 0917340 Info@skillscfa.org www.skillscfa.org 2012 Skills CFA
More informationGuidance for the Quality Assurance of Fire Protection Systems
Guidance for the Quality Assurance of Fire Protection Systems Prepared for: Office of Energy Research Office of Environment, Safety and Health Technical Support Prepared by: Roy F. Weston, Inc. October
More informationQuality Policy. JRI Orthopaedics Limited
JRI Orthopaedics Limited October 2014 Contents Clause 1. Policy statement 1 2. Who is covered by the policy? 2 3. Organisation and Responsibilities 2 4. Training and Communication 4 5. Suppliers 4 6. Monitoring
More information