1 2231 Alternative Quality Organizations in Highway Design and Construction Elizabeth KRAFT 1 and Keith MOLENAAR 2 1 Graduate Assistant, Civil, Architectural and Environmental Engineering, University of Colorado, Boulder, CO elizabeth.kraft@colorado.edu 2 Professor, Civil, Environmental and Architectural Engineering, Univ. of Colorado, Boulder, CO Molenaar@colorado.edu ABSTRACT A common dissent to alternative project delivery has been that the quality will not be equal to that of the traditional design-bid-build delivery method. One of the reasons for this concern is that the quality roles and responsibilities change when implementing an alternative delivery method due to early involvement of the contractor, a single contract for design and construction, and/or private funding being utilized for the project. While the fundamental quality activities remain the same, the overall project organization defining who is responsible for the activities and roles changes. Due to a lack of guidance and research the project quality organization shifts in an ad-hoc manner due to the time constraints of the project. This research determines the five fundamental quality management organizations based on the agency s quality responsibilities within the project quality management organization. INTRODUCTION A quality management organization (QMO) assigns the specific roles and responsibilities associated with the quality management of a project in both design and construction to a particular project participant (agency, contractor, designer, and/or consultant). Within a highway project the QMO can consist of the following roles: design quality assurance (QA), design quality control (QC), construction quality assurance, construction quality control, project quality assurance (PQA), independent assurance (IA) and verification. Historically highway projects have assigned all but the construction quality control to the agency. This is changing due to the reduction of agency staff sizes and the implementation of alternative delivery methods. In the 1990s, many state highway agencies (SHAs) experienced downsizing and that trend has continued. These downsizing efforts not only reduced the number of people able to manage increasing workloads but also impacted the expertise level within the SHA (Smith et al. 1998). No department within the SHA, including design, testing and inspection, was exempt from the downsizing. As a result, the testing and inspection that had previously been the responsibility been the responsibility of the agency started to shift to the contractor and the agency took on a role of acceptance. Personnel losses have been a major factor in the changes influencing the materials and construction acceptance process (Smith et al. 1998). In

2 2232 response, 23 Code of Federal Regulations 637 B was revised in 1995 to allow contractor QC test results to be used by the agency for acceptance. The industry is continuing to expand the use of alternative delivery methods within the industry because of the need to delivery projects in a shorter timeframe, while at the same time reducing the level of the DOT staff. Project delivery systems define the roles and responsibilities of the parties involved in a project, this includes design and construction (Oyetunji and Anderson 2006; Molenaar and et al. 2008; Touran et al. 2009). The project quality roles and responsibilities are also directly impacted by the project delivery method. Gransberg et al. states that the issues of alternative project delivery method and project quality management have become interrelated (Gransberg et al. 2010). Project QMOs have been adjusting to the needs of the alternative delivery methods on a project-by-project basis because of a lack of guidance available. In order for a consultant or a contractor to appropriately and accurately respond to a request for proposal (RFP) the clear identification of the quality responsibilities for the responder. There is a significant amount of investment and risk in agencies creating project-by-project QMOs and if it is not clearly thought out and communicated within the RFP then the agency does not get the best proposals possible. This research provides needed guidance for the highway industry by identifying the fundamental QMOs within the industry. It provides a novel definition of five QMOs that have been developed through a triangulation of literature review, contract document analysis and practitioner evaluation. The result is a consistent and efficient approach to QMO planning in the highway sector. While the model was derived from the highway sector, it has applications to other civil and building sectors that employ alternative delivery methods with owner agencies who have been traditionally involved in QA functions. QUALITY MANAGEMENT ORGANIZATION ROLES Quality management is the totality of the system used to manage the ultimate quality of the design as well as the construction encompassing the quality functions described previously as QA,QC, IA and verification (Gransberg et al. 2008) The project QMO identifies and assigns the quality management roles and responsibilities at the project level, from design through completion of construction. The roles that are included within a highway project QMO are project acceptance, quality assurance for design and construction, quality control for design and construction, project quality assurance (PQA), independent assurance, and verification. Overall QA is the planning and systematic actions required for a product to meet the quality requirements and QC is process control. However quality terminology can be frequently interchanged, therefore this research uses the TRB Glossary of Highway Quality Assurance Terms (TRB 2009) definitions for Quality Assurance (QA), quality control (QC), acceptance and independent assurance (IA) and the definitions for quality management (QM) and project quality assurance (PQA) from Gransberg et al (Gransberg et al. 2008). The project QMO also identifies the responsible party for deciding when the design can be released for construction and when construction can be released for final payment. The Integrated Quality Management Model (IQ2M) framework

3 2233 graphically represents all of the project quality roles, their relationships, and the surrounding project quality activities for both design and construction, as shown in Figure 1. Figure 1 Integrated Quality Management Model Framework METHODOLOGY Through three distinct phases of research, five fundamental QMO models were identified for the highway industry. A thorough literature review and national survey were used to identify a theoretical framework with 14 potential QMOs. The second phase employed a content analysis of 66 contract and policy documents to identify the QMO s that are currently in use by industry. The third phase reduced the identified industry QMO s down to the five fundamental QMOs based on the roles of the agency and three most common alternative project delivery methods: design-bidbuild (DBB); design-build (DB); construction manager/general contractor (GCCM); and public-private partnerships (PPP). The literature review was focused on construction, highway industry, quality, and design. The national survey was completed by state Departments of Transportation (DOTs), other public transportation agencies, design-builders, and DB design and construction consultants. A total of 63 complete responses and 13 partial responses were received from 47 states (Gransberg et al. 2008). The resulting primary roles making up the highway design and construction QMO framework are design QA, design QC, construction QA and construction QC. The assignment of the different quality roles to the agency, designer, contractor, and/or concessionaire resulted in 14 different theoretical QMOs.

4 2234 The second phase of the research studied the QMOs that the industry is currently using. The industry was broken into DBB, DB, CMGC and PPP. The literature review identified the QMOs utilized in the DBB delivery method and CMGC. The contracting relationships in CMGC are closely related to DBB and the applicable QMOs are the same as DBB. (Gransberg et al. 2010) Next to DBB, DB is the most prevalent project delivery method within the highway industry and has the most opportunity for change to the quality roles. Design-build also has the most industry documentation available with specified QMO organizations. Therefore, the content analysis focused on DB request for proposals (RFPs) and policy documents. The content analysis reviewed project solicitation documents (RFPs) and policy documents for 66 different projects from 26 transportation agencies from 23 states, the District of Columbia, the U.S. DOT Eastern Federal Lands Highway Division, and one Canadian Province, totaling $11.5 billion in contracted work. The QMOs identified by the research were then analyzed based on which quality roles and responsibilities were held by the agency. If the agency shared a role, directly contracted the role out to an independent firm, or had sole responsibility, it was considered an agency project quality role and responsibility. Many of the previously identified QMOs became variations of the fundamental QMOs because of the variation in how the agency performed the role and/or if the non-agency quality roles and responsibilities were contracted to a single party or multiple parties. This final analysis resulted in five fundamental QMOs utilized within the highway industry. FUNDAMENTAL HIGHWAY QMOS The five fundamental QMOs for the highway construction and design industry identified by this research are listed below: Deterministic The traditional approach to quality within the highway industry. The owner agency retains all control except for the construction QC, which is assigned to the contractor Assurance The owner agency is responsible for all aspects of the quality management except for QC. Variable Design and construction take different approaches to quality. One will either have a proactive approach by assigning both QA and QC to the party contracted to perform the scope of work, while the other will be a reactive approach by only having responsibility for QC. The version of this seen in industry is when all design QC/QA and construction QC is assigned to a design-builder Oversight the owner agency takes on an oversight role by assigning design QA, design QC, construction QA and construction QC to the parties that are contracted to perform these scopes of work. Acceptance Currently only used in a PPP arrangement, the owner agency is responsible for verification testing and final acceptance. All other quality roles and responsibilities are assigned to the concessionaire. Table 1 shows a summary of the roles and responsibilities associated with the five fundamental QMOs. Any role or responsibility held by the agency can either be performed with in-house resources or can be outsourced to a third party consultant, but ultimately the responsibility is Agency s.

5 2235 Quality Management Organization Table 1- Fundamental QMO roles and responsibilities Design QA Design QC Const. QA Const. QC PQA (agency) Deterministic Agency Agency Agency Contractor N/A Assurance Agency Designer Agency Contractor N/A Variable Designer Designer Agency Contractor Design Oversight Designer Designer Contractor Contractor Design and const. Acceptance *Concess. *Concess. *Concess. *Concess. Design and const. *Concess. = Concessionaire Deterministic Quality Management Organization The Deterministic QMO is the traditional quality organization on highway construction projects and is well understood by the primary parties involved on a project: agency, contractor and designer. The agency s roles in the Deterministic QMO include design QA, design QC, and construction QA. Project QA is not required because the agency is responsible for all QA (design and construction) on the project. The agency s role in the deterministic is one of control. In this QMO, the agency develops the designs, specifies the materials to be used, and watches over the construction (Gransberg et al. 2008). The lack of any sort of collaboration in the Deterministic approach contributes to the frequently contentious relationship between the owner and the contractor. There is no place for collaboration because the contractor and the designer have no input in the QA of their own product, they are merely responding to what the agency dictates within the RFP, plans, specifications, and bidding documents. Difficulties can arise when there are conflicts because the quality expectations are not explicitly called out in the bidding documents and/or when contract change orders are needed. The Deterministic QMO is most often implemented on DBB projects, especially when the design is performed within the agency, rather than outsourced to a design consultant. Gransberg and Shane concluded that the quality systems used in DBB pertain to CMGC because the owner still occupies the same contractual position with respect to the designer and builder (Gransberg et al. 2010). The Deterministic QMO would be most appropriately applied to CMGC if the scope of preconstruction work for the contractor was limited to items not directly relating to the design: cost estimates and project scheduling. In contrast, the Deterministic QMO is not well suited for a DB project. This is because one of the benefits of the DB delivery method is that the agency can transfer some of the risks associated with the quality of design and construction, which requires a shift in authority for each of these tasks. Applying the Deterministic QMO to a DB project would mean the agency would

6 2236 retain the quality authority for design and construction which no longer allows the design builder to manage and assume the risks associated with those tasks (Gransberg et al. 2008). Assurance Quality Management Organization In the Assurance QMO, the agency has the responsibility for QA in design and construction and the decisions to release the design for construction and to release construction for final payment. The designer and the contractor are responsible for performing QC of their respective fields. Because the agency is still responsible for all QA on the project, project QA is not necessary. While the contractor and the designer perform their own QC, typically the agency will perform independent assurance and testing to verify the QC tests results (Gransberg et al. 2008). Because the agency is still responsible for all QA on the project without input from either the designer or contractor, the owner still has a very controlling role in the project. The quality responsibilities have not shifted very far from the Deterministic QMO and there is still a focus on inspections and materials testing as the way to assure quality, rather than emphasizing building quality into the project. Because the agency s high level of control over the quality, the designer and the contractor assume less ownership for the quality of the project and collaboration between the agency and the designer and contractor regarding quality is not possible. The Assurance QMO has been applied to both DBB and DB projects. When applied to the DB delivery method all QC activities are the responsibilities of the design builder. Gransberg et al. speculated that agencies which have limited experience with the DB method apply quality management policies and procedures which are still evolving from the DBB method in which the contractor controls construction QC and the DOT has control over all QA functions and over design QC (Gransberg et al. 2008). While no evidence of CMGC employing the assurance QMO, there is no fundamental reason preventing it use for a CMGC project. Variable Quality Management Organization The Variable QMO differs from the four others because it is described by the function of the model rather than by the role of the agency. The Variable QMO is defined as having a mixed approach to quality between the design and the construction phases. An example of this method has been found on a DB project when the agency is responsible for the construction QA but not design QA. Because the agency is no longer responsible for design QA, the agency must perform project QA on the design side of the project (Gransberg et al. 2008). As a result, the agency has minimal control of quality on the design phase yet still retains a high level of control over the construction quality. This results in implementing two different approaches to quality across not only the agency but also the design builder, which can complicate attempts at creating continuity across the project. A critical element for the agency relieving its high level of control over the quality and successfully shedding the QA responsibility is the agency s identification of the quality requirements to be included in the RFP, rather than the detailed technical details of the project. Agencies must provide enough guidance so that respondents can include the appropriate services and approach to quality in their

7 2237 proposals (Gransberg et al. 2008). While the traditional skills and responsibilities of the agency resources focus on the testing and inspections required to perform construction QA when the agency retains a high level of control over quality. This requires the traditional skills possessed by a transportation agency, focused on checking all the technical details of the project. The Variable QMO can be difficult for an agency to manage because the project team must have the abilities to manage both low level of agency control over quality as well as a high level of agency control over quality within one project team. The Variable QMO construction assurance variation has been implemented on Design-Build projects. There are many possible variations for this QMO, however no others have currently been observed in industry. No examples have been found of the Variable QMO being applied to either DBB or CMGC projects; however, there is nothing fundamentally preventing it from being implemented on a dual contract (DBB or CMGC) project. Oversight Quality Management Organization In the Oversight Quality Management Organization, the agency is responsible for the decisions to release the designs for construction and to release construction for final payment and project quality assurance. The designer is responsible for design QA and design QC, while the contractor is responsible for construction QA and construction QC. Because the agency does not have any responsibility for the design QA or construction QA, it is responsible for performing project QA. While the agency always ultimately has the risk for quality on a project, in the Oversight QMO, risk is shifted to the designer and the contractor. The agency no longer has direct control over the day-to-day quality management of the project and is no longer dictating how to produce the quality required by the project; rather the agency s role is to approve the designer and contractor created quality management plans based on meeting the agency s quality requirements stipulated in the contract and that the plans are being implemented. Because the Oversight QMO shifts the responsibility for QA to the designer and the contractor the level of integration between the agency, designer and contractor increases and requires a higher level of collaboration amongst the three in order to meet the quality requirements for all parties. In this QMO, all parties are involved in the quality management of the project and the designer and contractor also have contractual accountability for not only the quality of the final product that they deliver to the agency, but the actual processes of delivering that product. Because of the high level of collaboration required by the Oversight QMO, it would be difficult to implement on a project with a linear approach where the designer and the contractor are not involved early in the project; as a result, the Oversight QMO would not be a good choice for a DBB project. However, in project delivery methods when the designer and contractor are brought in early on a project, such as DB and CMGC, the Oversight organization would be complimentary to the collaborative nature of these methods. Acceptance Quality Management Organization The Acceptance QMO has only been found in PPP project. The owner only has responsibility for the final project acceptance and owner verification testing while

8 2238 the party contracted to complete the project is responsible for all other quality responsibilities on the project. Since the agency is no longer providing 100% of the financing for design, construction, operations, and maintenance, there is a shift in financial liabilities which also pertains to the shift of the quality responsibilities (Gransberg et al. 2008). The Acceptance QMO provides the agency with the least amount of direct control over the QM of the project. The agency s primary focus, as required by FHWA Technical Advisory , is to perform design and construction quality oversight to satisfy their legal responsibilities to the public.(gransberg et al. 2008) This requires the agency to perform owner verification testing commonly performed by an independent engineer. Additionally, the agency s involvement in the quality of the project is establishing the quality requirements, approving submitted quality management plans and ensuring that quality plans are being implemented. The designer, contractor and/or concessionaire create the quality plans required by the contract and as long as they meet the requirements of the contract, the agency approves them. Meeting the quality requirements for the project is placed in the hands of the concessionaire, while the agency performs enough of an oversight role to ensure that they are meeting the federal requirements for due diligence and making sure the concessionaire is following their own project quality management plan. CONCLUSION The quality roles and responsibilities on a project are shifting on highway projects due to the use of different project delivery methods, the needs of the industry for faster and better projects, and the growing acceptance of the utilization of consultants by DOTs for traditional DOT tasks. The five fundamental QMOs for the highway design and construction industry range from the agency having sole responsible for all quality functions except construction QC, to the agency only being responsible for final acceptance and meeting federal requirements. Table 2 summarizes the level of owner control, the project delivery methods and states that associated with each of the five QMOs. Table 2 Summary of the five fundamental quality management organizations QMO Level of owner control Identified delivery methods Potential delivery methods States using QMO Deterministic High DBB, CMGC None ALL Assurance High DB CMGC, DBB NM, SD, LA, MS, NC, AK, FL Variable Medium DB CMGC NC,FL,MN,VA,UT,ME,CA Oversight Low DB CMGC CA, CO, MN, MO, NV, OR, TX, UT, VA, WA, WASH DC, EFLHD, ALBERTA Acceptance Low PPP None TX, FL During the reduction process there were some common traits/factors observed amongst all of the QMO models:

9 Construction QC is the responsibility of the contractor. Project quality assurance is always performed by the agency. 2. Final project acceptance is always performed by the agency. 3. The contract verbiage regarding the roles and responsibilities for quality has to be very concise and documented to be successful. 4. The decision as to the QMO of a project has to be determined at the time of the first request for proposal, whether it is design, construction, or both at the same time. The quality management responsibilities have to be clearly laid out in the Request for Proposals in order for the designer and/or the contractor to be able to appropriately provide for quality management activities commensurate with the amount of risk they will be assuming for project quality. What this research has provided is the identification of the fundamental QMOs for the highway industry. This research also provides a basic understanding of the individual QMOs. However there needs to be further research as to how to select an appropriate project QMO. Also, there is still a need to better understand the impact of each of the QMOs on all of the project stakeholders as well as the projects quality level. This research provides a springboard for the continued research on QMOs that is needed within the industry. Having a pool of QMOs to select from for the start of a new project is a great improvement to re-creating the QMO wheel for every project start, but without a method to select the appropriate QMO for a project the ad-hoc manner of implementing project quality management continues. In order to provide guidance as to the project QMO selection research needs to be conducted. Additionally People have a difficult time with change. The introduction of a non-traditional project QMO is a huge change for all the project stakeholders. The QMOs all have a different impact on the stakeholders of the project. There is research needed to identify the appropriate project stakeholder training and education required for each of the QMOs. This training is not only to provide the skills required to perform the responsibilities successfully, but also on breaking down the barriers to non-traditional QMOs and the overall quality philosophy of each QMO. Without this research the implementation of the non-traditional QMOs will be very difficult and frustrating. Lastly, there needs to be research conducted to identify how these QMOs impact the final quality of the project. Within the area of alternative project delivery, there was research conducted as to resulting level of quality as compared to a DBB project. The same sort of analysis needs to be conducted regarding the non-traditional QMOs in comparison to the deterministic QMO (the traditional). If these do not provide quality at least as good as the deterministic QMO, then the value of the implementation of alternative QMOs may have to be re-evaluated. REFERENCES Gransberg, D. D., Datin, J., Molenaar, K., National Research Council, National Cooperative Highway Research Program, American Association of State Highway and Transportation Officials, and United States. (2008). "Quality assurance in design-build projects." Rep. No. 376, Transportation Research Board, Washington, D.C.

10 2240 Gransberg, D. D., Shane, J. S., National Research Council, National Cooperative Highway Research Program, American Association of State Highway and Transportation Officials, and United States. (2010). Construction Manager-at- Risk Project Delivery for Highway Programs. Transportation Research Board, Washington, D.C. Molenaar, K. R., and et al. (2008). AASHTO Guide for Design-Builde Procurement. American Association of Highway Transportation Officials, Washington D.C. Oyetunji, A. A., and Anderson, S. D. (2006). "Relative effectiveness of project delivery and contract strategies." J.Constr.Eng.Manage., 132(1), Smith, G. R., National Cooperative Highway Research Program, National Research Council, American Association of State Highway and Transportation Officials, and United States. (1998). State DOT management techniques for materials and construction acceptance. National Academy Press, Washington, D.C. Touran, A., Gransberg, D. D., Molenaar, K. R., Ghavamifar, K., Mason, D. J., and Fithian, L. A. (2009). "A Guidebook for the Evaluation of Project Delivery methods." Rep. No. TCRP Report 131, TRB,. TRB. (2009). "Glossary of Highway Quality Assurance Terms." Rep. No. E-C137, Transportation Research Board, Washington D.C.

Construction Manager/General Contractor Issue Identification

Construction Manager/General Contractor Issue Identification Construction Manager/General Contractor Issue Identification Jennifer S. Shane, Principal Investigator Department of Civil, Construction, and Environmental Engineering Construction Management and Technology

More information

Analysis of Site-level Administrator and Superintendent Certification Requirements in the USA (2010)

Analysis of Site-level Administrator and Superintendent Certification Requirements in the USA (2010) Analysis of Site-level Administrator and Superintendent Certification Requirements in the USA (2010) Stephen H. Davis, Ed.D. California State Polytechnic University, Pomona Summer 2010 Introduction The

More information

NCHRP 20-68A US Domestic Scan Program. Scan 13-02 Advances In Civil Integrated Management (CIM)

NCHRP 20-68A US Domestic Scan Program. Scan 13-02 Advances In Civil Integrated Management (CIM) NCHRP 20-68A US Domestic Scan Program Scan 13-02 Advances In Civil Integrated Management (CIM) Scan Team Visits 2014 Presenter: Fangyu (Denise) Guo PhD student from Iowa State University CIM is the collection,

More information

CHRISTOFER M. HARPER, Ph.D., LEED AP CURRICULUM VITAE. 208A Old Forestry Building Baton Rouge, LA 70803 charper@lsu.

CHRISTOFER M. HARPER, Ph.D., LEED AP CURRICULUM VITAE. 208A Old Forestry Building Baton Rouge, LA 70803 charper@lsu. CHRISTOFER M. HARPER, Ph.D., LEED AP CURRICULUM VITAE 208A Old Forestry Building Baton Rouge, LA 70803 charper@lsu.edu (225) 578-0131 EDUCATION University of Colorado Doctor of Philosophy, Civil Engineering,

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

How To Rate Plan On A Credit Card With A Credit Union

How To Rate Plan On A Credit Card With A Credit Union Rate History Contact: 1 (800) 331-1538 Form * ** Date Date Name 1 NH94 I D 9/14/1998 N/A N/A N/A 35.00% 20.00% 1/25/2006 3/27/2006 8/20/2006 2 LTC94P I F 9/14/1998 N/A N/A N/A 35.00% 20.00% 1/25/2006 3/27/2006

More information

U.S. Department of Housing and Urban Development: Weekly Progress Report on Recovery Act Spending

U.S. Department of Housing and Urban Development: Weekly Progress Report on Recovery Act Spending U.S. Department of Housing and Urban Development: Weekly Progress Report on Recovery Act Spending by State and Program Report as of 3/7/2011 5:40:51 PM HUD's Weekly Recovery Act Progress Report: AK Grants

More information

State Survey Results MULTI-LEVEL LICENSURE TITLE PROTECTION

State Survey Results MULTI-LEVEL LICENSURE TITLE PROTECTION MULTI-LEVEL LICENSURE TITLE PROTECTION Prior AK MN TN MO AL MO KY VA AZ MS MO DC NYC NE HI ME OR IA RI PA IL TX VA KS WA LA WI MA WV Prior AK ME OR TN AL MI PA HI CO MS FL DC NC MN IA NE UT IL NV WA IN

More information

Table 12: Availability Of Workers Compensation Insurance Through Homeowner s Insurance By Jurisdiction

Table 12: Availability Of Workers Compensation Insurance Through Homeowner s Insurance By Jurisdiction AL No 2 Yes No See footnote 2. AK No Yes No N/A AZ Yes Yes Yes No specific coverage or rate information available. AR No Yes No N/A CA Yes No No Section 11590 of the CA State Insurance Code mandates the

More information

A N S W E R S R E L 2 0 0 9 N

A N S W E R S R E L 2 0 0 9 N ISSUES& ANSWERS REL 2009 No. 076 Reducing stereotype threat in classrooms: a review of socialpsychological intervention studies on improving the achievement of Black students U.S. D e p a r t m e n t o

More information

VDOT GOVERNANCE DOCUMENT

VDOT GOVERNANCE DOCUMENT VDOT GOVERNANCE DOCUMENT Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects Location and Design Division Alternate Project Delivery

More information

The Lincoln National Life Insurance Company Variable Life Portfolio

The Lincoln National Life Insurance Company Variable Life Portfolio The Lincoln National Life Insurance Company Variable Life Portfolio State Availability as of 12/14/2015 PRODUCTS AL AK AZ AR CA CO CT DE DC FL GA GU HI ID IL IN IA KS KY LA ME MP MD MA MI MN MS MO MT NE

More information

CONTRACTOR S PROTECTIVE, PROFESSIONAL AND POLLUTION LIABILITY INSURANCE APPLICATION FORM. Limits of Liability Requested: / Deductible: /

CONTRACTOR S PROTECTIVE, PROFESSIONAL AND POLLUTION LIABILITY INSURANCE APPLICATION FORM. Limits of Liability Requested: / Deductible: / PROFESSIONAL AND POLLUTION LIABILITY INSURANCE APPLICATION FORM Coverage Desired: Protective Liability Professional Liability Pollution Liability Limits of Liability Requested: / Deductible: / / / / /

More information

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: PTA Supervision Requirements

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: PTA Supervision Requirements These tables provide information on what type of supervision is required for PTAs in various practice settings. Definitions Onsite Supervision General Supervision Indirect Supervision The supervisor is

More information

State of the Workers Compensation Market

State of the Workers Compensation Market State of the Workers Compensation Market Natasha Moore, FCAS, MAAA Practice Leader and Senior Actuary August 25, 2015 WCEC Orlando, Florida Copyright 2015 National Council on Compensation Insurance, Inc.

More information

Table 11: Residual Workers Compensation Insurance Market By Jurisdiction

Table 11: Residual Workers Compensation Insurance Market By Jurisdiction Table 11: Residual Workers Market By AL Yes/NCCI 3 Two declination AK Yes/NCCI Two declination AZ Yes/NCCI Three declination, including one from the State Fund Agent/ ()/ Access? 4 Recommend NWCRP Recommend

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Organization Project

More information

NCHRP REPORT 808. Guidebook on Alternative Quality Management Systems for Highway Construction NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM

NCHRP REPORT 808. Guidebook on Alternative Quality Management Systems for Highway Construction NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM NCHRP REPORT 808 NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM Guidebook on Alternative Quality Management Systems for Highway Construction TRANSPORTATION RESEARCH BOARD 2015 EXECUTIVE COMMITTEE* OFFICERS

More information

Request for Proposal for Design-Build Services for Construction Package 2-3

Request for Proposal for Design-Build Services for Construction Package 2-3 California High-Speed Rail Program RFP No.: HSR 13-57 Request for Proposal for Design-Build Services for Construction Package 2-3 Book IV, Part D.2 Master Quality Plan Revision No. Date Description 0 04/02/2014

More information

Office: (785) 864-6851 E-mail: daniel.tran@ku.edu

Office: (785) 864-6851 E-mail: daniel.tran@ku.edu CURRICULUM VITAE for DANIEL TRAN, PH.D. Assistant Professor Department of Civil, Environmental, and Architectural Engineering University of Kansas, 2150 Learned Hall 1530 West 15th Street Lawrence, KS

More information

AmGUARD Insurance Company EastGUARD Insurance Company NorGUARD Insurance Company WestGUARD Insurance Company GUARD

AmGUARD Insurance Company EastGUARD Insurance Company NorGUARD Insurance Company WestGUARD Insurance Company GUARD About Us For over 30 years, we have protected the interests of the small- to mid-sized businesses that insure with us. At Berkshire Hathaway Insurance Companies, we dedicate our efforts in the areas that

More information

NCHRP 20-68A. Domestic Scan 13-01 Advances in Developing a Cross- Trained Workforce. Significant Findings and Recommendations July 22, 2015

NCHRP 20-68A. Domestic Scan 13-01 Advances in Developing a Cross- Trained Workforce. Significant Findings and Recommendations July 22, 2015 NCHRP 20-68A Domestic Scan 13-01 Advances in Developing a Cross- Trained Workforce Significant Findings and Recommendations July 22, 2015 Greg Duncan Applied Pavement Technology, Inc. 1 Overview Scan Objectives

More information

INTRODUCTION. Figure 1. Contributions by Source and Year: 2012 2014 (Billions of dollars)

INTRODUCTION. Figure 1. Contributions by Source and Year: 2012 2014 (Billions of dollars) Annual Survey of Public Pensions: State- and Locally- Administered Defined Benefit Data Summary Report: Economy-Wide Statistics Division Briefs: Public Sector By Phillip Vidal Released July 2015 G14-ASPP-SL

More information

4.3 Project Construction

4.3 Project Construction 4.3 Project Construction 4.3.1 Contract Management Contract management practices may vary depending on the type of construction delivery method (e.g. Design-Bid-Build, Stipulated Sum, Construction Management).

More information

Project Delivery Methods & Contract Types CSTM 102 Spring 2013

Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Schedule February 16- Building Information Modeling February 21- Midterm Review February 23- Midterm In the industry the term Pre-Construction

More information

National Traffic Incident Management Responder Training Nebraska Update. Nebraska Asphalt Paving Conference February 11-12, 2014

National Traffic Incident Management Responder Training Nebraska Update. Nebraska Asphalt Paving Conference February 11-12, 2014 National Traffic Incident Management Responder Training Nebraska Update Nebraska Asphalt Paving Conference February 11-12, 2014 1 Why this presentation? Why a presentation on Traffic Incident Management

More information

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: Continuing Competence

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: Continuing Competence This document reports CEU (continuing education units) and CCU (continuing competence units) requirements for renewal. It describes: Number of CEUs/CCUs required for renewal Who approves continuing education

More information

Annual Survey of Public Pensions: State- and Locally- Administered Defined Benefit Data Summary Brief: 2015

Annual Survey of Public Pensions: State- and Locally- Administered Defined Benefit Data Summary Brief: 2015 Annual Survey of Public Pensions: State- and Locally- Administered Defined Benefit Data Summary Brief: Economy-Wide Statistics Division Briefs: Public Sector Graphical Summary By Phillip Vidal Released

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

ehealth Price Index Trends and Costs in the Short-Term Health Insurance Market, 2013 and 2014

ehealth Price Index Trends and Costs in the Short-Term Health Insurance Market, 2013 and 2014 ehealth Price Index Trends and Costs in the Short-Term Health Insurance Market, 2013 and 2014 June 2015 1 INTRODUCTION In this report, ehealth provides an analysis of consumer shopping trends and premium

More information

PEOPLE, PRICE, PRODUCT, PROMOTION and PRIDE

PEOPLE, PRICE, PRODUCT, PROMOTION and PRIDE Contact Information 1603 Lyndon B Johnson Freeway Suite 350 Dallas, Texas 75234 (972) 243-7648 Fax: (972) 243-2494 corporate@sunridgemanagement.com www.sunridgemanagement.com Proven Keys to Successful

More information

Life Settlements Source List

Life Settlements Source List BROKERS Ashar Group LLC - Life Settlement Specialists 407-772-1818 www.ashargroup.com Except AK NH VT Except AK NH VT Varies based on current market opportunities and groups that pass Ashar s due diligence

More information

Regional Electricity Forecasting

Regional Electricity Forecasting Regional Electricity Forecasting presented to Michigan Forum on Economic Regulatory Policy January 29, 2010 presented by Doug Gotham State Utility Forecasting Group State Utility Forecasting Group Began

More information

TITLE POLICY ENDORSEMENTS BY STATE

TITLE POLICY ENDORSEMENTS BY STATE TITLE POLICY ENDORSEMENTS BY STATE State Endorsement ID Endorsement Description AK ARM ALTA 6 Adjustable (Variable) Rate AK BALLOON FNMA Balloon Endorsement AK CONDO ALTA 4 Condominium AK COPY FEE Copies

More information

Understanding Payroll Recordkeeping Requirements

Understanding Payroll Recordkeeping Requirements Understanding Payroll Recordkeeping Requirements 1 Presented by Sally Thomson, CPP Directory of Payroll Training American Payroll Association sthomson@americanpayroll.org 2 Agenda Recordkeeping Requirements

More information

EFFECTS OF LEGALIZING MARIJUANA 1

EFFECTS OF LEGALIZING MARIJUANA 1 EFFECTS OF LEGALIZING MARIJUANA 1 Effects of Legalizing Medical On Illegal Use Professor Elizabeth Jacobs, PhD Psychology 230 November 29, 2010 EFFECTS OF LEGALIZING MARIJUANA 2 Introduction With the increasing

More information

Construction Quality Assurance for Federally Funded Local Public Agency Projects

Construction Quality Assurance for Federally Funded Local Public Agency Projects TECHBRIEF Construction Quality Assurance for Federally Funded Local Public Agency Projects FHWA Publication No.: FHWA-HRT-15-009 FHWA Contact: Richard Duval, HRDI-20, (202) 493-3365, richard.duval@dot.gov

More information

New York Public School Spending In Perspec7ve

New York Public School Spending In Perspec7ve New York Public School Spending In Perspec7ve School District Fiscal Stress Conference Nelson A. Rockefeller Ins0tute of Government New York State Associa0on of School Business Officials October 4, 2013

More information

State Corporate Income Tax-Calculation

State Corporate Income Tax-Calculation State Corporate Income Tax-Calculation 1 Because it takes all elements (a*b*c) to calculate the personal or corporate income tax, no one element of the corporate income tax can be analyzed separately from

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

Admitting Foreign Trained Lawyers. National Conference of Bar Examiners Chicago, May 2, 2015

Admitting Foreign Trained Lawyers. National Conference of Bar Examiners Chicago, May 2, 2015 Admitting Foreign Trained Lawyers National Conference of Bar Examiners Chicago, May 2, 2015 Professor Laurel S. Terry Penn State s Dickinson Law Carlisle, Pennsylvania LTerry@psu.edu Overview of Remarks

More information

Who provides this training? Are there any requirements? The parents/guardians and the doctor go through the medication curriculum with the student.

Who provides this training? Are there any requirements? The parents/guardians and the doctor go through the medication curriculum with the student. AL AK AZ AR Student, if they have a chronic condition school nurse or school administrators The student, if their parent/guardian authorizes them to. Trained school personnel can also administer Students

More information

Piloting a searchable database of dropout prevention programs in nine low-income urban school districts in the Northeast and Islands Region

Piloting a searchable database of dropout prevention programs in nine low-income urban school districts in the Northeast and Islands Region ISSUES& ANSWERS REL 2008 No. 046 Piloting a searchable database of dropout prevention programs in nine low-income urban school districts in the Northeast and Islands Region U.S. D e p a r t m e n t o f

More information

2016 Individual Exchange Premiums updated November 4, 2015

2016 Individual Exchange Premiums updated November 4, 2015 2016 Individual Exchange Premiums updated November 4, 2015 Within the document, you'll find insights across 50 states and DC with available findings (i.e., carrier participation, price leadership, gross

More information

NAAUSA Security Survey

NAAUSA Security Survey NAAUSA Security Survey 1. How would you rate the importance of each of the following AUSA security improvements. Very important Somewhat important Not too important Not at all important Secure parking

More information

NHIS State Health insurance data

NHIS State Health insurance data State Estimates of Health Insurance Coverage Data from the National Health Interview Survey Eve Powell-Griner SHADAC State Survey Workshop Washington, DC, January 13, 2009 U.S. DEPARTMENT OF HEALTH AND

More information

ANTHONY P. CARNEVALE NICOLE SMITH JEFF STROHL

ANTHONY P. CARNEVALE NICOLE SMITH JEFF STROHL State-Level Analysis HELP WANTED PROJECTIONS of JOBS and EDUCATION REQUIREMENTS Through 2018 JUNE 2010 ANTHONY P. CARNEVALE NICOLE SMITH JEFF STROHL Contents 1 Introduction 3 U.S. Maps: Educational concentrations

More information

State Technology Report 2008

State Technology Report 2008 About This Report This State Technology Report is a supplement to the 11th edition of Technology Counts, a joint project of Education Week and the Editorial Projects in Education Research Center. As in

More information

CONTRACTOR WARRANTY CA-8 3 POINTS GOAL CREDIT REQUIREMENTS DOCUMENTATION RELATED CREDITS SUSTAINABILITY COMPONENTS BENEFITS

CONTRACTOR WARRANTY CA-8 3 POINTS GOAL CREDIT REQUIREMENTS DOCUMENTATION RELATED CREDITS SUSTAINABILITY COMPONENTS BENEFITS Greenroads Manual v1.5 Construction Activities CONTRACTOR WARRANTY GOAL Incorporate construction quality into the public low bid process through the use of warranties. CREDIT REQUIREMENTS The project construction

More information

STATES VEHICLE ASSET POLICIES IN THE FOOD STAMP PROGRAM

STATES VEHICLE ASSET POLICIES IN THE FOOD STAMP PROGRAM 820 First Street NE, Suite 510 Washington, DC 20002 Tel: 202-408-1080 Fax: 202-408-1056 center@cbpp.org www.cbpp.org Revised July 1, 2008 STATES VEHICLE ASSET POLICIES IN THE FOOD STAMP PROGRAM States

More information

Auto Insurance Underwriting/Rating

Auto Insurance Underwriting/Rating Auto Insurance Underwriting/Rating Insurance Underwriting/Rating Variables Driver Demographics Driver History Type of Vehicle Vehicle History Auto Po olicy 1 Name: John Smith Age: 32 Gender: Male Marital

More information

Department of Legislative Services

Department of Legislative Services Department of Legislative Services Maryland General Assembly 2008 Session HB 1169 FISCAL AND POLICY NOTE House Bill 1169 Ways and Means (Delegate Barve) Sales and Use Tax - Computer Services Exemption

More information

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: Continuing Competence

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: Continuing Competence This document reports CEU requirements for renewal. It describes: Number of required for renewal Who approves continuing education Required courses for renewal Which jurisdictions require active practice

More information

State Small Business Credit Initiative. SSBCI Overview

State Small Business Credit Initiative. SSBCI Overview 6/11/2014 State Small Business Credit Initiative Opportunity Finance Network June 10, 2014 SSBCI Overview Created in Small Business Jobs Act of 2010 to spur up to $15 billion in lending and investing to

More information

Dashboard. Campaign for Action. Welcome to the Future of Nursing:

Dashboard. Campaign for Action. Welcome to the Future of Nursing: Welcome to the Future of Nursing: Campaign for Action Dashboard About this Dashboard: These are graphic representations of measurable goals that the Campaign has selected to evaluate our efforts in support

More information

AAIS Personal and Premises Liability Program

AAIS Personal and Premises Liability Program Policy Forms and Endorsements IT IS WOLTERS KLUWER FINANCIAL SERVICES' POLICY TO LIMIT THE SALE OF BUREAU FORMS TO THE MEMBERS AND SUBSCRIBERS OF THOSE RESPECTIVE BUREAUS. PURCHASE AND USE OF BUREAU FORMS

More information

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS Advancing Professional Construction and Program Management Worldwide ACKNOWLEDGMENTS CMAA gratefully acknowledges the time and efforts of those who served as

More information

Nurse Practitioners and Physician Assistants in the United States: Current Patterns of Distribution and Recent Trends. Preliminary Tables and Figures

Nurse Practitioners and Physician Assistants in the United States: Current Patterns of Distribution and Recent Trends. Preliminary Tables and Figures Nurse Practitioners and Physician Assistants in the United States: Current Patterns of Distribution and Recent Trends Preliminary Tables and Figures Kevin M. Stange, PhD Assistant Professor Gerald R. Ford

More information

Highway Loss Data Institute Bulletin

Highway Loss Data Institute Bulletin Highway Loss Data Institute Bulletin Helmet Use Laws and Medical Payment Injury Risk for Motorcyclists with Collision Claims VOL. 26, NO. 13 DECEMBER 29 INTRODUCTION According to the National Highway Traffic

More information

Evaluating Project Delivery Options

Evaluating Project Delivery Options Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager

More information

Funding Your Technology and Archive Conversion Needs

Funding Your Technology and Archive Conversion Needs Funding Your Technology and Archive Conversion Needs Presented at the NACRC Legislative Conference March 5, 2011 Facilitators: Larry Burtness & Carol Foglesong Technology funding The question was asked

More information

FHWA SCOC 2015 Update

FHWA SCOC 2015 Update FHWA SCOC 2015 Update Bryan Cawley Construction Team Leader Office of Infrastructure, FHWA 202-366-1333 or bryan.cawley@dot.gov Objectives Rule Making What is FHWA doing with Highway Construction Program

More information

Mortgage Broker / Mortgage Originator Bond Requirements Nationwide

Mortgage Broker / Mortgage Originator Bond Requirements Nationwide Surety One Email: Underwriting@SuretyOne.org Facsimile: 919-834-7039 Mail: P.O. Box 37284, Raleigh, NC 27627 Mortgage Broker / Mortgage Originator Bond Requirements Nationwide AK Mortgage Broker License

More information

FILING MEMORANDUM ITEM U-1399A REVISIONS TO STATISTICAL PLAN FOR WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE AMENDED PENSION TABLE VALUES

FILING MEMORANDUM ITEM U-1399A REVISIONS TO STATISTICAL PLAN FOR WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE AMENDED PENSION TABLE VALUES (Applies in: AK, AL, AR, AZ, CO, CT, DC, FL, GA, HI, IA, ID, IL, IN, KS, KY, LA, MD, ME, MO, MS, MT, NE, NH, NM, NV, OK, OR, RI, SC, SD, TN, UT, VA, VT, WV) PAGE 1 FILING MEMORANDUM To become effective

More information

Building Healthy and Active Communities through Partnerships. Society for Outdoor Recreation Professionals April 16, 2015

Building Healthy and Active Communities through Partnerships. Society for Outdoor Recreation Professionals April 16, 2015 Building Healthy and Active Communities through Partnerships Society for Outdoor Recreation Professionals April 16, 2015 Patti Miller Nemours Health & Prevention Services Kendall Sommers Delaware State

More information

Mapping State Proficiency Standards Onto the NAEP Scales:

Mapping State Proficiency Standards Onto the NAEP Scales: Mapping State Proficiency Standards Onto the NAEP Scales: Variation and Change in State Standards for Reading and Mathematics, 2005 2009 NCES 2011-458 U.S. DEPARTMENT OF EDUCATION Contents 1 Executive

More information

List of HUD Accepted Insured Ten-Year Protection Plans (As of September 22, 2008) Posted as a courtesy by MSI on 11/05/08

List of HUD Accepted Insured Ten-Year Protection Plans (As of September 22, 2008) Posted as a courtesy by MSI on 11/05/08 List of HUD Accepted Insured Ten-Year Protection Plans (As of September 22, 2008) Posted as a courtesy by MSI on 11/05/08 NAME OF PROVIDER INSURANCE BACKING STATE ACCEPTANCE American ewarranty 6360 Flank

More information

Community Eligibility Option: Guidance and Procedures for Selection of States for School Year 2012-2013

Community Eligibility Option: Guidance and Procedures for Selection of States for School Year 2012-2013 United States Department of Agriculture Food and Nutrition Service 3101 Park Center Drive Alexandria, VA 22302-1500 DATE: February 9, 2012 MEMO CODE: SP 12-2012 SUBJECT: TO: Community Eligibility Option:

More information

Hail-related claims under comprehensive coverage

Hail-related claims under comprehensive coverage Bulletin Vol. 29, No. 3 : April 2012 Hail-related claims under comprehensive coverage Claims for hail damage more than doubled in 2011 compared with the previous three years. Hail claims are primarily

More information

The following rates are the maximum rates that should be illustrated. Be sure to update the IRIS illustration system

The following rates are the maximum rates that should be illustrated. Be sure to update the IRIS illustration system INTEREST RATES - June 16, 2016 to July 15, 2016 Notices 1. Before soliciting or taking any annuity applications, it is required that you have completed Lafayette Life's Annuity Training and any Continuing

More information

10 Reasons Why Vertex SMB is A Better Way to Handle Your Sales and Use Tax Automation 11:00 11:30. Scott Coleman. Channel Sales Manager

10 Reasons Why Vertex SMB is A Better Way to Handle Your Sales and Use Tax Automation 11:00 11:30. Scott Coleman. Channel Sales Manager 11:00 11:30 10 Reasons Why Vertex SMB is A Better Way to Handle Your Sales and Use Tax Automation Scott Coleman Channel Sales Manager Agenda Landscape of the Market Today 10 Reasons Why Vertex SMB is a

More information

PROGRAM HIGHLIGHTS. Association of Collegiate Schools of Architecture 2011-12 ACSA100. Visit ACSA100.org to make your donation.

PROGRAM HIGHLIGHTS. Association of Collegiate Schools of Architecture 2011-12 ACSA100. Visit ACSA100.org to make your donation. ACSA100 In 2012, ACSA will celebrate 100 years of advancing critical issues facing architectural education. The organization has planned four major projects surrounding the centennial: an engaging scholarly

More information

Suitability Agent Continuing Education Requirements by State

Suitability Agent Continuing Education Requirements by State Suitability Agent Continuing Education Requirements by State STATE AL AK AZ AR CA CO CT DE DC FL GA HI ID Insurance producers holding a life line of insurance license must complete a one-time 4 hour annuity

More information

Estimating college enrollment rates for Virginia public high school graduates

Estimating college enrollment rates for Virginia public high school graduates ISSUES& ANSWERS REL 2011 No. 104 Estimating college enrollment rates for Virginia public high school graduates ISSUES& ANSWERS REL 2011 No. 104 Estimating college enrollment rates for Virginia public high

More information

50-State Analysis. School Attendance Age Limits. 700 Broadway, Suite 810 Denver, CO 80203-3442 303.299.3600 Fax: 303.296.8332

50-State Analysis. School Attendance Age Limits. 700 Broadway, Suite 810 Denver, CO 80203-3442 303.299.3600 Fax: 303.296.8332 0-State Analysis School Attendance Age Limits 700 Broadway, Suite 810 Denver, CO 80203-32 303.299.3600 Fax: 303.296.8332 Introduction School Attendance Age Limits By Marga Mikulecky April 2013 This 0-State

More information

2014 National 911 Progress Report

2014 National 911 Progress Report 2014 National 911 Progress Report National Highway Traffic Safety Administration National 911 Program Washington, DC March 2015 About the National 911 Program The mission of the National 911 Program is

More information

Sample Quality Management Plan

Sample Quality Management Plan This reference documents project-specific quality assurance and quality control procedures appropriate to the size, complexity, and nature of the project. Quality improvements are also documented and may

More information

PRODUCTS CURRENTLY AVAILABLE FOR SALE. Marquis SP

PRODUCTS CURRENTLY AVAILABLE FOR SALE. Marquis SP INTEREST RATES - August 16, 2016 to September 15, 2016 Notices 1. Before soliciting or taking any annuity applications, it is required that you have completed Lafayette Life's Annuity Training and any

More information

U.S. Department of Education NCES 2011-460 NAEP. Tools on the Web

U.S. Department of Education NCES 2011-460 NAEP. Tools on the Web U.S. Department of Education NCES 2011-460 NAEP Tools on the Web Whether you re an educator, a member of the media, a parent, a student, a policymaker, or a researcher, there are many resources available

More information

Standardized Pharmacy Technician Education and Training

Standardized Pharmacy Technician Education and Training Standardized Pharmacy Technician Education and Training Kevin N. Nicholson, RPh, JD Vice President, Pharmacy Regulatory Affairs National Association of Chain Drug Stores May 19, 2009 Overview of how technicians

More information

HUD REO M & M III. FHA Webinar on HUD REO 203-K Standard 203-K Streamline. HUD REO (Real Estate Owned) 203(k) Streamline.

HUD REO M & M III. FHA Webinar on HUD REO 203-K Standard 203-K Streamline. HUD REO (Real Estate Owned) 203(k) Streamline. FHA Webinar on HUD REO 203-K Standard 203-K Streamline HUD REO (Real Estate Owned) 203(k) Streamline 203-K Standard National Servicing Center (NSC) is responsible for direct oversight of the MCM contractor:

More information

2014-2015 Fact Sheet* Physical Therapist Assistant Education Programs October 2015

2014-2015 Fact Sheet* Physical Therapist Assistant Education Programs October 2015 Last updated: //0 Contact: accreditation@apta.org 04-0 Fact Sheet* Physical Therapist Assistant Education Programs October 0 *This fact sheet is in-progress and will be updated with new data sets & charts

More information

Larry R. Kaiser, MD. President The University of Texas Health Science Center at Houston

Larry R. Kaiser, MD. President The University of Texas Health Science Center at Houston Larry R. Kaiser, MD President The University of Texas Health Science Center at Houston HealthCare Workforce: UTHealth Experience CHALLENGE To train the Healthcare Workforce of the 21 st Century SOLUTIONS:

More information

Alaska (AK) Arizona (AZ) Arkansas (AR) California-RN (CA-RN) Colorado (CO)

Alaska (AK) Arizona (AZ) Arkansas (AR) California-RN (CA-RN) Colorado (CO) Beth Radtke 50 Included in the report: 7/22/2015 11:15:28 AM Alaska (AK) Arizona (AZ) Arkansas (AR) California-RN (CA-RN) Colorado (CO) Connecticut (CT) Delaware (DE) District Columbia (DC) Florida (FL)

More information

NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM NCHRP SYNTHESIS 376. Quality Assurance in Design-Build Projects. A Synthesis of Highway Practice

NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM NCHRP SYNTHESIS 376. Quality Assurance in Design-Build Projects. A Synthesis of Highway Practice NCHRP SYNTHESIS 376 NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM Quality Assurance in Design-Build Projects A Synthesis of Highway Practice TRANSPORTATION RESEARCH BOARD 2008 EXECUTIVE COMMITTEE* OFFICERS

More information

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: License Renewal Who approves courses?

Federation of State Boards of Physical Therapy Jurisdiction Licensure Reference Guide Topic: License Renewal Who approves courses? Federation of State s of Physical The table below provides information on approval of continuing education/competence courses and for each jurisdiction. Summary Number of jurisdictions requiring approval

More information

New Mexico DOT Transportation Asset Management Implementation Plan. final plan

New Mexico DOT Transportation Asset Management Implementation Plan. final plan New Mexico DOT Transportation Asset Management Implementation Plan final plan February 23, 2015 report New Mexico DOT Transportation Asset Management Implementation Plan date February 23, 2015 Table

More information

CHAPTER TEN. Quality Assurance and Quality Control MAINE RIGHT OF WAY MANUAL

CHAPTER TEN. Quality Assurance and Quality Control MAINE RIGHT OF WAY MANUAL CHAPTER TEN Quality Assurance and Quality Control MAINE RIGHT OF WAY MANUAL December 2010 Section Table of Contents Page 10-1 PURPOSE AND OBJECTIVES... 10-1(1) 10-1.01 Purpose... 10-1(1) 10-1.02 Quality

More information

Uniform Application for Business Entity Adjuster License/Registration (Please Print or Type)

Uniform Application for Business Entity Adjuster License/Registration (Please Print or Type) Business Entity License/Registration (Please Print or Type) Check appropriate box for license requested. Resident License Resident Designated Home State: License #: Non-Resident Designated Home State:

More information

Community College/Technical Institute Mission Convergence Study

Community College/Technical Institute Mission Convergence Study Center for Community College Policy Education Commission of the States Community College/Technical Institute Mission Convergence Study Phase 1: Survey of the States Prepared by Donald E. Puyear, Ph.D.

More information

STATE HOMELESSNESS. The. An examination of homelessness, economic, housing, and demographic trends at the national and state levels.

STATE HOMELESSNESS. The. An examination of homelessness, economic, housing, and demographic trends at the national and state levels. The STATE of HOMELESSNESS in America 2014 An examination of homelessness, economic, housing, and demographic trends at the national and state levels. The National Alliance to End Homelessness (Alliance)

More information

A descriptive analysis of state-supported formative assessment initiatives in New York and Vermont

A descriptive analysis of state-supported formative assessment initiatives in New York and Vermont ISSUES& ANSWERS REL 2012 No. 112 At Education Development Center, Inc. A descriptive analysis of state-supported formative assessment initiatives in New York and Vermont ISSUES& ANSWERS REL 2012 No. 112

More information

Pre-Bidders' Web Conference for SHRP 2 Reliability Project RFP for L 34 Project: E-Tool for Business Processes To Improve Travel Time Reliability

Pre-Bidders' Web Conference for SHRP 2 Reliability Project RFP for L 34 Project: E-Tool for Business Processes To Improve Travel Time Reliability Pre-Bidders' Web Conference for SHRP 2 Reliability Project RFP for L 34 Project: E-Tool for Business Processes To Improve Travel Time Reliability Presenter: Gummada Murthy, Senior Program Officer, SHRP

More information

The Economic Impact of Commercial Airports in 2010

The Economic Impact of Commercial Airports in 2010 The Economic Impact of Commercial Airports in 2010 January 2012 Prepared for: Airports Council International North America Prepared by: CDM Smith 8805 Governor s Hill Drive Cincinnati, Ohio 45249 Table

More information

Computer Forensics Examiners as Private Investigators: The Role of Academia in the Debate. CDFSL 2008 Oklahoma City, OK April 23, 2008

Computer Forensics Examiners as Private Investigators: The Role of Academia in the Debate. CDFSL 2008 Oklahoma City, OK April 23, 2008 Computer Forensics Examiners as Private Investigators: The Role of Academia in the Debate CDFSL 2008 Oklahoma City, OK April 23, 2008 Gary C. Kessler Champlain College Burlington, VT DISCLAIMER I teach

More information

May 16, 2013. The Honorable Arne Duncan Secretary U.S. Department of Education. K-12 Education: States Test Security Policies and Procedures Varied

May 16, 2013. The Honorable Arne Duncan Secretary U.S. Department of Education. K-12 Education: States Test Security Policies and Procedures Varied 441 G St. N.W. Washington, DC 20548 May 16, 2013 The Honorable Arne Duncan Secretary U.S. Department of Education K-12 Education: States Test Security Policies and Procedures Varied Dear Mr. Secretary:

More information

Professional Practice Commission: March 2013. Alternative Project Delivery Systems

Professional Practice Commission: March 2013. Alternative Project Delivery Systems Professional Practice Commission: March 2013 Alternative Project Delivery Systems UIA Accord Building project delivery systems. Definition Building project delivery systems are defined as the contractual

More information

STATE INCOME TAX WITHHOLDING INFORMATION DOCUMENT

STATE INCOME TAX WITHHOLDING INFORMATION DOCUMENT STATE INCOME TAX WITHHOLDING INFORMATION DOCUMENT Zurich American Life Insurance Company (ZALICO) Administrative Offices: PO BOX 19097 Greenville, SC 29602-9097 800/449-0523 This document is intended to

More information

Enrollment Snapshot of Radiography, Radiation Therapy and Nuclear Medicine Technology Programs 2013

Enrollment Snapshot of Radiography, Radiation Therapy and Nuclear Medicine Technology Programs 2013 Enrollment Snapshot of Radiography, Radiation Therapy and Nuclear Medicine Technology Programs 2013 A Nationwide Survey of Program Directors Conducted by the American Society of Radiologic Technologists

More information

Enrollment Snapshot of Radiography, Radiation Therapy and Nuclear Medicine Technology Programs 2015

Enrollment Snapshot of Radiography, Radiation Therapy and Nuclear Medicine Technology Programs 2015 Enrollment Snapshot of, Radiation Therapy and Nuclear Medicine Technology Programs 2015 December 2015 2015 ASRT. All rights reserved. Reproduction in any form is forbidden without written permission from

More information