Percorso di Eccellenza in PROJECT MANAGEMENT. Cost estimating and estimate to completion. Ing. Locatelli Giorgio.
|
|
- Ezra James
- 8 years ago
- Views:
Transcription
1 Cost estimating and estimate to completion Ing. Locatelli Giorgio Cost Estimating The project s costs management evolves during the whole project life cycle and can be distinguished in three phases: 1. Estimating 2. Cost control 3. Estimate to finish 1
2 Estimates Accuracy The cost estimating accuracy is connected to: Project s phase (labour portion not yet performed) Level of the engineering progress (required resources definition) Reliability for the cost data available (database of historical data availability) Estimates Accuracy % Estimate s error Project Life Cycle t 2
3 Cost estimating levels Different cost estimating levels correspond to different grades of belief: Ball Park estimate (preliminary information to the customer) Semi-analytic estimate (feasibility study) Analytic estimate (proposal) Cost estimating levels Increasing the cost estimating levels the estimate s cost exponentially increases in terms of: Resources allocated Time requested From few hours for the lower level to: 5-10% of the total project engineering s hours 1-2% of the whole investment cost 3
4 Cost estimating techniques At different cost estimating levels correspond two cost estimating techniques: Parametric (cost driver) Analytic (cost = quantity x unit cost) Ball Park Estimate The Ball Park estimate presupposes well-known: Plant typology Plant Size The whole cost for same type plants 4
5 Ball Park Estimate Scale Factor On the basis of the previous information, the scale factor is used in the following equation: C C P P C = Cost estimate for the new plant C 0 = Historical cost for the plant in the database P = New Plant size P 0 = Historical plant size M = Scale factor (0.6 < M < 0.9) 0 0 M Ball Park Estimate Scale Factor /MWe Validity Zone MWe 5
6 ACCOUNT Direct costs Ball Park Estimate Scale Factor Example: Values for a Nuclear Power Plant Scale exponent Land and land rights 0 Structures and improvements 0.5 Reactor/boiler plant equipment 0.6 Turbine plant equipment 0.8 Electric plant equipment 0.4 Miscellaneous plant equipment 0.3 Main condenser heat rejection system 0.8 Indirect costs Construction services 0.45 Home office engineering and services 0.2 Field office engineering and services 0.4 Owner's costs 0.5 Ball Park Estimate Corrective Factors It is necessary considering also: Location Factor (LF): Per cent whole plant cost variation connected to the specific environmental conditions presents where the plat is build Escalation Factor (EF): index summarizing the temporal cost trend for the resource used to build the plant 6
7 Ball Park Estimate Corrective Factors Example 1 New plant (1986) Size: T/Y Location: Saudi Arabia Reference plant (1974) Size: T/Y Location: Italy Cost: 14 M (without draining purification plant) Scale Factor: 0.6 Escalation Factor: / = 4.22 Location factor: 2.3 / 2 = 1.15 Ball Park Estimate Corrective Factors Example 1 DESCRIPTION COST Plant build in the x 4.22= M Size reduction: Draining purification plant (estimate): 7 M 0.6 M Total plant cost build in Italy: = M Total p. c. build in Saudi Arabia: x 1,15 = M 7
8 Factorial Estimate It is used to: Estimate using the comparison of the different design choices Perform feasibility studies Estimate the stock in hand allocation (budget) It is based on the cost breakdown and considers: Analytic cost items estimate Other costs estimate by per cent factors Factorial Estimate Equipment Cost ( E ) Fb Bulk factor ( % of E) Materials Cost ( M ) Fc Construction factor (50-80% of M) Erected Cost ( M + L ) Fs Services factor (15-30 % of M + L) Total Base Cost ( BC ) Fk Markup factor (10-20 % of BC) Total Investment Cost ( TIC ) 8
9 Factorial Estimate The Mark up factor considers: Escalation Contingencies Overheads Financial costs Insurances Guarantees Taxes Exchanges Profits Analytic Estimate It is the cost estimate for each account in the breakdown cost: Engineering Materials Transport Construction Supervision + Mark up (in order to determinate the cost) 9
10 Analytic Estimate For each account it is necessary to point out the single resources allocated (quantity x unit cost) Labour Material Means of production Services Analytic Estimate - Design It consists in the accounts relative to the base and detail engineering. The project cost on the whole plant cost is a very variable component and depends on the plant type and size. 10
11 Analytic Estimate - Materials It is possible to distinguish: Items Bulk materials (piping, instrumentation, electrical material, metallic structures etc.) Various material (Spear parts, ) Analytic Estimate Transport It includes the following accounts: PACKING: like percentage of materials costs TRANSPORTS: special (unit price) normal ( /Kg) The local transportation could be very risky and difficult to evaluate: INSURANCE: percentage of the material and transport cost CUSTOMS AND PORT FEES 11
12 Analytic Estimate Construction It is the cost component with major uncertainty and evaluation risks, particularly for plants in foreign countries: Two, not alternative, ways are available: Market research through preliminary subcontractor proposal Internal evaluation through: o Standard Man Hours (SMh) o Effective Man Hours Estimated (EMh) Analytic Estimate Construction INTERNAL EVALUATION Q = Physical quantities SMh = Standard Man hour EMh = Effective Man hour Is based on the ideas of: Yield: Productivity: P Where: Y Q SMh SMh EMh 12
13 Analytic Estimate - Contingency It includes the major cost for: Project indeterminateness and incompleteness Costs uncertain grade Delays Forgetfulness and estimate s errors Unexpected and incidental facts etc. Analytic Estimate - Contingency It not includes great risk from: Socio-economical upheaval, wars and revolutions Geothermic surprises Legislations changes Supplier bankruptcy Failure to pay 13
14 OBJECTIVES Times Costs Quality WORK DESCRIPTION WBS, OBS, CBS Developments control RESOURCES ALLOCATION Planning ACTIVITIES SCHEDULING CPM, Gantt RESOURCES LEVELLING Series and parallel approach BUDGETING Costs, Cash Flow CORRECTIVE ACTIONS PERFORMANCE ANALYSIS AND ESTIMATES TOFINISH Times, Costs Control MONITORING AND REPORTING Variances Analysis Partial balance-sheet PROJECT REALIZATION OUTPUT 27 The Project control phase that is possible to separate in the two phases of: monitoring and reporting of the parameters necessary to the project control; estimate at completion for project costs and times. Two method for the system management: feedback method (difference between forecasted and obtained values) feed forward method (performance realized until the time now and hypothesis about future performance C/SCS) The performance analysis and the estimate at completion can be realized for: the whole project Each project WP 14
15 Steps: 1. Choose the calculation method 2. Choose the most suitable typology of performance index 3. Individualize the most suitable modality to estimate the previous index 1. Calculation method 1.1 Future performance index (portion of work that needs to be done) EAC ACWP c BAC BCWP c Indice di perf. futuro ACWP c BCWR c Indice di perf. futuro 1.2 Final index of performance for the whole project EAC Indice BAC di perf. globale 15
16 2. Typology of performance index 2.1 CPI = BCWP / ACWP (Cost Performance Index) Cost efficiency 2.2 SCI = SPI CPI (Schedule Cost Index) Where SPI = BCWP / BCWS Cost and scheduling efficiency 2.3 Weighted SCI = W1 SPI + W2 CPI (Weighted Schedule Cost Index) con W1 + W2 = 1 Cost and scheduling efficiency 3. Modality to estimate 3.1 extrapolation on the basis of the time now value for the considered index 3.2 extrapolation on the basis of the trend analysis for the considered index 3.1. It is possible to estimate the time now value for the considered index as: the actual period index value mean value of the index related to x most recent period index cumulated value 3.2 Future index of performance estimation is performed by the extrapolation (for example using regression techniques), on the basis of the index value trend. The index can be the CPIm type also in this case. 16
17 Therefore the EAC depend on: the calculation method (future index of performance or global index of performance); the typology of the index of performance selected (CPI, SCI o WSCI); the criterion adopted for its evaluation (extrapolation on the basis of actual values or the trend analysis); The modality of the index calculation (CPI m, CPI mmx and CPI c ). Applicative case: To consider a project with start date at November 97 and estimate finish date at October The initial Budget At Competition (BAC) is equal to 859 M. The time now is the end of June 1999 It is asked to evaluate 1. The time now situation compared with the situation forecasted at the project beginning 2. The (EAC) through the extrapolation on the basis of the actual values 3. The (EAC) through the extrapolation on the basis of the trend analysis 17
18 BCW Si ACW Pi BCW P BCW Sc ACW Pc BCW Pc CVi SVi CVc SVc i nov ,00 0,00 0,00 0,00 dic ,45 15, ,45 31,30-0,15-0,70-0,15-0,70 gen ,03 24, ,48 55,95 0,62-2,35 0,47-3,05 feb ,41 23, ,89 79,71-1,65-3,24-1,18-6,29 mar ,29 22, ,18 102,06-0,93-4,64-2,11-10,94 apr ,40 22, ,58 124,56-2,90-4,50-5,01-15,44 mag ,02 23, ,59 148,08-1,50-3,48-6,51-18,92 giu ,00 23, ,59 171,78-3,30-3,30-9,81-22,22 lug ,98 21, ,58 193,28-3,48-5,50-13,30-27,72 ago ,90 23, ,48 216,48-2,70-3,80-16,00-31,52 set ,00 22, ,48 239,18-2,30 1,70-18,30-29,82 ott ,10 19, ,58 258,18-2,10-2,00-20,40-31,82 nov ,47 19, ,05 277,33-4,32-1,85-24,72-33,67 dic ,80 19, ,85 296,73-1,40-1,60-26,12-35,27 gen ,20 19, ,05 316,53-3,40-22,20-29,52-57,47 feb ,77 24, ,82 340,53-6,77-6,00-36,29-63,47 mar ,80 37, ,62 377,83 2,50 7,30-33,79-56,17 apr ,00 27, ,62 405,43-1,40 4,60-35,19-51,57 mag ,30 27, ,92 433,36-1,37 4,93-36,56-46,64 giu ,57 21, ,48 454,96-2,97-1,40-39,52-48,04 lug ago set ott nov dic gen feb mar apr mag giu lug ago set ott Actual Situation [M ] Cost [M ] BCWSc ACWPc BCWPc 0 nov-97 may-98 nov-98 may-99 nov-99 may-00 Months 18
19 1. Actual Situation [M ] Cost [M ] BCWSi ACWPi BCWPi nov-97 may-98 nov-98 may-99 nov-99 may-00 Months Project performance at the time now CPI c SPI c SCI A e A p c BCWPc ACWPc BCWPc BCWSc CPI c BCWPc BAC BCWSc BAC SPI 454,13 494,48 454, c ,83 454, ,92 0,90 52,86% 58,56% CVc = BCWPc - ACWPc = -40,35 M SVc = BCWPc - BCWSc = -48,87 M 19
20 2. (EAC) on the basis of the actual situation BAC - BCWPc EAC = ACWPc + Future index of performanc e BCWRc = ACWPc + ACWPc ETC future CPI 2.1 CPI related to the most recent actual period (June 99): = EAC = ACWPc BAC - BCWPc + CPIm = = Most recent value for the CPI moving average related to 3 period (therefore centered on may 99) BCWPm 3 CPImm3 = 0.93 ACWPm EAC = ACWPc 3 BAC - BCWPc + CPImm3 = Cumulated CPI at the time now (June 99): CPIc BCWPc CPIc = ACWPc 0.92 BAC - BCWPc EAC = ACWPc + CPImm3 = = 935 =
21 Using as future index of performance the CPIc, the relation of linear projection can assume the following streamlined version EAC = ACWPc BAC - BCWPc + CPIc BCWPc ACWPc + BAC - BCWPc ACWPc CPIc ACWPc CPIc + BAC - BCWPc = = CPIc BAC = CPIc This consideration are based on the hypothesis that the CPIc at the project conclusion has the same actual value (value at the time now) 3. (EAC) through the extrapolation on the basis of the trend analysis The trend analysis allows to individualize a general tendency about the proceeding of a certain variable. Steps: 1. to identify the trend of the selected index; 2. future values forecast (monthly or moving average in the period from the time now to the end of the project) or the future value (cumulated of the end of the project) of the selected index 3. EAC calculation 21
22 Nov-97 Dec-97 Jan-98 Feb-98 Mar-98 Apr-98 May-98 Jun-98 Jul-98 Aug-98 Sep-98 Oct-98 Nov-98 Dec-98 Jan-99 Feb-99 Mar-99 Apr-99 May-99 Jun-99 CPIm 1 0,99 1,03 0,94 0,96 0,89 0,94 0,88 0,86 0,90 0,91 0,90 0,82 0,93 0,85 0,78 1,07 0,95 0,95 0,88 CPImm3 1,008 0,982 0,973 0,926 0,928 0,901 0,892 0,878 0,888 0,901 0,875 0,880 0,865 0,845 0,914 0,940 0,997 0,931 CPIc 1 0,995 1,008 0,985 0,980 0,961 0,958 0,946 0,936 0,931 0,920 0,927 0,918 0,919 0,915 0,904 0,918 0,920 0,922 0,920 1,10 1,05 CPIm 1,00 0,95 0,90 0,85 0,80 0,75 0,70 aug-97 nov-97 feb-98 Jun-98 sep-98 dec-98 mar-99 jul-99 22
23 1,1 1,05 CPImm3 1 0,95 0,9 0,85 0,8 0,75 0,7 aug-97 nov-97 feb-98 jun-98 sep-98 dec-98 mar-99 jul-99 23
24 Regression line b = n Y = a + b X X Y X Y 2 n X X 2 a = n Y b n X r 2 n X Y X Y X X n Y 2 n Y 2 Therefore there are two possibilities: a) to compute the monthly values b) to compute the cumulated value a) Monthly values 1,050 1,000 0,950 0,900 0,850 0,800 CPImm3 Line 0,750 dec-97 apr-98 aug-98 dec-98 apr-99 24
25 Observations: the work is late (compared to the forecasted schedule) costs for the future will be greater than how much is expected (related to the work not yet done) Steps: 1 SV BCWSi * i SVc ( Jun.99 ) Oct BCWSi Jul BCWRi = SVi + BCWSi Oct BCWRi = SVi * + Jul. 99 Oct Jul. 99 Oct Jul. 99 BCWSi 3 The obtained BCWR are divided in accordance to the corresponding CPIp-mm3 individualized with the regression line. In this way it is possible to obtain the real monthly cost foreseen (projected cost). Their sum represents the ETC (Estimate To Complete) value 4 The sum of ETC and ACWP (June 99) is the Estimate at Completion In this case: EAC = ACWPc(Jun 99) + ETC = = 961 M The EAC individualized value allows to individualize the foreseen CPIc for the whole project (Project Completion) CPIc(Project Completion) = BAC/EAC = 859/961 =
26 1,02 1 0,98 0,96 0,94 0,92 0,9 b) Cumulated value If the CPIc value is used CPIc (Y) 0,88 nov-97 mar-98 jul-98 nov-98 mar-99 jul-99 Line Regression line coefficients: a = b = -0,005 r 2 = CPIc = = 0.81 EAC = BAC/CPIc = 859 / 0.81 = 1060 M Variation of trend toward September 98 or November 98, that allows to exclude from the regression analysis the values before that period The regression line obtained without considering the first 10 months has the following coefficients. a = b = r 2 = In this case the CPIc final value is: CPIc = = EAC = BAC/CPIc = 859 / = 953 M 26
27 If it is necessary to obtain also in this case the PCIi monthly value is possible to compute ETC as: ETC = EAC AWCPc (Jun. 99) = = M And distributing it proportionally to the BCWR future values (as has been previously done for the SV) Consideration about the competition time SPI index expression EAC ACWP BAC BCWP CPI f BAC ACWP BAC ACWP EAC ACWP BAC ACWP CPI f BAC ACWP BAC BCWP ACWP BAC ACWP CPI f CPI O BC T BAC AC T SPI BAC f BCWP BCWS BC T T SPI SPI f O 27
28 Exercise: A project is started on June 99 and absolutely must be finished before the end of January 2000 (overall duration 18 months). The monthly data related to the past performances (first 11 months of the project execution), in K$, are summarized in the table. 3.1 To estimate the project competition total cost, justifying carefully eventual hypotheses and used methodology 3.2 To determine a plan showing how is possible to recover for the period July January
29 Month Aug-98 Sep-98 Oct-98 Nov-98 Dec-98 Jan-99 Feb-99 Mar-99 Apr-99 May-99 Jun-99 Jul-99 Aug-99 Sep-99 Oct-99 Nov-99 Dec-99 Jan-00 29
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationEarned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
More informationAT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More informationContract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget
Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge
More informationPROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
More informationThe work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
More informationEarned Value Management
Earned Value Management Program and Project Management Enablement April 2010 Contact: jjacobi@scottmadden.com cmlyons@scottmadden.com What is Earned Value Management and Why Do I Need It? Complex projects
More informationplans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
More informationAnalysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
More informationCase 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
More informationearned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
More informationCOINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
More informationL10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
More information700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
More informationEnhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
More informationCost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
More informationJAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
More informationPERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
More informationSoftware Project Scheduling. - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis
Software Project Scheduling - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis Eight Reasons for Late Software Delivery An unrealistic deadline established by someone
More informationProject Cost & Schedule Monitoring Process Using MS Excel & MS Project
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the
More informationPROJECT SCHEDULING AND TRACKING
PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort
More informationAshley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationEquipping your Forecasting Toolkit to Account for Ongoing Changes
Equipping your Forecasting Toolkit to Account for Ongoing Changes Presented by: Roger Parlett Supply Chain Manager January 23, 2014 Overview Forecast Set-up Objectives of Creating a Forecast Identify Critical
More informationAn introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
More informationProject Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
More informationAppendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
More informationBusiness Idea Development Product production Services. Development Project. Software project management
Page 1, 1/20/2003 Ivica Crnkovic Mälardalen University Department of Computer Engineering ivica.crnkovic@mdh.se Development Project Product Lifecycle Business Idea Development Product production Services
More informationBasic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and
More informationPOLICY FEEDING RENEWABLE. How the Energy Bill might affect green electricity suppliers and also renewable generators
FEEDING RENEWABLE POLICY How the Energy Bill might affect green electricity suppliers and also renewable generators Holly Tomlinson Regulation and Compliance Analyst for Ecotricity 18 th January 2013 Contents
More informationProject Cost Control: The Way it Works By R. Max Wideman
Project Cost Control: The Way it Works By R. Max Wideman 12/21/05 In a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how
More informationNATIONAL CREDIT UNION SHARE INSURANCE FUND
NATIONAL CREDIT UNION SHARE INSURANCE FUND PRELIMINARY & UNAUDITED FINANCIAL HIGHLIGHTS RENDELL L. JONES CHIEF FINANCIAL OFFICER MANAGEMENT OVERVIEW Balance Sheet Other - Insurance and Guarantee Program
More informationIT S ALL ABOUT THE CUSTOMER FORECASTING 101
IT S ALL ABOUT THE CUSTOMER FORECASTING 101 Ed White CPIM, CIRM, CSCP, CPF, LSSBB Chief Value Officer Jade Trillium Consulting April 01, 2015 Biography Ed White CPIM CIRM CSCP CPF LSSBB is the founder
More informationProject Execution - PM Elements
Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status
More informationPune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
More informationProject Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp.
Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Code for Course: MBL45-5 Assignment Number: 2 Student number: 75-163-3 Group Code Number: BOT1 Table of Contents
More informationTracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
More informationUnit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
More informationNeed to know finance
Need to know finance You can t hide from it Every decision has financial implications Estimating sales and cost of sales (aka direct costs) Gross Profit and Gross Profit Margin (GPM) Sales cost of sales
More informationBrainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
More informationProfesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
More informationAACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
More informationThe principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
More informationIntroduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
More informationConstruction Contracts
Compiled Accounting Standard AASB 111 Construction Contracts This compiled Standard applies to annual reporting periods beginning on or after 1 January 2009 that end on or after 30 June 2009. Early application
More informationDemand forecasting & Aggregate planning in a Supply chain. Session Speaker Prof.P.S.Satish
Demand forecasting & Aggregate planning in a Supply chain Session Speaker Prof.P.S.Satish 1 Introduction PEMP-EMM2506 Forecasting provides an estimate of future demand Factors that influence demand and
More informationEstimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
More informationCENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR
JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf
More informationEarned value method as a tool for project control
Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618
More informationTraining Pack. Key Performance Indicators - KPI s
Training Pack Key Indicators - KPI s Aims & Objectives Target Audience : Site Management to Team Leaders Purpose of Module :To ensure employees have the skills to quantify impact, and provide timely direction
More informationPROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
More informationCAFIS REPORT 2015.10
CAFIS REPORT 2015.10 INDEX Message CAFIS Inbound 03-06 07-08 CAFIS Arch 09-10 CAFIS Brain 11-12 CAFIS Global 13-14 What We Do 15-16 About CAFIS 17-18 Services for Member Stores 19-34 Services for Card
More informationPower generation assets valuation adopting a real options approach applied to the Colombian electricity market
Power generation assets valuation adopting a real options approach applied to the Colombian electricity market Simón Pérez-Arango Tutors: Gabriel Vizcaino-Sánchez (Celsia S.A.) Freddy Marín-Sánchez (EAFIT)
More informationChapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationStart Your. Business Business Plan
Start Your Waste Recycling Business A TECHNICAL STEP-BY-STEP-GUIDE OF HOW TO START A COMMUNITY-BASED WASTE RECYCLING BUSINESS Start Your Waste Recycling Business Business Plan INTERNATIONAL LABOUR OFFICE
More informationAdvanced ICT services for students
Centro InfoSapienza Roberto Messa Centro Infosapienza Integrated information system In 2009 La Sapienza started the development of an integrated information system. Pagina 2 Integrated information system
More informationS&OP Case Study Creating Value at O Neal Manufacturing Services. Anthony Zampello, CPIM, CIRM, CSCP Adjunct Faculty Bentley University
S&OP Case Study Creating Value at O Neal Manufacturing Services Anthony Zampello, CPIM, CIRM, CSCP Adjunct Faculty Bentley University Prepared by: Jamie Cochran, Strategic Business Applications Manager,
More informationMethodology For Illinois Electric Customers and Sales Forecasts: 2016-2025
Methodology For Illinois Electric Customers and Sales Forecasts: 2016-2025 In December 2014, an electric rate case was finalized in MEC s Illinois service territory. As a result of the implementation of
More informationSoftware Engineering. Pert and Gantt exercises. Lecturer: Giuseppe Santucci
Software Engineering Pert and Gantt exercises Lecturer: Giuseppe Santucci Degree of freedom! I.3a 3 3 I. I. 3 I.3b I.3c I.4 Exercise s goals. Draw a PERT network (AON) representing a project s characteristics.
More informationProject Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
More informationMEASURES FOR EXCELLENCE Getting a "RUNAWAY" Software Development. Under Control. A Case Study
MEASURES FOR EXCELLENCE Getting a "RUNAWAY" Software Development Under Control A Case Study.J.W.E Greene QUANTITATIVE SOFTWARE MANAGEMENT LTD 7 rue Fenoux 93 Blythe Road, Paris 71 London W1 OHP Tel: 33-1-311
More informationEarned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
More informationP/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014
2014-2015 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2014 TERM Key: P/T = Part of Term P/T Description
More informationEVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
More informationP/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013
2013-2014 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2013 TERM Key: P/T = Part of Term P/T Description
More informationIndustry Environment and Concepts for Forecasting 1
Table of Contents Industry Environment and Concepts for Forecasting 1 Forecasting Methods Overview...2 Multilevel Forecasting...3 Demand Forecasting...4 Integrating Information...5 Simplifying the Forecast...6
More informationProject Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
More informationP/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015
2015-2016 SPECIAL TERM ACADEMIC CALENDAR For Scranton Education Online (SEOL), Masters of Business Administration Online, Masters of Accountancy Online, Health Administration Online, Health Informatics
More informationEXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
More informationInsurance and Banking Subcommittee
Insurance and Banking Subcommittee Citizens Depopulation Update September 16, 2015 Christine Ashburn VP Communications, Legislative and External Affairs 2 3 Depopulation Customer Communications 1. 40 days
More informationBUSINESS LOAN APPLICATION
BUSINESS LOAN APPLICATION Superior National Bank & Trust Company 235 Quincy Street, P.O. Box 450 Hancock, MI 49930 phone 906.482.0404 toll-free 1.866.482.0404 1 INTRODUCTION Thank you for considering Superior
More informationQ1 2010 Results Analyst Presentation Henk van Dalen, CFO 3 May 2010
Q1 2010 Results Analyst Presentation Henk van Dalen, CFO 3 May 2010 Overall trading conditions continue to improve GROUP Operating income 251 million ( 163 million in Q1 20); quarter benefited from four
More informationA Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
More informationEARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
More information10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
More informationEarned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
More information2016 Examina on dates
Please note the following informa on: The following exams are available throughout the year: Please click on the exam for which you wish to see the dates. When you have finished, you can select to return
More informationSimple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
More information2015 Examination dates
Please note the following information: The following exams are available throughout the year: BULATS Paper-based: Please click on the exam for which you wish to see the dates. When you have finished, you
More informationHow To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
More information300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
More informationGrain Stocks Estimates: Can Anything Explain the Market Surprises of Recent Years? Scott H. Irwin
Grain Stocks Estimates: Can Anything Explain the Market Surprises of Recent Years? Scott H. Irwin http://nationalhogfarmer.com/weekly-preview/1004-corn-controversies-hog-market http://online.wsj.com/news/articles/sb10001424052970203752604576641561657796544
More informationFixed Income 2015 Update. Kathy Jones, Senior Vice President Chief Fixed Income Strategist, Schwab Center for Financial Research
Fixed Income 2015 Update Kathy Jones, Senior Vice President Chief Fixed Income Strategist, Schwab Center for Financial Research 1 Fed: Slow and Low 2015 Fixed Income Outlook 2 Yield Curve Flattening 3
More informationLecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
More informationComputing & Telecommunications Services Monthly Report March 2015
March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Last Modified
More informationQi Liu Rutgers Business School ISACA New York 2013
Qi Liu Rutgers Business School ISACA New York 2013 1 What is Audit Analytics The use of data analysis technology in Auditing. Audit analytics is the process of identifying, gathering, validating, analyzing,
More informationEARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
More informationII. Measuring and Analyzing GDP
A Macroeconomic Perspective on the Real Sector: Growth, Economic Fluctuations and Inflation Workshop for Staff of Ministry of National Planning and Economic Development Nay Pyi Taw, Myanmar June 2 3, 2014
More informationWorking Capital and the Financing Decision C H A P T E R S I X
Working Capital and the Financing Decision C H A P T E R S I X Limited 2000 Figure 6-1a The nature of asset growth A. Stage I: Limited or no Growth PPT 6-1 Dollars Temporary current assets Capital assets
More informationLeSueur, Jeff. Marketing Automation: Practical Steps to More Effective Direct Marketing. Copyright 2007, SAS Institute Inc., Cary, North Carolina,
Preface. Overview. PART 1: Marketing Financials. Chapter 1 Profit and Loss Fundamentals. Chapter 2 Profit and Loss Component Details. Chapter 3 Managing the P&L. Chapter 4 Measuring Marketing Effectiveness.
More informationIST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
More informationMC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A
MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A 1) What is a project? 2) What is software project management? 3) What are the characteristics of a project? 4) What is the different software projects and
More informationCoffee year 2014/15 ends with prices at 20-month low
Coffee year 2014/15 ends with prices at 20-month low The coffee market slumped further in September, following a slight rally in August, with the weakness of the real and peso again proving the most influential
More informationRELIABILITY OF ELECTRIC POWER GENERATION IN POWER SYSTEMS WITH THERMAL AND WIND POWER PLANTS
Oil Shale, 27, Vol. 24, No. 2 Special ISSN 28-189X pp. 197 28 27 Estonian Academy Publishers RELIABILITY OF ELECTRIC POWER GENERATION IN POWER SYSTEMS WITH THERMAL AND WIND POWER PLANTS M. VALDMA, M. KEEL,
More informationExample of a diesel fuel hedge using recent historical prices
Example of a diesel fuel hedge using recent historical prices Firm A expects to consume 5,, litres of diesel fuel over the next 12 months. Fuel represents a large expense for the firm, and volatile prices
More informationEarned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
More information