Software Engineering. Pert and Gantt exercises. Lecturer: Giuseppe Santucci
|
|
- Charlene Blair
- 8 years ago
- Views:
Transcription
1 Software Engineering Pert and Gantt exercises Lecturer: Giuseppe Santucci
2 Degree of freedom! I.3a 3 3 I. I. 3 I.3b I.3c I.4
3 Exercise s goals. Draw a PERT network (AON) representing a project s characteristics. Compute earliest/latest time of start (tmin/tmax) and earliest/latest time of finish (tmin_c/tmax_c) for each activity 3. Compute Critical Path(s) 4. Draw the Gantt diagram for the project 3
4 Project s characteristics A project has activities, they are referred to by the letters A, B,..., L Between such activities the following dependencies hold: A, L < C (C cannot start before A and L are complete) C < B B, E, H < D D, G, I < F L < G Each activity is estimated to last t(x), that we consider fixed for the sake of simplicity. Time unit of measure is week Duration of activities is as follows A B C D E F G H I L 39 4
5 Goal : draw the PERT network. Nodes: a) An activity is represented by a node b) There are two special nodes: s and t, meaning start and end of the project, respectively (source, target). Arcs: a) A precedence relationship is represented by a directed arc b) There is an arc from node s to every starting node (identified at point ) c) There is an arc from every dead-end node (identified at point ) to node t 5
6 3. Labels: Goal : draw the PERT network a) Each node X is labeled with its duration t(x) b) Nodes s and t are labeled with (their duration is conventionally )
7 Goal : draw the PERT network L G s A H E C B D F A,L<C t I 39 7
8 Goal : min and max times -- Definitions Minimum time for starting activity A (tmin(a) ): minimum time within is possible to finish all needed activities to start A Minimum time for finishing the project: tmin (t) Maximum time for starting activity A (tmax(a) ): maximum time within it is mandatory to finish all needed activities to start A in order to not delay the whole project
9 Goal : Computing tmin Algorithm for computing tmin Pre-condition: acyclic network tmin(s) = ;. Take a node Y such that tmin(z i ) have been computed, with Z i predecessors of Y. tmin(y) = max [tmin(z i ) + t(z i )]; // t(z i ) is duration of Z 3. if Y!= t go to step ; 4. end 9
10 s L A H E I Goal : Computing tmin 39 C B D G F Z = set of predecessors of Y tmin(y) = max [tmin(z i ) + t(z i )] t
11 s L A H E I Goal : Computing tmin 39 C B D G F Z = set of predecessors of Y tmin(y) = max [tmin(z i ) + t(z i )] t
12 s L A H E I Goal : Computing tmin 39 C 7 B D G F Z = set of predecessors of Y tmin(y) = max [tmin(z i ) + t(z i )] t
13 s L A H E I Goal : Computing tmin 39 C 7 B D G F Z = set of predecessors of Y tmin(y) = max [tmin(z i ) + t(z i )] t
14 s L A H E I Goal : Computing tmin 39 C 7 B D G F 39 Z = set of predecessors of Y tmin(y) = max [tmin(z i ) + t(z i )] t 4
15 s L A H E I Goal : Computing tmin 39 C 7 B D G F 39 5 Z = set of predecessors of Y tmin(y) = max [tmin(z i ) + t(z i )] t 5
16 Goal : Computing tmax Algorithm for computing tmax Pre-condition: acyclic network. tmax(t) = tmin(t);. Take a node Y such that all tmax(z i ) have been computed, with Z successors of Y 3. tmax(y) = min[tmax(z i )] t(y); // t(y) is duration of Y 4. if Y!= s go to step ; 5. end
17 Goal : Computing tmax 4.. L A C 9 B 37 D G 5..5 s H E F 39 t 9 39 I Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y) 7
18 Goal : Computing tmax 4.. L A C 9 B 37 D G 5..5 s H E F t 9 39 I Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y)
19 Goal : Computing tmax.... L A C 7 B..37 D G 5..5 s H E F t 39 I.. Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y) 9
20 Goal : Computing tmax.... L A C 7..9 B..37 D G 5..5 s H.. E F t I.. Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y)
21 Goal : Computing tmax.... L A C B..37 D G 5..5 s H.. E F t I.. Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y)
22 Goal : Computing tmax L A.. C B..37 D G 5..5 s H.. E F t I.. Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y)
23 Goal : Computing tmax L A.. C B..37 D G 5..5 s H.. E F t I.. Z = set of successors of Y tmax(y) = min [tmax(z)] - t(y) 3
24 Goal 3: Critical path -- Definitions Critical activity: activity A such that tmin(a) = tmax(a) Critical path: s-t path compound of all critical activities Minimum time for completing activity A: tmin_c(a) = tmin(a) + t(a) Maximum time for completing activity A: tmax_c(a) = tmax(a) + t(a) 4
25 Goal 3: Critical Path Activity A B C D E F G H I L Duration 39 tmin 7 39 tmax tmin_c tmax_c I and F are critical activities s-i-f-t is the unique critical path 5
26 Goal 4: Gantt Chart Note: we can delay some activity e.g. C and E, that are not in a critical path x
27 Comments From a PERT network you can always draw a Gantt Chart By starting all activities at their tmin, or By starting activities consistently with their tmin and tmax (consistently means between tmin and tmax) From the same PERT network I can derive several Gantt Charts I cannot deduce a PERT network from a Gantt Chart 7
28 Additional issues Duration of activities is a statistical variable Some resources can be unavailable in certain time period
29 E is delayed so it s not in parallel with C Availability Constraints As a consequence D is delayed Example: it is not possible to perform activities C and E in parallel Possible solution: E is delayed and, consequently D 9
30 Availability Constraints We have to verify that Gantt changes did not violate any PERT precedence Note: several commercial tools allow for checking PERT and Gantt consistency 3
31 Exercise A simple software project has the following activities Requirement analysis, implies customer interview (A) and a questionnaire to be filled by old customers (B) Preparation of the questionnaire (C) Requirement analysis and conceptual design (D) Coding in Java (E) Test (F) The project starts at //. The team that will perform the test won t be available during July because involved in another project Durations of activities (in months) are as follows A B C D E F 3 3
32 Exercise s goals. Draw a PERT network (AON) representing project s characteristics. Compute earliest/latest time of start (tmin/tmax) for each activity 3. Compute Critical Path(s) 4. Draw the Gantt diagram for the project 5. Verify consistency between the PERT network, the Gantt Chart, and constraints. If needed, change the Gantt chart 3
33 Analysis From the description of the activities, it can be deduced that the process model applied is the waterfall model Requirement analysis activities can be conducted in parallel The other activities have to be performed in sequence as defined by the waterfall 33
34 Goal : Draw the PERT network s C A B D A customer interview C<B 3 B customer questionnaire B<D C questionnaire preparation A<D D req. analysis and conc. design D<E E coding E<F F test 34 E F t
35 Goal : compute tmin and tmax s.. C A.. B D E 5..5 F.. t
36 Goal 3: Critical Path Activity A B C D E F Duration 3 tmin 3 5 tmax 3 5 tmin_c 3 5 tmax_c 3 5 B, C, D, E and F are critical activities s-c-b-d-e-f-t is the only CP 3
37 Goal 4: Gantt Chart Jan Feb Mar Apr May Jun Jul Aug A X We delay activity A B C X X D X E X X F X X X 37
38 Goal 5: Consistency The Gantt chart is not considering the unavailability of the testing team By modifying the Gantt Chart based on tmin/tmax we cannot comply to such constraint We have to suspend activity F (Test) in July, meaning that it will finish in September 3
39 Goal 5: Change the Gantt GEN FEB MAR APR MAG GIU LUG AGO SET A B X X C X D X E X X F X X X 39
The work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
More information2.3.4 Project planning
.. Project planning project consists of a set of m activities with their duration: activity i has duration d i, i =,..., m. estimate Some pairs of activities are subject to a precedence constraint: i j
More informationProject Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
More information2.3.5 Project planning
efinitions:..5 Project planning project consists of a set of m activities with their duration: activity i has duration d i, i = 1,..., m. estimate Some pairs of activities are subject to a precedence constraint:
More informationChapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
More informationProject Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
More informationScheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
More informationProject Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp.
Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Code for Course: MBL45-5 Assignment Number: 2 Student number: 75-163-3 Group Code Number: BOT1 Table of Contents
More informationProject and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
More informationAT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More informationGoals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
More informationTime Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
More informationBasic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and
More informationImportance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationMECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework
More informationTime Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.
Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation
More informationME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
More informationProject Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
More informationCambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationPROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
More informationGuidance on Critical Path Analysis
Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain
More informationThe principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
More information5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
More informationModule 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
More informationApplication Survey Paper
Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring
More informationProject Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
More informationUse project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
More informationCase 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
More informationAnalysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
More informationChapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
More information8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
More informationBasic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
More informationPROJECT PROPOSAL: PROJECT BLUE ZUMA
PROJECT PROPOSAL: PROJECT BLUE ZUMA To: From: CC: Dr. Edward J Glantz Alex Bok (ayb5041@psu.edu) Mark Randall Date: February 28 th, 2008 The following documents are detailed reports on our project proposal
More informationEnhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
More informationPrecedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationOperational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
More informationEarned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
More informationChapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
More informationAshley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
More informationIntroduction to Project Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project
More informationPercorso di Eccellenza in PROJECT MANAGEMENT. Cost estimating and estimate to completion. Ing. Locatelli Giorgio. Giorgio.locatelli@polimi.
Cost estimating and estimate to completion Ing. Locatelli Giorgio Giorgio.locatelli@polimi.it 0223394096 1 Cost Estimating The project s costs management evolves during the whole project life cycle and
More informationProject Scheduling by Critical Path Method (CPM)
12.1 Project Scheduling by Critical Path Method (CPM) Katta G. Murty Lecture slides CPM is application of DP to problems in Construction (project) Management. Many large construction projects going on
More informationPriori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
More informationCRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
More informationScheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
More informationB. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9
Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in
More informationLECTURE 5: SOFTWARE PROJECT MANAGEMENT. Software Engineering Mike Wooldridge
LECTURE 5: SOFTWARE PROJECT MANAGEMENT Mike Wooldridge 1 Introduction The software crisis of the 1960s and 1970s was so called because of a string of high profile software project failures: over budget,
More informationTIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
More informationProject Scheduling and Gantt Charts
Project Scheduling and Gantt Charts Siddharth Gangadhar Dr. Prasad Kulkarni Department of Electrical Engineering & Computer Science Lab Presentation siddharth@ku.edu prasadk@ku.edu 4 November 2015 2015
More informationMicrosoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
More informationtechnical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
More informationSE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
More informationNetwork Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
More informationChapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
More informationSession 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza
Session 6 Microsoft Project Emanuele Della Valle http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Credits 2 This slides are largely based on CEFRIEL s slides for PMI Certification and Prof.
More informationInformation Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
More information763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
More informationCSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
More informationChapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
More informationBPEL disadvantage: more time to product BPEL advantage: better reusability, analysis
Modeling Page 1 To BPEL or not to BPEL? 5:56 PM To BPEL or not to BPEL? BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis Modeling Page 2 A tale of two strategies 5:57
More informationLecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
More informationSystems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
More informationChapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
More informationTest Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
More informationProject Cost & Schedule Monitoring Process Using MS Excel & MS Project
Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the
More informationCritical Path Analysis & PERT Charts (taken from www.business.com.
Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage
More informationProject plan: document used to keep the project under control.
Planning and Scheduling: Basic tools & expectations for the SrD Project [References: The Mechanical Design Process, Ullman, 2003] and Product Design and Development, Ulrich and Eppinger, 2000] Project
More informationPROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
More informationIntroduction to Project Management ECE 480. Erik Goodman
Introduction to Project Management ECE 480 Erik Goodman What is Project Management? a method for organizing tasks a structured framework to help a group work productively tools to aid in task sequencing,
More informationA Computer Application for Scheduling in MS Project
Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and
More informationGraphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover
Introduction/Purpose Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover The purpose of this brief tutorial is to present an
More informationA STUDY OF TASK SCHEDULING IN MULTIPROCESSOR ENVIROMENT Ranjit Rajak 1, C.P.Katti 2, Nidhi Rajak 3
A STUDY OF TASK SCHEDULING IN MULTIPROCESSOR ENVIROMENT Ranjit Rajak 1, C.P.Katti, Nidhi Rajak 1 Department of Computer Science & Applications, Dr.H.S.Gour Central University, Sagar, India, ranjit.jnu@gmail.com
More informationActivity Networks And Gantt Charts
Activity Networks And Gantt Charts (Session 3 in the Project Planning And Management Module) Russ Pimmel Electrical and Computer Engineering University of Alabama October, 2001 The development of this
More informationProject Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
More information2016 Examina on dates
Please note the following informa on: The following exams are available throughout the year: Please click on the exam for which you wish to see the dates. When you have finished, you can select to return
More informationSoftware Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics
Software Application: Information System Elements Project Scheduling Basics Working With Resources Fine Tuning the Project Managing the Project Project Presentations Project Management in Information Technology
More informationTest Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
More informationPROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
More informationBusiness Idea Development Product production Services. Development Project. Software project management
Page 1, 1/20/2003 Ivica Crnkovic Mälardalen University Department of Computer Engineering ivica.crnkovic@mdh.se Development Project Product Lifecycle Business Idea Development Product production Services
More information2015 Examination dates
Please note the following information: The following exams are available throughout the year: BULATS Paper-based: Please click on the exam for which you wish to see the dates. When you have finished, you
More informationMSc Project Planning
MSc Project Planning Dr Paul Brunn 4 th February 2009 Project Planning and Control Intro to General Methods Some simple examples How to plan and complete an MSc Dissertation project EPS Graduate Education
More informationLeSueur, Jeff. Marketing Automation: Practical Steps to More Effective Direct Marketing. Copyright 2007, SAS Institute Inc., Cary, North Carolina,
Preface. Overview. PART 1: Marketing Financials. Chapter 1 Profit and Loss Fundamentals. Chapter 2 Profit and Loss Component Details. Chapter 3 Managing the P&L. Chapter 4 Measuring Marketing Effectiveness.
More informationpm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationChapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationAppendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
More informationModule 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
More informationResearch on Task Planning Based on Activity Period in Manufacturing Grid
Research on Task Planning Based on Activity Period in Manufacturing Grid He Yu an, Yu Tao, Hu Da chao Abstract In manufacturing grid (MG), activities of the manufacturing task need to be planed after the
More informationNetwork Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
More informationEXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
More informationChapter 3 Managing the Information Systems (IS) Project
Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project
More informationSYSM 6304: Risk and Decision Analysis Lecture 5: Methods of Risk Analysis
SYSM 6304: Risk and Decision Analysis Lecture 5: Methods of Risk Analysis M. Vidyasagar Cecil & Ida Green Chair The University of Texas at Dallas Email: M.Vidyasagar@utdallas.edu October 17, 2015 Outline
More informationwww.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP
PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with
More informationPERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
More informationThe management of the projects with MS Project
The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist
More informationPearson Education Limited 2003
156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule
More information2.8 An application of Dynamic Programming to machine renewal
ex-.6-. Foundations of Operations Research Prof. E. Amaldi.6 Shortest paths with nonnegative costs Given the following graph, find a set of shortest paths from node to all the other nodes, using Dijkstra
More information