Earned Value Management
|
|
- Cornelius Wells
- 8 years ago
- Views:
Transcription
1 Earned Value Management Program and Project Management Enablement April 2010 Contact:
2 What is Earned Value Management and Why Do I Need It? Complex projects have a need for accurate and consistent status information 70% of large projects are over budget and behind schedule 1 50% of all projects finish at 190% of their initial budget 1 And some, after huge investments of time and money, are simply never complete 1 EVA compares the PLANNED amount of work with what has actually been COMPLETED to determine if COST, SCHEDULE, and WORK ACCOMPLISHED are progressing as planned Work is earned or credited as it is completed Earned Value Management (EVM) is needed because There are different measures of progress for different types of tasks There is a need to roll up progress of many tasks into an overall project status There is a requirement for a uniform unit of measure (dollars or work-hours) Additionally, EVM provides an early warning signal for prompt corrective action Earned Value Management is required for ARRA projects and DOE Grants, but is also a premium project management tool in its own right ScottMadden has built, managed, and evaluated Earned Value systems on behalf of our clients with projects as large as $250 million in value Note 1: The Standish Group 1
3 Why is Earned Value Different? Integrated project performance is determined by the three parameters displayed in the Performance Triangle below All three dimensions of project performance must be monitored and controlled to ensure that all project deliverables are attained Scope Cost/Resources Schedule Traditional project management often reverts to pick any two; EVM is a way to look at all three simultaneously, a true measure of project effectiveness 2
4 Earned Value Basics Earned Value Management (EVM) is a systematic approach to the integration and measurement of cost, schedule, and technical (scope) accomplishments on a project or task In comparing Earned Value Management to Traditional Management, Traditional Management does not allow for analysis of the physical amount of work performed. Earned Value Management allows for both schedule and cost analysis against physical amount of work performed The inputs required for an EVM system include: Work Breakdown Structure (WBS) Organizational Breakdown Structure (OBS) Project schedule Time-phased baseline budget Cost/resource control plan Change control plan WBS/OBS Project Schedule Resource Planning Define/Assign Schedule/Budget Establish Baseline Accounting System $$$ The Earned Value Management system includes: Earned Value (EV) Actual Cost (AC) Metrics and performance measurements Forecasting Integrated baseline review Earned Value Management system Performance Measurement Early Warning & Detection Informed Management Decisions Corrective Actions Recovering Planning The outputs required for an EVM system include: Reporting requirements Proper analysis of reports Correct action taken 3
5 Earned Value is a National Standard Earned Value Management (EVM) has become an ANSI standard primarily driven by PMI (Project Management Institute) sponsorship since the 1990 s, and is prominently included in PMBOK EVM is a system that manages project cost and schedule performance measurements as integrated elements and not as separate entities EVM is a primary element of the all government sponsored projects, but is also utilized by major construction companies, nuclear organizations, and some fossil organizations EVM is essentially based on three basic metrics: Budgeted Cost of Work Scheduled BCWS How much work (in terms of both time and money) is planned for the project? Actual Cost of Work Performed ACWP How much did that same work actually cost (labor, materials, etc.) to perform? Budgeted Cost of Work Performed (or Earned Value) BCWP (or EV) What was/is the value of the work that was/is planned for a given time period in the project schedule? The BCWS can be depicted as an S curve with cost on the vertical axis and schedule (time) on the horizontal axis The BCWP is the % task complete multiplied by the task s total project budget (BAC or Budget at Completion) The ACWP (actual cost incurred) will be reported from the company financial system at a total project level Earned Value is the standard for all federal projects including all stimulus work, and is an industry standard used by large construction EPC contract management firms 4
6 Earned Value Starts With the WBS and OBS The Work Breakdown Structure (WBS) is a tool that defines a project and groups the project s discrete work elements in a way that helps organize and define the total work scope of the project WBS provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Additionally the WBS is a dynamic tool and can be revised and updated as needed by the project manager WBS WBS = Work Breakdown Structure OBS = Organization Breakdown Structure Control Accounts (CA), where work scope, schedule and cost are planned and managed OBS The Organization Breakdown Structure (OBS) indicates the organizational relationships and is used as the framework for assigning work responsibilities The OBS is structured by Responsible Department and then by Performing Department at the lowest level. The Performing Department level is where the responsibility and resource needed to accomplish the project will be assigned Source: PMI 5
7 Calculating Earned Value Metrics There are a variety of useful metrics that can be generated within the EVM system all derived from the three basic measurements of BCWS, ACWP, and BCWP Metrics Basic BCWS = Budgeted Cost of Work Scheduled ACWP = Actual Cost of Work Performed BCWP (or EV) = Budgeted Cost of Work Performed or Earned Value BAC = Budget at Completion (total dollars budgeted for project) Variance CV (Cost Variance) = BCWP ACWP CV % (Cost Variance %) = (BCWP - ACWP) / BCWP SV (Schedule Variance) = BCWP - BCWS SV % (Schedule Variance %) = (BCWP BCWS) / BCWS Performance Indices CPI (Cost Performance Index) = BCWP / ACWP Is the work tracking above/below budget given the actual work completed to date? SPI (Schedule Performance Index) = BCWP / BCWS Is the work tracking above/below schedule given the actual work completed to date? Managing through a well-constructed Earned Value system will provide the ability for project managers to identify schedule and cost issues early enough to positively react 6
8 EVM Dashboard Displays From ScottMadden Toolkit Project-Level Summary Basic Metrics Status Metrics Summary (BCWP) Budgeted Cost of Work Performed (BCWS) Budgeted Cost of Work Scheduled (ACWP) Actual Cost of Work Performed (BAC) Budget at Completion % Scheduled: (BCWSc/BAC) % Complete: (BCWPc/BAC) Proj X $0 $0 $0 $21,117, % 0.0% Variance Metrics Performance Indices Data Updated: xx/xx/xxxx Reporting Month: xx/xxxx (CV) Cost Variance: (SV) Schedule Variance: (CV %) Cost Variance %: (SV %) Schedule Variance %: (CPI) Cost Performance (SPI) Schedule Performance Index: (BCWP-ACWP) (BCWP-BCWS) (BCWP-ACWP/BCWP) (BCWP-BCWS/BCWS) Index: (BCWP/ACWP) (BCWP/BCWS) $0 $0 0.0% 0.0% $22,500,000 $20,000,000 $17,500,000, $15,000,000 $12,500,000 $10,000,000 $7,500,000 $5,000,000 $2,500,000 $- The Blue line is the BCWS 7
9 Earned Value Management Terminology EVMS BASIC COMPONENTS AC = actual cost = ACWP = actual cost of work performed EV = earned value = BCWP = budgeted cost for work performed PV = planned value = BCWS = budgeted cost for work scheduled BAC = cumulative PV = cumulative BCWS = budget at completion VARIANCES CV = EV - AC = BCWP - ACWP = cost variance SV = EV - PV = BCWP - BCWS = schedule variance CV% = (EV - AC)/EV = (BCWP - ACWP)/BCWP = cost variance, percentage SV% = (EV - PV)/PV = (BCWP -BCWS)/BCWS = schedule of variance, percentage VAC = BAC - EAC = variance at completion OVERALL STATUS % scheduled = PV cum /BAC = BCWS cum /BAC % complete = Ev cum /BAC = BCWP cum /BAC %b budget spent = AC cum /BAC = ACWP cum /BAC WR = BAC - EV cum = BAC - BCWP cum = work remaining BR = BAC - AC cum = BAC - ACWP cum = budget remaining PERFORMANCE INDICES CPI = EV/AC = BCWP/ACWP = cost performance index SPI = EV/PV = BCWP/BCWS = schedule performance index TCPIBAC = WR/BR = to complete performance index, BAC TCPIEAC = WR/ETC = to complete performance index, EAC
10 S Integrating EVM Into Other ScottMadden Project Management Tools Project Management Tools Overview Risk Map Low Value High Low Technological Architecture Project Documentation Resources Data Migration and Go-Live Resources Change Management Project Governance Change Management Data Migration and Go-Live Project Governance Interfaces Project Management Manageability Project Management Technological Architecture Application Legacy Systems Legacy Systems Application DOE PVMS (for stimulus projects) PROJECT PRGTnnnn Implementation REF. 1 / 24 MONTH MARZO 2001 PHASE PROTOTIPAZIONE MONTHLY STATUS REPORT PROJECT STATUS E stato definito il System Integrator. E' stato definito il Piano di progetto. E' stata impostata la proposta di Struttura Organizzativa di Progetto. E' stata impostata la baseline per i costi di Progetto Sono state attivate le Procedure di Gestione Scope Change Request, di Gestione Issue List e di Gestione della Documentazione. E' stato Definito il tool di gestione della documentazione di Progetto. E' stata impostata l'analisi del Rischio. High Interfaces Project Documentation OPEN ISSUES ACTIONS RESPONSILE DUE DATE 1 - L'Ambiente di Prototipazione non è disponibile. Predisporre ambiente prototipazione p IT Project Manager 06/04/01 / NEXT STEPS Ufficializzazione Struttura Organizzativa di progetto. Definizione dei componenti dei team da parte dei Responsabili/Referenti. Verifica profilo di spesa e budget Architettura Tecnologica. Impostazione attività di Quality Assurance. Dashboard F.G.P. PROJECTS DRIVING BOARD 30-Apr M ay-01 Tendency Tendency Status TIME COST (Euro) Open issues (previous) (actual) Project Manager Type Impact Baseline Baseline Forecast Budget Order Project Description Actual Forecast & Critical Points Start End End CMFR0027 PRGT00PB Powerbrain Sorrenti F M 1-Nov Aug Aug-01 26,550 26,085 26,550 CMEV0007 PRGT1572 Impl. Verrone Plant Serafino F M 15-Jan Sep Sep-01 82, ,633 CMSP0015 PRGT2982 HRMS new. Devel. Pukly F H 1-Jan Dec Dec , ,785 CMSP0015 PRGT3044 Web professional Pukly F M 15-Apr Dec Dec-01 71, ,975 CMSP0039 PRGT0017 Estesa Di Carlo O L 7-May Jun Jun-01 23, ,750 CMSP0015 PRGT3047 I.I.S. HR FGP Pukly F L 1-Jan Jul Jul-01 77, ,468 CMSP0028 PRGT0014 Engine Sperim. Appl. Brezigar O M 12-Apr Dec Dec , ,479 Legend Total 549,640 26, ,640 Type Compulsory (O) Impact High (H) Statust Critical Tendency Flat Firm (F) Medium (M) Medium Raising Opportunity (O) Low (L) On track Falling Integrated Cost and Progress (EVM) Baseline (Core) Baseline (Contingency) Actual Forecast CODE NAME TYPE ORDER XXX XXX Date 05/17/ PROJECT PRGTnnnn CODEImplementation NAME Compulsory Firm TYPE Opportunity ORDER XXX XXX Date 05/17/ PROJECT PRGTnnnn CODEImplementation NAME Compulsory Firm TYPE Opportunity Description: References Architecture ORDER XXX XXX Date 05/17/ Client: Operating System: Windows NT Client Legal Entity/Functions: PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity CODE IT Project Manager: NAME HW Platform: TYPE Description: References Architecture Server Compaq NT ORDER XXX IT Client Manager: XXX Data Base: Date 05/17/ Client: Operating System: Windows NT User Legal Entity/Functions: IT Application Manager: Client Legal Entity/Functions: PROJECT PRGTnnnn CODEImplementation IT Project Manager: NAME Compulsory Firm HW Platform: TYPE Opportunity Server Compaq NT Description: IT Architect: References Architecture ORDER XXX IT Client Manager: XXX Data Base: Client: Operating System: Date 05/17/2001 Windows NT User Legal Entity/Functions: IT Application Manager: Impact on other Client Projects/Applications Legal Entity/Functions: PROJECT PRGTnnnn Implementation Compulsory Firm Opportunity Description: IT Architect: Notes IT Project Manager: Operating HW Platform: References Costs Forecast Architecture Server Compaq NT 5000 IT Client Manager: Data Base: Operational: Client: Operating System: Windows NT User Legal Entity/Functions: IT Application Manager: Maintenance: Impact on other Client Projects/Applications Legal Description: Entity/Functions: Notes IT Project Manager: Operating HW Platform: Costs IT Architect: References Forecast Architecture Server Compaq NT IT Client Manager: Data Base: Operational: 0 Client: Operating System: Windows NT Milestones User Legal Entity/Functions: Costs (Euro) IT Application Manager: Maintenance: Issues Impact on other Client Projects/Applications Legal Entity/Functions: Notes IT Project Manager: Operating HW Platform: Costs Forecast Server Compaq NT Start 28-Feb-01 Initial Budget IT Architect: IT 40,949 Client Manager: Data Base: Operational: End (Baseline) Milestones User Legal 31-Mar-03 Entity/Functions: Actual Costs (Euro) IT 19,208 Application Manager: Open Issues Issues 10 Maintenance: End (Estimate Impact to date) on other Projects/Applications Start 31-Mar Feb-01 Total Cost Initial Forecast Budget IT 38,489 Architect: Notes Operating Costs Forecast 40,949 Operational: Expected End gap (Baseline) 0.00% 31-Mar-03 Expected Actual gap -6.01% 19,208 Closed Open Issues Issues 20 Milestones Costs (Euro) Issues 10 Maintenance: End (Estimate Impact to date) on other Projects/Applications Start 31-Mar-0328-Feb-01 Total Cost Initial Forecast Notes Operating Costs Forecast Budget 38,489 40,949 todayy actual Total Issues Operational: 30 Expected End gap (Baseline) 0.00% 00% M Expected At gap -6.01% 6 Closed Issues 20 Milestones 31-Mar-03 Actual Costs (Euro) 19,208 Open Issues 10 Maintenance: Issues 50% 100% 150% End (Estimate 200% to date) Start 31-Mar Feb-01 50% 100% Total 150% Cost Initial Forecast 200% Budget 38,489 % Open 40,949 Issues/Total Issues 33.33% today Total Issues 30 Expected actual End gap (Baseline) 0.00% Expected gap -6.01% Closed Issues 20 Milestones 31-Mar-03 Actual Costs (Euro) 19,208 Open Issues Issues 10 total 50% duration 100% forecast150% End (Estimate 200% to date) total 50% cost forecast Start 31-Mar-0328-Feb % Total 150% Cost Initial Forecast 200% Budget 38,489 % Open 40,949 Issues/Total Issues 33.33% today actual Total Issues 30 Expected End gap (Baseline) 0.00% 31-Mar-03 Expected Actual gap -6.01% 19,208 Closed Open Issues Issues total 50% duration 100% forecast150% End (Estimate 200% to date) 31-Mar-03 total 50% cost forecast 100% Total 150% Cost Forecast 200% 38,489 Overall Project Status Project Characteristics % Open Issues/Total Issues 33.33% today Best Practice Total Adherence Issues 30 Expected gap 0.00% actual Expected gap -6.01% Closed Issues 20 Costs Detail total duration forecast total cost forecast CRITICAL MEDIUM GOOD 50% 100% 150% 200% Impact: HIGH MEDIUM 50% LOW 100% 150% 200% Overall Project Status Project Characteristics 0 1 % Best Practice 2Open 3Issues/Total Adherence 4 Issues 33.33% today actual Total 30 Supplier: ORDER COMM NameComm BASELINE VS ACTUAL VS FORECAST F.G.P. total duration forecast total cost forecast CRITICAL MEDIUM GOOD 50% 100% 150% 200% 50% 100% 150% 200% Impact: HIGH MEDIUM LOW Overall Project Status Project Characteristics 0 1 Best % Practice 2Open 3Issues/Total Adherence 4 Issues 33.33% PROJECT PRGTnnnn Implementation Back to index Supplier: total duration forecast total cost forecast CRITICAL MEDIUM GOOD Impact: HIGH MEDIUM LOW Overall Project Status Project Characteristics 0 1 Best Practice 2 3Adherence 4 Supplier: COST (Euro) CRITICAL MEDIUM GOOD Impact: HIGH MEDIUM LOW Overall Project Status Project Characteristics 0 1 Best Practice 2 3Adherence 4 Supplier: Cost Type Cost Element Baseline Actual Forecast Notes CRITICAL MEDIUM GOOD Impact: HIGH MEDIUM LOW Supplier: Development & Implementation 18,550 2,434 18,550 External Resources Operational/Applicational li l Mngt , ,783 3,783 Total System Development 22,333 6,217 22,333 Schedule HW/SW Design & Consultancy 1,572 1,572 1,572 HW/SW Acquisition 6,500 6,500 6,500 I costi relativi all'architettura tecnologica saranno dettagliati al termine SW Licences 3,145 3,145 3,145 della fase di definizione dei requisiti Total HW/SW Mgnt 11,217 11,217 11,217 Project Scorecard (each project and a roll-up) System Dev velopment HW/SW Management Gen 01 Feb 01 Mar 01 Apr 01 Mag 01 Giu 01 Lug 01 Ago 01 Set 01 Ott 01 Nov 01 Dic 01 Gen 02 Feb 02 Mar 02 Apr 02 Mag 02 Giu 02 Lug 02 Ago 02 Set 02 Ott 02 Nov 02 Dic 02 Gen 03 Feb 03 Mar 03 Total External Costs 33,550 17,434 33,550 APPROVED CHANGE REQUESTS Nr. Description Approval Allocated Date Contingency Total Internal Resources 4,564 1,674 4,564 Partial Project Total 38,114 19,108 38,114 Contingency 2, Sono state attivate 3 Scope Change Request Overall Project Total 40,949 19,208 38,489 9
11 Jere (Jake) Jacobi Sustainability Practice Leader ScottMadden, Inc Piedmont Rd, Bldg 10 Cristin M. Lyons Partner ScottMadden, Inc Glenwood Ave Suite 805 Suite 480 Atlanta, GA Raleigh, NC Phone: Phone: Mobile: Mobile:
TeamSTEPPS. Evolving The Culture of Safety Through Teamwork. Strategies and Tools to Enhance Performance and Patient Safety
TeamSTEPPS Strategies and Tools to Enhance Performance and Patient Safety Evolving The Culture of Safety Through Teamwork New York State Dept of Health Patient Safety Conference May 21-22, 2007 Heidi King,
More informationINSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
More informationPROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
More informationAn introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
More informationPercorso di Eccellenza in PROJECT MANAGEMENT. Cost estimating and estimate to completion. Ing. Locatelli Giorgio. Giorgio.locatelli@polimi.
Cost estimating and estimate to completion Ing. Locatelli Giorgio Giorgio.locatelli@polimi.it 0223394096 1 Cost Estimating The project s costs management evolves during the whole project life cycle and
More informationPredicting progress on your project
www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
More informationCOINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
More information700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
More informationIntroduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
More informationAACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
More informationEarned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
More informationEarned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
More informationPune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
More informationSimple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
More informationAppendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
More informationEarned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
More informationEarned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
More informationBrainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
More informationEarned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
More informationEarned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
More informationFERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
More informationEARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
More informationRules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use
More informationEarned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
More informationHow To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
More informationEarned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
More informationIST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
More informationEARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
More informationplans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
More informationL10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
More informationLecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
More informationChapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:
More informationearned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
More informationMTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)
MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned
More informationEstimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
More informationProject Execution - PM Elements
Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status
More informationThis EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
More informationEVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
More informationA Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
More informationChapter 7: Project Cost Management. Munawar moenawar@gmail.com
Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
More informationIntegration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
More informationUsing Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
More informationProject Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
More informationCLARITY PPM TIPS, TRICKS, and TERMINOLOGY
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...
More informationProject Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
More informationCost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
More informationAssessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
More informationIQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au
More informationJAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
More informationProject Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
More informationSoftware Project Scheduling. - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis
Software Project Scheduling - Introduction - Project scheduling - Task network - Timeline chart - Earned value analysis Eight Reasons for Late Software Delivery An unrealistic deadline established by someone
More informationAT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More information10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
More informationUnit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
More informationProject Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
More informationPERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
More informationEarned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
More informationEarned Value Management System Description
LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS
More informationCreate Stoplight charts using Milestones Professional
Stoplight Charts: Ideal for At-a-Glance Project Reporting Create Stoplight charts using Milestones Professional In a report which has extensive data, how can action items be quickly highlighted and addressed?
More informationInformation Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
More informationProject Cost Management
Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
More informationBrief Introduction to Earned Value Management (EVM)
Brief Introduction to Earned Value Management (EVM) 12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing
More informationAppendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
More informationEarned Value Management Best Practices
Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November
More informationTHE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
More informationProject Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationPROJECT SCHEDULING AND TRACKING
PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort
More informationPM in construction industry
PM in construction industry Construction 2. Lepel BME Department of Construction Technology and Management 19-03-2014 PM in general Project integration Project plan development Project plan execution Integrated
More informationManaging Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
More informationEarned Value Management Best Practices
WHITE PAPER Earned Value Management Best Practices Contents Best Practices for EVMS Use...1 Use an EVMS Description and Keep it Up to Date...1 Use EVMS on Every Project...2 When to Use EVMS on a Program...3
More informationAgile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
More informationForecasting Project Schedule Completion by Using Earned Value Metrics
Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems svv@fabricom.be 1 Agenda Introduction Schedule performance indicators
More informationEarned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
More informationBEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationChapter 3: Project Cost Management
Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different
More informationEarned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
More informationEarned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
More informationApplication of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study
2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian
More informationContract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget
Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge
More informationpm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationTracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
More informationProject Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 -
Jefferson Science Associates, LLC 600 Progress Status Project Control System Manual Revision 7-44 - 600 Progress Status This chapter of the JSA Project Control System Manual explains how the status of
More information300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
More informationEssential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
More informationTraining Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
More informationProject Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
More informationBasic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and
More informationThe Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
More informationEarned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,
More informationCVR/IT Consulting LLC
2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com info@cvr-it.com Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value
More informationProject Management Institute (PMBOK 2000) PMP Preparation Worksheet
Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning
More informationPrinciples of Project Management
IPM 2012 Conference Principles of Project Management David Radkovich, PMP, EVP Subsystem Technologies david.g.radkovich.ctr@mail.mil Karen Jordan, PMP Subsystem Technologies karen.f.jordan.ctr@mail.mil
More informationAssignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
More informationProcurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
More informationIncentivising project performance in the construction of new facilities Utilising the earned value-based method
The current issue and full text archive of this journal is available at www.emeraldinsight.com/1472-5967.htm PRACTICE BRIEFING in the construction of new facilities Utilising the earned value-based method
More informationProfesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
More information