How project management software can smooth the way

Size: px
Start display at page:

Download "How project management software can smooth the way"

Transcription

1 How project management software can smooth the way By Michael V. Brown New Standard Institute The most demanding call on maintenance resources comes when a plant or facility is shut down for an extended period of time for scheduled maintenance. Usually a large complement of work must be scheduled into a relatively short period of time. Work schedules may have to be modified. Special equipment may have to be rented. Contractors may have to be hired to fill additional labor requirements and special needs. The scheduled down period is called different names by different industries. Whether it's called a shutdown, shutin, down-turn, turnaround, or outage, it can be the time when the maintenance department shines, or reveals its functional failings. This is the reason some maintenance managers dread these down periods. All eyes are focused on the work they do. Scheduled shutdowns, however, can provide unique opportunities to a maintenance department not normally available during standard operation or even during short shutdown periods. Lost capacity can be restored to an overtaxed facility during an extended shutdown. Major equipment overhauls can be performed to help prevent future unscheduled shutdowns. Government mandated inspections and repairs can be accomplished during a shutdown, bringing a plant into better compliance. Critical Path Method Although historically applied to engineering and construction work, the process of project management is easily adaptable to a maintenance shutdown. One tool used extensively in project management is the critical path method (CPM). CPM was developed in the 1950s by U.S. government contractors to speed the construction of the first nuclear powered submarine, the Nautilus. Over 3,000 contractor and subcontractor companies had to be coordinated to develop the submarine. Traditionally, a Gantt chart (or bar chart, as it was commonly called) was used to lay out the tasks to be performed on a timeline. Each bar represented a task and its length represented the elapsed time required to complete the task. Gantt charts failed to meet the needs of very large projects because they did not clearly show the interdependency between different tasks. The critical path method takes the interdependency of jobs into account. In a common shutdown, some jobs must follow other jobs, some jobs must precede other jobs, and some jobs can be performed concurrently with other jobs. Although it may at first seem difficult to determine all these relationships for each job in a shutdown, the task can be greatly simplified by asking one question of each job. That question is, "Which activity or activities must immediately precede this activity" The result of this exercise will reveal the true relationship of all jobs in the shutdown.

2 Assume you have the following list of jobs: Activity Duration Precedent A Shut down and cool down boiler 24 hrs - B Inspect refractory 4 hrs C C Open manways and clean boiler 4 hrs A D Replace bad tubes 8 hrs C E Perform hydrostatic test on boiler tubes 6 hrs D F Repair damaged refractory 16 hrs B G Close manways 1 Hr E, F H Fire up boiler 1 hr G The precedent question was asked of all the activities in the list to identify the corresponding precedent activities. This questioning process is referred to as determining the precedent logic. These activities can be tied together graphically as shown below. A C B F G H Shut down & cool down boiler Open manways & clean boiler Inspect refractory Repair damaged refractory Close manways Fire up boiler D Replace bad tubes E Hydrostatic test on boiler tubes The resultant diagram is called a logic network or a PERT (Project Evaluation and Review Technique) diagram. This diagram not only shows the relationship activities have with preceding activities, but also the succeeding and concurrent activities. It should be noted that this was all accomplished by determining the precedent logic only. The critical path (or sometimes paths) is the one, which defines the shortest period of time in which the project can be completed. As such, it is the series of interrelated jobs, which add up to the longest period time. All other concurrent paths usually have float or slack time. Refer back to logic network example. The path that adds up to the longest total duration consists of activities A, C, B, F, G and H, for a total of 62 hours. This is also the shortest period of time in which the total project can be completed. Knowing the critical path is helpful, but knowing the jobs with float or slack is equally helpful. Activities D and E are non-critical jobs totaling 14 hours. Activities B and F are critical jobs totaling 20 hours and can be performed concurrently with D and E. The difference in duration between these two paths is 6 hours. This is called the float or slack. Either D or E can be delayed 6 hours, or both jobs can be delayed any combination which totals 6 hours without extending the project. Assume activities B and D require the same resources to complete them and that activity F requires different resources. Using the available float, the start of activity D can be delayed by the 4 hours required to complete activity B without extending the duration of the shutdown.

3 It is important to make the distinction between what facility personnel may consider to be critical jobs and jobs that fall on the critical path. In reality they may not be the same. It s all a matter of definition. The job plant personnel feel is important during the shutdown may require the most resources or may be the most technically challenging. This job may can be a not be on the critical path. The critical path method works under the assumption that the project must be completed in the shortest period of time. If a critical path job is ignored and allowed to extend beyond its scheduled duration, the duration of the total project will be extended. This may be more devastating to the operation of the plant than the extension of a non-critical, albeit technically challenging. Project Management Software The project status should be updated continuously during the execution phase of a shutdown. This means redrawing the logic network and resulting Gantt charts to show delays and extended job durations as they occur. A new critical path may develop so formally non-critical jobs can become critical. Building and updating a large project manually can be a daunting task that few would consider practicable. CPM computer programs were developed to solve these problems in the early 1950s however, these programs were only developed on mainframe computers for a select few organizations. Project management software for the PC, developed and improved over the last 10 years, has made project management more accessible. These programs can help the user organize interdependent tasks using precedent logic. Resources with different working hours, schedules and costs can be assigned to these tasks and the results can be viewed on screen or printed. These software tools are also helpful in analyzing and communicating project activity. The progress of the shutdown can be tracked and updated using these programs and the associated costs can be monitored. Choosing the Right Program Complex and sophisticated programs are, and have been, available for years. However, the simpler the program, the quicker someone can start receiving the benefit. It's a good idea to try a few programs out to see which one is best for you. Low end programs are inexpensive, usually under $600 US, while high end programs can range from $4000 to $12,000 US. Low end programs are sufficient if you are looking to get a fast start with computerized project management software. Intelligent, on-line, support is available in some programs. This feature can lead a novice through the process of project management without much difficulty. Most project management programs are designed for general business applications and not maintenance. However, many offer the ability to customize the program to your specific needs. Customized fields can be added for entry of work order numbers or equipment numbers. These fields can be sorted, filtered, or searched quickly if the need arises. Most can import a simple ASCII or spreadsheet file. If a computerized maintenance management system (CMMS) can export to these formats (and most can), then the need for double entry is eliminated. Much of the work of a shutdown coordinator requires communicating with other people about a shutdown in progress. Project management programs can make this task easy too. Logic network diagrams and Gantt charts can be printed on demand. Although almost any printer can be used, this is best accomplished using a color printer or plotter as the output device. Tasks in the critical path can be displayed in a different color than the other tasks on a logic diagram. These charts can be annotated by the user to highlight certain sections. Reports can be customized to present project information the way the user wants it to be presented. Common canned reports available are baseline-to-actual, resource allocation, cost distribution, earned value analysis, and actual to budget. Most users feel a need to modify the output of these reports in a word processing program. File import and export capability is built into most of the programs. Not only can reports be sent to a word processing file, data can be transferred between different formats. Many of the common formats such as ASCII comma separated text (.CSV), dbase (.DBF), Lotus (.WK?), or Excel (.XLS), are available. It also possible to just cut and paste data between spreadsheets and software programs. Additionally, Microsoft Project can be transferred between many programs through a format called MS Project Exchange (.MPX) format.

4 All popular programs operate in a LAN or a client server environment, so project information can be updated by more than one user. Some programs allow the user to send project via to inform project members and update the project data files. The process is called "distributed or workgroup project management". Not only can multiple resources and levels of resource be identified, but each resource can have its own individual calendar. These calendars indicate the working days and hours for each resource or resource group. The duration of a project can be extended if insufficient resources are available. Some programs have difficulty dealing with shift schedules for resources. If this is a major requirement, consider some of the high-end programs. Multiple projects can be worked and managed simultaneously using most project software. Multiple projects can use the same people or other resources with overlapping assignments. Handling more than one project with a single project software file helps to sort out these situations. Some programs feature the ability to draw resources from a common pool for all projects and improves the ability to level resources between these projects. Getting the Most from Project Software Some people's initial forays into using project programs were tainted by the limitations of early software programs, such as the inability to handle part of an hour or restrictions on the number of resources which could be defined. Unfortunately, sometimes it was the limited knowledge of project management methods by the user that led to the initial frustration with the programs. Many of the software limitations cited in the early days have been eliminated. The following rules should be followed to get the most out of project programs. Identify jobs by duration. Maintenance planners ordinarily identify job labor requirements in terms of total labor hours and the craft required to complete the job. Project management programs require that labor requirements be identified as elapsed time, resource type, and quantity of the resource. This distinction allows the software to determine the optimum resource level required to perform concurrent jobs on the critical and non-critical paths. A process called resource leveling is employed to delay the start time of non-critical jobs within float or slack to limit the peak requirements. Expand your idea of resources. Most people think of a resource as the technical labor required, such as mechanics and electricians. Inspectors, safety personnel, engineers, and operations personnel should also be included as a resource on jobs. Nonhuman resources in short supply, such as cranes, tools, and laser alignment instruments, should be considered as well. The process of load leveling will reveal any conflicts with these resources so the shutdown coordinator can deal with them ahead of time. Include operations activities. Maintenance people usually only think of the work that the maintenance department has to do during a shutdown. Often operations is involved in the preliminary stages to shut down, cool down, decontaminate, and lock out equipment. All these activities take time during the shutdown, so get estimates from operations and add these tasks to the project. Break larger jobs into smaller segments to separate out the resources required. For example, an eight hour job may require a mechanic and an operations person. The mechanic will be involved in the entire job, from start to finish. The operations person will only be involved in the initial shutdown of equipment, lock outs, issuing safety permits, and startup. These activities may only take the first half hour and last half hour of the shutdown. When using some project programs it is important to break this job into segments so it is clear the operations person is not required for the entire duration of the job. This distinction comes in handy during the load leveling process. Don't assign start times and/or end times when initially entering project data. Let the project program determine the logical start time from the precedent logic. Only make a change it if the resultant start time does not correspond to a convenient time for your shutdown.

5 Don't limit the number of resources when you initially enter data into a project management program. The critical path method provides optimal results when an assumption is made that resources are unlimited. Let load leveling determine which jobs can be delayed to optimize the use of resources. The needed delay may be accomplished within the float or slack time available and not effect the project duration. If some resources are not lowered to the available level, the duration of the shutdown may have to be extended as a last resort. Project management methods can be applied to extended maintenance shutdowns. A shutdown coordinator can gain even more control over the effort with the use of new off the shelf software. A professional project management approach will bring out the best in the maintenance effort. It will also give everyone confidence that the maintenance department can get the plant running again - on time and in better condition. This article was written by a consultant from New Standard Institute, Inc. For other articles on Maintenancerelated subjects, view our website at or contact us via at nsi@newstandardinstitute.com or call (203) to discuss the subject with one of our consultants. Copyright 1999 by New Standard Institute, Inc. This page may be freely copied and distributed subject to the inclusion of the copyright notice and our Web site address. go to first page Information contained in this article is extracted from New Standard Institute's seminar entitled Shutdowns Turnarounds and Outages. This seminar is available for onsite presentation and is also held at select locations throughout the year. Visit our website at to view the outline, dates and locations. New! Now available as downloadable computer based training.

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

The management of the projects with MS Project

The management of the projects with MS Project The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

Priori ty ... ... ...

Priori ty ... ... ... .Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Use project management tools

Use project management tools Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software. DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON 1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent

More information

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards... SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Project Management Dr. James A. Bednar

Project Management Dr. James A. Bednar Project Management Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Project Time Management

Project Time Management Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...

More information

Introduction to Project Management

Introduction to Project Management L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You

More information

Operational Research. Project Menagement Method by CPM/ PERT

Operational Research. Project Menagement Method by CPM/ PERT Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your

More information

Schedule Compression

Schedule Compression Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: rwhitney@discoveritt.com Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 This three-day, instructor-led course is intended for individuals who are interested in expanding their knowledge base and technical skills about Microsoft Project. The course begins with the basic concepts

More information

Leaving Certificate Technology. Project Management. Teacher Notes

Leaving Certificate Technology. Project Management. Teacher Notes Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These

More information

Project management Project Management

Project management Project Management Project management Project Management Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar A project is a temporary endeavour to produce a unique product, service, or result (PMI

More information

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR)

CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Chapter 6: Project Time Management

Chapter 6: Project Time Management CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for

More information

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL

More information

Shut down management For Coal handling plant of thermal power station A New Approach 1.0 Abstract: - 2.0 Introduction: -

Shut down management For Coal handling plant of thermal power station A New Approach 1.0 Abstract: - 2.0 Introduction: - Shut down management or oal handling plant of thermal power station New pproach y Makarand Joshi 1.0 bstract: - Shut down can be defined as scheduled down period for a plant for scheduled maintenance for

More information

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John

More information

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can

More information

Network Calculations

Network Calculations Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

Cambridge International AS and A Level Computer Science

Cambridge International AS and A Level Computer Science Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?... CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........

More information

TABLE OF CONTENTS CHAPTER DESCRIPTION PAGE

TABLE OF CONTENTS CHAPTER DESCRIPTION PAGE vii TABLE OF CONTENTS CHAPTER DESCRIPTION PAGE TITLE DECLARATION DEDICATION ACKNOWLEDGEMENT ABSTRACT ABSTRAK LIST OF CONTENTS LIST OF FIGURES LIST OF TABLES LIST OF APPENDICES i ii iii iv v vi vii xii

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating

More information

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision

More information

Time Management. Part 5 Schedule Development. Richard Boser

Time Management. Part 5 Schedule Development. Richard Boser Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms

More information

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,

More information

Chapter 3 Managing the Information Systems (IS) Project

Chapter 3 Managing the Information Systems (IS) Project Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project

More information

Notes on the Critical Path Method for project planning and management.

Notes on the Critical Path Method for project planning and management. E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Managing Projects. With. MinuteMan Project Management Software

Managing Projects. With. MinuteMan Project Management Software Managing Projects With MinuteMan Project Management Software Copyright 2011 by MinuteMan Systems Introduction This is a brief introduction to the use of Project Management Software to help you organize

More information

3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY. 3.1 Project Management Software Does it Really Do That?

3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY. 3.1 Project Management Software Does it Really Do That? 3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY 3.1 Project Management Software Does it Really Do That? Not really it doesn t do any management that takes a talented human like you! A betternamed

More information

CHAPTER FIVE THE PROJECT SCHEDULE

CHAPTER FIVE THE PROJECT SCHEDULE CHAPTER FIVE THE PROJECT SCHEDULE THE 2012 ULTIMATE PROJECT MANAGEMENT MANUAL HERE S WHAT YOU LL LEARN Primary reasons for scheduling the project Ten characteristics of a good schedule Common scheduling

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC

The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC The Art of the Possible Scheduling Options in SAP Mark W. Scott Vesta Partners, LLC The Tool and the Challenge The Parts The Options The Results Scheduling in SAP What I ll cover: The Parts The Options

More information

CPM-200: Principles of Schedule Management

CPM-200: Principles of Schedule Management CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright

More information

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps

Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate

More information

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)

PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.

More information

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment. Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.

More information

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration

Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical

More information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2

More information

Lecture 26 CPM / PERT Network Diagram

Lecture 26 CPM / PERT Network Diagram Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review

More information

Project management using Excel spreadsheets: The case of Jules Event Planning Company

Project management using Excel spreadsheets: The case of Jules Event Planning Company Project management using Excel spreadsheets: The case of Jules Event Planning Company ABSTRACT Raida Abuizam Purdue University Calumet Lin Zhao Purdue University Calumet The Jules Event Planning Company

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Resource Allocation and Scheduling

Resource Allocation and Scheduling 90 This section is about the general overview of scheduling and allocating resources. Assigning people and machines to accomplish work (work on tasks). Resource Allocation: Time-Constrained. Assigning

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Project Scheduling: PERT/CPM

Project Scheduling: PERT/CPM Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project

More information

SELECTING PROJECT MANAGEMENT SOFTWARE

SELECTING PROJECT MANAGEMENT SOFTWARE SELECTING PROJECT MANAGEMENT SOFTWARE Information needs People at different levels within an organization have different information needs. Information should be made available to all as needed, in a standardized

More information

CPM and GANTT: The Next Step in Multi-Project Management

CPM and GANTT: The Next Step in Multi-Project Management CPM and GANTT: The Next Step in Multi-Project Management Stephen Sloan, Accenture, New York, NY Lindsey Puryear, SAS Institute, Cary, NC ABSTRACT Challenge Instead of managing a single project, we had

More information

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary

More information

Scheduling Resources and Costs

Scheduling Resources and Costs Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used

More information

Systems Analysis and Design

Systems Analysis and Design Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

Introduction to IT Project Management

Introduction to IT Project Management Adapted from Managing Information Technology Projects, Chapter 1, Schwalbe Introduction to IT Project Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Sep 17th, 2015 Outline

More information

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule

More information

Project Management Courses

Project Management Courses "A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the

More information

Information Technology Project Management

Information Technology Project Management Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Implementing Resource Scheduling Techniques

Implementing Resource Scheduling Techniques Implementing Resource Scheduling Techniques A Guide for Planners and Scheduler s By Raphael M Düa FAICD, MACS(Snr),PCP, CP, GradDISC Owner & CEO Micro Planning International Asia Pacific Pty Ltd Micro

More information

Construction Project Scheduling

Construction Project Scheduling Construction Project Scheduling Produced and Distributed by Engineer Educators 857 East Park Avenue Tallahassee, FL 32301 1 Disclaimer The material in this course manual is not meant to infringe on any

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

Work Breakdown Structure & Schedules

Work Breakdown Structure & Schedules A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a project. Resources are identified for each item within the WBS that facilitates budgeting as well as assignment of responsibilities.

More information

Project Plan Version 0.0

Project Plan Version 0.0 Software Development Templates Project Plan Version 0.0 DOCUMENT NO: VERSION: CONTACT: EMAIL: Authors Name xxx.xxx@xxx.xxx DATE: 15/07/2003 Unlimited distribution subject to the copyright. Project Plan

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

Application Survey Paper

Application Survey Paper Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi

Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking

More information

Leaving Certificate Technology. Project Management. Student Workbook

Leaving Certificate Technology. Project Management. Student Workbook Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage

More information

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT 8. COMPUTER TOOLS FOR PROJECT MANAGEMENT The project management is a complex activity that requires among others: Information intercourse referred to the project, information that is in big amounts more

More information

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to

More information

Microsoft Project 70-178 Exam Study Guide

Microsoft Project 70-178 Exam Study Guide Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the

More information