The Montana Public Works Standard Specifications are modified as follows:
|
|
- Lesley Griffith
- 7 years ago
- Views:
Transcription
1 The Montana Public Works Standard Specifications are modified as follows: 1. SECTION TRENCH EXCAVATION AND BACKFILL FOR PIPELINES AND APPURTENANT STRUCTURES 02. STANDARD DRAWINGS Standard Drawing No Typical Utility Trench Detail - Delete type 1 pipe bedding and insert pipe bedding material as specified. Standard Drawing No Pipe Bedding Alternate, delete Pipe Bedding shall be a minimum 12 inches above the pipe. 05. B. TRENCH BACKFILL PIPE BEDDING MATERIAL (1) Type 1 Pipe Bedding "PIPE EMBEDMENT. Unless otherwise shown on the drawings, pipe bedding material shall be placed in a thickness equal to ~ x pipe O.D. below the pipe (4 inches minimum) to 6 inches above the pipe. Bedding material shall be clean, non-cohesive, natural, unwashed gravel, sand or crushed hard stone graded as follows: Sieve Size Percent Passing 1" #4 # Less than 10 Except where groundwater is encountered at the trench bottom, in which case embedment material shall be washed, crushed rock passing a I-inch screen. Native trench material shall not be used for pipe bedding material without approval from the City Engineer. In rock areas, the minimum bedding below the pipe shall be 6". Bedding material shall be compacted to 90% of theoretical maxiltium proctor density as determined by AASHTO T -99. Special pipe embedment Inay be required when shown on the drawings. Placement and Compaction. All granular fill material beneath the pipe shall be spread and compacted to provide a uniform and continuous support beneath the pipe at all points between bell holes or pipe joints. It will be permissible to slightly disturb the finished subgrade surface by the withdrawal of pipe slings or other lifting tackle. No part of any bell or coupling shall be in contact with the trench bottom, trench walls, or granular fill when the pipe is jointed. 1
2 After each pipe has been graded, aligned and placed in final position on the bedding materials, and shoved home, sufficient pipe embedment material shall be deposited and compacted under and around each side of the pipe and back of the bell or end thereof to hold the pipe in proper position and alignment during subsequent pipe jointing, embedment and backfilling operations. Embedment material shall be deposited and compacted uniformly and simultaneously on each side of the pipe to prevent lateral displacement of the pipe." C. TRENCH BACKFILL Type A trench backfill will be required in all areas. 2. SECTION 02250, WATERING 03. USE OF CITY WATER: "The Contractor shall be responsible for providing the water required for executing their work." 3. SECTION 02610B, SANITARY SEWER MAIN MATERIALS 03. POL YVINYL CHLORIDE (PVC) PIPE E. Fittings Delete "Wye or" and add the following: "Sewer service connections shall be made by installing either standard tee fittings or tapping saddles. Tapping saddles shall be Predco Fast-Fit sewer saddle with epoxy kit and tapping donut, or equal." 4. SECTION 02722, SANITARY SEWER MAINS STANDARD DRAWINGS "Standard Drawing No Sanitary Sewer and Storm Drain Manhole" - Change channel depth to 0.80 dia. of pipe vice Yz dia. Slope shelf at 1/4" per foot. Delete the following: "Standard Drawing No Standard Cast Iron Cover. "Standard Drawing No Standard 24" Cast Iron Ring No " Manhole Frame "Dept. of Engineering, Missoula, MT - Dwg. STD # 190" PIPE INSTALLATION: E. TOLERANCES "Variance from established line and grade shall not be 2
3 greater than ~ inch, provided that such variation does not result in a level or reverse sloping invert." c.) ) MANHOLES A. GENERAL a. Delete Standard Drawing # and add the following: "Dept. of Engineering, Missoula, MT, STD Dwg. No. 190." b. "Manhole shall have eccentric cones only" 2.) D. RINGS AND COVERS "Dept. of Engineering, Missoula, MT, std. dwg. #190" 3.) F. CONSTRUCTION Paragraph 2, Delete, "The established high groundwater level is as shown on the plans or noted in the Special Provisions." d.) 06. TESTS: 1.) D. T.V. INSPECTION The Engineer shall be required to use a television camera for all sewer inspections before final acceptance. The television inspection shall be done after the seven day deflection test, under the direction of the Engineer and not the Contractor. All lines inspected shall be cleaned with a commercial hydraulic sewer cleaner and televised within one hour of cleaning. An approved measuring device shall also be attached to the camera for verification of ponding. A sewer line is deficient and unacceptable if: (1) The alignment is outside the specified limits, (2) Water ponds in any section equal to or greater than two (2) times the grade tolerance specified under Section , and as modified below, (3) The pipe has visible defects such as open joints, pinched gaskets, cracked barrels or bell, or similar defects. All costs incurred for the television inspection performed shall be the Contractor's responsibility. All television inspections shall be DVD format. Pull the camera through the sewer at thirty (30') feet per minute (9 n1eters per minute maximum). If the camera is pulled by attaching to the hose of a hydraulic sewer cleaner, assure the hose is not active during the pulling process. The Engineer and the City Engineer shall confer and decide as to the remediation if necessary. 3
4 2.) E. DEFLECTION TEST "The 7 day deflection test is required on all City of Missoula sanitary sewer mains." 5. SECTION 2724, SANITARY SEWER AND STORM DRAIN SERVICES 02. STANDARD DRAWINGS: Delete and refer to plans. 03. MATERIALS: "Sewer service connections as shown on the drawings will be marked for location in the field by the Engineer, and shall be made using either standard tee fittings or by installing tapping saddles. Tapping saddles shall be Predco Fast-Fit sewer saddle with epoxy kit and tapping donut, or equal. Flexible couplings shall be flexible elastomeric PVC couplings with stainless steel bands. Flexible couplings shall be designed for connecting gravity sewer pipe and shall be No Series as manufactured by Femco, or an approved equal." c.) 04. INSTALLATION A. GENERAL Delete "standard drawings and " and add the following:... with "Detail on the Plans." E. LAYING PIPE Second paragraph, first and second sentence, delete "wye or" and after "tee fittings... " insert "or tappng saddles." d.) 06. END PIPE MARKER: Change "2" x 2" " to "2" x 4" "and add steel fence post taped to 2 x 4 as shown on plans. 6. ADD SECTION 02725, INSULATION 01. GENERAL This section covers the furnishing and installation of insulation as shown on the drawings and specified. 02. MATERIALS 4
5 Materials shall be as specified herein. Insulation material shall be extruded polystyrene insulation board, in conformance with AASHTO designation M Insulation material shall be designed specifically for inground installation. Installation material shall be square edge and shall have the following properties: A. Compressive Strength: 35 psi minimum at 5 percent deformation of yield, as determined by ASTM D B. Water Absorption (Percent by Volume): 0.25 percent maximum as determined by ASTM C272. C. Thermal Resistance (R) Value: 5.0 ft hr. FIBTU at 75 degrees F, mean temperature in a 1 inch thickness as determined by ASTM C INSTALLATION 7. SECTION 3310, STRUCTURAL CONCRETE Thickness and overall dimensions of insulation material shall be as shown on the drawings. Minimum length of insulation material boards shall be 8 feet. Insulation material shall be installed in the locations shown on the drawings. Each thickness shall be obtained by the use of at least two layers of insulation material boards with staggered joints to prevent heat loss. All joints shall be tightly butted. All field cutting of insulation material board shall be done with a straight edge to a neat line. Insulation shall be covered with 6 inches minimum of pipe bedding material prior to backfilling, except in location of shallow bury (8 inches or less) where the insulation is backfilled with topsoil. 03. COMPOSITION OF CONCRETE C. PROPORTIONING - Table 1 Add to M3000 "Minimum cement content is 5 12 sacks per cubic yard." Add to M4000 "!v:iinimum cement content is 6 Yz sacks per cubic yard." 5
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationCHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationSECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
More informationSTANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationEXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
More informationSECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationBeacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
More informationExhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationSECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationThe Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21
September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,
More informationSUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
More informationSECTION 02401 - SANITARY SEWER PIPE
PART 1 - GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing sanitary sewer pipe, in accordance with
More informationSERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
More informationA. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
More informationC. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
More informationSECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
More informationSECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
More informationSection 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
More informationSECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
More informationSECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationBethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL
155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS
More informationSECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
More informationSECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
More informationUltra-Rib PVC Storm Sewer Pipe 8" - 30"
Ultra-Rib PVC Storm Sewer Pipe 8" - 30" Ultra-Rib is a PVC Storm Sewer Pipe That Provides Superior Structural Capabilities Waterworks Products PW Eagle s Ultra-Rib is an open profile PVC gravity-flow storm
More information32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
More informationSECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)
CHAPTER 9 SEWER / STORM DRAIN / IRRIGATION LINES SECTION 9.01 GENERAL This section covers the requirements for piping materials and installation of Lehi City sewer, storm drainage and irrigation collection
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
More informationSTANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified
More informationARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION
ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of
More informationSANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
More informationDIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
More informationCCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationModel Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer The user may choose to adopt part or all of this Model Specification; however, the user should ensure that all parts
More informationAIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
More information53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationTECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS
TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer
More informationSECTION 9. All sewer laterals shall tie into the sewer main lines unless approved by the City Engineer.
SECTION 9 SEWER/DRAINAGE LINES 9.1 GENERAL This section covers the requirements for piping materials and installation in the Cedar Hills City sewer and drainage collection system. All materials and workmanship
More informationSection 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
More informationTABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
More informationSECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.
SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY
More informationCITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General
General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling
More informationSECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD
SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials
More informationSpecification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
More informationFY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
More informationSTANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete
More informationSeptember 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM
1.0 General Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM a) It is the intent of this specification to ensure that all gravity sewer system infrastructure constructed within the service
More informationINDEX. Sec. No. Items Page Nos.
INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............
More information1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
More informationSECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
More informationARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.
ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationSECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
More informationSECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction)
SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction) 6001 SCOPE. This section covers excavation and trenching work and shall include the necessary clearing, grubbing, and preparation
More informationSECTION 7- STORM SEWER
SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...
More informationSECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
More informationOAR52 A-1 (September, 1981)
APPENDIX A SEWER PIPELINES (1) MINIMUM REQUIREMENTS FOR SEWER - PIPELINES (a) Capacity: Sewers shall be of such diameter as to pass without overflow, bypass, or back flow onto damageable property of a
More informationSECTION 03400 PRECAST CONCRETE STRUCTURES
PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, and equipment required to install precast concrete manholes, sanitary leaching rings, pump station, valve chamber, structures, frames,
More informationSECTION 724 PIPE CULVERTS
SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate
More informationThe Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall
More informationSECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
More informationSECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
More informationSECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes the repair, demolition, and disposal of asbestos
More informationSANITARY GRAVITY SEWER LINE TESTING. B. Section 02732 CCTV Inspection of Gravity Sewer Lines
PART 1 GENERAL 1.1 SECTION INCLUDES A. Low Pressure Air Test B. Deflection Test 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02732 CCTV Inspection of Gravity Sewer Lines
More informationSECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes all labor, materials, equipment, and incidentals required and installation of Polyvinyl Chloride
More informationRoyal Seal Gasketed Sewer Pipe
Royal Seal Gasketed Sewer Pipe Royal Seal Gasketed Sewer Pipe Royal Seal gasketed sewer pipe with our specially designed Double Seal Locked-In (DSLI ) gasket is an extremely durable pipe with a leak proof
More informationCity of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014
City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 Section Subsection Name Date Modification Division 1 All subsections General Provisions
More informationTown House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
More informationCONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements
16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications
More informationSECTION 200: STORM SEWER CONSTRUCTION STANDARDS
SECTION 200: STORM SEWER CONSTRUCTION STANDARDS Page No. Description 200-2 201 GENERAL 200-2 201.1 SPECIFICATIONS 200-2 201.2 CONNECTION TO EXISTING FACILITIES 200-3 202 MATERIALS 200-3 202.1 PIPES 200-4
More informationSewer Line Rehabilitation
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
More informationCW 2130 - GRAVITY SEWERS TABLE OF CONTENTS
August 2010 CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard Details...
More informationSECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION
SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density
More informationSEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
More informationSIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS. Prepared by Risi Stone Systems Used by permission.
SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS Prepared by Risi Stone Systems Used by permission. 1-800-UNILOCK www.unilock.com FOREWORD This outline specification has been prepared for
More informationSanitary Sewer Mains and Services
Sewer Title Sanitary Sewer Mains and Services STitle Sewer Table of Contents "CORRECTIVE PERIOD & INSPECTION FOR SANITARY SEWERS & SERVICES"... 1 1. TERM OF GUARANTEE... 1 2. CONTRACTOR LICENSE AND PERMITS...
More informationSTORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES
CITY OF PETALUMA STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES AUGUST 1999 Revised 10/98 City of Petaluma Petaluma, California STORM DRAIN INSTALLATION DETAIL
More informationSpecification Guidelines: Allan Block Modular Retaining Wall Systems
Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's
More informationSECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
More informationSection 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS
TABLE OF CONTENTS 2.18 CONCRETE AND/OR CORRUGATED STEEL STORM SEWER... 1 2.18.1 GENERAL... 1 2.18.2 MATERIALS... 1 2.18.2.1 Storm Sewer Pipe... 1 2.18.2.2 Cement Mortar... 1 2.18.2.3 Granular Materials...
More informationCity of West Linn Public Works Standard Construction Specifications. Table of Contents
City of West Linn Public Works Standard Construction Specifications Table of Contents DIVISION SIX STORM DRAIN TECHNICAL REQUIREMENTS... 1 601 PIPE AND FITTINGS... 1 601.01 Description...1 601.02 Materials...1
More informationSECTION 603 SANITARY SEWER FORCE MAINS
SECTION 603 SANITARY SEWER FORCE MAINS 1. GENERAL Pipelines for sanitary sewer force main systems shall conform to the following specifications and shall be installed at the locations indicated on the
More informationSPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
More information