Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012

Size: px
Start display at page:

Download "Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012"

Transcription

1 Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012

2 6:00 6:30 p.m. Open House 6:30 7:00 p.m. Presentation 7:00 8:00 p.m. Open House 2

3 Project Overview Carla Kahn Community Outreach Coordinator 3

4 Agenda Introduction of Project Team Project Overview Construction Scope of Work Preliminary Construction Schedule Questions 4

5 Community Outreach Team Carla Kahn s Role Community Outreach Coordinator Liaison between the project & community Knows & understands the community Issue resolution Creates project updates Gary Flunoy s Role Business Assistance Specialist Contact for business assistance programs Knows & understands the community 5

6 Project Team John Taylor Valley Metro, Project Manager Brian Mason Valley Metro, Resident Engineer Erik Yingling Sundt/Stacy & Witbeck, Project Manager Albert Santana City of Phoenix, Light Rail Project Administrator 6

7 Route 7

8 Project Status Design Complete Contractor Sundt/Stacy & Witbeck Joint Venture Received notice to proceed Begin work January

9 Construction Outreach Plan Communication/notification 24-hour hotline Personal contact Public meetings Doorhangers & mailers blasts Sign-up by contacting Carla Social media Facebook/METROrailconstruction Twitter - #Northwest Website 9

10 Business Assistance Toolbox METRO Max Rewards Program General marketing & advertising support Multi-media marketing campaigns Business-to-business resources & consulting Community Advisory Board (CAB) Business access signage Business Access Coordinator 10

11 Construction Scope of Work Brian Mason, PE Resident Engineer 11

12 Utility Relocation & Road Widening Activities include: Utility relocation Demolition of existing roadway, grading & re-paving Construction of traffic lanes, curbs, gutter, sidewalks, streetscape & lighting 12

13 Track & Station Installations Activities include: Installation of track Installation of overhead power lines Construction of stations & integration of artwork Construction of park & ride facility and traction power substations 13

14 Light Rail Testing/Operations Activities include: Signals & communication Traction power substation testing Overhead contact system testing Safety certification 14

15 What to Expect Access maintained to businesses & residential Notification & coordination of construction activities Modification to traffic lanes & sidewalks Day & night time work Temporary utility interruptions Coordination 15

16 Preliminary Construction Schedule Sundt/Stacy Witbeck JV Erik Yingling Project Manager 16

17 Sundt/Stacy and Witbeck JV 17

18 Sundt/Stacy & Witbeck JV Line Section 4 Line Section 5 Maintenance & Operations Facility 18

19 Northwest Extension 45,000 lineal feet waterline materials 16,000 lineal feet sewerline materials 22,000 lineal feet drainage materials 36 water line Storm drain 19

20 Northwest Extension 214,000 tons aggregate materials 30,000 cubic yard ready mix Bus pullouts Roadway milling New sidewalks 20

21 Northwest Extension Mainline track 31,000 track feet single crossovers 1 double crossover 750 pressure welds 500 thermite welds Track crossing 56 th Street and Washington 21

22 Setting traction power substation Signals & communication Overhead catenary system 22

23 Early Construction Activities Begins January 2013 Relocation of utilities including: Water mains/services Sanitary sewer/storm sewer Gas main services SRP/Private irrigation Power (overhead conversion) Phone/Cable (overhead conversion) 23

24 Construction Schedule 24

25 Planned Construction Schedule 25

26 Upcoming Events Public Art Meeting December 5, 2012 Peer to Peer Business Forum December 12, 2012 Groundbreaking Event January 12,

27 Questions Carla Kahn Community Outreach Coordinator Direct Line: (602) Cell number: (623) Gary Flunoy Business Assistance Specialist Direct Line: (602) Cell Number: (602)

Light Rail Transit in Phoenix

Light Rail Transit in Phoenix 4. Presentation and Discussion: Phoenix Light Rail Implementation Wulf Grote Planning and Development Director, Phoenix Valley Metro Light Rail Transit in Phoenix Broadway Citizen s Task Force February

More information

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Final As-Builts nearing completion

More information

EXHIBIT A Accessible Truck Routes Map

EXHIBIT A Accessible Truck Routes Map EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT

More information

Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014

Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Economic Empowerment Program Scope of Work Providing advocacy for small and disadvantaged business capacity,

More information

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection

More information

AGENCY COORDINATION AND PUBLIC INVOLVEMENT

AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5 AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5.1 AGENCY COORDINATION As part of the planning process for the Oregon Avenue Final EA, DDOT conducted an agency coordination program. This coordination included

More information

Draft Transportation Management Plan for Via Verdi Repair Project

Draft Transportation Management Plan for Via Verdi Repair Project for Via Verdi Repair Project prepared for City of Richmond This report was prepared by: This report was reviewed by: Ryan McClain, P.E. Fehr & Peers TABLE OF CONTENTS 1.0 INTRODUCTION & PROJECT DESCRIPTION...

More information

APPENDIX K Capital Costs Methodology Report

APPENDIX K Capital Costs Methodology Report APPENDIX K Capital Costs Methodology Report September 2013 Capital Cost Estimating Report Table of Contents 1.0 Information... 5 1.1 Introduction... 5 1.2 Purpose and Goal... 5 2.0 Description of Project...

More information

COPPER BEECH TOWNHOME DEVELOPMENT

COPPER BEECH TOWNHOME DEVELOPMENT COPPER BEECH TOWNHOME DEVELOPMENT This 28 acre, 30 Townhome development is slated to open doors in time for the 2007 2008 college school year. To accommodate this project s tight time line, Dennis Corporation

More information

LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities

LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities American Public Works Association Utilities & Public Right of Way Committee February 29, 2000 Table o of Contents Index...Page

More information

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul July 2010 Chair Peter Bell of the Metropolitan Council speaks about the Met Council s contribution of $1 million to a $1.5 million small business loan fund during a July 20 news conference with Mayor R.T.

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

Pavement Management Program

Pavement Management Program Pavement Management Program 2014 Street Maintenance Program Executive Summary 01/21/2014 Presented by Mark Thiel Assistant Director of Public Works Program Overview Start of current program 2005 825.1

More information

City of Hilshire Village Pine Creek Ln Reconstruction

City of Hilshire Village Pine Creek Ln Reconstruction City of Hilshire Village Pine Creek Ln Reconstruction OVERVIEW The City will be soliciting bids for the Pine Creek Reconstruction Project with construction scheduled to begin in January 2015. This project

More information

VILLAS OF TRADITIONS AT GREY OAKS

VILLAS OF TRADITIONS AT GREY OAKS Report of Turnover Survey VILLAS OF TRADITIONS AT GREY OAKS Grey Oaks Development Naples, Collier County, Florida Forge Engineering Project Number 2907-001.01 March 2015 Richard P..Lundberg, P.E cn=richard

More information

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons)

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) DATE: March 8, 2006 TO: FROM: SUBJECT: Plan Commission Larry D. Nelson, P.E., City Engineer 5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons) The City Engineering

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32104-E Cancelling Revised Cal. P.U.C. Sheet No. 28312-E Electric Sample Form No. 62-0685 Application for Service

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million

More information

Pavement Management Program

Pavement Management Program Pavement Management Program 2013 Street Maintenance Program Executive Summary 1/15/2013 Presented by Mark Thiel Assistant Director Public Works Program Overview Start of current program 2005 812.5 Lane

More information

How To Write A City Of Lakewood

How To Write A City Of Lakewood Click to edit Master title style Bay Village Sunset Area: Storm Sewer & Pavement Replacement Engineering Click toosborn edit Master title style Talented Staff Headquartered in Cleveland Resource Base of

More information

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section: . Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based

More information

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer Development Services Department City of San Antonio Development Process 101 Permits & Licenses Michael Dice Development Services Manager Kathy Rodriguez Deputy Historic Preservation Officer 1 Permit &

More information

DEPARTMENT OF DEVELOPMENT SERVICES PLANNING FEES AND COSTS Revised 10/26/2012

DEPARTMENT OF DEVELOPMENT SERVICES PLANNING FEES AND COSTS Revised 10/26/2012 ZONING DEPARTMENT OF DEVELOPMENT SERVICES PLANNING FEES AND COSTS Revised 10/26/2012 [ ] PD Sketch Plan with phasing plan $2,000 plus $20/acre over 5 acres Retainer - $1,500 [ ] PD Preliminary Site Plan

More information

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Public Works Projects in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works Planned Projects in Marina Del Rey Waterline Projects Phase II Phase III Roadway Projects Admiralty

More information

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST State of California Business, Transportation and Housing Agency DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST District / EA: District 3/ EA 03-3E380 Date Prepared: 1/10/2013 Prepared By: Robert Himes Stage

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32106-E Cancelling Revised Cal. P.U.C. Sheet No. 28314-E Electric Sample Form No. 62-0687 Application for Service

More information

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS UPDATED: 01/31/14 SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS Q. 1. What are the County s plans for Seminole Pratt Whitney Road between SR 80 (Southern Blvd) and the Bee Line

More information

Belmont Street Bridge Rehabilitation Project

Belmont Street Bridge Rehabilitation Project Belmont Street Bridge Rehabilitation Project Christian Gospel Church Worcester 43 Belmont Street Worcester MA February 20, 2015 7:00PM Agenda Introductions Project site and overview Project history Construction

More information

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland 20850

More information

Surface Transportation Program (STP)

Surface Transportation Program (STP) Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface

More information

Principles of Traffic Management on sites / road network

Principles of Traffic Management on sites / road network IOSH Ireland, Construction Specialist Section Springfield Hotel, Leixlip, County Kildare. 25 March 2015 Principles of Traffic Management on sites / road network Padraig Watters, Chartered Engineer This

More information

CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW)

CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW) CITY OF VISTA STANDARD DRAWINGS (PRELIMINARY, FOR REVIEW) January, 2013 THIS SHEET INTENTIONALLY LEFT BLANK TABLE OF CONTENTS DRAINAGE STRUCTURES DRN-01 Corrugated metal pipe drop inlet DNR-02 Storm Drain

More information

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are

More information

Bond Release Process for New Subdivision Developments in Fairfax County

Bond Release Process for New Subdivision Developments in Fairfax County Bond Release Process for New Subdivision Developments in Fairfax County An Overview for Homeowners Associations A Fairfax County, Va., publication April 2009 For more information or to request this document

More information

Los Angeles Metro Rapid

Los Angeles Metro Rapid Los Angeles Metro Rapid Why BRT In Los Angeles Public dissatisfied with slow bus service Average bus speeds had declined by 10% since late- 1980s LADOT found that 50% of the time a bus is in service it

More information

Gardnerville Water Company Regular Board Meeting Minutes Tuesday, April 8, 2014 5:00 p.m. Board Room 1579 Virginia Ranch Rd Gardnerville, NV 89410

Gardnerville Water Company Regular Board Meeting Minutes Tuesday, April 8, 2014 5:00 p.m. Board Room 1579 Virginia Ranch Rd Gardnerville, NV 89410 Gardnerville Water Company Regular Board Meeting Minutes Tuesday, April 8, 2014 5:00 p.m. Board Room 1579 Virginia Ranch Rd Gardnerville, NV 89410 Board Members Present: Barbara Henningsen, Chairman Mark

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

Public Involvement Meeting Handout

Public Involvement Meeting Handout Public Involvement Meeting Handout WIS 93 Detloff Drive to WIS 95 Trempealeau County Project ID 7130-01-72 June 18, 2014 5:00 P.M. 401 W. Main Street Arcadia WI Purpose of the meeting The Wisconsin Department

More information

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) To be considered for STP funding, a proposed project must

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

CONSTRUCTION SAFETY POLICY

CONSTRUCTION SAFETY POLICY California Institute of Technology CONSTRUCTION SAFETY POLICY Caltech Environment, Health, and Safety Office 1200 E. California Blvd., M/C 25-6 Pasadena, CA 91125 Phone: 626.395.6727 Fax: 626.577.6028

More information

11 p.m. to. Tuesday, June. will remain open. 14. closed

11 p.m. to. Tuesday, June. will remain open. 14. closed June 3, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures June 5 11 Include Northbound Beltway Lanes, Eastbound Dulles Airport Access

More information

CD i -STREETS- Detail #

CD i -STREETS- Detail # -STREETS- Detail # 3000 Vertical Curb, Gutter and Sidewalk 3010 Low-Profile Curb, Gutter and Sidewalk 3020 Rolled Curb, Gutter and Sidewalk 3030 Separated Sidewalk, Curb & Gutter 3040 Sidewalk Staged Construction

More information

TOWN OF HILLSBOROUGH BUILDING & PLANNING DEPARTMENT DESIGN, CONSTRUCTION AND LANDSCAPE PROFESSIONAL NEWSLETTER Fall Greetings 2013

TOWN OF HILLSBOROUGH BUILDING & PLANNING DEPARTMENT DESIGN, CONSTRUCTION AND LANDSCAPE PROFESSIONAL NEWSLETTER Fall Greetings 2013 TOWN OF HILLSBOROUGH BUILDING & PLANNING DEPARTMENT DESIGN, CONSTRUCTION AND LANDSCAPE PROFESSIONAL NEWSLETTER Fall Greetings 2013 TIS THE SEASON - GRADING MORATORIUM! Once again our Grading Moratorium

More information

Plumbers Packet. Right-of-Way Management Program Permit Fees and Regulations

Plumbers Packet. Right-of-Way Management Program Permit Fees and Regulations Plumbers Packet Right-of-Way Management Program Permit Fees and Regulations Plumbers doing work in the City ROW will be required to apply for and obtain an Excavation Permit or an Obstruction Permit depending

More information

5. MAJOR STREET CONSTRUCTION The B-Permit. 5.1. B-Permit Description and Purpose

5. MAJOR STREET CONSTRUCTION The B-Permit. 5.1. B-Permit Description and Purpose 5. MAJOR STREET CONSTRUCTION The B-Permit 5.1. B-Permit Description and Purpose The B-Permit is required for major street construction in the public right-of-way. This includes the widening of streets,

More information

FM 969 CORRIDOR. APPENDIX c

FM 969 CORRIDOR. APPENDIX c FM 969 CORRIDOR APPENDIX c c utility technical memorandum State of Texas Registered Firm No. F-3572 CAS CONSULTING & SERVICES, INC. Civil, Transportation, and Environmental Engineering Austin Dallas Houston

More information

RESOLUTION NO. 1539 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BONNEY LAKE, PIERCE COUNTY, WASHINGTON, APPROVING THE 192 ND CORRIDOR STUDY AND DIRECTING THE MAYOR TO PROCEED WITH PARTIAL DESIGN AND

More information

MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011. TIP Public Review Meeting

MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011. TIP Public Review Meeting MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011 TIP Public Review Meeting Meeting Agenda New York Metropolitan Transportation Council Major Products Transportation Improvement Program

More information

FOR IMMEDIATE RELEASE September 17, 2013 Contact:

FOR IMMEDIATE RELEASE September 17, 2013 Contact: NEWS RELEASE FOR IMMEDIATE RELEASE September 17, 2013 Contact: Diana L. Klink 757.514.4104 757.359.1845 Tim Kelley 757.514.4103 757.871.3039 UPDATE (Bridge Road/Mills Godwin Bridge) The work scheduled

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

S-11: Tacoma Link Extension to Tacoma Community College

S-11: Tacoma Link Extension to Tacoma Community College Project Number S-11 Subarea Pierce Primary Mode Light Rail Facility Type Corridor Length 3.65 miles Version ST Board Workshop Date Last Modified 11-25-2015 PROJECT AREA AND REPRESENTATIVE ALIGNMENT SHORT

More information

Communications and Service Plans for Upcoming Major Events

Communications and Service Plans for Upcoming Major Events Customer Services, Operations, and Safety Committee Board Information Item III-B March 13, 2008 Communications and Service Plans for Upcoming Major Events Washington Metropolitan Area Transportation Authority

More information

CITY OF COTTAGE GROVE CAPITAL PROJECTS FUNDS BUDGET SUMMARY FY2008-09 ACTUAL FY2010-11 BUDGET FY2009-10 ACTUAL FY2007-08 ACTUAL FY2011-12 ADOPTED

CITY OF COTTAGE GROVE CAPITAL PROJECTS FUNDS BUDGET SUMMARY FY2008-09 ACTUAL FY2010-11 BUDGET FY2009-10 ACTUAL FY2007-08 ACTUAL FY2011-12 ADOPTED CITY OF COTTAGE GROVE CAPITAL PROJECTS FUNDS BUDGET SUMMARY FUND/DEPARTMENT FY2007-08 FY2008-09 FY2009-10 FY2010-11 BUDGET FY2011-12 ADOPTED Water SDC Fund 412,539 105,533 34,677 27,045 42,160 Street SDC

More information

ADVERTISEMENT FOR BIDDERS

ADVERTISEMENT FOR BIDDERS ADVERTISEMENT FOR BIDDERS Sealed Bids will be received by the City of Lookout Mountain, Georgia, 1214 Lulu Lake Road, Lookout Mountain, Georgia 30103, Attention: Brad Haven, City Manager until: for the

More information

5. Environmental Analysis

5. Environmental Analysis 5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the

More information

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs KENTUCKY TRANSPORTATION CABINET Department of Rural and Municipal Aid Office of Local Programs Office of Local Programs Transportation Enhancements Safe Routes to School Congestion Mitigation and Air Quality

More information

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Executive Summary. Transportation Needs CHAPTER. Existing Conditions CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in

More information

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required

More information

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Transportation & Mobility projects that meet the following criteria: enhances regional mobility; supports public transit;

More information

How To Build A City Of Virginia Beach Arena

How To Build A City Of Virginia Beach Arena City of Virginia Beach Arena Infrastructure Preliminary Conceptual Cost Estimates Doug Smith, Deputy City Manager Carl Tewksbury, Kimley-Horn City Council Briefing July 8, 2014 July 8, 2014 Presentation

More information

Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements

Moving Ruston Forward. City of Ruston Infrastructure Maintenance and Improvements Moving Ruston Forward City of Ruston Infrastructure Maintenance and Improvements MLK Extension Project will be done in conjunction with proposed water and sewer improvements Connect Martin Luther King

More information

FIBER-OPTIC CABLE PLAN CHECK

FIBER-OPTIC CABLE PLAN CHECK Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW

More information

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1 Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important

More information

Walkable Communities Florida Department of Transportation State Safety Office Pedestrian and Bicycle Program April 1995 www.dot.state.fl.us/safety Twelve Steps for an Effective Program Page 1 Twelve Steps

More information

CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS

CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS 10.1 APPLICATION REQUIREMENTS AND PROCEDURES 10.1.1 A permit shall be required for any construction or installation within the public right-of-way

More information

Capacity Deficiency Project Application Jackson MPO Surface Transportation Program

Capacity Deficiency Project Application Jackson MPO Surface Transportation Program Capacity Deficiency Project Application Jackson MPO Surface Transportation Program The following information must be completed for all Capacity Deficiency proposed Jackson MPO STP projects. MPO staff will

More information

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing.

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing. COLORADO DEPARTMENT OF TRANSPORTATION CONTRACTOR PREQUALIFICATION STATEMENT (EXPERIENCE, EQUIPMENT AND FINANCIAL) Return to: Contracts & Market Analysis Prequalification Unit 4201 E. Arkansas,4th Floor

More information

Key Performance Indicators. 2012 - KPI s

Key Performance Indicators. 2012 - KPI s Key Performance Indicators As part of the government service contracts, which took effect on January 1, 2012, key performance indicators were identified for each contract tied to each particular department

More information

Special Inspection/Re Inspection, all Divisions $100.00 per hour, one hour minimum

Special Inspection/Re Inspection, all Divisions $100.00 per hour, one hour minimum Community Development Department 408 Spokane St. Post Falls, ID 83854 Ph: 208 773 8708 Fax: 208 773 2505 www.postfallsidaho.org BUILDING S Building Plan Check (Paid at Plan Submittal) Residential $150.00

More information

**The Winter 2010 edition of The Road Ahead newsletter is available online.

**The Winter 2010 edition of The Road Ahead newsletter is available online. RTC e-news Brief for January 29, 2010. This e-newsletter was created to keep you informed about key activities and issues pertaining to Your RTC. I encourage you to share this information with your board

More information

Appendix 6. Permeable Alley Preliminary Evaluation

Appendix 6. Permeable Alley Preliminary Evaluation Appendix 6 Permeable Alley Preliminary Evaluation ACHD Alley Retrofit Project Initial Evaluation Site Selection, Design, and Construction (October 2014) The purpose of this document is to characterize

More information

Moving a House in Pasadena

Moving a House in Pasadena Moving a House in Pasadena To assist homeowners and contractors wishing to relocate a home in Pasadena, this handout summarizes the steps in the permitting process. Please keep in mind that the sequence

More information

Soapstone Connector Feasibility Study

Soapstone Connector Feasibility Study Technical Report Soapstone Connector Feasibility Study Prepared by ATCS, plc., 2553 Dulles View Drive, Herndon, VA 20171, (703) 430-7500 www.atcsplc.com In association with: Michael Baker Corporation,

More information

ORDINANCE CODES FOR PARKING TICKETS

ORDINANCE CODES FOR PARKING TICKETS ORDINANCE CODES FOR PARKING TICKETS Ordinance Ordinance Fine Fine if towed Code 001 Expired Meter (Municipal Lot) - Did park a motor vehicle in a municipal lot without paying or depositing in the meter,

More information

Planning and Zoning Commission Johnston, Iowa June 29, 2015

Planning and Zoning Commission Johnston, Iowa June 29, 2015 ITEM NO. 15-19 Planning and Zoning Commission Johnston, Iowa June 29, 2015 SUBJECT: Consider recommending approval of the Final Plat for Crosshaven Plat 6 subdividing 28.28 acres into 47 single family

More information

Florida Avenue Multimodal Transportation Study. June 19, 2013

Florida Avenue Multimodal Transportation Study. June 19, 2013 Florida Avenue Multimodal Transportation Study June 19, 2013 Today s Agenda Team & project introduction Project Timeline What you said Tools we use Mapped data and what clues it can provide Highlights

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

Development Project Report For the Month of: March 2014

Development Project Report For the Month of: March 2014 Project Project Description Project Status Commercial / Office Projects Collierville Auto Center DD# 12-046 Relocation of used automobile dealership comprised of two properties totaling 0.76 acre at 651

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

STANDARDIZED CLASSIFICATION SYSTEM TO ASSESS THE STATE AND CONDITION OF INFRASTRUCTURE IN EDMONTON

STANDARDIZED CLASSIFICATION SYSTEM TO ASSESS THE STATE AND CONDITION OF INFRASTRUCTURE IN EDMONTON STANDARDIZED CLASSIFICATION SYSTEM TO ASSESS THE STATE AND CONDITION OF INFRASTRUCTURE IN EDMONTON Theresa Cloake, P.Eng. Infrastructure Analyst and K.L. Siu, P.Eng. Senior Infrastructure Officer Office

More information

AGENDA ITEM SUMMARY FORT COLLINS CITY COUNCIL 11

AGENDA ITEM SUMMARY FORT COLLINS CITY COUNCIL 11 DATE: September 4, 2012 STAFF: Patrick Rowe, Terry Tyrell Helen Matson AGENDA ITEM SUMMARY FORT COLLINS CITY COUNCIL 11 SUBJECT Second Reading of Ordinance No. 080, 2012, Authorizing the Acquisition by

More information

BGE Service Application Guidelines Commercial & Industrial Projects

BGE Service Application Guidelines Commercial & Industrial Projects BGE Service Application Guidelines Commercial & Industrial Projects To the Customer Following is important information to assist you in applying for BGE gas and/or electric service and in completing the

More information

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting? Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting

More information

WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW

WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-02 WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW Mark Oberschmidt, P.E., Stantec,

More information

IDOT Chicago - St. Louis High-Speed Rail Program Management

IDOT Chicago - St. Louis High-Speed Rail Program Management 1 www.idothsr.org www.connectthemidwest.com IDOT Chicago - St. Louis High-Speed Rail Program Management Lessons Learned: Sealing the Corridor For 110 MPH Operations Thomas W. Hunter Parsons Brinckerhoff

More information

Floodplain Development Land Use Review

Floodplain Development Land Use Review COMMUNITY DEVELOPMENT DEPARTMENT Planning Division P.O. Box 490 333 Broadalbin Street SW Albany, OR 97321 Phone 541-917-7550 Fax 541-791-0150 www.cityofalbany.net Floodplain Development Land Use Review

More information

STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN

STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN JULY 2015 Standard Elements of a Construction Management Plan (CMP) This guidance tool was developed through partnership between the Department of Planning

More information

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline GOUVEIA ENGINEERING Pre-Bid Conference Meeting Minutes City of Los Banos Henry Miller Area Storm Drain and L Street Waterline Conference held at Intersection of West I Street and L Street, in Los Banos

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

RESIDENTIAL BUILDING PERMIT REQUIREMENTS

RESIDENTIAL BUILDING PERMIT REQUIREMENTS RESIDENTIAL BUILDING PERMIT REQUIREMENTS The Building Inspection Division has compiled this packet to help our customers obtain a Building Permit. Enclosed we have listed all departments and inspection

More information

AREA: 2.37 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF. Single-family, Non-conforming machine shop

AREA: 2.37 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF. Single-family, Non-conforming machine shop FILE NO.: Z-8958 NAME: Rock Structure Repair Short-form PID LOCATION: Located at 8024 Stanton Road DEVELOPER: Rock Structure Repair Attn. Rudy Gutierrez 3 Kipling Court Little Rock, AR 72209 ENGINEER:

More information

Capital Projects Town Hall Meeting

Capital Projects Town Hall Meeting Capital Projects Town Hall Meeting Planning, Architectural & Engineering Services September 15, 2014 Agenda Project Updates Recently Completed and in Construction Projects in Design Projects in Planning

More information

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS COMMUNITY OUTREACH MEETING AGENDA Introductions History of PWSA Actions August 31 Storm Impacts Short

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

Owner s Procurement Forum

Owner s Procurement Forum Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

City of Powder Springs

City of Powder Springs Metropolitan North Georgia Water Planning District 214 Implementation Survey WATERSHED MANAGEMENT PLAN Name: Jurisdiction: City of Powder Springs Email: Phone: Stormwater Management Action Item 5.D.2:

More information