1 The Institution of Engineering and Technology Savoy Place BREEAM Bespoke 2008 Credit Man 9 Publication of Building Information Case Study Report 1

2 Contents Project Description Sustainability Innovation at Savoy Place BREEAM Rating and Score The Key Innovative and Low Impact Design Features Of The Building Costs Functions and Areas Predicted Energy Consumption Construction Management Techniques to reduce Environmental Impacts Next Steps 2

3 Project Description Background The IET is a world leading professional organisation sharing and advancing knowledge to promote science, engineering and technology across the world 167,000 members worldwide in 127 countries. Savoy Place is the institutional headquarters and a unique conferencing venue set beside the Thames in London s city centre, blending historic character, the latest built in technology, stunning waterside views and top notch catering Project Aspirations, Aims and Priorities Introduce a distinct sense of place and belonging for the Institution members Apply the Vision, Mission and Values of the Institution wherever appropriate. Provide a generous and welcoming arrival and entry sequence Restore clear vertical and horizontal circulation routes throughout Create a series of contemporary uplifting spaces and places while retaining the important heritage aspects of the building and of the Institution. Introduce facilities appropriate to the beginning of the 21 century Capitalise on the riverside location and exploit the stunning views Optimise the revenue earning potential for functions and events Project Team Team Role Architect Services Engineers Structural Engineer Quantity Surveyor Contractor Company Pringle Richards Sharrat MTT Limited Alan Baxter Associates Rider Hunt Gilbert Ash 3

4 Sustainability Innovation at Savoy Place Overview As part of its role to share and advance knowledge to promote science, engineering and technology, the IET actively engaged with the Building Research Establishment (BRE) and others to explore current and emerging best practice in sustainable refurbishment. This engagement has allowed lessons learnt from project experiences at Savoy Place, along with the wider knowledge that the IET has in the Built Environment Sector, to be shared to the benefit of all. Project Team dialogue with the BRE A Sustainability Review of the proposed scheme was undertaken starting in June 2012 between the Project Team and sustainability experts from the BRE. This explored a range of issues under the headings of energy performance, sustainable materials, benefits of refurbishment to building users, building performance monitoring and innovation, appearance, cost and information/technology insight The Sustainability Review also set out an aspiration to substantiate any claims about the environmental performance of the building by benchmarking it against an appropriate and recognised scheme and to inform the development of the project in response to recommendations arising from that exercise. Site Visits BRE Innovation Park and Arcola Theatre As part of the Sustainability Review, in May 2012 the Project Team visited the BRE Innovation Park in Watford, a showcase of sustainable buildings and hundreds of low carbon products, materials and technologies. The Victorian Terrace (supported by The Department of Energy and Climate Change) gave useful insight into measures to improve the energy performance of hard to treat heritage buildings whilst retain their original character a living laboratory demonstrating the latest processes, materials and technological advances in sustainable refurbishment. The Project Team also visited the Arcola Theatre in Dalston the world s first Carbon Neutral theatre to understand how sustainability is integrated in to the core ethos of this arts and community venue and to visit their Clean Energy Technology Incubator. 4

5 BREEAM Non Domestic Refurbishment Pilot Project Whereas Savoy Place is being assessed under BREEAM 2008, a key outcome of the engagement with the BRE was work to help develop their new BREEAM standard for sustainability in historic building refurbishments, with Savoy Place used as a key pilot case study. Through close liaison with the Project Team and BREEAM assessor, a detailed review of the design was undertaken against the BREEAM Refurbishment criteria to identify and document the key challenges and achievements for the project, with a focus on the more challenging and sensitive issues to achieve in historic buildings. These issues included improving daylighting, air quality, building fabric and services and use of sustainable materials in order to understand the restrictions and opportunities. The pilot study looked at how sustainability standards can be set for historic buildings by testing out strict environmental criteria now adopted in BREEAM Refurbishment and Fit Out on the design proposals for Savoy Place. A description of the contribution of the Savoy Place to this process now features on the BRE website and in their publication Sustainable Refurbishment of Heritage Buildings 5

6 BREEAM Rating and Score Overview BREEAM (the Building Research Establishment Environmental Assessment Method) is an independent, transparent environmental labelling scheme for new build and major refurbishment projects. It assesses the environmental quality of a project by considering the broad concerns of climate change, use of resources, pollution and impacts on biodiversity. The BREEAM scheme assesses the scheme at both the design and post construction stages. The post construction review serves to confirm the interim assessment (done at the design stage) and, most importantly, that the as built performance matches that envisaged at the design stage. An overall rating of the building s performance is given using the terms Pass, Good, Very Good, Excellent, or Outstanding. BREEAM Scheme BRE have confirmed that Savoy Place should be assessed under BREEAM Bespoke BREEAM Bespoke is also known as BREEAM Other Buildings. Presently, all refurbishment projects are still assessed under the BREEAM 2008 schemes, as BREEAM 2011 is for new construction only. It is expected that BRE will launch BREEAM 2012 for refurbished building later this year, but other than generally being more onerous, no details of what the scheme will contain have been published. Based on the changes for new building between BREEAM 2008 and BREEAM 2011 New Construction, it is likely that a rating (say from Very Good to Good ) would be dropped by the same project if scored under the newer scheme. 6

7 7

8 BREEAM Scoring A BREEAM Bespoke 2008 Rating of Very Good is to be achieved; the score currently targeted is 58.60% Maximum % Outstanding 85.00% Excellent 70.00% Savoy Place 58.60% Very Good 55.00% Good 45.00% Pass 30.00% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Target BREEAM Rating Very Good (58.60%) Savoy Place Maximum Man. H & W. Ene. Trans. Water Matls. Waste LUE Pol. Target BREEAM Scores by Category 8

9 Key Innovative and Low Impact Design Features of the Building Overview Building Fabric Measures Potential Measure Enhance Glazing Insulation (double, low e, triple...) Fit Draught Stripping Around Windows/Doors Shading Devices to Reduce Heat Gain Enhancement of Insulation to External Wall Construction Roof Insulation Floor Insulation Use Pale Colours In Walls And Ceilings Typical Approach Secondary double glazing Reglazing existing window units; replacement of single glazed panes with double Replacement of complete double units with glazed units Replacement of complete units with triple glazed units Internal blinds manually operated Internal blinds automatically operated External blinds Brise soleil Filling existing cavity wall with insulation injected cavity wall Internal lining of external walls with insulation and dry lining Over cladding building externally with insulated panels Installation of additional insulation within existing pitched roof construction Insulation of existing flat roof construction; additional existing roof covering insulation overlaid on Insulation of existing flat roof coverings replaced construction; roof Insulation of existing flat roof construction; roof coverings replaced Application of additional insulation within floor finish 9

10 Building Services Measures Potential Measure Energy Efficient Lighting Lighting Control Zones Daylight Sensors Enhance daylight by placing lights where they are most cost effective. Adjust lighting levels to type of activity undertaken Reflective Baffles for Luminaires Upgrade to More Efficient Boiler Optimise Heat Recovery Optimise Pipe Sizes and Layouts to Reduce Resistance to Fluid Flow Upgrade Pumps Heating Control Zoning Upgrade Mechanical Ventilation System Ventilation System Optimisation Upgrade Chillers/Cooling Plant Typical Approach Upgrading of existing lamping Up grading of luminaires Installation of movement sensors Installation of sensors May be provided by discrete task lighting in existing situations or incorporated within a fundamental lighting redesign By use of thermal wheel, plate heat exchanger or run around coil Optimise Length and Size of Hot Water Pipes, Recirculate Mains Circuit LTHW (low temperature hot water) Options include: Tempered fresh air supply system, Full Mechanical Ventilation Optimise Duct Sizes And Layouts To Reduce Resistance To Fluid Flow Option; Ammonia chillers in lieu of air or water cooled chillers Specific Energy Efficiency Measures Potential Measure Building Energy Management System (BEMS) Maintenance Plans and Energy Audits Energy Efficient Policies and Staff Awareness And Training Building Energy Management System (BEMS) Typical Approach As a part of building management plan As a part of building management plan 10

11 Energy Low and Zero Carbon Energy Systems Measures Potential Measure Solar Water Heating Combined heating and Power (CHP) or Combined Cooling Heating and Power (CCHP) Ground Source Cooling Micro Wind Turbines Photovoltaics Typical Approach Roof mounted tiles Various configurations are possible, depending on availability of land and local ground conditions. Roof mounted tiles Water Measures Potential Measure Meter Consumption Implement a Water Management Plan Rainwater Recycling Grey Water Dual Flush Toilets Aerated Taps/Flow Regulated Taps Optimise Length and Size of Water Pipes Place Hot Water Pipes Above Cold Water Ones to Reduce Heat Transfer Reed Bed Water Treatment Drainage Irrigation Insulation on Heating/Hot Water Pipes Typical Approach Provision of water meters and as a part of building management plan As a part of building management plan Recycling hot water main with short tails to individual outlets to minimise volume of water required to run before reaching desired temperature; recirculating mains circuit Waste and Building Materials Measures Potential Measure Carpet Selection Vinyl Flooring Selection Underlay Selection Plasterboard Replacement Typical Approach Provision of water meters and as a part of building management plan As a part of building management plan 11

12 Ecology, Biodiversity and Land Use Measures Potential Measure Green Roof Green Wall Bird and Bat Boxes Perches and Voids Additional Rooftop or Terrace Planting Enhanced External Landscaping Water Features Typical Approach Extensive (shallow substrate usually planted with sedum, grass or moss) or intensive (deep substrate capable of supporting larger p ants, can be used as a garden or park) External vertical planting structure or terrace planting Ponds, swales and fountains Final Selected Measures Improved lighting efficiency including daylight control throughout is a reasonable target for the building. Internal gains can be reduced by specifying energy efficient equipment, lamps and luminaires, or controls to switch off lighting/equipment when not required. Where practicable, the IET office spaces should have openable windows, enabling natural ventilation for the occupants as current ambient conditions allow and providing a 'future proofed' cooling strategy should local noise and air quality conditions improve Providing a high level Energy Management Strategy for building management, particularly with respect to optimising the building s operation, small power loads and equipment should be seen as a priority for the building. As far as possible, areas of the building shall be metered separately to encourage energy efficiency and responsible use of heating, cooling, ventilation and lighting. A high efficiency mechanical ventilation heat recovery (MVHR) system should be installed where possible to air handling units serving the building. Specific Fan Powers of W/l/s, heat exchanger efficiency of 65% or more are possible for the building. 12

13 Costs Element Total Building Cost Based on the Contract Sum of 20,485, and a GIA of 8,875m2 M and E Services Based on the Contract Sum value of the services of 10,131,950 (including additions for GA Prelims and OHP) External Works (Inc Drainage and Ext Services) Based on the Contract Sum value of the external works of 81,413 (including additions for GA Prelims and OHP), Cost /m 2 2,308 / m 2 1,142 / m 2 9 / m 2 Functions and Areas Function Area m 2 Arrival Hall and Foyers 167 Reception Desk 33 Offices 504 Meeting Room 185 Conference and Events 983 Council Chamber and Lecture Theatre 285 Library 373 Catering Station 233 Kitchen 138 Kelvin Lounge 173 Bar 24 Staff Changing 70 Breakout/Exhibition Space

14 Construction Management Techniques to Reduce Environmental Impacts A requirement of the BREEAM assessment is to publicise to relevant stakeholders information relating to the aspects of the design and procurement which will reduce the building s overall environmental impact. Construction has been planned and executed to minimise the impact of the work on the environment. Steps taken include: The contractor and site are registered under the Considerate Contractors Scheme with regular inspection. The contractor is committed to going beyond best practice under this scheme and is aiming to achieve a score of more than 32 points The contractor has implemented a construction site waste management plan to maximise the amount of waste that will be recycled and reused The contractor is committed to monitoring site energy and water consumption and to implementing best practice procedures to minimise dust (air) pollution and water pollution Recycling facilities are provided in the building and onsite The construction elements are all Green Guide A or A+ rated Specific Measures implemented during construction to reduce environmental impacts include Metered Temporary Services Segregation of Site Waste Recycled Timber used for site hoardings Constant monitoring of site noise (sound insulated tools and silenced plant to be used Site dust (wet cutting used to reduce dust) Accurate measurement of site materials to minimise waste Labour, plant and materials will use local suppliers. 14

15 Next Steps To understand the ongoing sustainability performance of the completed Savoy Place, it is proposed to assess the building under the BREEAM In Use standard. BREEAM In Use assists property managers and occupiers to drive sustainable improvements through effective building management. It seeks to reduce operational resource use (energy, water, materials), improving the wellbeing, productivity and satisfaction of people working and visiting in the building and helping bridge the 'performance gap' between modelled performance and that experienced in use. It provides independent third party certification of a building s sustainability, contributing to corporate social responsibility, business reporting and sustainability leadership. 15

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched

More information

Elaine Harvie & Jeremy Cruickshank Jan 10

Elaine Harvie & Jeremy Cruickshank Jan 10 Elaine Harvie & Jeremy Cruickshank Jan 10 3 Assembly Square, Cardiff - EXCELLENT BREEAM International Introduction Elaine Harvie Mechanical Engineer BREEAM Assessor Offices School/Education Industrial

More information

Energy Efficiency HOSPITALITY. www.energia.ie

Energy Efficiency HOSPITALITY. www.energia.ie Energy Efficiency HOSPITALITY www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real

More information

BREEAM Europe. This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe.

BREEAM Europe. This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe. BREEAM Europe BREEAM Europe This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe. Key objectives Provide consistency and comparability

More information

Code for Sustainable Homes Guidelines

Code for Sustainable Homes Guidelines Canoldir Penrhos Anglesey LL65 2TS Phone: 01407 860666 Email: saps@easonline.co.uk www.easonline.co.uk Code for Sustainable Homes Guidelines A CSH rating is the responsibility of the Developer/ Architect

More information

Energy Efficiency. Bars & RestauRants. www.energia.ie

Energy Efficiency. Bars & RestauRants. www.energia.ie Energy Efficiency Bars & RestauRants www.energia.ie 2 Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could

More information

HHHHH Outstanding 85%

HHHHH Outstanding 85% Provinciehuis_Assessment_2040204_74,32%Final Score and Rating BREEAM Scheme: Europe 2009: Offices H Pass 30% Building Name: Provinciehuis Antwerpen HH Good 45% BREEAM Registration No.: BREEAM-0048-4626

More information

Green and Sustainable Buildings

Green and Sustainable Buildings Green and Sustainable Buildings Design Criteria and Application in Hong Kong Green building is the practice of increasing the efficiency with which buildings use resources energy, water and materials.

More information

Industrial & Research Profile

Industrial & Research Profile OXFORD Bagley Croft Hinksey Hill Oxford OX1 5BS Tel: 01865 329 100 Fax: 01865 326 822 BRISTOL The Workshop 254 Southmead Road Bristol BS10 5EN Tel: 0117 958 1500 Fax: 0117 958 1501 www.oxford-architects.com

More information

Green House, Hungary

Green House, Hungary Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support noel.morrin@skanska.se Green House, Hungary Case Study 109 Aspects of Sustainability This project

More information

Holistic Approach in Delivering Government Buildings The Low Carbon Concept

Holistic Approach in Delivering Government Buildings The Low Carbon Concept International Conference on Planning for Low Carbon Cities 22 May 2009 Holistic Approach in Delivering Government Buildings The Low Carbon Concept Ir. HO Sai-king, Assistant Director (Building Services),

More information

Sustainability: Green hotels

Sustainability: Green hotels Sustainability: Green hotels 10 October 2013 How green is your hotel? Azita Dezfouli and Adam Mactavish of Sweett Group look at the practical steps for reducing the environmental impact of hotels during

More information

Rainwater Harvesting

Rainwater Harvesting Rainwater Harvesting With climate change now a reality rather than a speculated possibility, the demand on water resources has gone up, whilst the amount of water available for supply has gone down. Forth

More information

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) 1. In addition to the information scheduled below, the pre-tender designer is responsible for: (i)

More information

250 St Georges Tce, Perth, WA (QV1)

250 St Georges Tce, Perth, WA (QV1) 250 St Georges Tce, Perth, WA (QV1) Building Profile Building Construction date 1991 Refurbishment date Owner Building Size Refurbishment Team Building Management Awards Ratings QV.1, 250 St Georges Terrace,

More information

HEATING, VENTILATION & AIR CONDITIONING

HEATING, VENTILATION & AIR CONDITIONING HEATING, VENTILATION & AIR CONDITIONING as part of the Energy Efficiency Information Grants Program Heating and cooling can account for approximately 23 % of energy use in pubs and hotels 1. Reducing heating

More information

CONDUIT MAYFAIR READY FOR OCCUPATION SPRING 2014 GLINSMANWELLER.CO.UK A DEVELOPMENT BY LONDON PROPERTY PARTNERSHIP LTD

CONDUIT MAYFAIR READY FOR OCCUPATION SPRING 2014 GLINSMANWELLER.CO.UK A DEVELOPMENT BY LONDON PROPERTY PARTNERSHIP LTD 12 CONDUIT S T R E E T MAYFAIR READY FOR OCCUPATION SPRING 2014 020 7495 2728 GLINSMANWELLER.CO.UK A DEVELOPMENT BY LONDON PROPERTY PARTNERSHIP LTD 12 CONDUIT STREET The entire building is undergoing a

More information

EFA PSBP. Natural Ventilation Strategy. Introduction. 1.1 Relevant legislation. 1.1.1 The Building Regulations 2010

EFA PSBP. Natural Ventilation Strategy. Introduction. 1.1 Relevant legislation. 1.1.1 The Building Regulations 2010 EFA PSBP Natural Ventilation Strategy Introduction The Baseline Designs Project will provide scheme design details for a number of Primary and Secondary School Exemplars. For the purposes of setting a

More information

Report Date: 04/03/2014. Assessor: John Doyle Address: BLOCK K APT 108 SANDYFORD VIEW DUBLIN 18 BER: 106178106 MPRN: 10301589669

Report Date: 04/03/2014. Assessor: John Doyle Address: BLOCK K APT 108 SANDYFORD VIEW DUBLIN 18 BER: 106178106 MPRN: 10301589669 Report Date: 04/03/2014 Assessor: John Doyle Address: BLOCK K APT 108 SANDYFORD VIEW DUBLIN 18 BER: 106178106 MPRN: 10301589669 About this Advisory Report Energy use in our homes is responsible for almost

More information

Low Carbon Domestic Refurbishment

Low Carbon Domestic Refurbishment www.breeam.com Briefing Paper Low Carbon Domestic Refurbishment Kiruthiga Balson, Gavin Summerson and Steven Stenlund 2 BRE Global Ltd 2014 Permission is granted for this report to be distributed only

More information

Our Triple Bottom Line...

Our Triple Bottom Line... Our Triple Bottom Line... A Better Approach We embrace what we consider to be our responsibility as developers to balance profits with environmental and social dividends. We believe that our long-term

More information

Council s energy efficiency upgrades benefit community

Council s energy efficiency upgrades benefit community Council s energy efficiency upgrades benefit community Project Snapshot Objective: reduce energy, save money & improve comfort in public buildings Where: Meander Valley Council, Northern Tasmania Total

More information

Energy Company Obligation (ECO): Technical Monitoring Questions

Energy Company Obligation (ECO): Technical Monitoring Questions Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified

More information

SUSTAINABLE BUILDINGS

SUSTAINABLE BUILDINGS SUSTAINABLE BUILDINGS ACHIEVING A BREEAM EXCELLENT RATING GUIDANCE NOTE FOR BREEAM 2008 ASSESSMENTS Document Issued January 2009 CURRENT REQUIREMENTS: The Welsh Assembly Government has a duty to have a

More information

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues Design Guide Retrofitting Options For HVAC Systems In Live Performance Venues Heating, ventilation and air conditioning (HVAC) systems are major energy consumers in live performance venues. For this reason,

More information

Introduction to the London Energy Efficiency Fund (LEEF)

Introduction to the London Energy Efficiency Fund (LEEF) Executive Summary Introduction to the London Energy Efficiency Fund (LEEF) 1. The London Green Fund (LGF) is a 100m Fund comprising of 50m from the London 2007-13 European Regional Development Fund (ERDF)

More information

Passive & Active Design

Passive & Active Design Passive & Active Design CIBSE Building Simulations Group Peter A. Brown CEng, MBA October 2010 Introduction Passive & Active Design Introduction What are the interactions between passive and active design?

More information

RULES FOR THE SETTING UP OF SUSTAINABLE BRANCHES Summary

RULES FOR THE SETTING UP OF SUSTAINABLE BRANCHES Summary RULES FOR THE SETTING UP OF SUSTAINABLE BRANCHES Summary January 2013 TABLE OF CONTENTS INTRODUCTION... 3 GENERAL RECOMMENDATIONS... 3 Communication with customers in the field of environmental sustainability...

More information

Energy efficient home design

Energy efficient home design Energy efficient home design GUIDELINES How an energy efficient home can help you live in comfort and save money An energy efficient home is designed to provide shade and allow cooling breezes to enter

More information

energy in education promoting energy efficiency in schools

energy in education promoting energy efficiency in schools The DART Energy Research Programme Recognising that the programme should be as much about people and changing cultures while delivering service the approach was developed initially through the four different

More information

Archant London Environmental Awards

Archant London Environmental Awards Archant London Environmental Awards Environmental Business of the Year Big Yellow Self Storage PLC Barking Central, Hertford Road, Barking, IG11 8BL Introduction Big Yellow is a local business that has

More information

Lead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers

Lead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers SOLUTIONS FOR SUSTAINABLE BUILDINGS THE GUIDE TO BREEAM Lead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers Reynaers develops innovative and sustainable aluminium solutions, for

More information

AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries

AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries Hot tips and cool ideas to save energy and money! Air conditioning units or systems are often used by foundries

More information

Each icon on this map represents the physical location of a station.

Each icon on this map represents the physical location of a station. ABBOTSFORD SCHOOL DISTRICT: GREEN TOUR TOMORROW S SUSTAINABLE SOLUTIONS TODAY Welcome to the Abbotsford School District: Green Tour. Our goal is to create an interactive learning experience for visitors

More information

The Business Case Annual fuel cost savings of 26% worth more than 28,000 Annual fuel savings of 1.3million kwh Annual CO2 savings of over 245 tonnes

The Business Case Annual fuel cost savings of 26% worth more than 28,000 Annual fuel savings of 1.3million kwh Annual CO2 savings of over 245 tonnes North Lanarkshire Council The Business Case Annual fuel cost savings of 26% worth more than 28,000 The Sir Matt Busby Sports Complex is an important local facility for the people of Bellshill, North Lanarkshire.

More information

50 St Mary Axe London EC3

50 St Mary Axe London EC3 50 St Mary Axe London EC3 Letting specification 1.Structure and Envelope The main superstructure comprises of a braced steel fame (app 7m span / 90min fire rated) and the elevations are formed from a series

More information

WINDSOR GARDENS VOCATIONAL COLLEGE REDEVELOPMENT

WINDSOR GARDENS VOCATIONAL COLLEGE REDEVELOPMENT PP 283 FINAL REPORT WINDSOR GARDENS VOCATIONAL COLLEGE REDEVELOPMENT 484TH REPORT OF THE PUBLIC WORKS COMMITTEE Published pursuant to section 17(7) & (8) P tamentaty C-onentitter1991 Second Session, Fifty-Second

More information

Capital Expenditure. The common definition of capital expenditure is

Capital Expenditure. The common definition of capital expenditure is Capital Expenditure Under standard accounting practices local authorities are required to account for revenue expenditure and capital expenditure differently. Capital expenditure is defined in the Local

More information

Public Sector Sustainability Report 2013-14

Public Sector Sustainability Report 2013-14 Public Sector Sustainability Report 2013-14 Date: August 2014 Version number: 3 Owner: Approval route: Approval status: Michael Browne, Estates Operations Manager Audit Committee and Senior Management

More information

BAM CONSTRUCT. Dunsbury Hill Farm. BREEAM Pre-assessment Summary. BAM Sustainability department 2015

BAM CONSTRUCT. Dunsbury Hill Farm. BREEAM Pre-assessment Summary. BAM Sustainability department 2015 BAM CONSTRUCT Dunsbury Hill Farm BREEAM Pre-assessment Summary BAM Sustainability department 2015 1.0 Introduction This report is intended as a summary of the pre-assessment for the following BREEAM assessment:

More information

case studies Safely applied, Environmentally creative and effective engineering solutions

case studies Safely applied, Environmentally creative and effective engineering solutions Safely applied, Environmentally creative and effective engineering solutions T: 02392 435050 @: eng@itdconsultants.co.uk www.itdconsultants.co.uk case studies Churchill House Main Features: A 1.5m refurbishment

More information

Guide to Improving Your Home

Guide to Improving Your Home Guide to Improving Your Home WELCOME Contents Where to start 03 Improvement ideas 04 Outside 04 Kitchen 05 Living space 05 Bathroom 06 Bedrooms 06 Get more space 07 Add an extension 07 Convert a garage

More information

CULLINAN STUDIO FOUNDRY (CULLINAN STUDIO OFFICES)

CULLINAN STUDIO FOUNDRY (CULLINAN STUDIO OFFICES) FOUNDRY ( OFFICES) Location: Islington, London, UK Client: Cullinan Studio Started on site: October 20 Completed: September 202 Size: 78sqm (GIA) Construction cost:.m Awards: RICS London Awards - Design

More information

Energy Efficiency and Renewable Energy For Schools

Energy Efficiency and Renewable Energy For Schools Energy Efficiency and Renewable Energy For Schools Jesse Putzel & David Pitcher (energy conservation and solar centre) ecsc - who we are Environmental Charity involved in both energy efficiency and renewable

More information

Business energy management and. investment. Case studies

Business energy management and. investment. Case studies Business energy management and Case studies Ashley Primary School Ashley Shopping Centre Birtley House Nursing Home Canon Coulsdon Audi Guildford Borough Council Harlequin Theatre and car park High Ashurst

More information

MILTON HALL BCO AWARDS 2014 THE WORKSPACE CONSULTANTS LLP

MILTON HALL BCO AWARDS 2014 THE WORKSPACE CONSULTANTS LLP MILTON HALL BCO AWARDS 2014 EXTERNAL ELEVATIONS MILTON HALL THE EAST WING THE LINK BUILDING NORTH - WEST ELEVATION (1:200@A3) MILTON HALL THE LINK BUILDING THE NORTH WING SOUTH - EAST ELEVATION (1:200@A3)

More information

Assessment Methods. 15 th November 2010 Huw Jenkins Simon Lannon

Assessment Methods. 15 th November 2010 Huw Jenkins Simon Lannon Assessment Methods 15 th November 2010 Huw Jenkins Simon Lannon Assessment Methods Program Country Year Program Country Year 1 R-2000 Canada 1982 12 LEED US 2000 2 P-mark Sweden 1989 13 ECO-Quantum Netherlands

More information

CULLINAN STUDIO. Design for Schools

CULLINAN STUDIO. Design for Schools CULLINAN STUDIO Design for Schools This page: Torriano Junior School Gatehouse, Camden. Photo Edmund Sumner Cover: Holy Cross Primary School, Swindon. Photo Paul Raftery We design great schools We are

More information

Case Studies of Successful Code for Sustainable Homes Projects

Case Studies of Successful Code for Sustainable Homes Projects Case Studies of Successful Code for Sustainable Homes Projects Sustainable Homes publish the Sustainable Homes Index For Tomorrow (SHIFT) and are a leading trainers of Code for Sustainable Homes assessors.

More information

Only two floors remaining

Only two floors remaining Only two floors remaining 2,697-20,615 sq ft St Peter s Square www.stpetersstockport.com Stockport town centre s first grade A, BREEAM Excellent office building. TO LET Stockport 51,402 sq ft Full grade

More information

Best Practice Guide BPGCS007

Best Practice Guide BPGCS007 Best Practice Guide BPGCS007 ENERGY MANAGEMENT Introduction: With rising fuel costs, opening of electricity and gas markets to alternate suppliers and climate change, the requirement to monitor and reduce

More information

Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings

Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings Duchy Homes Site: Cantley Lane Doncaster Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings 22 nd February 2013 Leanne Brooksbank Accredited Energy & Code

More information

Energy Saving Tips. They can have a dramatic impact on your bill. The cheapest energy is the energy you don t use.

Energy Saving Tips. They can have a dramatic impact on your bill. The cheapest energy is the energy you don t use. Energy Saving Tips They can have a dramatic impact on your bill. The cheapest energy is the energy you don t use. Drive by your building at night. Driving by your building at night makes it easy to check

More information

Bloomsbury Colleges Environmental Policy Statement

Bloomsbury Colleges Environmental Policy Statement 15 December 2011 P a g e 1 Bloomsbury Colleges Environmental Policy Statement The Bloomsbury Colleges are committed to the responsible use of energy, water and other resources with the aim of minimising

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

Measures for reducing risk and increasing

Measures for reducing risk and increasing Design for Adaptation Measures for reducing risk and increasing resilience Flooding Avoiding flood risk areas, ensuring areas and buildings are resistant or resilient. Extreme weather Construction & design

More information

Apartments. Setting a new standard in medium density public housing. Change View

Apartments. Setting a new standard in medium density public housing. Change View Setting a new standard in medium density public housing Enter Department of Human Services - Office of Housing Main menu 03 Introduction 05 Site Planning 07 Building Form 08 Passive Solar Design 10 Life

More information

www.adaptcbe.co.uk Business Support

www.adaptcbe.co.uk Business Support www.adaptcbe.co.uk Business Support Events and Seminars The UEA Exemplar Low Carbon Building Project was awarded 6.2m from the European Regional Development Fund in October 2011. As a condition of this

More information

C21 Ecologically Sustainable Development

C21 Ecologically Sustainable Development C21 Ecologically Sustainable Development Sustainable Schools Initiative The Australian Sustainable Schools Initiative (AuSSI) is a partnership between the Australian Government and States and Territories

More information

A global list. The Fortification Depot A CO 2 -reduction project

A global list. The Fortification Depot A CO 2 -reduction project The Fortification Depot A CO 2 -reduction project A global list Passive measures: Windows, glazing, solar shading Insulation of walls, roofs, floors Improving air tightness 1 A global list Technical measures:

More information

VE 6.4.0.5: Thermal / Systems Pack. 1. Tabular Room Data editing for thermal properties

VE 6.4.0.5: Thermal / Systems Pack. 1. Tabular Room Data editing for thermal properties VE 6.4.0.5: Thermal / Systems Pack 1. Tabular Room Data editing for thermal properties There is a new button in Apache, UK Part L2, and PRM Tabular Room Data. This tool represents a real productivity enhancement

More information

ALWAYS ON GLOBALSWITCH.COM

ALWAYS ON GLOBALSWITCH.COM ALWAYS ON GLOBALSWITCH.COM Data Centre Design Considerations Kelvin Fong Managing Director, Hong Kong ALWAYS ON GLOBALSWITCH.COM Agenda 1. Introduction to Global Switch 2. Customer Requirements 3. Development

More information

Klosterenga, Oslo, Norway, 1998-2000 page - 1

Klosterenga, Oslo, Norway, 1998-2000 page - 1 Klosterenga, Oslo, Norway, 1998-2000 page - 1 Introduction Klosterenga is an urban revitalisation project close to the city centre of Oslo. The 3 apartments were built with a focus on energy saving. Next

More information

Facility Support Services

Facility Support Services Facility Support Services The Precision Group has a breadth of experience delivering innovative, first class facility support service solutions to clients across the public and private sectors. Our expert

More information

Sustainable Features. High-performance HVAC. High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure

Sustainable Features. High-performance HVAC. High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure Sustainable Features High-performance HVAC High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure Sustainable Landscaping Recycled and Regional Materials Storm-water Management District

More information

Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study

Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study Robert C. Burns, AIA, LEED AP Principal Director of Historic Architecture 804. 648. 5040, ext. 1107

More information

Tips on Saving Energy in Your Business

Tips on Saving Energy in Your Business Fact Sheet #3 Tips on Saving Energy in Your Business In this fact sheet you will discover: Quick and easy changes to save energy. Cost effective ways to reduce your heating, cooling, lighting and office

More information

BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010

BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010 Building Control Charnwood Borough Council Southfield Road Loughborough LE11 2TN BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010 Page 1 of 6 PURPOSE: This Guidance

More information

CASH SAVING BEATS ECO CONCERNS AS MAIN REASON TO GREEN YOUR HOME

CASH SAVING BEATS ECO CONCERNS AS MAIN REASON TO GREEN YOUR HOME Press Release CASH SAVING BEATS ECO CONCERNS AS MAIN REASON TO GREEN YOUR HOME Saving money is now our main motivation for carrying out green home improvements ahead of concerns for the environment. One

More information

Information for the Supply Chain on Green Deal Measures. Version 1

Information for the Supply Chain on Green Deal Measures. Version 1 Information for the Supply Chain on Green Deal Measures Version 1 January 2013 Contents Introduction... 3 Introduction to the links between Green Deal measures and the Green Deal assessment tools... 4

More information

Fire Resistant Systems

Fire Resistant Systems Fire Resistant Systems A R C H I T E C T U R A L A L U M I N I U M G L A Z I N G S Y S T E M S Fire Resistant Systems Introduction Kawneer are pleased to introduce two new comprehensive Fire Resistant

More information

BRE, BRE Global, BREEAM, Smartwaste and the Green Guide are all trademarks owned by either BRE or BRE Global Limited and

BRE, BRE Global, BREEAM, Smartwaste and the Green Guide are all trademarks owned by either BRE or BRE Global Limited and blank page Terms & conditions Terms and conditions Disclaimer This scheme document is the property of BRE Global Limited and is made publicly available for information purposes only. Any testing, assessment,

More information

City Council Report for Information

City Council Report for Information City Council Report for Information Report to: Subject: Report of: Neighbourhood Scrutiny Committee Sustainable Development Assistant Chief Executive (Regeneration) Summary This report outlines measures

More information

http://www.bca.gov.sg/greenmark/others/gm_nreb_v2.1.pdf

http://www.bca.gov.sg/greenmark/others/gm_nreb_v2.1.pdf Green Mark Criteria for Non-residential Existing Building (Version 2.1) GM for Non-residential Existing Buildings Criteria (Ver. 2.1) can be downloaded from : http://www.bca.gov.sg/greenmark/others/gm_nreb_v2.1.pdf

More information

Part 3 Ancillary technologies. Chapter 3.2. Mechanical ventilation with heat recovery

Part 3 Ancillary technologies. Chapter 3.2. Mechanical ventilation with heat recovery Part 3 Ancillary technologies Chapter CONTENTS SCOPE Clause Page DESIGN Design standards D1 1 Statutory requirements D2 1 System design D3 1 Building integration D4 2 Noise D5 2 Access and controls D6

More information

WELCOME TO OUR EXHIBITION

WELCOME TO OUR EXHIBITION WELCOME TO OUR EXHIBITION The purpose of the exhibition is to provide you with the opportunity to view our proposals and give feedback prior to the submission of a planning application to the London Borough

More information

Concepts. Products. Service. 30 Crown Place, London EC2

Concepts. Products. Service. 30 Crown Place, London EC2 Concepts Products Service 30 Crown Place, London EC2 1 Project Report 30 Crown Place, London EC2. Bold design makes this a striking addition to the London skyline. Occupying an important site close to

More information

Advice Note on Windows in Listed Buildings

Advice Note on Windows in Listed Buildings Advice Note on Windows in Listed Buildings Introduction Windows are an important part of a building s history and can be invaluable to our understanding of historic properties. They can tell us not only

More information

MCS 021. HEAT EMITTER GUIDE FOR DOMESTIC HEAT PUMPS Issue 2.0

MCS 021. HEAT EMITTER GUIDE FOR DOMESTIC HEAT PUMPS Issue 2.0 MCS 021 HEAT EMITTER GUIDE FOR DOMESTIC HEAT PUMPS Issue 2.0 This Guidance is the property of Department of Energy and Climate Change (DECC), 3 Whitehall Place, London,SW1A 2HH. DECC 2014 This guide has

More information

HANLO The WELCOME HOME Experience.!! Simply better homes!!

HANLO The WELCOME HOME Experience.!! Simply better homes!! HANLO The WELCOME HOME Experience!! Simply better homes!! The Mission Our mission is to provide individual, sustainable and affordable homes to self builders and developers that can be built fast, efficient

More information

Systems Selection Enclosure Systems Material Selection Assessment and Mitigation

Systems Selection Enclosure Systems Material Selection Assessment and Mitigation Return to Curriculum Home CES Home Find an AIA/CES Registered Course Self Report a Learning Activity MATERIALS AND METHODS To develop professionally in Practice with a focus on sustainable design, you

More information

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP research journal 2013 / VOL 05.01 www.perkinswill.com SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP ARCHITECTURE AND ENGINEERING OF SUSTAINABLE BUILDINGS Current Trends in Low-Energy HVAC Design

More information

Deep Energy Savings in Existing Buildings

Deep Energy Savings in Existing Buildings Case Study Deep Energy Savings in Existing Buildings Overview Site Details Owner: Alliance for Sustainable Colorado Location: Denver, CO Building Type: Office Project Description: Major Renovation Size

More information

HVAC Processes. Lecture 7

HVAC Processes. Lecture 7 HVAC Processes Lecture 7 Targets of Lecture General understanding about HVAC systems: Typical HVAC processes Air handling units, fan coil units, exhaust fans Typical plumbing systems Transfer pumps, sump

More information

glyndwr.ac.uk/sustainability environmental sustainability strategy

glyndwr.ac.uk/sustainability environmental sustainability strategy glyndwr.ac.uk/sustainability environmental sustainability strategy 2012-2014 overview of the environmental sustainability strategy 2012-2014 Glyndŵr University s Environmental Sustainability Strategy 2012-2014

More information

Welcome. kingscross.iop.org

Welcome. kingscross.iop.org Welcome The Institute of Physics Team Welcome to our exhibition. The purpose of the exhibition is to provide you with the opportunity to view our proposals and give feedback prior to submitting a planning

More information

This report presents the findings and recommendations of the assessment of energy use and

This report presents the findings and recommendations of the assessment of energy use and This report presents the findings and recommendations of the assessment of energy use and environmental stewardship of Arlington Street Church, Boston, MA. As stewards of the earth it is important that

More information

Park View Place. Compass. House. Royal Wharf Gardens Endeavour. House. Thameside. Sienna. House. House. Apartments Townhouses.

Park View Place. Compass. House. Royal Wharf Gardens Endeavour. House. Thameside. Sienna. House. House. Apartments Townhouses. The Townhouses Park View Place A A Compass House A T T T Royal Wharf Gardens Endeavour House T A A Thameside House T Sienna House A A A A T Apartments Townhouses River Thames Compass House Compass House

More information

SAVE ENERGY AT HOME INSULATE AND AIR SEAL

SAVE ENERGY AT HOME INSULATE AND AIR SEAL SAVE ENERGY AT HOME INSULATE AND AIR SEAL Check the roof insulation level and add insulation to maintain minimum R-38 (6 of blown cellulose or equal). Use R-19 between frame or R-10 rigid insulation for

More information

Case Study: Low carbon refurbishment of Westborough Primary School

Case Study: Low carbon refurbishment of Westborough Primary School Case Study: Low carbon refurbishment of Westborough Primary School Summary The buildings at Westborough Primary had evolved through a fragmented and piecemeal series of building additions and adaptations

More information

BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0

BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0 BCA-IDA Green Mark for Existing Data Centres Version EDC/1.0 To achieve GREEN MARK Award Pre-requisite Requirement All relevant pre-requisite requirements for the specific Green Mark Rating are to be complied

More information

Heat Recovery from Data Centres Conference Designing Energy Efficient Data Centres

Heat Recovery from Data Centres Conference Designing Energy Efficient Data Centres What factors determine the energy efficiency of a data centre? Where is the energy used? Local Climate Data Hall Temperatures Chiller / DX Energy Condenser / Dry Cooler / Cooling Tower Energy Pump Energy

More information

Industrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit?

Industrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit? Industrial Green Building 101 Opportunities and Challenges Joanne Sawatzky Senior Project Manager, Light House Sustainability at Work Re-visioning a Sustainable False Creek Flats Light Industrial Green

More information

Fläkt Woods Building Future

Fläkt Woods Building Future Energy, Expertise and Environment with Fläkt Woods Fläkt Woods Building Future Saving energy in building ventilation You must save 20% on energy before 2020. Following the Kyoto protocol the European Union

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: PHONE: PHONE: ARCHITECT/ENGINEER

More information

Advice Series. the maintenance and repair of historic buildings

Advice Series. the maintenance and repair of historic buildings Advice Series the maintenance and repair of historic buildings Jacqui Donnelly - Architectural Conservation Advisor, Department of the Environment, Heritage & Local Government Current publications in the

More information

AN AUDITAC PROPOSED PRELIMINARY AUDIT METHODOLOGY FOR AIR- CONDITIONING FACILITIES

AN AUDITAC PROPOSED PRELIMINARY AUDIT METHODOLOGY FOR AIR- CONDITIONING FACILITIES Technical guides for owner/manager of an air conditioning system : volume 4 AN AUDITAC PROPOSED PRELIMINARY AUDIT METHODOLOGY FOR AIR- CONDITIONING FACILITIES Team France (Project coordinator) Armines

More information

HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015. May 2015

HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015. May 2015 HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015 May 2015 MAYOR OF LONDON Housing Standards: Transition Policy Statement. On 25 March 2015 through a written ministerial statement,

More information

Apartment and Communal Heating Solutions

Apartment and Communal Heating Solutions Apartment and Communal Heating Solutions Apartment and Communal Heating Due to the increasing requirements for more energy efficient buildings and changes to the Code for Sustainable Homes Legislation,

More information

Tysons Sustainability Summit Evidence Based Urban Design. Roger E. Frechette III, PE, LEED-AP

Tysons Sustainability Summit Evidence Based Urban Design. Roger E. Frechette III, PE, LEED-AP Tysons Sustainability Summit Evidence Based Urban Design 2013 Autodesk Roger E. Frechette III, PE, LEED-AP Live in Harmony with Nature Transit Community Energy Waste Air Quality Water Yujiapu Financial

More information