Joints in Concrete Structures

Size: px
Start display at page:

Download "Joints in Concrete Structures"

Transcription

1 Joints in Concrete Structures Joints are usually part and parcel of structures made up of concrete, steel, masonry etc. Concrete structures usually call for a varieties of joints. The most commonly experienced among them are a) Construction joint b) Expansion joint c) Contraction joint and d) Isolation joint. Of these, expansion joint and isolation joint are sometimes found to be regarded as the same type. That could be because an expansion joint is also seen as an isolation joint as it too isolates one part of the structure from another. Similarly, an isolation joint is sometimes seen as an expansion joint as well because it too can accomodate heat-induced expansion of concrete members. But, actually both are distinct joints. An expansion joint is meant to take care of the stresses developed purely due to the heat-induced expansion of concrete members while an isolation joint is provided to tackle the stresses likely to result from differential settlement of adjacent members or structures. a) Construction joint : This type is the most commonly experienced joint in most concreting work in spite of the fact that this type of joint is actually not a must in concrete structures unlike the other three types. A construction joint is provided when concrete pouring needs to be stopped due to some reason and then is continued again later. This is done to retain the monolithic nature of the structure which otherwise would be broken due to the break in the continuity. In other words, the joint could have been avoided if the entire concreting were completed without any stopping in between so that no part of the structure needs to be continued (by concreting) at a later date. Practically that is often not possible, especially for larger structures. Interruptions can happen due to varieties of reasons such as sudden breakdown of machinery, stopping of work at the end of the day, sudden heavy rain, installation of formwork for next lift (for wall, column etc.) and so on. Sometimes provisions for future extention of a building or a structure are required to be kept. Construction joints are often required at the ends of beams, slabs, tie beams etc, in such cases, for the purpose of future extention.

2 Since, construction joints are practical requirements for most concrete structures they should preferably be planned beforehand, wherever possible, and shown in the construction drawings. That would help in planning the concrete pour-plan accordingly and also in preparing the joints properly. Construction joints resulting from unforeseen events like rain, machinery breakdown etc, however, can arise at any moment and one should just stay prepared for such cases. A construction joint can be avoided if it can be coincided with an expansion joint as monolithic nature of structure is always broken at expansion joints. Where contraction joints are required to be provided, it is always better to plan construction joints to coincide with contraction joints so as to minimise the number of joints in a structure. Concrete s capacity to take bending stresses is negligible. In reinforced concrete the steel bars take the stresses due to bending moment (BM) while the concrete has to endure primarily the shear stresses. Hence, planes of minimum shear force (SF) in structures are the ideal locations for providing construction joints. One need not worry about BM stresses as there always are enough reinforcement to take care of it and concrete does not have to bear stresses due to BM. So, in case of a beam or a slab the middle third span is the zone for providing construction joints where shear stresses are the minimum. For a column, a construction joint may be provided 3 to 4 inches below the lowermost soffit of the adjoining beams. The plane of a construction joint should be perpendicular to the steel reinforcement of the concrete member. The formwork for construction joints should have shear key blocks. Shear keys provide better interlocking and thus more efficient transfer of SF between the old and new concrete. Forms should also have well located perforations to allow the reinforcement or dowel bars to pass through. Dowel bars are usually provided when a slab, pavement etc would be subjected to heavy loads or vehicular traffic. They may as well have to be provided when concreting has to be stopped at high SF zone due to sudden unforeseen reasons as mentioned above. Shear keys are not necessary where dowel bars are provided. Before continuing concreting the formwork and shear key blocks are stripped. If concreting is continued within a day or two of stopping the work, the construction joint is thoroughly water cleaned and then a layer of rich mortar is applied onto it before proceeding with the concreting.

3 For an older joint it s surface is roughened first and then water cleaned well to get rid of all dirts, loose materials etc. Thereafter, a layer of rich mortar is applied and concreting is resumed. Discussion on the other three types ie, expansion joint, isolation joint and contraction joint is continued in Part II & III. Expansion joint : Concrete structural members such as slabs, pavement, walls etc expand in hot environment. For members of smaller dimensions this expansion may be negligible. For members exceeding certain lengths, widths the expansion may be more than sufficient to induce flexural stresses and thus induce cracks in the structure unless they are given the opportunity to expand freely. These cracks, besides weakening the structure, can lead to corrosion of steel reinforcement due to ingress of moisture through them which can pose even bigger problems. That is where the expansion joints come into the picture. An expansion joint is provided in order to allow a concrete member to expand freely in hot environment and thus relieve the unwanted stresses so that no damage is caused to the it or the structure as a whole. These joints are common features in masonry and metallic structures. Expansion joints are essential elements of long bridges, railway tracks, long walls, piping networks etc. These joints are provided in such a way that the overall structure is not weakened due to their presence. In liquid retaining concrete structures expansion joints are equipped with water stops. Diverse materials are used for preparing these joints. Typical expansion joints in concrete structures can be about half inch to 20mm wide. The joints are prepared by placing forms of required thickness through full depth of the concrete members. A quite common as well as economic formwork material is fibre impregnated bitumenous boards. Other compressible joint fill materials used in expansion joints are cork, polystyrene, rubber etc. Sometimes, wooden forms are used which are removed after the concrete sets. Thereafter, the concrete members on both sides of the joint are given sufficient time to go through expansion or contraction for some days. Then the compressible joint fill materials, as mentioned above, of adequate thickness are inserted in the gaps through full depth of the concrete members such that the top of the filler boards remain about 20mm below the top of the concrete member. This 20mm or so deep voids are later sealed with elastomeric compounds like polyurethane (PU) or polysulphide etc. These are applied to seal the joints completely from ingress of water, dust, dirt etc and also to render better appearance. These

4 elastomeric sealants are quite capable of accommodating the expansion or contraction of the concrete structures. On the other hand, some prefer to install the compressible fill materials as sacrificial forms, ie they are not withdrawn upon completion of casting of the members. Elastomeric sealants are applied after some days as mentioned above to seal the joints. Reinforcing steel bars are always discontinued at expansion joints to enable free expansion of the concrete members. However, sometimes dowel bars have to be provided in order to prevent differential settlement of the members on both side of the joint. This is especially true for concrete members subjected to heavy load or high traffic. When dowels are provided they are usually kept fixed inside concrete at one end while the other ends (on the other side of the joint) have to be kept free by some means, eg by installing hollow tube inserts inside the concrete. The other ends remain inside the hollow tubes so that they can move freely when the concrete members expand or contract. The forms or the compressible joint fills should have perforations accordingly to let the dowel bars pass through them. Construction drawings usually clearly show the details of dowel bars wherever they are required. A little suggestion from this author in this regard. There are coatings available that can completely prevent bond between a bar and the sorrounding concrete. Such coatings can be applied to dowel bars and two small compressible caps can be fitted at both ends of these bars after installing them. Even one cap of adequate thickness at one end should serve the purpose. These compressible caps should be able to facilitate movements of the bars inside the concrete even as the coating prevents bonds. This would eliminate the cumbersome process of installing hollow tubes etc besides proving to be more economical. In fact, this looks so simple that such a practice could already be existing unless there are some shortcomings in the suggestion. Construction joints and expansion joints (aka movement joints) were discussed in Part-I & II respectively. Isolation joints and contraction joints are discussed in this post. Isolation joint : In concrete structures isolation joints are provided in order to relieve the stresses developed due to differential movement of the adjacent members or structures, thus preventing cracks (or damage) in the members or the structure as a whole. Isolation joints around machine foundations also perform the function of cutting off the vibrations generated by the machines, thus safeguarding the adjoing slabs or other structural elements from possible damage.

5 Isolation joints may be required at the junctions of horizontal members (slabs etc) and vertical members (columns, walls etc) when there are possibilities of significant differential movements. These joints may very well be required when a slab or a roof of a newly built structure has to meet an existing structure, or, a new block has to be extended from an old building in relatively softer soil or in a filled area. In both the cases there is every likelihood that the newly built slab or the newly extended block would settle more as compared to their old counterparts. Unless isolated, these differential movements can develope sufficient stresses causing cracks and damage to the structural members. The same issue might develope at the junction of large columns and slabs. While the slab would tend to move horizontally the column would always move vertically due to expansion or load related settlement causing differential movement. So, if the same is expected to be significant, an isolation joint along the periphery of the column can prove quite worthy. Isolation joints are seen in bridges as well. Isolation joints are usually about half an inch to 20mm wide. Like expansion joints these too are filled with compressible joint fillers such as fibre impregnated bituminous boards, cork, polystyrene, rubber etc. Either the joint fill boards are installed about 20mm short of top of the concrete surface or after installing the compressible boards through full depth of the joint the top 20mm (or so) portion is cut off. This void is later filled with elastomeric sealing materials like Polyurethane (PU) or Polysulphide (PS) sealants for better appearance as well to render the joints water and dirt proof. For best results, joint fillers and elastomeric sealants are to be installed only after the concrete members are cast and full loads are transferred through them. Contraction Joint : When concrete sets and dries it tends to shrink. This shrinkage or contraction can cause hair cracks on the surface of the concrete. Besides affecting the appearance of the finished surface these cracks could lead to other problems in the course of time. This is not an issue for concrete members with small surface area such as beams, columns etc. That s because the quantum of shrinkage is negligible. But cracks due to drying shrinkage can be a major issue for concrete structures with large surface area such as concrete roads, other large concrete pavement or floors etc. By forming contraction joints on the surface this issue is sorted out. Contraction Joints are also known as control joints. These joints are created in the concrete surface by inserting thin strips in fresh concrete, by saw cutting using either dry-cut or wet-cut saws, by grooving using grooving tools etc.

6 An important aspect is the depth of these joints as unless the depth of joint is adequate they won t serve the purpose well. According to a popular thumb rule the depth of a contraction joint should be at least one fourth of the depth of a concrete slab. Similarly, thumb rules are also there regarding spacing of control joints. Unlike an isolation joint or an expansion joint, a contraction joint is quite thin as the purpose of it is just to guide the cracks to a predetermined weak plane which is the joint itself. As already mentioned these joints should be preplanned to coincide construction joints so as to minimise the number of joints in a structure. Source:

Chapter 2 Basis of design and materials

Chapter 2 Basis of design and materials Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural

More information

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

Chapter. Restoration of Damaged Structures

Chapter. Restoration of Damaged Structures 5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety

More information

Technical Notes 3B - Brick Masonry Section Properties May 1993

Technical Notes 3B - Brick Masonry Section Properties May 1993 Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications

More information

LAYING BLOCK AND BRICK

LAYING BLOCK AND BRICK LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct

More information

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced

More information

CAST IRON THE BASICS. Heatline - Cast Iron Radiators SMOOTH FLAT FILE TO REMOVE ANY SWARF. ONE TIME. ASSEMBLY. JOINTS SHOULD BE TIGHTENED.

CAST IRON THE BASICS. Heatline - Cast Iron Radiators SMOOTH FLAT FILE TO REMOVE ANY SWARF. ONE TIME. ASSEMBLY. JOINTS SHOULD BE TIGHTENED. CAST IRON THE BASICS 1. DO NOT LIFT ON YOUR OWN. 2. ONLY LIFT THE RADIATOR VERTICALLY. 3. DO NOT LIFT MORE THAN 8/10 SECTIONS AT ANY ONE TIME. 4. POSITION THE RADIATOR BEFORE FINAL ASSEMBLY. 5. THIS PRODUCT

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia DESIGN OF SLABS Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia Introduction Types of Slab Slabs are plate elements

More information

State of Connecticut Department of Public Health RADON PROGRAM

State of Connecticut Department of Public Health RADON PROGRAM State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon

More information

How to build a Pizza Oven in 4 days

How to build a Pizza Oven in 4 days How to build a Pizza Oven in 4 days Preparation day (slab) 1. Foundation 1500 deep x 1300 wide x 75mm deep Required 20 bags cement pre mix. If you already have a concrete base, you save this prep day DAY

More information

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the Chapter 7 PLUMBING AND ELECTRICAL 7.1 Introduction to Plumbing and Electrical Consideration of support services such as plumbing and electrical systems from the preliminary schematics phase through final

More information

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE 86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is

More information

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14 Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318

More information

Minor Cracks in Horizontal Surfaces

Minor Cracks in Horizontal Surfaces Cracks, chips and broken or flaking areas in concrete are not only unsightly, they can lead to further deterioration of the surface. The result is a costly replacement project as opposed to a simple repair.

More information

Guide for SOLID CONCRETE BLOCK SEALS

Guide for SOLID CONCRETE BLOCK SEALS Guide for SOLID CONCRETE BLOCK SEALS July, 2006 Mine Safety and Health Administration SOLID CONCRETE BLOCK SEAL Formersection 30 CFR 75.335(a)(1) specifies requirements for seals constructed using solid

More information

September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900

September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900 September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation

More information

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS AN ERGONARMOR COMPANY TECHNICAL INFORMATION SPECIFICATION FOR INSTALLATION 07/11 SUPERSEDES 04/00 PAGE 1 OF 6 CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS 1. SCOPE 1.1 This specification

More information

Chapter. Earthquake Damage: Types, Process, Categories

Chapter. Earthquake Damage: Types, Process, Categories 3 Chapter Earthquake Damage: Types, Process, Categories Earthquakes leave behind a trail of damage and destruction. People s lives are affected by the loss of loved ones, destruction of property, economic

More information

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS May 29, 2013 Revision B Structural Guideline for Design and Installation Holes in Composite Floor Slab Terminal 3, Departure Level

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

Improving the flood resistance of your home. Advice sheet 6: Flood-resilient floors

Improving the flood resistance of your home. Advice sheet 6: Flood-resilient floors Improving the flood resistance of your home Advice sheet 6: Flood-resilient This sheet provides guidance on identifying different types of floor, assessing the routes floodwater may enter, and describes

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

www.pitchmasticpmb.com PmB Expansion Joints World leaders in expansion joint technology

www.pitchmasticpmb.com PmB Expansion Joints World leaders in expansion joint technology www.pitchmasticpmb.com Expansion Joints World leaders in expansion joint technology High performance expansion joint solutions Pitchmastic offers a comprehensive range of specialist services to the civil

More information

Structural Failures Cost Lives and Time

Structural Failures Cost Lives and Time Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major

More information

The minimum reinforcement for the stem wall is the placement of:

The minimum reinforcement for the stem wall is the placement of: PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20

More information

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Construction Specification for Concrete Curb and Concrete Curb and Gutter Engineering & Construction Services Division Standard Specifications for Road Works TS 3.50 April 2015 for Concrete Curb and Table of Contents TS 3.50.01 SCOPE... 3 TS 3.50.02 REFERENCES... 3 TS 3.50.03

More information

Issue of the Guidelines on Prevention of Water Seepage in New Buildings

Issue of the Guidelines on Prevention of Water Seepage in New Buildings graphic: Buildings Department Your REF 來 函 檔 號 :. OUR REF 本 處 檔 號 :.BD GR/1-55/173 FAX 圖 文 傳 真 :..28400451 TEL 電 話 :..2626 1717 www.info.gov.hk/bd To : All Authorized Persons 7 March 2005 Registered Structural

More information

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Introduction Wastewater of petrochemical industries and refineries contains high amounts of emulsified aliphatic or

More information

Precast Concrete Parking Structures

Precast Concrete Parking Structures Precast Concrete Parking Structures Durability starts at the joints BY DAVID C. MONROE AND JOSEPH L. WHITE Parking structures comprise the largest market segment for the structural precast, prestressed

More information

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling Asphalt Pavements 7-7 Chapter 7 Pavement Rehabilitation Pavement rehabilitation can be accomplished

More information

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an

More information

Waterproofing construction Joints

Waterproofing construction Joints WaterproofingSystems Waterproofing construction Joints Area waterproofing Backing rod KÖSTER Joint Sealant FS-H KÖSTER FS Primer Contents Basics Connective, loadable and resilient: Joints in building construction

More information

HOUSE BUILDING DIGEST

HOUSE BUILDING DIGEST HOUSE BUILDING DIGEST (Construction Specifications-Foundations) Creating Enabling Environment for Affordable Housing for All This is an attempt by BMTPC to provide useful but often ignored information

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

If stepping is required, step at 180mm as seen in this picture.

If stepping is required, step at 180mm as seen in this picture. Cast Foundations to standard building regulations requirements. Foundations must be cast completely level, 600mm wide by 230mm deep for single storey, double storey is not allowed by NHBRC. If stepping

More information

Metropolitan Builders Association Masonry & Concrete Standard

Metropolitan Builders Association Masonry & Concrete Standard Metropolitan Builders Association Masonry & Concrete Standard Background Masonry and concrete work in residential construction often provides the base structure upon which the house is built or as a veneer.

More information

Module 7 (Lecture 24 to 28) RETAINING WALLS

Module 7 (Lecture 24 to 28) RETAINING WALLS Module 7 (Lecture 24 to 28) RETAINING WALLS Topics 24.1 INTRODUCTION 24.2 GRAVITY AND CANTILEVER WALLS 24.3 PROPORTIONING RETAINING WALLS 24.4 APPLICATION OF LATERAL EARTH PRESSURE THEORIES TO DESIGN 24.5

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure

More information

Site Inspection Report

Site Inspection Report Site Inspection Report Project Title: 1 Canada Square Location: 1 Canada Square, Canary Wharf, London Date of Inspection: 16/05/12 System / Products: TBA (suggested flame free application) Attendees: G

More information

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt

More information

Fifteen years experience of design, production and assembling of prestressed Bridge decks in Timber

Fifteen years experience of design, production and assembling of prestressed Bridge decks in Timber Fifteen years experience of design, production and assembling of pre-stressed Bridge decks in Timber P. Jacobsson 1 Fifteen years experience of design, production and assembling of prestressed Bridge decks

More information

16. Beam-and-Slab Design

16. Beam-and-Slab Design ENDP311 Structural Concrete Design 16. Beam-and-Slab Design Beam-and-Slab System How does the slab work? L- beams and T- beams Holding beam and slab together University of Western Australia School of Civil

More information

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY GENERAL SPECIFICATIONS These specifications are intended to cover the construction of the

More information

INTERIM ADVICE NOTE 96 /07 Revision 1 GUIDANCE ON IMPLEMENTING RESULTS OF RESEARCH ON BRIDGE DECK WATERPROOFING

INTERIM ADVICE NOTE 96 /07 Revision 1 GUIDANCE ON IMPLEMENTING RESULTS OF RESEARCH ON BRIDGE DECK WATERPROOFING Interim Advice Note 96/07 INTERIM ADVICE NOTE 96 /07 Revision 1 GUIDANCE ON IMPLEMENTING RESULTS OF RESEARCH ON BRIDGE DECK WATERPROOFING Summary This interim advice note provides guidance on improving

More information

Tunnels & Arches OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM

Tunnels & Arches OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM P r o d u c t a p p l i c a t i o n s a n d t e c h n i c a l i n f o r m a t i o n 5 Tunnels & Arches V OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM V Create dry usable space with the original X pattern

More information

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems: Reading Assignment SLAB DESIGN Chapter 9 of Text and, Chapter 13 of ACI318-02 Introduction ACI318 Code provides two design procedures for slab systems: 13.6.1 Direct Design Method (DDM) For slab systems

More information

Design and Construction of Cantilevered Reinforced Concrete Structures

Design and Construction of Cantilevered Reinforced Concrete Structures Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures

More information

Embedded Parts Introduction - Anchors

Embedded Parts Introduction - Anchors In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical

More information

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials SECTION 03 92 50 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings,

More information

Always. Reliable. Tight. Wall sleeves Versatile solutions for building entries. cablepipebuildingentry+

Always. Reliable. Tight. Wall sleeves Versatile solutions for building entries. cablepipebuildingentry+ Always. Reliable. Tight. Wall sleeves Versatile solutions for building entries. cablepipebuildingentry+ The wall sleeve The wall sleeve a largely unnoticed but very important sealing part. Wall sleeves

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01. Section 5.0 Basements Wall insulated externally Product: Polyfoam ECO Ba01 Wall insulated internally Product: Polyfoam ECO Ba02 Basements Basements Basement design Waterproofing BS 8102: 2009 Code of practice

More information

DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP

DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP CONTENTS WHAT IS RISING DAMP STEP 1 SURVEY STEP 2 METER READINGS STEP 3 CONCLUSION STEP 4 PREPARATION FOR TREATMENT STEP 5 TYPE OF TREATMENT STEP 6

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

Understanding BS EN 771-3: Aggregate concrete masonry units

Understanding BS EN 771-3: Aggregate concrete masonry units 60 Charles Street, Leicester LE1 1FB Tel: 0116 253 6161 Fax: 0116 251 4568 Email: enquiries@cba-blocks.org.uk Website: www.cba-blocks.org.uk February 2006 Understanding BS EN 771-3: Aggregate concrete

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

K2 STONE NATURAL VENEER

K2 STONE NATURAL VENEER INTRODUCTION WHAT IS K2 NATURAL THINSTONE VENEER? Natural K2 Stone veneer is real stone, cut 1 inch thick, making it light enough to be installed as a veneer. Sometimes referred to as thin veneer, thin

More information

Formwork Direct International Ltd Phone No +44 (0151) 532 0179 Fax no +44 (0151) 523 8330 E-Mail: sales@formworkdirect.co.

Formwork Direct International Ltd Phone No +44 (0151) 532 0179 Fax no +44 (0151) 523 8330 E-Mail: sales@formworkdirect.co. Joint Fillers Formwork Direct are proud to be The UK and Ireland distributor for LJA Miers & Co. who have been responsible for many of the developments in Joint Fillers that are today accepted as common

More information

FIRESTOPPING & SMOKE SEALS

FIRESTOPPING & SMOKE SEALS SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of

More information

Waterproofing Problems: A Simple Explanation, A Simple Solution

Waterproofing Problems: A Simple Explanation, A Simple Solution Waterproofing Problems: A Simple Explanation, A Simple Solution The purpose of this paper is to point out the underlying causes of waterproofing problems and simple means of preventing them. Such problems

More information

Installation instructions of the MIDI-Heki roof light with operating bar, with crank or electrical version

Installation instructions of the MIDI-Heki roof light with operating bar, with crank or electrical version Installation instructions of the MIDI-Heki roof light with operating bar, with crank or electrical version with operating bar with crank electrical version 1. Prerequisite for a correct installation of

More information

SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS

SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS Fracture Mechanics of Concrete Structures Proceedings FRAMCOS-3 AEDIFICA TIO Publishers, D-79104 Freiburg, Germany SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS H.

More information

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow. 9.2 One-way Slabs This section covers the following topics. Introduction Analysis and Design 9.2.1 Introduction Slabs are an important structural component where prestressing is applied. With increase

More information

Monocouche Best Practice Guide. New-Build Housing Managing movement to avoid cracking

Monocouche Best Practice Guide. New-Build Housing Managing movement to avoid cracking Monocouche Best Practice Guide New-Build Housing Managing movement to avoid cracking Avoiding Cracking For The Designer Visible cracks in render are unsightly and although not hazardous to the construction

More information

APPENDIX B. I. Background Information

APPENDIX B. I. Background Information APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement

More information

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER

METHOD STATEMENT FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER Page 1 of 6 FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER 0 Issued for Review & Comments Rev. Date Description Eng. A.H Prepared by Checked by Approved by Page 2 of 6 REVISION CONTROL SHEET REV. NO. DATE

More information

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14)

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14) POLYMERIC CONCRETE BRIDGE DECK OVERLAY (Adopted 02-20-14) Description The polymeric concrete bridge deck overlay shall consist of an epoxy polymer that acts together with special aggregate to form an overlay

More information

Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors

Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors The Right Concrete Mix Placing and Finishing Joints Correctly Spaced Curing for Durability "Concrete durability is the ability to

More information

WATERPROOFING OF WET ROOMS

WATERPROOFING OF WET ROOMS WATERPROOFING OF WET ROOMS Waterproofing under tiles For longterm enjoyment of a wetroom area a complete and resistant waterproofing system is an important precondition. Most tiles are by themselves waterproof

More information

RMS Guide for design of concrete pavements in areas of settlement. Version 1.0. Roads and Maritime Services www.rms.nsw.gov.au

RMS Guide for design of concrete pavements in areas of settlement. Version 1.0. Roads and Maritime Services www.rms.nsw.gov.au Guide for design of concrete pavements in areas of settlement Version 1.0 RMS Guide for design of concrete pavements in areas of settlement Version 1.0 Roads and Maritime Services www.rms.nsw.gov.au Title:

More information

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges 7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience

More information

COMMONLY USED RESIDENTIAL BUILDING CODES

COMMONLY USED RESIDENTIAL BUILDING CODES COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section

More information

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests Product Data Sheet Edition 05/12/2014 Identification no: 020204030010000044 Sikadur -41 CF Rapid 3-part thixotropic epoxy patching mortar Construction Product Description Uses Characteristics / Advantages

More information

BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"

BILL OF QUANTITY FOR THE WORK OF REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP" Sl. 1 DISMANTLING WORK 1.1 Stripping off worn out plaster (outside and inside) and raking out joints

More information

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance 02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW

More information

CHAPTER 2 QUANTITY TAKE-OFF

CHAPTER 2 QUANTITY TAKE-OFF CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate

More information

Interior Walls below and above ground OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM

Interior Walls below and above ground OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM P r o d u c t a p p l i c a t i o n s a n d t e c h n i c a l i n f o r m a t i o n 2 below and above ground V OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM V The flexible, fast and cost-effective answer

More information

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio Seven Easy Steps to Installing Your Own Walkway, Driveway and Patio Without Mortar or Concrete Brick is one of the world s oldest and most enduring building materials. Those same qualities also make it

More information

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,

More information

3 Masonry and Manufactured Stone (Interior and Exterior)

3 Masonry and Manufactured Stone (Interior and Exterior) 3 Masonry and Manufactured Stone (Interior and Exterior) 3.1 Efflorescence (a whitish crystalline powder) is present on masonry surfaces. Efflorescence commonly occurs on masonry surfaces. This is not

More information

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally

More information

Knauf Aquapanel Interior. Tile Backing. Cement board for wet areas. Will not deteriorate in water. Easy to score and snap

Knauf Aquapanel Interior. Tile Backing. Cement board for wet areas. Will not deteriorate in water. Easy to score and snap Tile Backing Will not deteriorate in water Easy to score and snap Resistant to mould and mildew Knauf Aquapanel Interior Cement board for wet areas Knauf Aquapanel Interior Cement Board Drywall for Wet

More information

How to Install Hardwood Flooring Over a Sub Floor

How to Install Hardwood Flooring Over a Sub Floor How to Install Hardwood Flooring Over a Sub Floor Installation Preparation Instructions Read the entire instructions before starting your project. 1) INSPECT EACH PLANK (see fig. a) Wood is a natural product

More information

PANELIZED HOME INSTALLATION GUIDELINE

PANELIZED HOME INSTALLATION GUIDELINE PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.

More information

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing. CONCRETE REPAIR GUIDELINES Concrete repairs can be broken down into four basic types, plus special repairs and planing. Note: It is recommended that investigation into soundness of pavement be performed

More information

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS 1.0 DESIGN 1.1 Scope of Work 1.1.1 This work shall consist of furnishing Isolation Bearings and installing Isolation Bearing Assemblies at the locations

More information

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to

More information

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls Pre- insulated pipe systems ecoflex Wall Penetration installation guide Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls Pre-insulated Pipe Systems

More information

Passive Fire Protection

Passive Fire Protection Firestopping Passive Fire Protection FS20 Firestop Compound 6 hour fire rated penetration seals for electrical and mechanical services FS20 Firestop Compound FS20 Firestop Compound is a Fire-Rated Penetration

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information