NEDCO- Business Plan VOLTA RIVER AUTHORITY Northern Electricity Distribution Company
|
|
- Dylan Morrison
- 7 years ago
- Views:
Transcription
1 NEDCO- Business Plan VOLTA RIVER AUTHORITY Northern Electricity Distribution Company
2 2 Presentation Outline! Purpose of Presentation! Executive Summary! NEDCo Profile! NEDCo Challenges! Objectives & Strategies! Conclusion
3 3 Purpose of Presentation! To introduce NEDCo to Donors! To begin a dialogue and seek their support on how NEDCo can become a self sustaining commercial operation in the next five years
4 4 Executive Summary (I)! NEDCo has grown substantially since its inception as the Northern Electricity Department (NED) in 1987! Customer growth: 19x; CAGR 13% ( )! Energy growth: 8.6x; CAGR 7%! Billed Revenue growth: 2,083x; CAGR 38%! NEDCo is today an unprofitable entity because the majority of its customers do not pay commercially viable tariffs! NEDCo s distribution system has been historically under-invested in and not capable to properly service the large geographic area it covers! Unacceptable quality of supply: Low voltages & frequent interruptions
5 5 Executive Summary (II)! NEDCo s objective over the next five years is to adequately resource the organisation to meet the extraordinary challenges it faces! Financial: Inadequate tariffs and commercial customers! Commercial : High losses! Technical: Unreliable and weak infrastructure and delivery systems! People & Systems: Well trained with appropriate logistics and IT systems! NEDCo s opportunity and challenge are to serve as a key partner in Government initiatives to transform the north into a major agricultural production zone! NEDCo s ability to resource to meet these challenges will ensure a self-sustaining commercial entity in the long-term
6 6 Profile- NEDCo! NEDCo supplies Electricity in Brong-Ahafo, Upper East, Upper West and Northern regions of Ghana and the northern parts of Ashanti and Volta regions! NEDCo also supplies electricity to some border towns of Burkina Faso and Togo! NEDCo operations today cover 64% of the geographical area of Ghana! Population Access of the Electricity is 36 %! NEDCo Distributes 10.2% of total energy consumed in Ghana! Customer Population was 380,000 at end of 2011
7 7 Profile- Customer Analysis! Customer Population has grown from 20,000 in 1990 to 380,000 in 2011! Compounded Average Growth Rate (CAGR) of number of customers of 13 % per Annum
8 NEDCo Number of Customers TOTAL CAGR :9% :11% :12% :13% DOMESTIC CAGR :9% :10% :12% :13% Number of Customers (thousands) Domestic(000) Commercial('000) Industrial'('000) Total('000) COMMERCIAL CAGR :10% :12% :12% :13% Domestic(000) Commercial('000) Industrial'('000) Total('000) Year INDUSTRIAL CAGR :6% :4% :4% :6%
9 9 Profile- Energy Growth! Energy Consumption grew from 60 GWh in 1990 to 519 GWh in 2011! Consumption Pattern! Residential Customers ( 82%) : 57 % of Energy! Non Residential Customers (17.9 %) : 31.1 % of Energy! SLT Customers (0.01 %) : 11.2 % of Energy
10 NEDCo Billed Energy Energy (GWh) TOTAL CAGR :7% :7% :6% :7% DOMESTIC CAGR :6% :5% :5% :7% Domestic('000,000) Commercial('000,000) Industrial('000,000) COMMERCIAL CAGR :10% :11% :9% :9% Total('000,000) Domestic('000,000) Commercial('000,000) Industrial('000,000) Total('000,000) Year INDUSTRIAL CAGR :4% :6% :5% :5%
11 11 Profile- Billed Revenue! Billed Revenue for NEDCo has grown at a compounded average growth rate (CAGR) of:! 28% for 2007 to 2011! 27% for 2002 to 2011! 30% for 1997 to 2011 and! 36% for 1992 to 2011
12 NEDCo Billed Revenue Domestic('000,000) Commercial('000,000) Industrial('000,000) Total('000,000) TOTAL CAGR :28% :29% :36% :38% Cedis (millions) COMMERCIAL CAGR : 33% :33% :42% :40% DOMESTIC CAGR :22% :25% :34% :38% INDUSTRIAL CAGR :28% :27% :30% :36% Domestic('000,000) Commercial('000,000) Industrial('000,000) Total('000,000) Year
13 SNAPSHOT OF 2011 CUSTOMER PROFILE 13 Customer Type % age of Total Customer Population % of total Energy Consumed % of Billed Revenue Average Energy Consumed/ Month (kwh) Average Tariff (GHS/kWh) Residential Non- Residential LV , MV 393, HV 319,
14 14 NEDCo 2011 Number of customers Industrial'('000), 0.04, 0% Commercial('00 0), 68.01, 18% Domestic(000), , 82% Domestic(000) Commercial('000) Industrial'('000)
15 NEDCo 2011 Billed Energy (kwh) , 12% , 32% , 56% Domestic('000,000) Commercial('000,000) Industrial('000,000)
16 NEDCo 2011 Billed Revenue (Million Cedis) , 14% 44.75, 36% Domestic('000,000) Commercial('000,000) Industrial('000,000) 62.79, 50%
17 17 CUSTOMER NUMBER, BILLED ENERGY AND BILLED REVENUE ANALYSIS FOR SUNYANI AND NORTHERN AREAS OF NEDCo
18 Sunyani Area Number of Customers , 0% 20,345, 18% Domestic Commercial Industrial 93,607, 82%
19 Sunyani Area Billed Energy(kWh) ,669,888, 18% 39,990,291, 24% 98,058,278, 58% Domestic Commercial Industrial
20 Sunyani Area Billed Revenue (Cedis) ,476,960, 22% 15,028,227, 39% 14,991,163, 39% Domestic Commercial Industrial
21 Northern Area Number of Customers , 0% 16,747, 17% Domestic Commercial Industrial 81,323, 83%
22 Northern Area Billed Energy ,440,844, 15% 70,803,112, 47% 56,866,160, 38% Domestic Commercial Industrial
23 Northern Area Billed Revenue ,161,486, 15% 11,440,688, 29% 22,386,700, 56% Domestic Commercial Industrial
24 24 NEDCo s 5-Year Performance : Year Energy Purchased (GWH) Energy Sales (GWH) Energy Loss (GWH) Distribution Loss %age % % % % Energy Billed Amount (GHC Million) Revenue Realized (GHC Million) Collection Efficiency %age 81.36% % % % 76.59% Energy Paid (GWH) ATC & C Loss %age % % % % %
25 25 Profit and Loss Account GH '000 GH '000 GH '000 GH '000 GH '000 Sale of electricity 35,437 53,957 58,737 94, ,978 Other income 1,107 1,223 1,246 1,367 1,288 Total revenue 36,544 55,180 59,983 95, ,266 Operating Costs 45,299 67,437 68, , ,312 Depreciation 16,681 19,089 25,205 23,992 29,309 Total expenses 61,980 86,526 94, , ,621 Net Profit/Loss for the year ( 25,436) ( 31,346) ( 34,022 ) ( 39,430) ( 35,355 )
26 26 NETWORK STATISTICS Mar 34.5kV Overhead (km) 4,643 5,001 6, kV Underground (km) kV line length (km) kV line length (km) kV Overhead (km) 1,286 1,340 1,741 11kV Underground (km) No. of Bulk Supply Points serving NED No. of 34.5/11KV Primary Substations (Including Dalun & Airport) No. of Secondary Substations 2,293 2,609 2, V line length (km) 8,540 8,990 9,618 Number of Customers 342, , ,468 Peak load (MW) Installed Transformer Capacity (MVA) Average Feeder Reliability (%)
27 27 Comparison with other Utilities Unit Ghana 2010 * Ghana 2011 * KPLC (Kenya) 2009 UK 2008 Russia Average demand per customer kw Average grid tariff GHS/MWh Average grid tariff US$/MWh Annual power distributed per km MWh/km Annual revenue per km of dist. Grid US$/km 4,600 5,187 6,822 8,631 8,643 6 Length of distr, grid per customer, meters meters *The values relating to distances for Ghana (4, 5 and 6) are estimated. The actual length of the GRID is now being determined.
28 28 NEDCo Challenges Financial Technical Commercial People & Systems
29 29 Challenges- Financial! Inadequate Tariff! Inadequate number of SLT ( Special Load Tariff) Customers! Unwillingness of Customers (including MDAs) to pay bills! Low Customer Density leading to High Investment Cost! Difficulty in Generating Sufficient Revenue to meet operational & working Capital
30 30 Challenges Commercial! High Commercial Losses ( Theft & Pilferages)! Estimated as 9.6% of billed energy! Poor Metering, Billing & Collection Efficiency! Collection rate of 77%! Large & Growing Asset base with Low Demand for Electrical Energy! ECG s customers per sq km are 29 whiles that of NEDCo are 2. Network asset value per customer in NEDCo is GHS774 as at end 2011.! Lack of Infrastructure, Resources & Business Processes for Quality Customer Service
31 31 Challenges Technical! High Technical Losses %! Long Distribution network with overloaded transformers! Inadequate Network and Customer Mapping! Low Voltages (Outside Acceptable Limits) at various Feeders.! Aged Equipment & Poor Power System Reliability! Suppressed Demand! Lack of Spares for Effective O&M
32 32 Challenges - People! Difficulty in Recruiting & Retaining Qualified & Experienced Staff! Lack of sufficient Human Capacity and absence of Capacity Building Exercises
33 33 Challenges - Systems! Poor ICT Infrastructure! Lack of Resources (Customer Care Cell, Logistics, Buildings, Tools & Equipment, Vehicles)! Inadequate Business Processes
34 34 Objectives - Financial! To make NEDCo financially self-sustainable by 2017 NORTHERN ELECTRICITY DISTRIBUTION COMPANY PROJECTIONS TO 2017 Profit and Loss Account Projections GH '000 GH '000 GH '000 GH '000 GH '000 GH '000 Sale of electricity 139, , , , , ,076 Other income 2,254 3,945 6,903 8,629 10,786 13, , , , , , ,558 Deduct: Operating Costs 160, , , , , ,982 Depreciation 28,019 29,819 31,619 33,419 35,219 37,019 Total expenses 188, , , , , ,001 Net Profit/Loss for the year without depn (18,720) (19,196) (8,607) (353) 12,187 25,576 Net Profit/Loss for the year with depn (46,738) (49,014) (40,226) (33,772) (23,032) (11,443) Sonabel expected margin 1,777 1,866 1,959 2,057 2,160 2,268 Adjusted net profit with Sonabel (44,962) (47,149) (38,267) (31,715) (20,872) (9,176)
35 35 Strategies Financial (I)! Reduce Financial, Commercial, Technical and Collection Losses! Submit proposal to PURC for a break-even tariff! Submit proposals to PURC and MOE for the introduction of a levy to support NEDCo
36 36 Strategies Financial (II)! Identify new customers such as:! Transfer of selected VRA customers (SONABEL) to NEDCo! New border town communities! Collaborate with SADA, GIPC, AGI to attract large customers to NEDCo! To ensure Stringent Budgetary Controls & Process
37 37 Financial - Projects & Investment! Procurement and installation of 200,000 prepayment meters with installation accessories at a total cost of US$17.5m as shown below Year Project Estimated Cost (US$) Install 30,000 meters 3,000, Install 70,000 meters 7,000, Install 45,000 meters 4,000, Install 55,000 meters 3,500,000
38 38 Objectives - Commercial! Reduce commercial Losses to 6.5 % by 2017 from 9.6% in 2011! Improve collection rate to 97.5% by 2017 from 76.6% in 2011! Improve Customer service Delivery and achieve 70% satisfaction (Power Quality & Reliability, Excellent Communication & Quick services)
39 39 Strategies Commercial (I)! Test & Recalibrate all Energy Meters! Relocate Existing Energy Meters in Enclosures! Installation of Prepayment Meters to all Customers! Intensification of Disconnection of defaulting customers
40 40 Strategies Commercial (II)! Increase the number of Customer Service Centers! Use of IT infrastructure to improve Revenue collection! Implement a new computerized billing system and improved business processes
41 Commercial - Projects & 41 Investment Initiative Estimated Cost (US$) Implementation of Distribution Transformer Metering system for Energy Audit Implementation of streetlight metering system 3,000,000 1,250,000 1,250, ,000 1,900,000 1,000, , ,000 Reduce commercial losses by 1% by December 2012 by installing 120,000 prepayment meters on hand and relocation of existing meters Implement a new meter data management and reporting system Total- USD 3,500,000 2,500,000 1,000, , ,000 8,600,000 2,500,000 3,450,000-1,650,000-1,000,000
42 42 Objectives - Technical! Reduce the technical losses to 6.5% by 2017 from 10.6% in 2011! Improve supply quality to customers in compliance with voltage levels in LI1816! Provide minimum spares for effective O&M.! Increase Access to electricity to meet GoG agenda of universal access by 2020
43 43 Strategies - Technical! Reinforce the Distribution Network! Improve Reliability & Availability of Power! Increase the Access of Power & increase System Capacity! Implement the Technical Losses reduction exercises! Implementation of High Voltage Distribution System! Distribution Network Optimization! Implement an Energy Audit & Project Management Team
44 Technical - Projects & Investment (I) 44 Initiative Estimated Cost (US$) Preparation of tender documents for the procurement of a computerised Distribution maintenance management system 100, , NPSIP - Sunyani and Techiman Areas( Ongoing) NPSIP Tamale, Bolga and Wa Areas 4,900,000 2,500,000 2,400,000 4,000,000 4,000,000 4 Distribution Network Rehabilitation Project (DNRP)- Ongoing 2,500,000 2,500,000-5 Distribution Network Rehabilitation Project (DNRP Phase II & III) 26,000,000 4,000,000 4,000,000 2,000,000 16,000,000
45 45 Technical - Projects & Investment (II) Initiative Estimated Cost (US$) NEDCo Supply Improvement/ Rehabilitation Project (NSIRP) ongoing 2,500,000 2,500,000 - NEDCo Supply Improvement/ Rehabilitation Project (NSIRP Phase II) 10,000,000 4,000,000 4,000,000 2,000,000 BUIPE SUBSTATION PROJECT-ongoing 2,000,000 2,000,000 - Provide part of the needed electricity distribution network spares and equipment (transformers, fuses, conductors, line hardware etc) for efficient and effective O&M and also for network extensions 66,318,213 9,700,000 8,000,000 8,000,000 12,656,763 27,961,450 Installation of Capacitor Banks to improve voltage levels
46 46 Technical - Projects & Investment (III) Initiative To develop an extensive distribution network development plan Construction of about 150km of 34kV line and associated projects to mitigate the effect of GRIDCo Upgrade Projects Construction of 34.5KV bay with eight (8) panel breakers at Wa Switchyard Construction of 59KM length of 34.5 KV line from Wa Main Substation to Lassia Toulou. Upgrade of 34Km length of 11.5KV line from Lassia Toulou through Wechau to Dorimon to 34kV and Replacement of 3No, 20KV transformers and 6No. 11.5KV transformers with 34.5kV transformers Estimated Cost (US$) 0 21,000,000 3,000,000 2,880,000 2,080, ,000,000 7,000,000 7,000,000 3,000,000 1,500,000 1,500,000 1,000,000 1,880,000 1,000,000 1,080,000
47 Initiative Technical - Projects & Investment (IV) Construction of 6 NO. 34/11KV SUBSTATIONS AND INTENSIFICATION IN ALL NEDCO AREAS Construction of 34/11kV substations at UDS Tamale and Sunyani Hospital Implementation of high voltage distribution system and injection of new service stations (capacity expansion) Implement distribution system optimization ( re-configuration of distribution lines, proper sizing of conductors and transformers, load balancing etc) Prepare a long term distribution system expansion plan to meet the Government s vision 2020 agenda Estimated Cost (US$) 32,000,000 6,000,000 7,000,000 6,000,000 6,000,000 7,000,000 20,000,000-6,000,000 6,000,000 8,000,000 35,000,000-20,000,000 7,000,000 1,000,000 3,000,000 1,800, ,000 1,300,000 15,000,000 3,000,000
48 Objectives & Strategies 48 People & Systems (I)! Capacity building of personnel for effective deliveries in knowledge, skill and attitude for about 70 staff per annum.! Implement ICT infrastructure (LAN, WLAN, WAN, Radio Communication Infrastructure etc)! Provide adequate Logistics (vehicles (100), tools, equipment etc)! Creating additional suitable office and residential accommodation (135)! Review of Inadequate business processes. (new service connection, complaints receipt and resolution systems, customer data management systems etc)
49 49 Objectives & Strategies People & Systems (II)! Implementation of the approved New NEDCo Organogram! To equip NEDCo Management with the required skills and capacity to run NEDCo! To equip NEDCo with project management skills to manage all projects from this plan
50 50 People & System Project & Investment (I) 1 Estimated Initiative Cost (US$) Provide the needed 14,000,000 1,759,357 3,240,643 3,000,000 4,000,000 vehicles and specialised 2,000,000 equipment, tools, safety ware etc for better service. 2 Radio Communication improvement 4,920,000 1,700,000 1,300, , , ,000 3 NEDCo Wide Area Network (WAN), Local Area Networks and Wireless Broadband 4,720,000 2,820,000 1,500, , , NEDCo Billing System Improvement A complete ICT system to evaluate the distribution network loss, reduce the losses and enhance quality service delivery (GIS, load flow analysis, meter data management, call centers etc.) 500, ,000 7,000, ,000 5,270,000 1,000, ,000
51 51 People & System Project & Investment (II) Initiative Estimated Cost (US$) Effective 1,570, , , ,000 customer 250, ,000 education through sms group messaging Create more customer service centres and cash collection points Improve skills of staff & capacity building Provide adequate office/residential accommodation (complete ongoing projects, provision of furnishing for completed offices) 4,500,000 1,500,000 1,200,000 99, , ,000 31,800, ,000-2,000,000 1,500,000 1,500, ,000 2,000, ,000 17,000, ,000 10,000,000
52 52 Partner for Northern Economic Development! VRA is involved in several initiatives that will positively impact economic development in the NEDCo operating area! Construction of two hydro plants at Pwalugu and Juale by 2018/2019! Construction of 10 MW of solar facilities by 2014! Upgrade of inland port facilities at Buipe/Yapei and across the Volta Lake as well as injection of new investment and equity partners in VRA lake transport subsidiary ( VLTC )! Pwalugu 50 MW hydro plant is expected to provide important additional benefits! Irrigation and flood control! NEDCo has commenced a close collaboration with SADA to anticipate these developments. NEDCo s ability to service resulting newly created commercial customers will both provide new revenue and attract additional commercial customers for NEDCo
53 53 Summary Investment (I) Investment Estimated Cost (USD) Ongoing Projects (2012) 17,089,175 Short Term (Jan-13 to Dec-13) 63,950,826 Medium Term (Jan-14 to Dec-16) 192,236,763 Long Term (Jan-17..) 71,111,450 TOTAL (USD) 344,388,213
54 Summary Investment (II) 54 Profit and Loss Account Projections GH '000 GH '000 GH '000 GH '000 GH '000 GH '000 Sale of electricity 139, , , , , ,076 Other income 2,254 3,945 6,903 8,629 10,786 13,482 Deduct: 141, , , , , ,558 Operating Costs 160, , , , , ,982 Depreciation 28,019 29,819 31,619 33,419 35,219 37,019 Total expenses 188, , , , , ,001 Net Profit/Loss for the year without depn (18,720) (19,196) (8,607) (353) 12,187 25,576 Net Profit/Loss for the year with depn (46,738) (49,014) (40,226) (33,772) (23,032) (11,443) Sonabel expected margin 1,777 1,866 1,959 2,057 2,160 2,268 Adjusted net profit with Sonabel (44,962) (47,149) (38,267) (31,715) (20,872) (9,176)
55 55 Summary Investment (III)! Subsequent to the challenges identified, NEDCo has initiated some projects to address some of them as outlined below:! Distribution Network Rehabilitation Project (DNRP):! NEDCo Supply Improvement and Rehabilitation Project (NSIRP)! Installation of Prepayment Meters
56 56 Conclusion (I) 1. The Northern Electricity Department was created as a result of the extension of the National GRID to the Northern parts of Ghana. 2. Because of the low customer density and the absence of large industrial customers, the design standards of the network were relaxed in order to make the extension economically feasible. The design was to allow for the ultimate utilization of some components of the networks by Despite this, no substantial investment has been made in the network over the past 25 years except the US$10m GEDAP assistance.
57 57 Conclusion (II) 4. This lack of investment has created Financial, Technical, Commercial and People/System challenges to NEDCo which was formed as part of the Power Sector Reform. 5. Among others, the challenges have led to: a. Recurring financial losses to NEDCo b. High Distribution losses
58 58 Conclusion (III) c. Poor Collection rate d. Obsolete IT infrastructure e. Ineffective and inefficient business processes f. Staff with inadequate capacity g. Lack of logistics such as vehicles, tools and equipment h. Lack of suitable office and residential accommodation
59 Conclusion (IV) 59! Increase Collection Efficiency! Enhance the skills of Employees! Submitting a case for Tariff Review! Capacity Enhancement! Add more Bulk Customers! Implement an IT Infrastructure! Reduce Distribution Losses! Reduce the Gap of Revenue Vs Operating Expenses
60 60 Conclusion (V) 6. This Business Plan has identified some strategies and projects to address the challenges and achieve the following: i. Make NEDCo financially Self Sustainable by 2017 ii. Bring Technical Losses to 6.5 % by 2017 iii. Bring Commercial Losses to 6.5% by 2017
61 61 Conclusion (VI) iv. Achieve Collection rate of not less than 97 % by 2017 v. Upgrade the IT infrastructure vi. Better Customer Delivery vii. Capacity Enhancement of Staff 7. The total estimated cost of the investments is US$344m out of which US$17m projects are already ongoing from NEDCo s own resources. 8. We hope donors will support us to enhance our service delivery to our customers
62 62 Thank You
STRATEGIC ISSUES OF THE ELECTRICITY COMPANY OF GHANA PRESENTATION BY MR. WILLIAM HUTTON-MENSAH (AG. MANAGING DIRECTOR) ELECTRICITY COMPANY OF GHANA
STRATEGIC ISSUES OF THE ELECTRICITY COMPANY OF GHANA PRESENTATION BY MR. WILLIAM HUTTON-MENSAH (AG. MANAGING DIRECTOR) OUTLINE OF PRESENTATION (ECG) 2 Introduction Map of Operational Area Company Mandate,
More informationInvestment Brief for the Electricity Sector in Ghana
Investment Brief for the Electricity Sector in Ghana Overview Ghana s economy growth decelerated sharply to an estimated 4.2% in 2014, down from 7.4 % in 2013. Manufacturing and oil production from the
More informationFEED-IN OF EXCESS ENERGY AND SELF CONSUMPTION: NEW REGULATIONS IN GHANA S ENERGY SECTOR JULIUS NKANSAH-NYARKO ENERGY COMMISSION
FEED-IN OF EXCESS ENERGY AND SELF CONSUMPTION: NEW REGULATIONS IN GHANA S ENERGY SECTOR JULIUS NKANSAH-NYARKO ENERGY COMMISSION NOVEMBER 20, 2014 PRESENTATION OUTLINE Overview of Ghana s Energy Situation
More informationTARIFF AND GOVERNANCE ASSESSMENT
Power System Expansion and Efficiency Improvement Investment Program (RRP BAN 42378) A. Tariff Assessment 1. Introduction TARIFF AND GOVERNANCE ASSESSMENT 1. Electricity tariffs in Bangladesh are unbundled
More informationClimate Parliament Climate Change & Energy Access for the Poor March 26-28, 2010, Limbe, Cameroun
Climate Parliament Climate Change & Energy Access for the Poor March 26-28, 2010, Limbe, Cameroun SHEP Ghana s Self-help Electrification Programme By Henry Vanderpuye Energy Consultant, Ministry of Energy
More informationPower Distribution Feasibility Studies, Ghana
Power Distribution Feasibility Studies, Ghana Phase II Feasibility Assessment Electric Company of Ghana Final November 2014 ES062314053347WDC Prepared for U.S. Army Corps of Engineers, Europe District
More informationFIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
More information3.0 Results and Discussions
Estimating the cost of electrification technology options to aid electricity access scale up: The case of Ghana F. Kemausuor * 1, I. Adu-Poku 1, E. Adkins 2, A. Brew-Hammond 1 1.0 Introduction 1 The Energy
More informationA least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank
A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank 1. Introduction Kisiizi Hospital is a Church of Uganda "Private not-for-profit health care provider
More informationWATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR)
WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS A. Completed December 2001 Shedgum Debottlenecking # 45943/00 47.34 Million Total 600.8 Million 154 n American Oil Co. (ARAMCO) ARAMCO Feb. 1998 to Dec.
More informationESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe
NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3
More informationELECTRICITY COMPANY OF GHANA PROPOSAL FOR REVIEW IN DISTRIBUTION SERVICE CHARGE
ELECTRICITY COMPANY OF GHANA PROPOSAL FOR REVIEW IN DISTRIBUTION SERVICE CHARGE JUNE 2013 TABLE OF CONTENTS TABLE OF CONTENTS... i LIST OF TABLES... iv 1 Introduction... 5 1.1 Brief Background... 5 1.2
More informationINDEX S. No. PARTICULARS Note:
INDEX S. No. PARTICULARS T1 Profit & Loss Account - Transmission Business T2 Profit & Loss Account - SLDC Business T3 Annual Revenue Requirement - Transmission Business T4 Annual Revenue Requirement -
More informationNetwork Price List (excludes GST)
Network Price List (excludes GST) Effective from 1 July 2007 Monthly Monthly Monthly Network Network Network Energy Rates Step Rates Demand Capacity Capacity Price Network Price DLF Access Rates Rates
More informationSustainable and Renewable Energy Development Authority (SREDA) of Bangladesh Role and Responsibility
Sustainable and Renewable Energy Development Authority (SREDA) of Bangladesh Role and Responsibility Welcome to SREDA Siddique Zobair Member (EE & C) Sustainable & Renewable Energy Development Authority
More informationAgenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com
Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network
More informationKyrgyzstan: Power Generation & Transmission
Kyrgyzstan: Power Generation & Transmission October, 2010 Author: Artyom Zozulinsky, Business & Commercial Assistant, US Embassy Bishkek Contents SUMMARY... 2 POWER SECTOR OVERVIEW... 2 Infrastructure...
More information15 th UPDEA CONGRESS THEME: GEOGRAPHIC INFORMATION SYSTEM: ECG S EXPERIENCE ABSTRACT. PATRICE AFENYO, Electricity Company of Ghana
15 th UPDEA CONGRESS THEME: GEOGRAPHIC INFORMATION SYSTEM: ECG S EXPERIENCE Author: PATRICE AFENYO, Electricity Company of Ghana ABSTRACT GIS (Geographic Information System) is an integrated system of
More informationCOMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited
PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date
More informationELECTRICITY DISTRIBUTION TARIFFS The Chilean Experience. Hugh Rudnick Pontifícia Universidad Católica de Chile
ELECTRICITY DISTRIBUTION TARIFFS The Chilean Experience Hugh Rudnick Pontifícia Universidad Católica de Chile Brasilia, June 2009 Objective Describe the building of the electricity distribution tariff
More informationDaily Daily Network Network Network Energy Rates Step Rates Capacity. Price Rates Rates
Excludes GST Effective from 1 July 2010 Tariff Class Daily Daily Network Network Network Energy Rates Step Rates Capacity Capacity Price Rates Rates No. Network Price DLF Access Non-ToU Time of Use (ToU)
More informationPhase Attribute Identification using GPS Technology
Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits
More informationTransmission Related Station Power Use at Substations
Transmission Related Station Power Use at Substations BUSINESS PRACTICE This Business Practice identifies the cost responsibility for energy consumption at substations by American Transmission Company
More informationENERGY SUPPLY TO THE ECONOMY
Strategic National Energy Plan 2006 2020 Annex Two of Four ENERGY SUPPLY TO THE ECONOMY Electricity Energy Commission July, 2006 2 TABLE OF CONTENT PREFACE...5 Background......7 Institutional setup...7
More informationTARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents
Annexure-1-B ANNEXURE TO TARIFF ORDER PASSED BY MPERC For Financial Year 2006-07 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS Table of Contents Sr No Particulars
More informationSECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities
Country Partnership Strategy: Bangladesh, 2011 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Power generation gap. Bangladesh endures long
More informationGuide to Electric Power in Ghana
Guide to Electric Power in Ghana First Edition Error! RESOURCE CENTER FOR ENERGY ECONOMICS AND REGULATION INSTITUTE OF STATISTICAL, SOCIAL AND ECONOMIC RESEARCH UNIVERSITY OF GHANA, LEGON July 2005 First
More informationSP Energy Networks 2015 2023 Business Plan
Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from
More informationAFRICAN DEVELOPMENT BANK
AFRICAN DEVELOPMENT BANK EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT - PHASE I SUPPLEMENTARY GRANT PROPOSAL COUNTRY : ZIMBABWE APPRAISAL REPORT ONEC DEPARTMENT December 2013 Table of Contents
More informationHon. Jemma Nunu Kumba Minister Ministry of Electricity and Water Resources Republic of South Sudan
Hon. Jemma Nunu Kumba Minister Ministry of Electricity and Water Resources Republic of South Sudan South Sudan Electricity Sector Investment Opportunities Introduction Status of electricity supply in South
More informationIssues and Challenges in the Nigerian Electricity Industry: Case of Benin Electricity Distribution Company
Issues and Challenges in the Nigerian Electricity Industry: Case of Benin Electricity Distribution Company Roland Uhunmwagho Kenneth E. Okedu * Department of Electrical Engineering, College of Engineering,
More informationTitle of presentation
Title of presentation Edison Makwarela Senior Consultant, Eskom, Gauteng, South Africa Current Situation - The reserve margin is currently 8 10%, against an aspiration of 15% - Increased probability of
More informationPerspectives on Renewable Energy Investment in Ghana
Perspectives on Renewable Energy Investment in Ghana Seminar on Sustainable Energy Investment in Africa b UN City, Copenhagen, 24-25 June 2014 By Wisdom Ahiataku-Togobo Director, Renewable & Alternate
More informationSHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015
SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission
More informationCONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services
CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient
More informationBC Hydro. Electric Distribution System Cost of Service Study
BC Hydro Electric Distribution System Reimer Consulting Group Inc. Arnie Reimer May 7, 2010 Table of Contents 1. Executive Summary... 3 2. BC Hydro Electric Distribution System... 4 2.1. General Description...
More informationPRESENTATION. Improving the performance of Public Water Utilities A case study of Bangalore N.C. MUNIYAPPA, Chairman, BWSSB LOCATION MAP OF BANGALORE
Arabian Sea Mumbai KARNATAKA Delhi Chennai Nepal Calcutta Bay of Bengal PRESENTATION Improving the performance of Public Water Utilities A case study of Bangalore By N.C. MUNIYAPPA, Chairman, BWSSB LOCATION
More informationCommittee on the Northern Territory s Energy Future. Electricity Pricing Options. Submission from Power and Water Corporation
Committee on the Northern Territory s Energy Future Electricity Pricing Options Submission from Power and Water Corporation October 2014 Power and Water Corporation 1. INTRODUCTION On 21 August 2014, the
More information1 to 3 MARCH 2015, THE VIC HOTEL, KISUMU, KENYA
AN OVERVIEW OF WATER RESOURCES MANAGEMENT IN THE VOLTA BASIN WITH RESPECT TO FLOODS AND DROUGHT FIRST STEERING COMMITTEE MEETING OF THE FLOOD AND DROUGHT MANAGEMENT TOOLS PROJECT 1 to 3 MARCH 2015, THE
More informationMillennium Development Authority (MiDA)
Millennium Development Authority (MiDA) GENERAL PROCUREMENT NOTICE No 2 (March 2015) SCHEDULE OF ACTIVITIES PLANNED TO COMMENCE IN THE PERIOD MARCH JULY 2015 The Government of Ghana (the Government or
More informationHow To Get A Better Deal On Power From Powerline Power From Pse
ELECTRICITY RATES FOR COMMERCIAL AND INDUSTRIAL CUSTOMERS Rates Effective January 1, 2010 If you would like information about our services, details about your rights and responsibilities, or a copy of
More informationGhana's Economic Performance 2010
GHANA STATISTICAL SERVICE (GSS) Statistics for Development and Progress Ghana's Economic Performance 21 i n f i g u r e s P.O. Box GP 198, Accra www. statsghana.gov.gh 211 Ghana's Economic Performance
More informationMICRO-GRIDS FOR RURAL ELECTRIFICATION Case Study from Zambia on the Zengamina Micro-Hydro Power Grid
MICRO-GRIDS FOR RURAL ELECTRIFICATION Case Study from Zambia on the Zengamina Micro-Hydro Power Grid Presentation by Energy Regulation Board, Zambia 79 th IEC General Assembly Workshop for Industrialising
More informationEuropean Distribution System Operators for Smart Grids
European Distribution System Operators for Smart Grids Integrating electricity storage in distribution grids May 2016 Introduction Since the start of mass-electrification, the electricity industry has
More informationAPPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution
APPLICATION NOTE Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution INCREASING PV HOSTING WITH EMPOWER TM SOLUTION Executive Summary Distributed solar photovoltaic
More informationPOWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends
POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...
More informationMIDVAAL LOCAL MUNICIPALITY
MIDVAAL LOCAL MUNICIPALITY Determination of Charges Payable for Electricity July 2011 to Jun 2012 Tariff of Charges PART I: SUPPLY OF ELECTRICITY 1. BASIC CHARGES 1.1 Except as provided in 1.2 the following
More informationPower Tariff Structure in Thailand 23 October 2012, Singapore Dr. Pallapa Ruangrong Energy Regulatory Commission of Thailand
Power Tariff Structure in Thailand 23 October 2012, Singapore Dr. Pallapa Ruangrong Energy Regulatory Commission of Thailand Singapore EAS ABOUT THAILAND Population 67 Million Customers (at end-2011) 19
More informationSize template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer
Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders
More informationGEOGRAPHIC INFORMATION SYSTEM ECG S EXPERIENCE
UPDEA 15 TH CONGRESS, JUNE 2005, ACCRA-GHANA GEOGRAPHIC INFORMATION SYSTEM ECG S EXPERIENCE Presented By: Ing Patrice Afenyo In This Presentation.. ECG Brief Components of a GIS Why ECG Needs GIS Our Approach
More informationUtilization of Automatic Meter Management in Smart Grid Development
Utilization of Automatic Meter Management in Smart Grid Development Elenia Verkko Oy Ville Sihvola Head of Marketing and Sales ville.sihvola@elenia.fi Content of the presentation 1. What is Elenia Verkko
More informationSOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD
SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)
More informationSolar Energy in Africa Experiences from Ghana
Solar Energy in Africa Experiences from Ghana AfricaSolar Conference 2015, 25 27 June 2015, Ouagadougou David A. Quansah Kwame Nkrumah University of Science and Technology (KNUST) Kumasi Ghana 26 June
More informationPOWER AFRICA GEOTHERMAL ROADSHOW. Presented by Mekuria Lemma Ethiopian Electric Power Strategy & Investment Head SEP 28 Oct 3, 2014
POWER AFRICA GEOTHERMAL ROADSHOW Presented by Mekuria Lemma Ethiopian Electric Power Strategy & Investment Head SEP 28 Oct 3, 2014 Country in the horn of Africa Total area 1.13 million square km 90 million
More informationNORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September
More informationEVN SMART GRID PLAN. Technical and Operational Dept., Vietnam Electricity Nguyễn Hải Hà Hanh@evn.com.vn
EVN SMART GRID PLAN Technical and Operational Dept., Vietnam Electricity Nguyễn Hải Hà Hanh@evn.com.vn Frankfurt, 14 th November 2013 1 Content 1. Introduction of Vietnam Electricity (EVN) 2. EVN Smart
More informationGeneration Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine
More informationPROFILE ON DISTANCE EDUCATION AT ALL LEVELS
PROFILE ON DISTANCE EDUCATION AT ALL LEVELS 172-2 TABLE OF CONTENTS PAGE I. SUMMARY 172-3 II. SERVICE DESCRIPTION & APPLICATION 172-3 III. MARKET STUDY AND SERVICE CAPACITY 172-4 A. MARKET STUDY 172-4
More informationSA Power Networks Network Tariffs - Residential APPLIES TO USAGE FROM 1 JULY 2015
SA Power Networks Network Tariffs - Residential Low Voltage Residential - Single Rate DUOS excl TUOS excl PV JSO excl Total excl Total incl Block 1 Usage Rate $/kwh First 333.3 kwh/mth 0.0745 0.0300 0.0130
More informationFor Utility Operations
For Utility Operations Provided For: SCAMPS 2014 Annual Meeting Presented By: Michael E. Jenkins, PE What Are We Talking About? Simply, Preparing A Clear Picture Of Where And How The Utility Is Headed
More informationSAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES
SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES Table of Contents 1st. INTRODUCTION... 3 2nd. ELECTRICITY SECTOR BACKGROUND. 4 3rd. SCOPE OF WORK. 6 PHASE :
More information16 West Coast Regional Plan
16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast
More informationHow To Write A Report On The Afghanistan Distribution System
AYBAK CITY (SAMANGAN PROVINCE) DISTRIBUTION SYSTEM CLOSE-OUT REPORT Prepared by: Raul Zuniga/Clayton Strampher/Jack Whippen/Tufail Memon Date of Report: May 3, 2006 Project/Action Area: Distribution Project
More informationUnderstanding Network Tariff Reform
Understanding Network Tariff Reform A guide for small to medium business and residential customers who use less than 100MWh of electricity a year Ergon Energy is restructuring the way it charges for the
More informationOFF-GRID SOLAR CASE STUDY AND OPPORTUNITIES IN KENYA J.M.P. MBITHI Deputy Director, Renewable Energy MINISTRY OF ENERGY AND PETROLEUM
OFF-GRID SOLAR CASE STUDY AND OPPORTUNITIES IN KENYA J.M.P. MBITHI Deputy Director, Renewable Energy MINISTRY OF ENERGY AND PETROLEUM PRESENTATION SUMMARY Introduction-Power situation in Kenya Off-grid
More informationHydropower in Rwanda: Ongoing Initiatives & New Investment Opportunities. Yves Muyange Director General Energy Water & Sanitation Authority
Hydropower in Rwanda: Ongoing Initiatives & New Investment Opportunities Yves Muyange Director General Energy Water & Sanitation Authority Rwanda: A Thousand hills between the two Major Drainage Basins
More informationVOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB
More informationAsset Management Plan
2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the
More informationRENEWABLE ENERGY WORKSHOP
RENEWABLE ENERGY WORKSHOP Development of Bankable PPAs and Opportunities for Cooperation with ECG GIZ House, Reichpietschufer, Berlin January 18, 2016 OUTLINE OF PRESENTATION Introduction and Overview
More informationLadies and Gentlemen,
Ladies and Gentlemen, I would like to begin my speech by thanking deeply the Maniatakeion Foundation and especially the Chairman, Mr. Dimitris Maniatakis for his invitation and to congratulate him for
More informationELECTRICITY TARIFF (Effective from September 1, 1999.)
ELECTRICITY TARIFF (Effective from September 1, 1999.) * Payment period of electricity bill without surcharge is 30 days. * For late payment, surcharge @ 2% per month is applicable to all classes consumers.
More informationElectricity Generation from Renewable Energy in Sri Lanka: Future Directions
Electricity Generation from Renewable Energy in Sri Lanka: Future Directions Presented by M.M.C. Ferdinando, Secretary, Ministry of Power and Energy R.J. Gunawardana, Additional General Manager (Transmission),
More informationScorecard - Tillsonburg Hydro Inc.
Scorecard - Tillsonburg Hydro Inc. 9/18/215 Performance Outcomes Performance Categories Measures 21 211 212 213 214 Trend Industry Distributor Target Customer Focus Services are provided in a manner that
More informationInvestor day. November 17, 2010. Energy business Michel Crochon Executive Vice President
Investor day November 17, 2010 Energy business Michel Crochon Executive Vice President We built a global leadership in medium voltage and grid automation with Areva Distribution MV switchgears & systems
More informationGreen Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process
Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering
More informationARRA Grant Case Studies SMUD s Smart Grid Program
. ARRA Grant Case Studies SMUD s Smart Grid Program Jim Parks December 2012 Powering forward. Together. About SMUD 600,000 customers 1.4 million population $1.4 billion in revenues 900 mi 2, 2331 km 2
More informationGuideline for Energy Efficient Electrical systems for building. Presentation by TERI
Guideline for Energy Efficient Electrical systems for building Presentation by TERI Objective of study The study highlights how BBMP can implement energy efficiency measures in building in co-ordination
More informationPhiladelphia Navy Yard Microgrid Modernization. Will Agate LEED AP Senior Vice President Philadelphia Industrial Development Corporation (PIDC)
Philadelphia Navy Yard Microgrid Modernization Will Agate LEED AP Senior Vice President Philadelphia Industrial Development Corporation (PIDC) October 2014 THE NAVY YARD: The Campus. The Energy. The Opportunity.
More informationA Gazprom A Energy Gazprom whitepaper Energy Guide. Energy. What are you paying for?
A Gazprom A Energy Gazprom whitepaper Energy Guide Energy What are you paying for? 2 Introduction According to government statistics, the cost of buying electricity to businesses in the UK has increased
More informationINSTITUTIONAL, REGULATORY AND COOPERATIVE FRAMEWORK MODEL FOR THE NILE BASIN POWER TRADE QUESTIONNAIRE FOR INFORMATION GATHERING AND MANUAL
INSTITUTIONAL, REGULATORY AND COOPERATIVE FRAMEWORK MODEL FOR THE NILE BASIN POWER TRADE QUESTIONNAIRE FOR INFORMATION GATHERING AND MANUAL Prepared for: Prepared by: MERCADOS ENERGY MARKETS INTERNATIONAL
More informationSmartSacramento. Green Summit 2011. Jim Parks Program Manager SmartSacramento Team. April 19, 2011
SmartSacramento Green Summit 2011 April 19, 2011 Jim Parks Program Manager SmartSacramento Team The Current State of the Grid Current grid tends toward dumb We typically learn about outages via phone Many
More informationHyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas
ENERGY NETWORKS ASSOCIATION Electricity Industry EMF Measurement Protocol for High Field Areas Contents 1 Introduction 1.1 Background 1.2 High Field Areas 2 High Field Area - Generation Businesses 2.1
More informationEngineering innovation
Eaton's Electrical Engineering Services & Systems Solutions Focus Seamless Solutions for Reliable, Efficient and Safe Power Systems Engineering innovation Progressive solutions for today s power systems
More informationA Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
More informationA Green Sector Overview
A Green Sector Overview Micro Hydro Electric Power Ontario's Waterpower Resources: Past and Present The first hydroelectric generator in Canada was installed near Ottawa, which was the first city in North
More informationA Network Reference Model for Distribution Regulation and Planning: the Spanish Case
A Network Reference Model for Distribution Regulation and Planning: the Spanish Case Jesús Pascual Peco González Instituto de Investigación Tecnológica (IIT) Universidad Pontificia Comillas, Madrid http://www.iit.upco.es
More informationNetwork Consulting for Power Grid Optimization
Network Consulting for Power Grid Optimization Project experience in India Network Consulting Competences Page 1 Our worldwide representation Manchester The Hague Denver Schenectady San Diego Houston Mexico
More informationExecutive summary 2. 1 Introduction 4
Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring
More informationWelcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community. www.fortisbc.
Welcome to our open house Thanks for coming Please sign in and help yourself to refreshments Integrated System Plan (ISP) Looks ahead 20 years to identify the energy and infrastructure needs of our customers
More information7. Broadband Community Profiles Winters
7. Broadband Community Profiles Winters! A. Residential Two primary providers serve the Winters residential broadband market, AT&T of California and Wave Broadband. Fixed wireless providers also have coverage
More informationCOST OF DOING BUSINESS IN GHANA
NAME OF ORGANIZATION COST OF DOING BUSINESS IN GHANA REGISTRATION/INCORPORATION OF COMPANIES AND REGISTRATION OF INVESTMENTS TYPE OF SERVICE FEES (IN GHANA CEDIS) (GH ) REGISTRATION OF BUSINESS 1.Limited
More information1. Project Profile and Japan s ODA Loan
Sri Lanka Transmission and Grid Substation Development Project 1. Project Profile and Japan s ODA Loan Report Date: September 2002 Field Survey: July/August 2001 Site Map: Sri Lanka Site Photo: Matara
More informationSmart Metering for Automatic Demand Response
Smart Metering for Automatic Demand Response Sanjeev K Rana TATA Power Delhi Distribution Limited METERING BILLING/CRM BANGKOK 08-May-2012 Agenda Company Overview Challenges in Indian Power Sector Need
More informationADMS(Advanced Distribution Management System ) in Smart Grid
ADMS(Advanced Distribution Management System ) in Smart Grid 柯 佾 寬 博 士 Yi-Kuan Ke, Ph.D. 2014/03/28 Smart Grid Solution Smart Grid Solution Overview Smart Grid Solutions Smart Network Operation - Distribution
More informationHow To Grow A Global Power Company
Investor Day February 20, 2014 Infrastructure Business Frederic Abbal EVP, Infrastructure Business We have built a global leader A global leader in medium voltage, grid automation & network management
More informationStatus of Renewable Energy in Liberia
Status of Renewable Energy in Liberia Augustus V. Goanue Principal Officer Prototype Rural and Renewable Energy Agency of Liberia Email: gusgoanue@yahoo.com Mobile: +231 655 9266 Presentation Outline Background
More informationInternational Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center)
International Solar Energy Arena January 23rd, 2009, Istanbul STEAM (Strategic Technical Economic Research Center) Good morning. Sayin Bakanım. Members of Parliament. Ladies and Gentlemen. Slide 1: Opening
More informationPOWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends
POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination
More informationBy Manitoba Hydro, March 4 th 2013
Rebuttal to Bipole III Coalition underground cable report Potential Use of Underground Cables for Sections of the Planned 500 kvdc Bipole III Overhead Line in Manitoba By Manitoba Hydro, March 4 th 2013
More information