1 Solar Purchase Program Electrical Guide Please share this document with your electrician to ensure wiring is done correctly. Should you or your electrician have any questions, please let us know. Included In This Guide: General Requirements Metering Configurations Images of the Installed Meter Display General Requirements: Installations must meet all requirements of the Dominion Virginia Power Information and Requirements for Electric Service ( Blue Book ). In cases where conflicting requirements exist between this document and the Dominion Virginia Power Information and Requirements for Electric Service ( Blue Book ) this document shall take precedence. The customer s solar generation metering shall have the same characteristics (voltage and phasing) as the Company s electric delivery service. The solar generation metering and disconnect (where required by local ordinance or code) should be installed on the same exterior wall and within view of the existing electric delivery service meter. For the sub-meter configuration only, an Equipment Grounding Conductor may be installed through and/or connected to the generation meter base where required by local ordinance or code. The Equipment Grounding Conductor must be routed and/or secured in such a manner that it cannot come into contact with load or line terminals in the meter base. A Grounding Electrode Conductor is not to be installed in any meter base. A decal will be applied to the cover of the electric delivery meter base indicating that solar generation is interconnected at the premise. A decal will also be applied to the cover of the solar generation metering. An additional decal may also be placed inside the meter base for both meter types. All decals will be provided and applied by Dominion. Decal for Generator Meter Base Decal for Electric Delivery Generator Meter Base
2 metering configurations The Company s Solar Purchase Program requires metering capable of providing three sets of metering data in order to be able to determine both a customer s total electrical usage, and the total solar generation. A Load Profile (LP) meter at the existing electric delivery service point and installation of an additional meter base and LP meter to measure the total output of the solar generation system is required for all participants. Generated solar energy, and energy that is returned to the grid, will be captured on metering received channels, and all energy delivered to the customer will be captured on the metering delivered channels. Consequently, the solar generator should in all cases be connected to the load side terminals of the meter enclosure. The two potential metering configurations are sub-meter and second meter. Preferred Metering Configuration: Sub-Meter Illustrated In: Figure 1 and 4 Figure 1 Sub- Meter Configuration Dominion Solar Generation Meter Customer s Electric Distribution Panel Customer s Solar Disconnect (where required) Branch Circuits to other Loads Customer s Inverter Dominion Electric Delivery Meter Dominion Electric Delivery Service Customer s Solar Panels A = Energy supplied by Dominion B = Energy supplied by Customer C = Energy returned to grid A + B - C = Energy consumed on site B = Customer Generated Energy
3 sub-meter Configuration Continued 200A 120/240V 1P Meter Base Stock Number Provided By Dominion - Installed and Wired by Customer on the same exterior wall and within view of the existing electric service meter Solar Disconnect (where required by local ordinance or codes) From Solar Generator - Minimum conductor size #8 AWG To Customer Distribution Panel Figure 1 Wiring Connections Sub-Meter 200A or Less Single Phase 120/240v
4 metering configurations Second Meter Illustrated In: Figures 2, 5 and 6 Customer s Solar Disconnect (where required) Customer s Electric Distribution Panel Customer s Electric Distribution Panel Branch Circuits to other Loads Customer s Inverter Dominion Solar Generation Meter Dominion Electric Delivery Meter Dominion Electric Delivery Service Customer s Solar Panels A = Energy supplied by Dominion B = Energy supplied by Customer C = Energy Diverted (not allowed) Figure 2 Second Meter Grid Connected Configuration
5 Second Meter Configuration Continued Solar Disconnect (where required by local ordinance or codes) 200A 120/240V 1P - 2 Position Meter Base Stock Number Provided By Dominion Installed and Wired by Customer From Solar Generator - Minimum Conductor Size #8 AWG To Customer Distribution Panel Figure 5 Wiring Connections Second Meter Grid Connected 200A or Less Single Phase 120/240V
6 Second Meter Configuration Continued 200A 120/240V 1P Meter Base Stock Number Provided By Dominion Installed by Customer 1.25 Conduit installed by Customer. Conductor provided and installed by Dominion From Solar Generator or Solar Disconnect (Where Required) - Minimum Conductor Size #8 AWG Figure 6 Wiring Connections Second Meter Grid Connected 200A or Less Single Phase 120/240V
7 INSTALLED METER DISPLAY Sub-Meter Arrangement Delivery Meter Displays 04 Prompt - Energy delivered to customer Total cumulative kwh delivered 35 Prompt - Energy sent back to grid Total cumulative kwh to grid Current direction of energy flow - left arrow indicates flow back to grid Generation Sub-Meter Display 01 Prompt - Energy generated Total cumulative kwh generated
8 Second Meter (second line side) arrangement Generation Meter Display 35 Prompt - Solar energy sent to grid 04 Prompt - Energy used by inverters Total cumulative kwh sent Total cumulative kwh to inverters Current direction of energy flow - left arrow indicates flow from solar to grid Delivery Meter Display 01 Prompt - Energy delivered to customer Total cumulative kwh delivered Current direction of energy flow - right arrow indicates flow from grid to customer
Request for Proposals for Photovoltaic System Installation
Request for Proposals for Photovoltaic System Installation Presented by: Prepared by: Location: Contact: Date: Capitol Hill Housing Foundation Bonneville Environmental Foundation, Renewable Energy Group
More informationSolar Panel Installations
Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.
More informationSOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings
*** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not
More informationELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01)
ELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01) Rule 28-900 Standby Generator Installations Due to the increasing number of standby generator installations being established to maintain continuity
More informationCurrent Transformer (CT) Selection Guide
Current Transformer (CT) Selection Guide Article ESA-1008D December 5, 2014 Contents 1 Introduction.............................................. 3 1.1 Extending CT leads.......................................
More informationINSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1
City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included
More informationCurrent Cost TREC Current Cost ENVI Current Cost EnviR SmartNow Solar Monitoring Kit
Installation Guidelines Products Covered: Current Cost TREC Current Cost ENVI Current Cost EnviR SmartNow Solar Monitoring Kit This document is for the use of Qualified Electricians and Electrical Contractors
More informationDakota Energy Cooperative, Inc. POLICY STATEMENT
Dakota Energy Cooperative, Inc. POLICY STATEMENT Subject: Member Owned Small Renewable Energy Policy No. 57 Rate and Interconnection Requirements Issue Date: May 21, 2008 Revised Date: December 16, 2014
More information2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE
2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE PAGE 1 OF 5 This Reference provides a very comprehensive list of aspects of a solar PV installation that could be reviewed, clarifying
More informationUser Manual of Grid Tie Inverter with Limiter
User Manual of Grid Tie Inverter with Limiter Grid Tied Inverter With Limiter (GTIL) 1 www.chinesegrid.com 2014-8-1 All rights reserved Why we produced the GTI-L --- It is in response to the overwhelming
More informationExplanation of Net Energy Metering and Annual Net Surplus Electricity Settlement Options
Explanation of Net Energy Metering and Annual Net Surplus Electricity Settlement Options Applicability This document is applicable to any City of Palo Alto Utilities ( CPAU ) Customer Generator currently
More informationArticle 10 - ADMINISTRATIVE SECTION
Article 10 - ADMINISTRATIVE SECTION 10.1 TITLE These Administrative Regulations along with the requirements included in the 2011 Edition of the National Electrical Code (NFiPA-70-2011) as adopted by the
More informationWhite Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5
White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code June 2015 Revision 1.5 Shalhevet Bar-Asher; SolarEdge Technologies, Inc. Bill Brooks, PE; Brooks Engineering LLC
More informationListed are common requirements that apply to existing solar installations when altered, added to or reconfigured.
SOLAR ALTERATIONS REQUIREMENTS August 2015 These requirements address typical alterations to solar installations; they cannot address every scenario. In Victoria, an alteration to a solar installation
More informationInstallation Guide Solar Connect-11
Installation Guide Solar Connect-11 Version 1.1 Contents Important Product Information 3 System Registration Form 4 Solar Connect-11 Overview 5 Internet & Power Connections 6 Single Phase CT Connections
More informationLEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems
LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the
More informationInverter / Charger Installation General Operations and AC and DC Connections
Inverter / Charger Installation General Operations and AC and DC Connections The Inverter is just one piece. Sometimes, a tendency is to mount the inverter and batteries, and make it work It is better
More informationELECTRICAL CONTRACTORS, SUPPLIERS AND DISTRICT ENGINEERING, CONSTRUCTION & OPERATIONS PERSONNEL
January 2, 2014 ATTENTION: SUBJECT: ELECTRICAL CONTRACTORS, SUPPLIERS AND DISTRICT ENGINEERING, CONSTRUCTION & OPERATIONS PERSONNEL Electrical Service Manual (ESR) Several revisions have been made to the
More informationSERVICE - GENERAL Residential, Commercial, Industrial
PAGE 1 OF 9 USE: Rules and procedures for overhead or underground services. PREVIOUS REVISION 10-01-01 ORIGINATED 03-94 PREVIOUS NUMBER ER 1-290-B, 07-15-93 LATEST REVISION: Remove details of Facility
More informationDuke Energy Carolinas. Inverter Based Generation Interconnection
Duke Energy Carolinas Inverter Based Generation Interconnection Options for Non-Residential Service Customers Table of Contents Rider NM and Rider SCG: Net Metering Single Phase PV System Typical 120/240V
More informationWiser Panel Meter, Model Number WISERCTPM200 Installer s Guide
Instruction Bulletin EAV85226 08/2014 Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Retain for future use. Product Description Kit Contents The Wiser Panel Meter is for use in energy management
More informationQuestions and Answers for Heating and A/C Contractors
1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded
More informationExperiment NO.3 Series and parallel connection
Experiment NO.3 Series and parallel connection Object To study the properties of series and parallel connection. Apparatus 1. DC circuit training system 2. Set of wires. 3. DC Power supply 4. Digital A.V.O.
More informationSolar monitoring gateway quick start guide
Instructional Leaflet I70002E LGATE101-1B LGATE101-1A LGATE101-5B LGATE101-5A Contents Description Page General................................. 2 Information collection sheet............... 2 Quick reference
More informationGROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264
BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used
More informationWISCONSIN DEPARTMENT OF SAFETY & PROFESSIONAL SERVICES
Scott Walker Governor David Ross Secretary WISCONSIN DEPARTMENT OF SAFETY & PROFESSIONAL SERVICES 1400 E Washington Ave PO Box 8935 Madison WI 53708-8935 Email: dsps@wisconsin.gov Voice: 608-266-2112 FAX:
More informationOntario Electrical Safety Code 25 th Edition/ 2012
Ontario Electrical Safety Code 25 th Edition/ 2012 Ted Olechna Director, Codes and Standard Chief Engineer 1 What I Will Cover ESA s role is as the regulator Highlight of 2012 Code changes The Code and
More informationCity of San Diego Residential Photovoltaic Systems Inspection Guidelines
City of San Diego Residential Photovoltaic Systems Inspection Guidelines The purpose of inspections by DSD staff is to ensure compliance with the California Electrical Code (CEC), other applicable codes
More informationDANGER! HIGH VOLTAGE HAZARD
WattNode Pulse kwh Transducer Connection Instructions For use with HOBO H21, H22, U30, UX90, and UX120 series data loggers, and HOBO data nodes Applies to these WattNode Pulse kwh Transducers: Onset Part
More informationAMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5
AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC
More informationHow To Plan Out An Array Of Solar Panels
CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013
More informationFronius IG Plus. The next generation grid-connected PV inverter
Fronius IG Plus The next generation grid-connected PV inverter Maximum energy harvest cloudy or clear The first complete inverter solution. Reliable. Proven. Smart. An outstanding addition to the family:
More informationExpedited Permit Process for PV Systems AC Module
Module The Solar America Board for Codes and Standards (Solar ABCs) Expedited Permit Process provides a means to differentiate systems that can be permitted quickly and easily due to their similarity with
More informationAC Coupling in Renewable Energy Systems
AC Coupling in enewable Energy Systems Most renewable energy systems are DC coupled Most renewable energy systems are based on DC current, yet these have certain scalability limitations. Higher currents
More informationKey Concepts Of Distributed Generation
Key Concepts Of Distributed Generation National Grid - April 29, 2015 International Association of Electrical Inspectors Western Massachusetts Chapter - Springfield MA Bob Moran, Jim Kehrer, Patti Cox,
More informationTECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System
TECHNICAL BRIEF Commercial PV in Australia and New Zealand Using the Enphase Microinverter System 2015 Enphase Energy Inc. All rights reserved May 2015 Table of Contents Commercial PV in Australia and
More informationConnecting the Power of the Sun. DC Disconnects for Solar Photovoltaic Installations. DC disconnects for. solar photovoltaic installations
Connecting the Power of the Sun DC Disconnects for Solar Photovoltaic Installations DC disconnects for solar photovoltaic installations Solar energy is heating up Interest in renewable energy sources has
More informationGuideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10
Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10 This document was developed by the Orange County Fire Chiefs Association, Orange County Fire Marshal Committee.
More informationMetering for today s systems
Metering for today s systems The sub-meter gathers data on the building side of the utility company meter. This allows us to break out usage so data can be collected from individual circuits, a single
More informationLos Angeles Fire Department Requirement No. 96 SOLAR PHOTOVOLTAIC SYSTEM
Los Angeles Fire Department Requirement No. 96 SOLAR PHOTOVOLTAIC SYSTEM The following is the Los Angeles Fire Department s minimum requirement for Solar Photovoltaic System Installations. The City of
More informationApplied Electronics. Commercial Dimming System UPDATE NOTICE
REV. A Applied Electronics Commercial Dimming System UPDATE NOTICE This notice is to inform the end user of an additional feature added to this DP12/2400 dimming unit. This unit has been outfitted with
More informationINSTALLATION INSTRUCTIONS
LIGHTING CONTROL PANELS 4 AND 8 RELAYS INSTALLATION INSTRUCTIONS INSTALLATION OVERVIEW The installation instructions contained in this document are provided as a guide for proper and reliable installation.
More informationPERMIT APPLICATION REQUIREMENTS FOR RESIDENTIAL ROOF MOUNTED PHOTOVOLTAIC SYSTEMS
Butte County Department of Development Services PERMIT CENTER 7 County Center Drive, Oroville, CA 95965 Main Phone (530)538-7601 Permit Center Phone (530)538-6861 Fax (530)538-7785 FORM NO DBP-71 PERMIT
More informationCity of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov
City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov PHOTOVOLTAIC PERMITTING GUIDELINES The information provided in this document is general and is intended only as a
More informationGrounding & Bonding Why it is done And How to Install Properly
Grounding & Bonding Why it is done And How to Install Properly The technical information provided herein is to assist qualifi ed persons in planning and installing electric service to farms and residences.
More informationCENTRAL ELECTRIC COOPERATIVE, INC. NET METERING AGREEMENT
CENTRAL ELECTRIC COOPERATIVE, INC. NET METERING AGREEMENT This Agreement dated and effective this day of,, by and between Central Electric Cooperative, Inc. ( CEC ) and ( Customergenerator ) at (service
More informationDC disconnects for solar photovoltaic installations. Connecting the. power of the sun
DC disconnects for solar photovoltaic installations Connecting the power of the sun Solar energy is heating up Interest in renewable energy sources has never been greater, and the fastest growing of these
More informationApplication Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers
9229 Waterford Centre Dr. Bldg C, Suite 110 Austin, Tx 78758 Application Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers Current Version: 13 AC Modules are a new product
More informationWhat are the basic electrical safety issues and remedies in solar photovoltaic installations?
What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic
More information* DISCLAIMER: Contents. How to Use This Guide: COMMERCIAL INSTALL GUIDE 2
COMMERCIAL INSTALL GUIDE 2 Contents How to Use This Guide: The first section of this guide is designed to assist you with the installation of your DECK Monitoring hardware. The revenue grade meter and
More informationChapter 9. Bonding and Grounding
Chapter 9 Bonding and Grounding Objectives Describe why the cable should be bonded Describe bonding and grounding procedures Define Bonding and Grounding Explain Safety Benefits and intent of bonding and
More informationPS4-24 OWNERS MANUAL 24 VAC 90 WATT WALL MOUNTED CCTV POWER SUPPLY
PS4-24 OWNERS MANUAL 24 VAC 90 WATT WALL MOUNTED CCTV POWER SUPPLY 7320 Ashcroft, Suite 104 Houston, Texas 77081 p: 713-772-1404 f: 713-772-7360 e: info@juicegoose.com www.juicegoose.com 06-06 CONGRATULATIONS
More informationPV (photovoltaic) Basics There are generally two types of PV systems. The first and easiest (though the least flexible) is a grid tie system where
PV (photovoltaic) Basics There are generally two types of PV systems. The first and easiest (though the least flexible) is a grid tie system where the power generated by the solar panel (panels) runs an
More informationServices. Three Phase Service
Services Primary Service vs Secondary Service Overhead vs Underground Common Service Types Three Phase Wye Closed Open Delta Corner Grounded Center Tapped Open Single Phase Three Phase Service Wye Delta
More informationMASTER ELECTRICIAN CODE EXAMINATION EXAMINATION REFERENCE MATERIAL AND CONTENT OUTLINE. Answers to sample questions: CONTENT OUTLINE
Answers to sample questions: Question Answer Reference 1 4 Section 362.12(6) 2 2 Table 310-16; 310.15(B)(2)(a) 3 4 Table. 250-66 4 2 Table 430.250 & 430.52 5 2 American Electrician Handbook, Figure 7-159
More informationFLOW DIAGRAM OF FIVE DIFFERENT TYPES OF INVERTER SYSTEMS
FLOW DIAGRAM OF FIVE DIFFERENT TYPES OF INVERTER SYSTEMS FIGURE 1 Battery back up with no solar. This is the most basic system useful for occasional grid failures. The batteries are kept at full charge
More informationMAKING SOLAR ENERGY COST-EFFECTIVE TODAY IS A SNAP
MAKING SOLAR ENERGY COST-EFFECTIVE TODAY IS A SNAP Dr. James A. White, P.E. Senior Energy Services Engineer Chelan County Public Utility District P.O. Box 1231 Wenatchee, Washington 98807 jamesa@chelanpud.org
More informationSUFFOLK COUNTY CODE OF RULES GOVERNING RESTRICTED LICENSED ELECTRICIAN S
SUFFOLK COUNTY CODE OF RULES GOVERNING RESTRICTED LICENSED ELECTRICIAN S Including: 1. Heating, Ventilating and Air Conditioning (HVAC) 2. Irrigation Systems 3. Oil and Gas Burning Equipment 4. Signs and
More informationHOW TO CORRECTLY CONNECT DEEP CYCLE BATTERIES AND CHOOSE THE RIGHT CABLE SIZING
HOW TO CORRECTLY CONNECT DEEP CYCLE BATTERIES AND CHOOSE THE RIGHT CABLE SIZING There are several ways to wire multiple batteries to achieve the correct battery voltage or capacity for a particular DC
More informationThe U.S. Department of Labor projects that electrician careers will grow to 698,200 by 2022.
The U.S. Department of Labor projects that electrician careers will grow to 698,200 by 2022. Train now for affordable Electrician careers and get wired for success. Residential Electrician Diploma Program
More informationHP Designjet L65500 printer series Site preparation checklist (second edition)
HP Designjet L65500 printer series Site preparation checklist (second edition) Legal notices 2009 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without
More informationSPR-2800x SPR-3300x SPR-4000x SPR-5000x. Owner s Manual. SunPower Solar Inverter
SPR-2800x SPR-3300x SPR-4000x SPR-5000x Owner s Manual SunPower Solar Inverter SunPower Solar Inverter Owner s Manual Trademarks SunPower Solar Inverter is a trademark of SunPower Corporation. Other trademarks,
More informationREAD THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY!
READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! The main power to any existing system must be disconnected prior to the
More informationEnphase Microinverters and Ungrounded Renewable Energy Systems: Canadian Electrical Code Compliance
WHITE PAPER Enphase Microinverters and Ungrounded Renewable Energy Systems: Canadian Electrical Code Compliance Overview Enphase has developed a new microinverter family that includes the M250 and new
More informationCITY OF LOS ANGELES CALIFORNIA
BOARD OF BUILDING AND SAFETY COMMISSIONERS VAN AMBATIELOS PRESIDENT E. FELICIA BRANNON VICE-PRESIDENT JOSELYN GEAGA-ROSENTHAL GEORGE HOVAGUIMIAN JAVIER NUNEZ CITY OF LOS ANGELES CALIFORNIA ERIC GARCETTI
More informationCounty of Riverside Building and Safety Department
County of Riverside Building and Safety Department Mike Lara Director Photovoltaic Permitting Guidelines The information provided in this document is general and is intended only as a guide. Each project
More informationFIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851
FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
More informationPV System Disconnect PV System Discon-
PV System Disconnect PV System Discon- INSTALLATION & OPERATION MANUAL 97-600100-06-A02 Preface PV Powered PV Powered designs, manufactures, and markets the solar power industry s most reliable photovoltaic
More informationINFORMATION FOR METER SERVICE PROVIDERS (MSP) FOR ARIZONA CERTIFICATION
- 1 - FOR ARIZONA CERTIFICATION Meter Worker Qualification Requirements For Direct Access Metering in Arizona I. Introduction Three classes of meter worker qualifications are set forth as criteria for
More informationHM-W536 Install Guide
HM-W536 Install Guide 9/13/2013 IMPORTANT SAFETY INSTRUCTIONS Warning - When using electrical devices, basic safety precautions should be followed to reduce the risk of fire, electrical shock or injury.
More informationCarolina Power & Light Company 51 d/b/a Progress Energy Carolinas, Inc. SERVICE REGULATIONS
Carolina Power & Light Company 51 d/b/a Progress Energy Carolinas, Inc. 1. SERVICE AGREEMENT SERVICE REGULATIONS (d) (e) (f) Description: The Service Agreement (hereinafter sometimes termed "Agreement")
More informationHOW A DC UTILITY METER CAN TRANSFORM THE U.S. SOLAR INDUSTRY
HOW A DC UTILITY METER CAN TRANSFORM THE U.S. SOLAR INDUSTRY James A. White, P.E. Chelan County Public Utility District 327 N. Wenatchee Washington 98801 jim@applecapital.net ABSTRACT Moving the location
More informationLease Operations Guide
Lease Operations Guide Table of Contents Table of Contents... 2 GENERAL SAFETY INSTRUCTIONS... 3 HOW DOES MY SOLAR SYSTEM WORK?... 4 System Components... 4 Where does the power go?... 5 What happens if
More information12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting
12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.
More informationemobility WAGO Leading the Charge
emobility WAGO Leading the Charge Six Steps to a Full Battery WAGO supports every aspect of charging from: TO-PASS GPRS Modem, VPN Router, 761-520 Identification / Registration /Authorization RFID SMS
More informationAPPLICATION NOTE USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS. Abstract.
USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS Abstract This application note describes the necessary procedure to use a standard Pacific Power Source Model
More informationSolar Matters III Teacher Page
Solar Matters III Teacher Page Solar Powered System - 2 Student Objective Given a photovoltaic system will be able to name the component parts and describe their function in the PV system. will be able
More informationCHECKING AND TESTING ELECTRICAL INSTALLING WORK
CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical
More informationBattery Backup for Grid-Tied PV Systems
A presentation for solar industry professionals Presented by Doug Pratt, and SimpleRay Solar SMA Sunny Island System Large(!)Outback System But first, a moment of thanks for northern California growers
More informationSingle Phase Single Element Electronic Meters:
Single Phase Single Element Electronic Meters: September 2012 13 SEPTEMBER 2012 ISSUE 5 OPERATIONAL MANUAL Single Phase, Single Element Electronic Meters: PREPARED BY: METROLOGY SPECIALIST & LABORATORY
More informationSOLAR PV SYSTEMS PERMITTING PROCESS
Department of Consumer and Regulatory Affairs SOLAR PV SYSTEMS PERMITTING PROCESS How to Reach Us 1100 4 th Street, SW Washington, DC 20024 dcra@dc.gov Permit Center Hours Monday, Tuesday, Wednesday &
More informationSTREETLIGHT SYSTEM GROUNDING AND BONDING
Page: 1 of 8 STREETLIGHT SYSTEM GROUNDING AND BONDING 1. Scope This Construction Standard covers the grounding and bonding requirements for single phase streetlight systems served by the Looped Radial
More informationDucoterra Radiant Heating Panel Installation Manual
Ducoterra Radiant Heating Panel Installation Manual 1. Introduction Your new radiant heating panels are designed to heat living and working spaces rapidly and efficiently by radiant heating. Like the sun,
More informationCircuit Electrical Testing
Safe Isolation Procedure Circuit Electrical Testing Site Safety Management It is essential from the outset that effective management and control of the system, apparatus and equipment used on site is achieved
More informationSection III Schedule of Requirements TECHNICAL SPECIFICATIONS OF THE REQUIRED SYSTEMS
PART III TECHNICAL SPECIFICATIONS OF THE REQUIRED SYSTEMS I. GENERAL The objective of this specification is to describe a system which uses solar energy to produce electricity. For each site (lot) one
More informationFAQ s on Siemens Magmeters
FAQ s on Siemens Magmeters 1. The cables for the coils and electrodes for the magmeters look the same. Does it matter which cable is used for coils and which one is used for the electrodes? Both cables
More informationTECHNICAL SPECIFICATIONS
1. Standards BOS Item / System I ii iii TECHNICAL SPECIFICATIONS Applicable BIS /Equivalent IEC Standards / Applicable MNRE Specifications Standard Description Standard Number Crystalline Silicon Terrestrial
More informationRoy Allen, Technical Training, 17FEB2015 ABB Solar Days Residential Products, Design & Application Rapid Shutdown. ABB Feb 27, 2014 Slide 1
Roy Allen, Technical Training, 17FEB2015 ABB Solar Days Residential Products, Design & Application Rapid Shutdown Feb 27, 2014 Slide 1 ABB Single-Phase Products MICRO Inverter Single MPPT Dual MPPT MICRO-0.25-I
More information800 Communications Circuits
ARTICLE 800 Communications Circuits INTRODUCTION TO ARTICLE 800 COMMUNICATIONS CIRCUITS This article has its roots in telephone technology. Consequently, it addresses telephone and related systems that
More informationTERMS AND CONDITIONS
Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator
More informationSolar Inverter Sunny Boy 5000US, 6000US, 7000US
Solar Inverter Sunny Boy 5000US, 6000US, 7000US Installation Guide SB50US-70US-IUS090523 TBUS-SB50_60_70US Version 2.3 US Copyright 2008 SMA America, Inc. All rights reserved. No part of this document
More informationDefinition AC Power Distribution
COMMON AC POWER DISTRIBUTION CONFIGURATIONS The input voltage needed to power electronic equipment is provided by the manufacture in the product specifications. Matching this requirement to the facility
More informationHow To Power A Power Supply On A Powerline From A Power Source To A Power Box
Power Base AI Power Base AI Application Guide Table of Contents Product Overview Our Philosophy On Electrical... 4 System Overview... 5 Power Base AI Statement of Line.... 6 Power Base AI Components...
More informationErrata NFPA 70. Proposed 2014 Edition
Errata NFPA 70 National Electrical Code (Report on Proposals) Reference: 12-109 (Log #1618) Panel Meeting Action Proposed 2014 Edition The National Electrical Code Technical Correlating Committee notes
More informationYOUR SUNPOWER MONITORING SYSTEM GUIDE
YOUR SUNPOWER MONITORING SYSTEM GUIDE YOUR SUNPOWER MONITORING SYSTEM Congratulations on your new SunPower solar system with SunPower monitoring! SunPower s advanced monitoring solution allows you to easily
More informationFinancial Analysis of Solar Photovoltaic Power plant in India
Financial Analysis of Solar Photovoltaic Power plant in India M. Ganga Prasanna, S. Mahammed Sameer, G. Hemavathi Department of Management Studies MadanapalleInstitute of Technology& Science Post Box No:
More informationCOCHRANE TELECOM SERVICES CRTC 25350 TELEPHONE SYSTEM Page 1 Revision 2 Section 90 GENERAL TARIFF DEFINITIONS
TELEPHONE SYSTEM Page 1 ADJOINING EXCHANGES - Exchanges whose boundaries are common at any point, except where a boundary consists of a large natural barrier. BASE RATE AREA - The area served by an exchange
More informationNeuton Solar Power Diverter Quick Installation Guide
Neuton Solar Power Diverter Quick Installation Guide Product Description Important Note: The NSPD is designed to operate heating elements of 3kW maximum. The Neuton Solar Power Diverter (NSPD) is designed
More informationFIT TIER 2 Application
FIT TIER 2 Application Application Information The below information Auto-Fills from your registration information: Building Permit Application Date: Project Completion Date: Name: Address: City: State:
More informationAC Module Installation Guide Content
AC Module Installation Guide Content for ET-P660250AC May 9, 2012 2011-2012 ET Solar Group All Rights Reserved. No part of this publication may be reused in any manner nor in any form or format without