FIXING MAINTENANCE AT PORT WARATAH COAL SERVICES. Presented by Peter Morrison
|
|
- Bernard Butler
- 7 years ago
- Views:
Transcription
1 FIXING MAINTENANCE AT PORT WARATAH COAL SERVICES Presented by Peter Morrison
2 About PWCS Port Waratah Coal Services operates 2 coal loading terminals in the Port of Newcastle NSW Coal is delivered by train, stacked, blended and loaded onto ships for export Combined capacity of the terminals is 80M tonnes per year Coal sourced from about 20 mines in the Hunter Valley region Most coal goes to Asian customers PWCS is a 24 x 7 operation with capacity to allow scheduled machine outages for planned maintenance
3 Port of Newcastle NSW
4 10,000TPH Reclaimer
5 8,500 TPH Shiploader
6 Presentation Outline 1. A History of CMMS at PWCS. 2. Maximo 4i implementation 3. Maintenance Management
7 Maximo V3.03 Implemented No link to Financials or Stores / Purchasing software Maximo main uses: Initiate PMs. Record some corrective maintenance work. Record some breakdowns. Record some equipment specification data
8 ISSUES: Maximo V3.03 Implemented (cont.) 1000s of open Work Orders progress unknown. No detail of maintenance costs of machines. Inefficient Stores management. No system to use data to reduce breakdowns. <6 regular users across the company. Maximo source code modified thus PWCS were captives of the implementation contractor.
9 Other Issues High exposure to breakdown Operations Planning Dept. had no confidence in maintenance making gaining maintenance access to equipment difficult Poor maintenance morale due to decline in equipment condition and other factors Use of contractors restricted by union pressure Poor PM completion rates PMs not well integrated
10 Maintenance Business Constraints Coal delivery driven by mines Rail operations impacted by RIC outages and other rail traffic Ship arrivals and departures dependant on weather and tides Maintenance planning is critical to minimise delays to mine, rail and ship operations
11 Fixing Maintenance Mar 99 decision to investigate implementation of SAP. Aug 00. Scoping study completed for SAP implementation. SAP rejected as a solution for PWCS Nov 00. Study of other software options. (Must integrate to Oracle 11i). Maximo 4i selected. Mar 01 Maintenance organisation re-structured with defined accountabilities Apr 01 Re-implemented Maximo 3.03 as first step in the cultural change process. Apr 02 Maximo 4i implemented.
12 Maximo 3.03 Re-implementation Used re-implementation as a catalyst for cultural change Basic principle: No Work Order = No Work Defined organisation accountabilities Defined maintenance terminology eg breakdown, work type Introduced a Work Flow system Revamped planning and scheduling systems Basic performance measures introduced
13 Terminal Organisation Chart Terminal Manager Operations Supt. Maintenance Supt. Engineer Elec. Supv. Mech. Supv. Scheduler Mech. Tech. Shift BMs, PMs Shift BMs, PMs Planner Elec. Elec. Tech. Day-work PMs, CMs Day-work PMs, CMs Execution of weekly work schedule Repair of BMs Monitor machine performance Planner Mech. Planning & Scheduling work Management of data base BM Root Cause investigation & elimination. Monitor PM effectiveness Technical advice & research
14 Work Request raised WAPPR Basic Workflow Breakdown N Y BM Approved Requests WPLN Maintenance Planning PLN CM Work ready for scheduling. APPR Preventive Maintenance WSCH PM Maintenance Scheduling APPR Work execution INPRG Work Recording and Analysis COMP
15 Initiator Work Request Breakdown? Yes INPRG Maintenance Planner WAPPR No Review W/Os 'WAPPR' via Saved Query Pass vetting? Yes Preliminary Planning (5mins) No 'CAN' Originator PWCS Maintenance Workflow Maintenance Maintenance Scheduler Supt. Generate Maximo PMs. RESCH WSCH Circulate Preliminary Schedule for review. Weekly Planning Meeting. Maintenance Supervisor Set new target start date. No If PM, cancel? No 'CAN' Review BM' W/Os Tradespeople Start Maximo Workflow WAUTH Process Inbox OK to Schedule? Yes No Work Complete? Yes WPLN Weekly review of W/Os with Maintenance Supt. PLN WPLN Approved? No Print Supervisors Weekly Control Sheets and W/Os for next week. INPRG Manage work completion to weekly Schedule. Carry out activity per W/O. Detailed Planning APPR 'CAN' Originator CLOSE W/O Complete W/Os.
16 What Benefits From Re-implementing Maximo 3.03? Retraining meant more people using the system so computer skills increased. (Many older trades had few computer skills. Some still struggle.) Allowed support systems for work management to be established and trialled. More system use meant more informed ideas on what was needed for a replacement.
17 Maximo 4i Implemented April 1, 2002 Maintenance Stores Purchasing Contractor Management Seamless Interface General ledger Invoicing Other Accounting stuff MAXIMO 4.1 ORACLE 11i
18 Maximo 4i Implemented April 1, 2002 (Cont.) Maximo Location/ Equipment Structure completely revamped. PM program rewritten and rescheduled using RCM Turbo. Stores catalogue rewritten using Auslang (7,400 items). Equipment parts list items researched and entered (25,000+) Crystal Reports selected as the report writer package.
19 Maintenance Management
20 PM outage based on 8 week cycle. Basic PM Outage sequence assumptions and timing diagram Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 RE2 Slew RE4 Slew ST 1 SL 1 RR 2 RE 3 ST 3 SL 2 PA04 PA11 PA02 PA03 PA06 PA12 Wednesday Wednesday Wednesday Wednesday Wednesday Wednesday Wednesday Wednesday 03-Dec Dec Dec Dec Dec Jan Jan Jan-04 ST1 24W 2x4 CEP0177 SC1 Conveyor 16W 2x4 CEP0160 SL1 Ops Checks 24W 2x6 CEP0211 SB2A Bin Lev 24W 2x2 CEP0048 RC10 Convey 24W (1) 2x5 CEP0113 RC11 Convey 24W (1) 2x5 CEP0117 SC2A Convey 16W (1) 2x4 CEP0163 ST3 24W (1) 2x4 CEP0184 SC8 Convey 16W (1) 2x4 CEP0176 SL2 Ops Checks 24W 2x6 CEP0212 OC5 Conveyor 16W 2x4 CEP0010 PWCS forward maintenance plan published 4 weeks in advance to mines and shippers OC4 Conveyor 16W (1) 2x4 CEP0008 WC3 Weigher 24W (1) 2x2 CEP0197 Road F1-8 24W (1) 2x4 CEP0093 Road F W (1) 2x10 CEP0097 RC10 Weigher 24W (1) 2x2 CEP0112 OC2 Conveyor 16W 2x4 CEP0006 WC4 Weigher 24W (1) 2x2 CEP0199 SB2B Bin Lev 24W 2x2 CEP0094 RC10 Sampler 24W 2x4 CEP0015 ST1 Lube 8W 2x4 CML0023 SL1 Lube 8W 2x8 CML0001 PA02 Lube 24W 2x6 CML0008 RE3 Lube 8W 2x6 CML0015 ST3 Lube 8W 2x4 CML0025 SL2 Lube 8W 2x8 CML0002 ST1 Belt Cleaner 24W 2x4 CMP0182 SL1 Mech Part 2 24W 3x8 CMP0264 TC9 Convey 24W 2x3 CMP0044 RE3 Mech 24W 3x10 CMP0140 TC7 Convey 24W 2x3 CMP0042 SL2 Mech Part 1 24W 3x8 CMP0017 SL1 Boom Hoist Latch 24W 2x2 CMP1015 DS Hopper Structural Insp 24W 2x10 CMP0067 TC8 Convey 24W 2x3 CMP0043 SL2 Boom Hoist Latch 24W 2x2 CMP1016
21
22 Basic Work Order Management Planner Schedules work by date Supervisors review scheduled work 2 weeks in advance Terminal manager signs off on coming week outages Supervisors use check list to report work completion at weeks end Operations sign over machines for outage - maintenance sign back Uncompleted work can only be rescheduled or cancelled cannot be forgotten
23 Breakdown Elimination Emphasis on scheduled completion of PMs Breakdown data reviewed weekly by Maintenance Team. Repetitive BMs identified for follow-up Top 10 BMs by frequency and severity measured and reviewed monthly with General manager Unresolved repetitive breakdowns investigated for elimination PM system continually updated as result of BM investigation
24 The Results From Fixing Maintenance Work Order progress can be followed using the W/O Status Machine costs are available via Crystal reports from Oracle. Individual Work Order costs also in Maximo Materials are reserved in the Warehouse for particular jobs Breakdown management system in place with declining BM frequency and severity Users include all trades, Contractors, Engineers, Stores, Purchasing.
25 The Results From Fixing Maintenance (cont) Improved credibility with Operations Planning means more outage access Vastly improved maintenance morale Improved contractor payment system reduced PWCS workload and speeded up payments Ship Loading records set No longer captive to the CMMS implementation contractor
26 Lessons Learnt A CMMS needs support from General Manager level A CMMS provides the tools to focus maintenance resources where they can add the most value Stick to Out of the Box software The cultural change process is critical A disciplined work management system is essential
Computer Maintenance Management Systems CIWG Report - Meeting 27 June 2013
Computer Maintenance Management Systems CIWG Report - Meeting 27 June 2013 Computer Maintenance Management Systems CIWG Report Meeting hosted by This meeting was to share how organisations are trying to
More informationRail Network Configuration Management
Division / Business Unit: Function: Document Type: Enterprise Services Engineering Procedure Rail Network Configuration Management Applicability ARTC Network Wide SMS Publication Requirement Internal /
More informationHay Point Coal Terminal Queensland, Australia
Hay Point Coal Terminal Queensland, Australia Overview of Operations 1 BMA Coal Logistics Chain Export Terminals BMA owned and operated Shipping Tonnes FY02 Hay Point Services 30.6mt Common User Facilities
More informationMAXIMO 7 TRAINING GUIDE PURCHASING & RECEIVING FLORIDA INTERNATIONAL UNIVERSITY. P 202.262.2500 3451 NE 1 st Ave M1008 Miami, FL 33137
MAXIMO 7 TRAINING GUIDE PURCHASING & RECEIVING FLORIDA INTERNATIONAL UNIVERSITY P 202.262.2500 3451 NE 1 st Ave M1008 Miami, FL 33137 Table of Contents I CHAPTER 1 THE PURCHASING MODULES...5 1.1 Objectives...
More informationIBM Maximo Asset Management IBM Tivoli Asset Management for IT IBM Tivoli Service Request Manager. Version 7.1. Workflow Implementation Guide
IBM Maximo Asset Management IBM Tivoli Asset Management for IT IBM Tivoli Service Request Manager Version 7.1 Workflow Implementation Guide Note Before using this information and the product it supports,
More informationAshley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
More informationPerform Work Order Scheduling Process Improvements
Key Work Process(3.1): Perform Work Order Scheduling Process Owner: Perform Work Order Scheduling Process Improvements Work System Owner Ed Curry Work System Enabling Leader Dane Theodore, Director Priority
More informationAnalysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
More informationAT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More informationMAXIMO Project Manager User s Guide
MAXIMO Project Manager User s Guide Release 5.2 November 2003 This document and its publication do not constitute or create a contract. MRO Software, Inc. makes no warranties, express or implied, as to
More informationCase 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
More informationManaging Open Source Code Best Practices
Managing Open Source Code Best Practices September 24, 2008 Agenda Welcome and Introduction Eran Strod Open Source Best Practices Hal Hearst Questions & Answers Next Steps About Black Duck Software Accelerate
More informationResource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager
Resource Management Spreadsheet Capabilities Stuart Dixon Resource Manager Purpose Single view of resource data Shows rolling demand vs supply for 14 months, 2 months back, current month, and 11 forward
More informationPenn State University (PSU)
Penn State University (PSU) FAM Inventory Management Training Manual Prepared By Revision History Revision Date: March 18, 2014 Revision Number: 1 Revision # Date Collaborator Description 1.0 March 18,
More information7 Characteristics of High Performing Firms. Smartsoftware Seminar
7 Characteristics of High Performing Firms Smartsoftware Seminar Key Characteristics 1. Rock Solid Reputation 2. Determined Leadership 3. Enlightened Management 4. Well Managed Projects 5. Innovative Culture
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More information1. Introduction to the Automated Accounts Payable Development... 3. 2. Process Flows of Purchase Orders, Goods Receipts and Invoice Queries...
Contents 1. Introduction to the Automated Accounts Payable Development... 3 2. Process Flows of Purchase Orders, Goods Receipts and Invoice Queries... 4 2.1 Ideal MM Process... 4 2.2 Missing GRN process...
More informationwww.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in manufacturing
www.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in manufacturing Results from PwC s Global Data & Analytics Survey 2014 manufacturing Raw material supply
More informationCost Management. How Much Will This Project Cost?
Cost Management How Much Will This Project Cost? Moderator Janelle Abaoag Project Insight Marketing, Public Relations Janelle.Abaoag@projectinsight.com www.projectinsight.net All participants will be on
More informationHow to Configure and Use MRP
SAP Business One How-To Guide PUBLIC How to Configure and Use MRP Applicable Release: SAP Business One 8.8 All Countries English October 2009 Table of Contents Purpose... 3 The MRP Process in SAP Business
More informationMaximo 7 Training Guide. Service Provider. 3451 NE 1 st Ave M1008 Miami, FL 33137
Maximo 7 Training Guide Service Provider 3451 NE 1 st Ave M1008 Miami, FL 33137 TABLE OF CONTENTS I CHAPTER 1 SERVICE PROVIDER OVERVIEW... 3 1.1 Introduction to the Maximo Service Provider...3 1.2 Maximo
More informationTo provide a procedure and associated guidelines to facilitate the management of project dependencies.
Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,
More informationIMPLEMENTATION OF SAP STUDENT MANAGEMENT SYSTEM (SMS) AT UNIVERSITI TEKNOLOGI PETRONAS MALAYSIA
IMPLEMENTATION OF SAP STUDENT MANAGEMENT SYSTEM (SMS) AT UNIVERSITI TEKNOLOGI PETRONAS MALAYSIA 11 April 2001 Presenters :: 1. 1. Zulkarnan Abdul 2. 2. Kartini Sahlan 3. 3. Azlan Zahuri Agenda Objectives
More information2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc
July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
More informationFMMUG - 2016. Janet Spencer and Galen Winchip April 2016
FMMUG - 2016 Janet Spencer and Galen Winchip April 2016 Key Accomplishments Two Universities, 50+ combined years: Three CMMS systems Implemented two CMMS systems GL interfaces Dimensional data warehouses
More informationProject Management Planning
Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource
More informationRailroad Service Measurement
June 17, 2004 Railroad Service Measurement Prepared for: The Sandhouse Gang Northwestern University Transportation Center C O N F I D E N T I A L The AAR invited Mercer to evaluate the current state of
More informationJAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
More informationwww.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in healthcare
www.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in healthcare Results from PwC s Global Data & Analytics Survey 2014 healthcare Patient data. Precision
More information4. Maintenance and Materials Management
The Superintendent of Operations has various oversight responsibilities that impair his ability to effectively manage maintenance activities within the Project Operations Section. This impairment manifests
More informationENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA BACKGROUND INFORMATION DOCUMENT 1 BACKGROUND Transnet Limited s (Transnet) existing
More informationGet Britain Working Measures Official Statistics
Get Britain Working Measures Official Statistics Publication date: 9:30am Wednesday 21 August 2013 Contents Summary... 3 Introduction... 3 Get Britain Working Measures Policy Description... 3 Technical
More informationFinancial Management TRANSACTION CONTROL AND APPROVAL
Financial Management In today s complex, global, and regulated environment, organizations face numerous challenges in trying to meet deadlines, comply with local regulations and multiple reporting requirements,
More informationEXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
More informationWHITEHAVEN COAL LIMITED QUARTERLY REPORT TO 31 DECEMBER 2009 (Q2 FY 2010)
Highlights WHITEHAVEN COAL LIMITED WHITEHAVEN COAL LIMITED ABN 68 124 425 396 Level 9 1 York Street Sydney, NSW 2000 PO Box R1113 Royal Exchange NSW 1225 Ph: 02 8507 9700 Fax: 02 8507 9701 QUARTERLY REPORT
More informationCASE STUDY: E-PHARMACY AT CHELSEA AND WESTMINSTER HOSPITAL, UK
e-business W@tch European Commission, DG Enterprise & Industry E-mail: entr-innov-ict-ebiz@ec.europa.eu, info@ebusiness-watch.org This document is based on sector studies, special reports or other publications
More informationU.S. Department of Energy-Funded Performance Validation of Fuel Cell Material Handling Equipment
U.S. Department of Energy-Funded Performance Validation of Fuel Cell Material Handling Equipment UK Hydrogen and Fuel Cell Association Webinar Jennifer Kurtz, Sam Sprik, Todd Ramsden, Genevieve Saur, Chris
More informationCALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS
CALCULATION DIFFERENCES WHEN IMPORTING FROM MICROSOFT PROJECT 2003-2010 INTO ORACLE PRIMAVERA P6 VERSION 7 BY PAUL E HARRIS OF EASTWOOD HARRIS TABLE OF CONTENTS 1 INTRODUCTION 3 2 AIM 3 3 SUMMARY 3 4 LEVELS
More informationInsurance and Banking Subcommittee
Insurance and Banking Subcommittee Citizens Depopulation Update September 16, 2015 Christine Ashburn VP Communications, Legislative and External Affairs 2 3 Depopulation Customer Communications 1. 40 days
More informationEmployers Compliance with the Health Insurance Act Annual Report 2015
Employers Compliance with the Health Insurance Act Annual Report 2015 ea Health Council Health Council: Employers Compliance with the Health Insurance Act 1970 Annual Report 2015 Contact us: If you would
More informationBusiness Name. Table of Contents. Entrepreneur(s) name: Course: LCA VPG Enterprise 1. Date: 1 st May 2009. Business Plan / Enterprise Task Report
Business Name Company Slogan/Statement Entrepreneur(s) name: Course: LCA VPG Enterprise 1 Business Plan / Enterprise Task Report Date: 1 st May 2009 Table of Contents Page Number 3. Personal Profile 4.
More informationUsing the Safety Perception Survey to Assess Your Organization s Safety Culture
Using the Safety Perception Survey to Assess Your Organization s Safety Culture Robert S. Krzywicki Michael B. Keesey April 21, 2011 1 Agenda Safety Contact Grounding - Definition of Culture - 12 Elements
More informationThe Thinking Approach LEAN CONCEPTS. 2012-2013, IL Holdings, LLC All rights reserved 1
The Thinking Approach LEAN CONCEPTS All rights reserved 1 Basic Thinking to Manage the Journey MANAGEMENT TACTICS OF A LEAN TRANSFORMATION All rights reserved 2 LEAN MANAGEMENT Two key questions What is
More informationThe power to transform your business
The power to transform your business Optimus 2020 continues to be the number one choice for litho and packaging printers worldwide. What is the secret of our longevity? Constant research and forward thinking
More informationMarket Risk Management
Market Risk Management Hamish Treleaven, Executive General Manager, Market Risk Management 17 November 2010 The quantum of Market Risk at CBA Current Economic Capital attribution Current Market Risk Economic
More informationAccident & Emergency Department Clinical Quality Indicators
Overview This dashboard presents our performance in the new A&E clinical quality indicators. These 8 indicators will allow you to see the quality of care being delivered by our A&E department, and reflect
More informationImplementing Carbon Reduction Without Impacting Working Capital. Presented by Dylan Crompton
Implementing Carbon Reduction Without Impacting Working Capital Presented by Dylan Crompton Evolution of a Carbon Strategy Proactive organisations are on a journey to reduce carbon emissions. Marginal
More informationItems/Tasks required to be completed for Financial Services Division (FSD)
JAN 0 Events/Deadline New Years Day Holiday Public Holiday Finance One unavailable due to end of year roll over. Finance One unavailable due to end of year roll over. 7 0 FBT gift & Vehicle usage returns
More informationCENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR
JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf
More informationSUB: PLMH YEAR: IV, BRANCH: MECHANICAL ENGINEERING
SUB: PLMH YEAR: IV, BRANCH: MECHANICAL ENGINEERING Sl. UNIT-5 1 Explain the importance of material handling 2 Explain the relationship of material handling to plant layout 3 Explain importance of plant
More informationTraining Pack. Kaizen PDCA ( Plan / Do / Check / Act )
Training Pack Kaizen PDCA ( Plan / Do / Check / Act ) Introductions Name Department Current knowledge of Plan Do Check Act Aims & Objectives Target Audience : All! Purpose of Module : To train the delegates
More informationThe principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
More informationoutput: communications management plan
Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project
More informationearned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
More information20 Ways to Save Money Implementing Contractor Cost Tracking Software
20 Ways to Save Money Implementing Contractor Cost Tracking Software Introduction: Companies can save a considerable amount of time and money by implementing Contractor Cost Tracking Software when utilizing
More informationRochester Institute of Technology. Oracle Training: Performing Inquiries and Requesting Reports in the Oracle Applications
Rochester Institute of Technology Oracle Training: Performing Inquiries and Requesting Reports in the Oracle Applications Table of Contents Introduction Lesson 1: Lesson 2: Lesson 3: Lesson 4: Lesson 5:
More informationQ-Accounts Software Limited. Key Software Function Version 1.2
Q-Accounts Software Limited 2015 Key Software Function Table of Contents Background... 3 For Accountants... 3 Managed and Pre-posted Accruals... 3 Tracked Expenditure based Income... 5 Report Mailing Lists...
More informationRelease 2.0 May 2006. Maximo Calibration Release Notes
Release 2.0 May 2006 Maximo Calibration Release Notes This document and its publication do not constitute or create a contract. MRO Software, Inc. makes no warranties, express or implied, as to the accuracy
More informationMAXIMO 7 TRAINING GUIDE INVENTORY MANAGEMENT FLORIDA INTERNATIONAL UNIVERSITY. 3451 NE 1 st Ave M1008 Miami, FL 33137
MAXIMO 7 TRAINING GUIDE INVENTORY MANAGEMENT FLORIDA INTERNATIONAL UNIVERSITY 3451 NE 1 st Ave M1008 Miami, FL 33137 TABLE OF CONTENTS TABLE OF CONTENTS...2 I CHAPTER 1 INVENTORY MANAGEMENT...3 1 OBJECTIVES...
More informationActing today v/s tackling a larger problem tomorrow
White Paper Acting today v/s tackling a larger problem tomorrow Data Quality in Banks WE PUT THE BANKING INTO BUSINESS INTELLIGENCE www.icreate.in Acting today v/s tackling a larger problem tomorrow Data
More informationSupply Chain Trends in Intermodal
Supply Chain Trends in Intermodal Ken Miller VP Operations 1 SERVICE REVIEW: MARKET SHARE Market overview (segment specific) Market size: $12 Billion Capacity: 205,000 53 foot Containers Industry outlook:
More informationMaximo Scheduler Update
Anthony Honaker, Maximo Product Strategy Maximo Scheduler Update 2012 IBM Corporation 2009 IBM Corporation Please note: IBM s statements regarding its plans, directions, and intent are subject to change
More informationBreen Elementary School
Breen Elementary School Day: Monday Time: 1:40 pm to 3:10 pm (90 minutes) Session A Sept 21, Sept28, Oct 5, Oct 19, Oct 26, Nov 2 No class on Oct 12 Session B Nov 30, Dec 7, Dec 14, Jan 4, Jan 11, Jan
More informationITD Help Desk Traffic Report May 2002
ITD Help Desk Traffic Report May 2002 Call volumes and resolution times within the CONSULT Remedy workgroup June 10, 2002 Christopher King Help Desk Manager NC State University chris_king@ncsu.edu Information
More informationManagement Plan. Contractor Management
Management Plan Contractor Management Doc ID No. Version No. Owner Next Review Date Management Plan Contractor Management Risk Statement: High This document will be reviewed on a one yearly basis, unless
More informationIBM Tivoli Software. Maximo Business Intelligence Work Packs. Workorder, Asset Failure, Asset and Inventory Management
IBM Tivoli Software Maximo Asset Management Version 7.5 Releases Maximo Business Intelligence Work Packs Workorder, Asset Failure, Asset and Inventory Management Revision 4 Pam Denny Maximo Report Designer/Architect
More informationWorkers Compensation Insurance Proposal for the. New South Wales Coal Industry
Workers Compensation Insurance Proposal for the New South Wales Coal Industry Coal Mines Insurance Pty Limited ACN 000 011 727 ABN 70 000 011 727 as the workers compensation company approved under section
More informationAccounting for a Merchandising Business
Chapter 11 Accounting for a Merchandising Business ANSWERS TO SECTION 11.1 REVIEW QUESTIONS (text p. 428) The Merchandising Business 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 1. 2. 3. 4. 14. 15. Copyright
More informationIntegrated Financial Plan FY2012
Integrated Financial FY Delivering The new reality The fiscal year Integrated Financial (IFP) has an Operating with a projected Operating Loss of $3.0 billion, versus a loss of $2.2 billion in, despite
More informationfor Sage 100 ERP Work Order Overview Document
for Sage 100 ERP Work Order Document 2012 Sage Software, Inc. All rights reserved. Sage Software, Sage Software logos, and the Sage Software product and service names mentioned herein are registered trademarks
More informationSupplier Rating System
Supplier Rating System Supplier Manual Presented by Admiral Tool & Manufacturing Purchasing and Quality WI-PU-06-002 Rev. Lev. 003 Rev. Date 02/06/2003 1 Table of Contents Introduction 3 Scoring Criteria
More informationOptimising Your EAMS through Business Processes. Wyhan Jooste wyhanj@pragmaproducts.com
Optimising Your EAMS through Business Processes Wyhan Jooste wyhanj@pragmaproducts.com Presentation Overview Definitions and terminology What is a successful EAMS? Why EAMS implementations fail The benefit
More informationProject Cost Overrun Review Process Improvement
Project Cost Overrun Review Process Improvement xxx, IUPUI TECH 581 Quality and Productivity in Industry and Technology Abstract: This project used Lean Six Sigma tools to review the process performed
More informationGuest Presentation Test Environment Management
Guest Presentation Test Environment Management The Balance of Control & Agility By: Steven Iannuzzelli 1 Copyright ANZTB Agenda Our Services and Scope Why Test Environment Management CBA Context Environment
More informationCoordination and air quality monitoring during emergencies. Colin Powlesland Environment Agency
Coordination and air quality monitoring during emergencies Colin Powlesland Environment Agency Contents h Introduction h What do we want to achieve? h Implementation programme h Incident timeline h Proposed
More informationDepartures to the south from Runways 16L and 16R.
Mode 5 Method of operation Departures to the south from Runways 16L and 16R. Arrivals from the east on Runway 25. Arrivals from the north for those aircraft requiring to use the long runway. This runway
More informationBusiness Process Management Technology: Opportunities for Improved Efficiency and Reduced Costs in the Mining Industry
Business Process Management Technology: Opportunities for Improved Efficiency and Reduced Costs in the Mining Industry A Paper Prepared for Presentation to the Industry Summit on Mining Performance: Business
More informationDivision of Highways Staffing Report
Division of Highways Staffing Report to NCGA Joint Legislative Transportation Oversight Committee & Fiscal Research Staff Mike Holder, PE, Chief Engineer December 5, 2014 Staffing Study for Preconstruction
More informationQAD Enterprise Asset Management BI Metrics Demonstration Guide. May 2015 BI 3.11
QAD Enterprise Asset Management BI Metrics Demonstration Guide May 2015 BI 3.11 Overview This demonstration focuses on one aspect of QAD Enterprise Asset Management Business Intelligence Metrics and shows
More informationEnterprise Architecture 101. (Includes numerous samples/ templates produced using TOGAF methodology) Shail Sood
Enterprise Architecture 101 (Includes numerous samples/ templates produced using TOGAF methodology) Enterprise Architecture Key Question What is Enterprise Architecture? Why Enterprise Architecture? What
More informationTime Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.
Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation
More information763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
More informationEnhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
More informationAsset Suite 9 Training Course Catalogue
Asset Suite 9 Training Course Catalogue CONTENTS Please Note... 3 Asset Suite Orientation Training... 4 Asset Suite Train-The-Trainer (T3) / Power User Training... 5 Foundation Architecture End User Training...
More informationAsset registers, financial reporting, maintenance. Planned, project & corrective maintenance management. Service provider & staff OH&S certification
Your single, integrated facilities management software solution - seamless & simple! Future IT has developed kwiklook to be an essential tool that addresses risk management, public liability and occupational
More informationLean Production Performance Metrics Exercises
Lean Production Performance Metrics Exercises Course in Operations Management Prof. Sergio Cavalieri Adapted from the material provided by Mr. Giovanni Ferrari and Mr. Luca Manzoni Università degli Studi
More informationAtkins China Asset Management. Alan Wilson. Strategy Development
Atkins China Asset Management Alan Wilson Strategy Development " # " $%& & & ' ( ) * ) + + $,- & &. / 0, * ) + + 12 3 ) 4 ' 5 * 3 6 4 3 7 8 7 7 8 8 8 8 7 0 :3 ; / * 6 9 ) 8 ' * 6 0* 6 3 /9 < 9 = 3 10*
More informationCost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
More informationwww.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in retail
www.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in retail Results from PwC s Global Data & Analytics Survey 2014 retail Showrooming and mobile search.
More informationBay Park Sewage Treatment Plant Super Storm Sandy Recovery
County of Nassau Department of Public Works Bay Park Sewage Treatment Plant Super Storm Sandy Recovery Edward P. Mangano County Executive Shila Shah-Gavnoudias, P.E. Commissioner of Public Works Bay Park
More informationBusiness Technology Advisory Council May 2011
Business Technology Advisory Council May 2011 Leo de Sousa, Manager, Application Services and Enterprise Architecture British Columbia Institute of Technology Agenda BTAC Summary Statistics Compliance
More informationINCOME TAX : INCOME TAX ACT, 1962 (the Act) : SECTION 10(1)(o)(ii) : EXEMPTION FROM INCOME TAX: FOREIGN EMPLOYMENT INCOME
SOUTH AFRICAN REVENUE SERVICE INCOME TAX INTERPRETATION NOTE NO. 16 DATE: 27 March 2003 INCOME TAX ACT SECTION SUBJECT : INCOME TAX ACT, 1962 (the Act) : SECTION 10(1)(o)(ii) : EXEMPTION FROM INCOME TAX:
More informationCIMS: Centralized Inventory and Maintenance Software
CIMS: Centralized Inventory and Maintenance Software February 2014 DragonPoint, Inc. 877-542-0657 1 Contents Contents... 1 Executive Overview... 2 Consistency Contributes to Ease of Use... 3 Work Orders...
More informationFinancial Operating Procedure: Budget Monitoring
Financial Operating Procedure: Budget Monitoring Original Created: Jan 2010 Last Updated: Jan 2010 1 Index 1 Scope of Procedure...3 2 Aim of Procedure...3 3 Roles & Responsibilities...3 Appendix A Timetable...7
More informationNothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time.
T47400A, page 1 Nothing in this job description restricts management's right to assign or reassign duties and responsibilities to this job at any time. DUTIES Serves as the planner/scheduler for the Utilities
More informationFacilities Maintenance Contract
Re-tendering the Facilities Maintenance Contract Asset Management Services UTAS Property Portfolio Total Asset Management Reviewing options and preferences Contract structure & deliverables Tendering process
More informationTopic 1 Introduction. to the Fundamentals of Project Management INTRODUCTION LEARNING OUTCOMES
Topic 1 Introduction to the Fundamentals of Project Management LEARNING OUTCOMES By the end of this topic, you should be able to: 1. Describe the nature of projects; 2. Identify the project life cycle;
More informationComplaints Annual Report 2014-15. Author: Sarah Housham, Senior Complaints and PALS Officer
Complaints Annual Report 2014-15 Author: Sarah Housham, Senior Complaints and PALS Officer 1 Rnoh Complaints Annual Report 2014 / 2015 Complaints Handling & the Principles of Remedy Introduction Complaints
More informationRelease Date Updated by Reason for change. 1.0 June 6, 2014 Shaun Hern Initial Distribution
CustomerName AddressLine1 AddressLine1 City STATE ZIPCODE SYSPRO 7 Upgrade Version 1.0 Document Revision History Release Date Updated by Reason for change 1.0 June 6, 2014 Shaun Hern Initial Distribution
More information