Project Cost Overrun Review Process Improvement

Size: px
Start display at page:

Download "Project Cost Overrun Review Process Improvement"

Transcription

1 Project Cost Overrun Review Process Improvement xxx, IUPUI TECH 581 Quality and Productivity in Industry and Technology Abstract: This project used Lean Six Sigma tools to review the process performed by the Engineering Department to review, document and submit approvals for project cost overruns. Engineering spends approximately 800 hours annually performing these reviews, costing the Company over $68,000 a year. This work activity is not standardized across engineering and no process documentation or tools exist to ensure Company objectives are met to complete these reviews within 30 days. In this study key stakeholders and customers involved in the process were interviewed, process observations were performed and measurement data was collected and analyzed to determine where improvements could be made. Baseline measurements indicated high variability in process times ranging from 5 minutes to 120 minutes and analysis of the data collected found the Key Process Input Variable was the "type" of project being reviewed. The team developed process improvement documentation which included process flowcharts, job aids, and spreadsheet tools and kicked off a Pilot of the new process. During the Pilot the process documentation and tools will be refined and sustained improvement measured and documented prior to a full implementation. The initial results from the Pilot indicate reduced variability in process times and lower average process times are possible. Upon full implementation measurement data will be collected quarterly to ensure process improvement times are sustained. The key to implementing process improvements is have a standard process in place upon which to base those improvements. Having established this documented process, future mechanization efforts or process enhancements will have a basis for measuring improvements. Second, having well defined performance measures in place is key to understanding the cost and time impacts of process changes. Implementing the key measures through this project will position the company for making further improvements, possibly through mechanization efforts, by providing a basis for cost benefit studies. 1

2 Background: Each year Engineering creates and obtains approval for over 5,000 jobs. Approximately 20% of these jobs require supplemental approvals due to revisions, cost overruns and unforeseen field conditions. This process consumes approximately 800 engineering hours a year. The process to complete these reviews is not standardized and no standard process documentation exists within engineering to review, document and process these approvals. In previous years, this process received little attention but in 2009 managers were given an objective to complete their reviews and submit all supplemental approvals within 30 days. This objective has highlighted the need to improve the process to ensure these timeframes can consistently be met by the Engineering organization. Experimental Method: The Lean Six Sigma Methodology: The Six Sigma DMAIC Methodology was utilized for this investigation and is summarized below: Define a problem, set a goal striving for customer satisfaction and aligning business objectives. Measure the process by collecting relevant data to realize issues and for future comparison. Analyze to verify connection and cause of problems. Improve or the process by reducing variation, based upon the analysis. Control the process and maintain the reduction of variation. Define Phase: A project charter was completed by the project team that defined the business case, problem statement and goal statement for the Project Cost Overrun Review Process Improvement project. The project charter is shown in figure 1. 2

3 Lean Six Sigma Project Charter Project Name: Reduce Engineering Time to Prepare Cost Overrun Approvals Date Chartered Start Date: Target Completion Date: Project Team Phone/ Title Engineering Manager Process Owner Phone Title Engineering Manager Problem Statement The purpose of the project is to reduce the Engineering time required to review, document and submit supplemental approvals for job cost overruns. This process consumes approximately 800 Engineering hours annually in Indiana. Goal Statement Reduce the Engineering time required to prepare job cost overrun documentation by 25% (to 30 minutes or less for each submittal), saving approximately 200 engineering hours per year. Project Scope This process begins when a cost overrun on a project occurs which requires engineering to review the reasons for the job cost overrun and ends when the supplemental job approval is submitted and approved by management. Cost overruns are defined by Operating Procedure #46 which requires supplemental approval for jobs that exceed their current approved amount by >10%. In order to minimize disruption in the Engineering organization, only one Indiana Design Center will have engineers interviewed, observed, and process improvements implemented during the course of this study Deliverables 1. Documented process for efficiently reviewing, documenting and approving job cost overruns. 2. Consistent engineering time savings of 25% per job over current methods when preparing job supplemental approvals. Figure 1 Project Charter A Voice of the Customer (VOC) analysis was performed by interviewing engineers performing the process today along with Planning, Finance and other managers not on the project team and asking four key questions: 1. What do you like about the existing processes related to the OP46 process? 3

4 2. What are the weaknesses within these processes? 3. What are the opportunities for improvement within these processes? 4. What could potentially threaten the success of this project team? VOC analysis indicated that while a strength of the current process is that the system does provide proactive notification to the engineers that a review needs to be performed, the current process was not well understood by the engineers and they had no documentation developed specifically for these reviews. As a result, no single process was being used to complete these reviews. Instead, each engineer pulled different reports and looked at different information as they worked the process according to individual preferences. The VOC analysis also revealed there were opportunities to improve the process through proactive documentation, improved reports and more feedback from Construction on cost overruns. The analysis also found that the process was threatened by poor understanding of the financial systems and what steps needed to be performed to correctly complete the review requirements. Measure Phase: Baseline measurement of the following Key Process Input Variables (KPIVs) was performed: Number of Op46 notifications received each week by each engineer Number of Op46 notifications received each week that require a handoff to Planning Size of the project with an Op46 notification (dollars) Size of the project overrun with an Op46 notification (dollars) Project Type The overall process time was gathered using two methods to track the Key Process Output Variables: 1. Engineers self reported their total process time along with the error notification and approval submission dates on a data collection form placed in a shared data area; 2. Direct observations of engineers performing the process were performed to gather the same information in additional to other process steps that self reporting may have missed such as the number of systems accessed and reports pulled during the review. 4

5 This data was gathered over a period of 45 days and included 50 self reported observations and 15 direct observations of the process. A process map was created that documented how the engineers generally performed the process today as shown in Figure 2. However, since no standard process existed, each engineer performed the process slightly different from the one shown. The largest variation was related to the specific reports pulled during the review and how the information on those reports was used. Start Process: Engineer receives op46 error notification from CMC report Access CFAS to determine the size and scope of the error Engineer pulls Jam status & estimate reports and compares the forecast hours and costs to actuals Engineer reviews job file for revisions, change orders, or other items that increased cost after initial approval If Necessary, Engineer talks to Construction, the Field Coordinator, or accesses other systems concerning the cost overrun Planning project? Yes Provide Planning with documentation on their findings related to the project cost overrun Follow up to ensure Planning submits approval within 30 day objective. No Engineer documents the reason for cost overrun in CFAS Project Description section Update CFAS budget lines to meet or exceed current costs (if project not complete) Prepare and submit MIC addendum to supervisor End Process Figure 2 Process Map Results and Discussion: Analyze Phase: Multiple direct process observation studies were conducted by team members using process observation worksheets and spaghetti diagrams to quantitatively assess the impact of the primary operational barriers. Examples of process observation worksheets, spaghetti diagrams and other data collection and analysis tools for the Project Cost Overrun Review Process Improvement process are shown in the following figures: 5

6 Date Notification occurred Engineer ID Project Number Time Spent Preparing Supplemental Submittal Planning Project? (YES/NO) If Planning Project, Date sent to Planning Date Supplemental Submittal sent Figure 3 Observation Worksheet #1 (Engineers self-reported this data) Date Cost overrun notification received Date Supplemental Submittal sent Engineer Original cost of project Amount of cost overrun Project Type Job # Step Description Clock Time Task Time (min) Wait Time (min) # System Loads or Logins # Rpts or System Inquries Number of Interuptions Interuption time Observations 1 Review OP46 error report 2 Review Project in CFAS 3 Pull & Review Jam reports 4 Review paper job files 5 Calls to Construction, FC, etc? 6 Other systems? 7 Planning Project? (Y/N) 8 to Planning (process stops) 9 IF Not Planning Project, THEN 10 Document overrun reason in CFAS 11 Update CFAS budget lines 12 Prepare MIC addendum & Submit Total Time Figure 4 Observation Worksheet #2 (Used in direct observations by Process Team) 6

7 Figure 5 Spaghetti Diagrams The primary operational barrier to improving process times and ensuing that cycle time objectives were consistently met was the KPIV of Project Type. Stratification of the data by Project type found that some types of projects consistently required higher average process times than others (see Figure 6). Average minutes Time to Compete Process by Project Type 91% 77% 61% 43% % % 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Figure 6 - Time to Complete Process by Project Type 7

8 Data gathered during the direct process observation found that some Project Types required more reports, system queries and longer review times than other Project Types. A detailed analysis found that some projects had a higher percentage of material, utilized contractor labor in addition to internal construction labor, and often involved equipment placements (Figure 7 & Figure 8). % Costs FTTN F2 Projects % Costs Other Project Types 0% 18% 7% 0% 75% Construction Labor Materials Engineering Equipment Exempt Materials 6% 27% 16% 7% 23% 21% Construction labor Materials Engineering Equipment Exempt Materials Contract Labor Figure 7 - FTTN Project Costs Figure 8 - Other Project Costs The key findings of the Analyze phase were: The key process input variable driving process time is Project Type or Project Complexity (meaning more materials and equipment in addition to construction and engineering labor). FTTN F2 projects are less complex with few materials and mostly consist of internal construction labor and as a result it is easier to determine the cause of the cost overrun. Investigating overruns on the more complex project types of OSPRP, Legal Mandate and others requires 57% more reports and 122% more system inquiries. The engineers had some uncertainty on which reports or system queries will provide the best information resulted in pulling several unnecessary reports. The increased complexity of these projects also increases documentation time. Process times for complex projects are double that of the less complex FTTN F2 type projects. Improve Phase: Multiple solutions were generated to reduce or eliminate the impact of operational barriers: 1. Establish a documented process flow and create a job aid for Engineers to standardize the process. 8

9 2. Establish a documented process flow, job aid and request IT create customized reports that summarize and compare initial costs to actual costs along with details on key cost overrun areas. 3. Establish a documented process flow, job aid and Request IT automatically pull and send the existing JAM report required for every review to the engineer with the OP46 notification report. Solutions #2 and #3 build upon solution #1 by adding some system automation to the process review to reduce the manual work effort required to gather and evaluate the information. Each solution was evaluated on the basis of cost, likelihood of success, and ease of implementation using the solution matrix shown in Figure 9. Solution #1 Solution #2 Solution #3 KPIV: Establish a documented Process Flow and create a Job Aid for Engineers Establish documented process flow and Job Aid and request IT Establish a documented Process Flow create customized cost analysis and Job Aid and have IT send JAM reports report Complex Project Types* Total Impact* Success Criteria Likelihood of Success Cost ($$$) note: 10 = lowest cost Engineer Satisfaction Engineering Supervisor Satisfaction Finance Satisfaction Planning Satisfaction Consistent Quality of Supplemental Reviews Success Criteria Total Total Score Figure 9 - Solution Matrix 9

10 The team determined that while solution #3 had a strong potential of process time reduction, the timeframe required to obtain IT approval and development of the automatic report delivery impacted the likelihood of a successful Pilot in Instead, solution #1 was selected to be piloted beginning in December 2009 to ensure a consistent well documented process is in place. Process times will continue to be collected using Observation Worksheet #1 as shown in Figure 3 above. A Future State process map was developed to reflect the process changes developed by the project team. While the changes are not dramatic, it reflects the focus on pulling a single JAM status report (in process step 3) and eliminating the step where the engineer makes calls to the field for additional information. These calls were rare, did not provide any additional information during observations, and added unnecessary process delays. Start Process Engineer receives op46 error notification from CMC report Access CFAS to determine the size and scope of the error Engineer pulls Jam status report and compares the forecast hours and costs to actuals Engineer reviews job file for revisions, change orders, or other items that increased cost after initial approval Planning project? Yes Provide Planning with documentation on their findings related to the project cost overrun Follow up to ensure Planning submits approval within 30 day objective. No Engineer documents the reason for cost overrun in CFAS Project Description section Update CFAS budget lines to meet or exceed current costs (if project not complete) Prepare and submit MIC addendum to supervisor End Process Figure 10 - Future State Process Map Control Phase Pilot Implementation: Pilot implementation will be conducted using a staggered implementation strategy, utilizing small, incremental tests of the process change. One engineering office began the Pilot process 10

11 after a 12/11/2009 kick-off and a follow-up review on 12/15/09 to ensure the process was understood by the participants. This Pilot will run for at least 4 weeks or until at least 20 observations of both FTTN F2 and the other more complex Project Types can be collected. During this time refinements to the documentation will be made based on the feedback received during the Pilot. While the pilot is still in progress, the initial data gathered on 16 observations of the FTTN F2 projects was promising. Graphs of the results from the pilot phase as compared to pre-pilot results are shown in Figures 11 and 12. Average process times for even these project types declined but more importantly, process time variation was reduced Figure 11 Pre-Pilot Results FTTN Projects BoxPlot BoxPlot Figure 12 Pilot Phase Results FTTN Projects To date only one observation of the "Other Project Types" has been made so that comparisons to the Pre-Pilot process times cannot be made at this time. 11

12 Control Phase Full Implementation Plan: If the initial pilots are successful, the project team will host training for the other engineers in the N Central and South Bend Design centers. They will be trained using the updated flowcharts and documentation based on the Pilot feedback. Diffusion of the process to the rest of the engineering organization in Indiana will begin during this phase of the implementation. Supervisors and engineers from other parts of the State will be invited to observe the process in action and the flowcharts and documentation will be presented to them during staff meetings. Standardization of the process will be ensured by placing the documentation in a shared data documentation folder for reference by all Stakeholders and engineers. The documentation will be reviewed annually and updates made as required. To ensure process improvements are sustained the total process time will be collected for all projects with OP46 cost reviews for one week every quarter using the Pilot Plan Data collection tracking form. These results will be summarized for each Design area in the chart shown in Figure 13. OP46 Project Cost Review Data Collection (week of thru ) Engineer # Op46 Min Time Max Time Avg Time area reviews (minutes) (minutes) (minutes) Min Days Max Days Avg Days South Indianapolis N Central North Total Figure 13- Cost Review Summary Report This information will then be charted on a quarterly basis to ensure the process is in control. Figure 14 illustrates the quarterly tracking sheet that will be used to chart the Average process time for each Design area and for the State as a whole. 12

13 Average Time For OP46 Project Cost Reviews (minutes) Engineer area 1Q10 2Q10 3Q10 4Q10 South Indianapolis N Central North Total Figure 14- Cost Review Quarterly Tracking Report Comparisons to prior quarterly results will be performed by the Engineer Managers and posted on Engineering web for review. The existing OP46 tracking reports posted on the Results Web will be monitored monthly to ensure key objectives for the overall process continue to be met (15 day handoff to Planning and the 30 day overall submittal objective). Updated Cost/Benefit Analysis The current process is estimated to cost approximately $68,000 annually and require over 800 engineering hours to complete. The cost of implementing this project can be summarized as: Training the engineers on the process is expected to cost $4,420 in lost engineering time (1 hour * 52 engineers * $85/hour = $4,420) The documentation was developed off line and required no company costs to develop other than printing copies for the engineers to reference. The benefits of standardizing the process are consistent methods and the establishment of a platform for future process improvements. If the Pilot successfully delivers the 25% time savings objective, the project will save the company $17,000/year (800*25%*$85/hour = $17,000). Conclusions: The key to implementing process improvements is have a standard process in place upon which to base those improvements. Having established this documented process, future mechanization 13

14 efforts or process enhancements will have a basis for measuring improvements. Second, having well defined performance measures in place is key to understanding the cost and time impacts of process changes. Implementing the key measures through this project will position the company for making further improvements, possibly through mechanization efforts, by providing a basis for cost benefit studies. The initial Pilot results, while incomplete, indicate process time improvements and reduced process variation is possible through this project implementation. Appendices: Measurement Phase Data Checksheet #1 Measurement Phase Data Checksheet #2 Improve Phase Pilot Data Checksheet OP46 Baseline Process Job Aid OP46 Expenditure Inquiry Job Aid OP46 Process Flowchart Job Aid (Excel File) CFAS Cost Summary Template (Excel File) 14

Define. Measure. Analyze. Improve. Control. Project Name/Description. DMAIC Step Work Done/Tools Used by Team My Role/Contribution

Define. Measure. Analyze. Improve. Control. Project Name/Description. DMAIC Step Work Done/Tools Used by Team My Role/Contribution Six Sigma Green Belt DMAIC Project Logbook Please fill out this document (use as many pages as necessary). Detail what your team and you did in each step of the DMAIC. If the Project is a Kaizen Event,

More information

Lean Six Sigma Analyze Phase Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY

Lean Six Sigma Analyze Phase Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY Before we begin: Turn on the sound on your computer. There is audio to accompany this presentation. Audio will accompany most of the online

More information

Performance Excellence Process

Performance Excellence Process Performance Excellence Process The Performance Excellence Process is a resultsoriented, long-term approach to the way government does business It uses several best practice methodologies, including Strategy

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

Lean Six Sigma Black Belt Certification Recommendation. Name (as it will appear on the certificate) Address. City State, Zip

Lean Six Sigma Black Belt Certification Recommendation. Name (as it will appear on the certificate) Address. City State, Zip Lean Six Sigma Black Belt Certification Recommendation Name (as it will appear on the certificate) IQF Member Number Address City State, Zip Country We the undersigned, on behalf of the Sponsoring Organization,

More information

Computing Services Network Project Methodology

Computing Services Network Project Methodology Computing Services Network Project Prepared By: Todd Brindley, CSN Project Version # 1.0 Updated on 09/15/2008 Version 1.0 Page 1 MANAGEMENT PLANNING Project : Version Control Version Date Author Change

More information

Applying the DMAIC Steps to Process Improvement Projects

Applying the DMAIC Steps to Process Improvement Projects Applying the DMAIC Steps to Process Improvement Projects Define, Measure, Analyze, Improve, Control is the Roadmap to Improving Processes By Harry Rever, MBA, PMP, CSSMBB, CQM, CQC Project managers, in

More information

Perform Work Order Scheduling Process Improvements

Perform Work Order Scheduling Process Improvements Key Work Process(3.1): Perform Work Order Scheduling Process Owner: Perform Work Order Scheduling Process Improvements Work System Owner Ed Curry Work System Enabling Leader Dane Theodore, Director Priority

More information

PMO Metrics Recommendations

PMO Metrics Recommendations Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project

More information

Lean Six Sigma Training The DMAIC Story. Unit 6: Glossary Page 6-1

Lean Six Sigma Training The DMAIC Story. Unit 6: Glossary Page 6-1 Unit 6: Glossary Page 6-1 Glossary of Terms Unit 6: Glossary Page 6-2 Action Plan A technique that documents everything that must be done to ensure effective implementation of a countermeasure or improvement

More information

Improving Healthcare at. Lean Six Sigma

Improving Healthcare at. Lean Six Sigma Lean Six Sigma in Healthcare Improving Healthcare at Presbyterian Healthcare Services Using Lean Six Sigma Learning Objectives Why we need to improve our processes What is Lean Six Sigma Why do we need

More information

Project Management for Process Improvement Efforts. Jeanette M Lynch CLSSBB Missouri Quality Award Examiner Certified Facilitator

Project Management for Process Improvement Efforts. Jeanette M Lynch CLSSBB Missouri Quality Award Examiner Certified Facilitator Project Management for Process Improvement Efforts Jeanette M Lynch CLSSBB Missouri Quality Award Examiner Certified Facilitator 2 Project and Process Due to the nature of continuous improvement, improvement

More information

Framework for Conducting Post Implementation Reviews (PIR)

Framework for Conducting Post Implementation Reviews (PIR) Framework for Conducting Post Implementation Reviews (PIR) PMIWDC PM Tools Workshop June 15, 2010 Risk Analysis Mitchell Karlick, PMP Booz Allen Hamilton, Inc. 0 Agenda Introduction PIR Definition Why

More information

Agenda. Copyright 2012 2013 Acuity Business Solutions, LLC All Rights Reserved

Agenda. Copyright 2012 2013 Acuity Business Solutions, LLC All Rights Reserved Agenda Understand the reasons your firm purchased Vision analyzing your company s pain points What is an ERP and how is it different? Project Lifecycle Reasons why firms fail at implementation or user

More information

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam 44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION

More information

2010 Hiring Reform Action Plan

2010 Hiring Reform Action Plan Agency/Component: Nuclear Regulatory Commission Section 1 (a) (1) Eliminate any requirement that applicants respond to essay-style questions when submitting their initial application materials for any

More information

TOOL. Project Progress Report

TOOL. Project Progress Report TOOL SUMMARY: PROJECT PROGRESS REPORT The purpose of the is to compile information from the analysis done by project participants, partners and LWR country staff about the progress or advances the project

More information

SC21 Manufacturing Excellence. Process Overview

SC21 Manufacturing Excellence. Process Overview SC21 Manufacturing Excellence Process Overview Prepared by:- The SC21 Performance, Development and Quality (PDQ) Special Interest Group (SIG) Acknowledgement The scoring methodology used in the Management

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SECTION 6: QUALITY ASSURANCE PROCEDURE: PM 6.02 TITLE: QUALITY ASSURANCE AUDITS DATE:

More information

Lean Six Sigma Lean 201 Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY

Lean Six Sigma Lean 201 Introduction. TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY TECH 50800 QUALITY and PRODUCTIVITY in INDUSTRY and TECHNOLOGY Before we begin: Turn on the sound on your computer. There is audio to accompany this presentation. Audio will accompany most of the online

More information

Effective objective setting provides structure and direction to the University/Faculties/Schools/Departments and teams as well as people development.

Effective objective setting provides structure and direction to the University/Faculties/Schools/Departments and teams as well as people development. Effective objective setting provides structure and direction to the University/Faculties/Schools/Departments and teams as well as people development. The main purpose of setting objectives is to reflect

More information

Course Overview Lean Six Sigma Green Belt

Course Overview Lean Six Sigma Green Belt Course Overview Lean Six Sigma Green Belt Summary and Objectives This Six Sigma Green Belt course is comprised of 11 separate sessions. Each session is a collection of related lessons and includes an interactive

More information

Overview of the Voice of the Customer Project

Overview of the Voice of the Customer Project Overview of the Voice of the Customer Project The project will teach you how to conduct a Voice of the Customer, and how to incorporate the information that you collect into a professional survey. There

More information

Making the Business Case: Integration of Healthcare-Based Economic Evaluation Methodologies within Hospital QI Programs

Making the Business Case: Integration of Healthcare-Based Economic Evaluation Methodologies within Hospital QI Programs Making the Business Case: Integration of Healthcare-Based Economic Evaluation Methodologies within Hospital QI Programs Heather Woodward-Hagg Purdue University West Lafayette Deanna Suskovich Indiana University-Purdue

More information

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073 INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073 Audit of maintenance and building services provided by the Office of Central Support Services at Headquarters Overall results relating to the Office of Central

More information

INSTALLATION GUIDE 1.0.0 MC

INSTALLATION GUIDE 1.0.0 MC MC Extension Auto Review Reminder Emailer Irzoo Thank you for purchasing the Auto Review Reminder Emailer extension. Below are the installation instructions, please let us know if you have any questions

More information

Workflow and Process Analysis for CCC

Workflow and Process Analysis for CCC Section 3.6 Design Workflow and Process Analysis for CCC This tool introduces the importance of workflow and process improvement in a community-based care coordination (CCC) program, describes the value

More information

Lean Six Sigma Black Belt Body of Knowledge

Lean Six Sigma Black Belt Body of Knowledge General Lean Six Sigma Defined UN Describe Nature and purpose of Lean Six Sigma Integration of Lean and Six Sigma UN Compare and contrast focus and approaches (Process Velocity and Quality) Y=f(X) Input

More information

Using Lean/6 Sigma Methodology to Facilitate Medical Home Implementation

Using Lean/6 Sigma Methodology to Facilitate Medical Home Implementation Using Lean/6 Sigma Methodology to Facilitate Medical Home Implementation Timothy Quinn, MD, MBA President, MercyCare Community Physicians The MercyCare System MercyCare Community Physicians is a physician-led

More information

Audit of Project Management Governance. Audit Report

Audit of Project Management Governance. Audit Report Audit of Project Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 3 What we examined... 3 Why it is important... 3 What we found... 3 Background... 5 Objective... 6

More information

ILM Level 3 Certificate in Using Active Operations Management in the Workplace (QCF)

ILM Level 3 Certificate in Using Active Operations Management in the Workplace (QCF) PAGE 1 ILM Level 3 Certificate in Using Active Operations Management in the Workplace (QCF) CONTENTS Qualification Overview: ILM Level 5 Award, Certificate and Diploma in Management APPENDICES Appendix

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire

More information

Procurement Performance Measurement System

Procurement Performance Measurement System Public Procurement and Disposal of Public Assets Authority Procurement Performance Measurement System User's Guide August 2008 Public Procurement and Disposal of Public Assets Authority Procurement Performance

More information

Process Improvement Program Project Process

Process Improvement Program Project Process Process Improvement Program Project Process 1 P a g e 12/3/2014 The Process Improvement Program is part of the City of Fort Lauderdale s FL 2 STAT Approach to Exponential Improvement. Its objective is

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

Department of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One

Department of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One Motorist Modernization Project Phase One For Period: April - June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

Final. North Carolina Procurement Transformation. Governance Model March 11, 2011

Final. North Carolina Procurement Transformation. Governance Model March 11, 2011 North Carolina Procurement Transformation Governance Model March 11, 2011 Executive Summary Design Approach Process Governance Model Overview Recommended Governance Structure Recommended Governance Processes

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

Learning Objectives Lean Six Sigma Black Belt Course

Learning Objectives Lean Six Sigma Black Belt Course Learning Objectives Lean Six Sigma Black Belt Course The overarching learning objective of this course is to develop a comprehensive set of skills that will allow you to function effectively as a Six Sigma

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

Project Execution Guidelines for SESAR 2020 Exploratory Research

Project Execution Guidelines for SESAR 2020 Exploratory Research Project Execution Guidelines for SESAR 2020 Exploratory Research 04 June 2015 Edition 01.01.00 This document aims at providing guidance to consortia members on the way they are expected to fulfil the project

More information

Enhancing Law Enforcement Response to Victims:

Enhancing Law Enforcement Response to Victims: Enhancing Law Enforcement Response to Victims: Strategy Implementation Checklist Enhancing Law Enforcement Response to Victims is a new professional standard developed by the International Association

More information

Six sigma project management

Six sigma project management Six sigma project management Bizagi Suite Six sigma project management 1 Table of Contents Six Sigma Project Management... 3 Process Elements... 9 Project Charter... 9 Define... 11 Measure...12 Analyze...12

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Effectively Employing AMS Machinery Manager for Rotating Mechanical Assets

Effectively Employing AMS Machinery Manager for Rotating Mechanical Assets Asset Optimization Services Product Data Sheet June 2013 Effectively Employing AMS Machinery Manager for Rotating Mechanical Assets Increase effectiveness of your maintenance and operations staff by taking

More information

Developing and Implementing a Balanced Scorecard: A Practical Approach

Developing and Implementing a Balanced Scorecard: A Practical Approach RL Consulting Developing and Implementing a Balanced Scorecard: A Practical Approach White Paper Prepared by: Rick Leopoldi March 31, 2004 Copyright 2004. All rights reserved. Duplication of this document

More information

Six Sigma, ISO 9001 and Baldrige

Six Sigma, ISO 9001 and Baldrige Six Sigma, ISO 9001 and Baldrige Many organizations ask How Do these programs, processes and standards support each other? These initiatives are not mutually exclusive, in fact, understanding and applying

More information

ISO 9001 (2000) QUALITY MANAGEMENT SYSTEM ASSESSMENT REPORT SUPPLIER/ SUBCONTRACTOR

ISO 9001 (2000) QUALITY MANAGEMENT SYSTEM ASSESSMENT REPORT SUPPLIER/ SUBCONTRACTOR Page 1 of 20 ISO 9001 (2000) QUALITY MANAGEMENT SYSTEM ASSESSMENT REPORT SUPPLIER/ SUBCONTRACTOR SUPPLIER/ SUBCONTRACTOR NAME: ADDRESS: CITY AND STATE: ZIP CODE: SUPPLIER/MANUFACTURER NO PHONE: DIVISION:

More information

Performance Management Plan 2014-2015

Performance Management Plan 2014-2015 North Dakota Department of Health Performance Management Plan 2014-2015 1 North Dakota Department of Health Performance Management Plan 2014-2015 CONTENTS Purpose 3 Policy Statement 3 Organizational Structure

More information

Post-Implementation EMR Evaluation for the Beta Ambulatory Care Clinic Proposed Plan Jul 6/2012, Version 2.0

Post-Implementation EMR Evaluation for the Beta Ambulatory Care Clinic Proposed Plan Jul 6/2012, Version 2.0 1. Purpose and Scope Post-Implementation EMR Evaluation for the Beta Ambulatory Care Clinic Proposed Plan Jul 6/2012, Version 2.0 This document describes our proposed plan to conduct a formative evaluation

More information

Lean Six Sigma Black Belt-EngineRoom

Lean Six Sigma Black Belt-EngineRoom Lean Six Sigma Black Belt-EngineRoom Course Content and Outline Total Estimated Hours: 140.65 *Course includes choice of software: EngineRoom (included for free), Minitab (must purchase separately) or

More information

The Introduction of a New Performance Management System. for Administrative & Professional, and Exempt Employees at Brock University

The Introduction of a New Performance Management System. for Administrative & Professional, and Exempt Employees at Brock University The Introduction of a New Performance Management System for Administrative & Professional, and Exempt Employees at Brock University Your Role Today In your day-to-day activities you may wear many different

More information

A Case Study and Exercise on How To Use Lean Principles to Overcome A Broken Paradigm

A Case Study and Exercise on How To Use Lean Principles to Overcome A Broken Paradigm A Case Study and Exercise on How To Use Lean Principles to Overcome A Broken Paradigm Cynthia Seaver, Director of Process Excellence Mercy Health Muskegon Certified Six Sigma Black Belt & Lean Expert Case

More information

Revealing the Big Picture Using Business Process Management

Revealing the Big Picture Using Business Process Management Revealing the Big Picture Using Business Process Management Page 1 of 20 Page 2 of 20 Introduction In today s business environment, change is inevitable. Changes in technology, organizational structure,

More information

Xavier University: IT Portfolio Management and the Project Request Process

Xavier University: IT Portfolio Management and the Project Request Process A guideline and process document to establish the governance framework for technology related project requests laying the groundwork for strategic portfolio management Xavier University: IT Portfolio Management

More information

The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management.

The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management. Knowledge Areas The Project Management Body of Knowledge, generally known as PMBOK, deals with nine fundamental subjects for the project management. These are: Project Integration Management Project Scope

More information

Design for Six Sigma +Lean Toolset

Design for Six Sigma +Lean Toolset Stephan Lunau (Ed.) Christian Staudter Jens-Peter Mollenhauer Renata Meran Olin Roenpage Clemens von Hugo Alexis Hamalides Design for Six Sigma +Lean Toolset Implementing Innovations Successfully 4y Springer

More information

The PMP Application Process

The PMP Application Process The PMP Application Process The purpose of this document is to explain the PMP application process and provide helpful links and tools for submitting your application. Reference: The reference for the

More information

P3M3 Portfolio Management Self-Assessment

P3M3 Portfolio Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction

More information

Setting the Expectation for Success: Performance Management & Appraisal System

Setting the Expectation for Success: Performance Management & Appraisal System HILLSBOROUGH COUNTY CIVIL SERVICE BOARD OFFICE Setting the Expectation for Success: Performance Management & Appraisal System Supervisor s Guide PROCESS OVERVIEW Setting the Expectation for Success: Performance

More information

July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services

July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services

More information

Internal Customers Matter Too: Using VOC Methods to Understand and Meet Internal Customer Needs

Internal Customers Matter Too: Using VOC Methods to Understand and Meet Internal Customer Needs Internal Customers Matter Too: Using VOC Methods to Understand and Meet Internal Customer Needs Dr. Susan O. Schall 2011 SPQA Forum Copyright 2011 SOS Consulting, LLC. All rights reserved. Overview Introduce

More information

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE TABLE OF CONTENTS STEP 1 IDENTIFY THE CHANGE... 5 1.1 TYPE OF CHANGE... 5 1.2 REASON FOR THE CHANGE... 5 1.3 SCOPE THE CHANGE... 6 1.4 WHERE ARE YOU NOW?...

More information

TOOL. Project Progress Report

TOOL. Project Progress Report Purpose TOOL SUMMARY: LOGFRAME CHEAT SHEET The purpose of the is to compile information from the analysis done by project participants, partners and LWR country staff about the progress or advances the

More information

Contract Performance Framework

Contract Performance Framework Contract Performance Framework Version 4 September, 2014 1 Provincial CCAC Client Service Contract Performance Framework Introduction: Home care plays a critical role in achieving successful and sustainable

More information

THE SIX SIGMA YELLOW BELT SOLUTIONS TEXT

THE SIX SIGMA YELLOW BELT SOLUTIONS TEXT THE SIX SIGMA YELLOW BELT SOLUTIONS TEXT 2014 by Bill Wortman - All rights reserved SECTION II SIX SIGMA FUNDAMENTALS - SAMPLE QUESTIONS 2.1. The DPMO for a process is 860. What is the approximate six

More information

Continuous Quality Improvement Project

Continuous Quality Improvement Project Department Structure Continuous Quality Improvement Project Georgia Interview with Shelley Cyphers, Director, Office of Quality Management sacyphers@dhr.state.ga.us 404 657 3325 and Mary Franklin Barmore,

More information

System Development Life Cycle Guide

System Development Life Cycle Guide TEXAS DEPARTMENT OF INFORMATION RESOURCES System Development Life Cycle Guide Version 1.1 30 MAY 2008 Version History This and other Framework Extension tools are available on Framework Web site. Release

More information

FY 2016 ANNUAL PERFORMANCE PLAN

FY 2016 ANNUAL PERFORMANCE PLAN FY 2016 ANNUAL PERFORMANCE PLAN NSF s FY 2016 Performance Plan reflects NSF s priorities as identified through its planning and budget process. The table below provides a summary of NSF s performance goals

More information

SELF ASSESSMENT GUIDE FOR PLACEMENT SERVICE PROVIDERS 2009/2010

SELF ASSESSMENT GUIDE FOR PLACEMENT SERVICE PROVIDERS 2009/2010 SELF ASSESSMENT GUIDE FOR PLACEMENT SERVICE PROVIDERS 2009/2010 Electronic copies of this document are available by contacting the Manager Standards Monitoring Unit on 9222 2598 CONTENTS OVERVIEW...3 PURPOSE

More information

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope Activity Code 24010 B-1 Planning Considerations Estimating System Survey (ICR) Purpose and Scope The major objectives of this audit are to: Evaluate the adequacy of and the contractor s compliance with

More information

Audit of the Management of Projects within Employment and Social Development Canada

Audit of the Management of Projects within Employment and Social Development Canada Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can

More information

LEAN CERTIFICATION BODY OF KNOWLEDGE RUBRIC VERSION 3.0

LEAN CERTIFICATION BODY OF KNOWLEDGE RUBRIC VERSION 3.0 MODULE 1 LEAN CERTIFICATION BODY OF KNOWLEDGE RUBRIC VERSION 3.0 1. Cultural Enablers 15% 20% 25% 1.1. Principles of Cultural Enablers 3% 4% 5% 1.1.1. Respect for the individual 1.1.2. Humility 1.2. Processes

More information

Master Document Audit Program. or Interviews. Version 3.21, dated April 2016 B-1 Planning Considerations

Master Document Audit Program. or Interviews. Version 3.21, dated April 2016 B-1 Planning Considerations Activity Code 10310 Version 3.21, dated April 2016 B-1 Planning Considerations Non-Major Contractors Labor Floor Checks or Interviews Audit Specific Independence Determination Members of the audit team

More information

PERFORMANCE PLANNING AND APPRAISAL FORM MANAGEMENT PERSONNEL

PERFORMANCE PLANNING AND APPRAISAL FORM MANAGEMENT PERSONNEL Employee Name: Position Title: Department: Supervisor Name: Date of Review: For Period: To At the beginning of each performance cycle, employee and supervisor establish performance objectives based on

More information

MANUFACTURING EXECUTION SYSTEMS INTEGRATED WITH ERP & SIX SIGMA FOR PROCESS IMPROVEMENTS

MANUFACTURING EXECUTION SYSTEMS INTEGRATED WITH ERP & SIX SIGMA FOR PROCESS IMPROVEMENTS MANUFACTURING EXECUTION SYSTEMS INTEGRATED WITH ERP & SIX SIGMA FOR PROCESS IMPROVEMENTS Name: Sumanth Pandith Surendra Institution: Wichita State University Status: Current Full time graduate in Industrial

More information

The Power of Two: Combining Lean Six Sigma and BPM

The Power of Two: Combining Lean Six Sigma and BPM : Combining Lean Six Sigma and BPM Lance Gibbs and Tom Shea Lean Six Sigma (LSS) and Business Process Management (BPM) have much to contribute to each other. Unfortunately, most companies have not integrated

More information

Vermont Behavioral Risk Factor Surveillance System. Strategic Plan and Performance Measures

Vermont Behavioral Risk Factor Surveillance System. Strategic Plan and Performance Measures Vermont Behavioral Risk Factor Surveillance System 2012 Vermont Behavioral Risk Factor Survey Strategic Plan and Performance Measures Data collected as part of Vermont s Behavioral Risk Factor Surveillance

More information

21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against

21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against PMP Short Notes Based on PMBOK Guide fifth edition By Dilip Chaturvedi,PMP Email id: info@justpmp.com To know about our training schedule, please visit www.justpmp.com 1. Communication is more complex

More information

Governments information technology

Governments information technology So l u t i o n s Blending Agile and Lean Thinking for More Efficient IT Development By Harry Kenworthy Agile development and Lean management can lead to more cost-effective, timely production of information

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

Six Sigma Project Management Bizagi Process Modeler

Six Sigma Project Management Bizagi Process Modeler Six Sigma Project Management Bizagi Process Modeler www.bizagi.com Table of Contents 1 SIX SIGMA PROJECT MANAGEMENT... 4 1.1 SIX SIGMA PROJECT MANAGEMENT... 10 1.1.1 Process Elements... 10 1.1.1.1 Project

More information

VIII. Project Management Glossary

VIII. Project Management Glossary https://www.wrike.com/project-management-guide/glossary/ VIII. Project Management Glossary Project management, like any other industry, has its share of unique terms. Don t be overwhelmed. Here is our

More information

2011 Innovations Awards Application DEADLINE: MARCH 28, 2011

2011 Innovations Awards Application DEADLINE: MARCH 28, 2011 2011 Innovations Awards Application DEADLINE: MARCH 28, 2011 ID # (assigned by CSG): 2011- Please provide the following information, adding space as necessary: State: Pennsylvania Assign Program Category

More information

Risk and Contingency Planning. Today s Topics. Key Terms. A Vital Component of Your ICD-10 Program

Risk and Contingency Planning. Today s Topics. Key Terms. A Vital Component of Your ICD-10 Program Risk and Planning A Vital Component of Your ICD-10 Program Today s Topics Key Terms Why is Risk Management Critical for ICD-10? Effective Risk Management and Best Concepts ICD-10 Risk Management Examples

More information

Essential Elements for Any Successful Project

Essential Elements for Any Successful Project In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable

More information

BENCHMARK YOUR TEST FUNCTION AGAINST A WORLD-CLASS TESTING ORGANIZATION

BENCHMARK YOUR TEST FUNCTION AGAINST A WORLD-CLASS TESTING ORGANIZATION BENCHMARK YOUR TEST FUNCTION AGAINST A WORLD-CLASS TESTING ORGANIZATION PRACTICE OBJECTIVE This practice will enable you to conduct an assessment of your testing organization, using eight criteria that

More information

Department of the Treasury

Department of the Treasury Department of the Treasury Customer Service Plan 2011 Executive Summary As part of its mission managing the U.S. Government s finances and resources, the Department of the Treasury serves millions of customers.

More information

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING

More information

Customer Inquiry Call Center

Customer Inquiry Call Center Customer Inquiry Call Center Background Overview In 1990, a Governor s executive order, 90-28, established a statewide Child Support Hotline (renamed the Customer Inquiry Call Center) within the Office

More information

Lean and Six Sigma Healthcare Fad or Reality. Vince D Mello President

Lean and Six Sigma Healthcare Fad or Reality. Vince D Mello President Lean and Six Sigma Healthcare Fad or Reality Vince D Mello President TODAY S DISCUSSION About Lean Methodologies Application benefits and outcomes About Six Sigma Key learning's QUALITY FUNDAMENTALS Function

More information

Leadership Summit for Hospital and Post-Acute Long Term Care Providers May 12, 2015

Leadership Summit for Hospital and Post-Acute Long Term Care Providers May 12, 2015 Leveraging the Continuum to Avoid Unnecessary Utilization While Improving Quality Leadership Summit for Hospital and Post-Acute Long Term Care Providers May 12, 2015 Karim A. Habibi, FHFMA, MPH, MS Senior

More information

A Six Sigma Approach for Software Process Improvements and its Implementation

A Six Sigma Approach for Software Process Improvements and its Implementation A Six Sigma Approach for Software Process Improvements and its Implementation Punitha Jayaraman, Kamalanathan Kannabiran, and S.A.Vasantha Kumar. Abstract Six Sigma is a data-driven leadership approach

More information

Sound Transit Internal Audit Report - No. 2014-3

Sound Transit Internal Audit Report - No. 2014-3 Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management

More information

Requirements for 21 st CCLC Evaluation and Reporting

Requirements for 21 st CCLC Evaluation and Reporting Requirements for 21 st CCLC Evaluation and Reporting Tonetta Y. Scott, DrPH and Matthew Trengove, PhD 21 st CCLC Administrative Team, Research and Evaluation Unit August 2015 1 Agenda State and Federal

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Certified Quality Improvement Associate

Certified Quality Improvement Associate Certified Quality Improvement Associate Quality excellence to enhance your career and boost your organization s bottom line asq.org/certification The Global Voice of Quality TM Certification from ASQ is

More information

Fiscal Year 14-15. Kids Central Inc. John Cooper, CEO

Fiscal Year 14-15. Kids Central Inc. John Cooper, CEO Fiscal Year 14-15 Kids Central Inc. John Cooper, CEO KIDS CENTRAL, INC. BUSINESS PLAN Kids Central s Business Plan builds upon the organizations Strategic Plan. The plan will ensure the organization s

More information