Permit to Work Procedure

Size: px
Start display at page:

Download "Permit to Work Procedure"

Transcription

1 Procedure

2 Table of Contents 1. Purpose Scope Definitions Roles and Responsibilities Level 3 Manager Manager, Workplace Health and Safety Supervisor Permit Recipient Second Person Access Officer Permit User nd Tier Permit Authority Process Flow Function A PTW is issued to: A PTW is required for the following activities: Hardware & Software The hardware used in the PTW process includes: Process Application for a Call outs/ Breakdowns / Reactive Work Approval for Work Arrival at Site Entrance Arrival on Site PTW Activation Undertaking Isolations Issuing 2nd Tier Permits Carrying out Work Under an Activated Changes to the Work Under the Break in Work Change of Permit Recipient Change in Permit Recipient, no Break in Work: Change in Permit Recipient, Break in Work: Change in Permit Recipient, Recommencing Work: De-Isolating Inching and Testing...20 Document Number: PRO Version Date: 19/11/2012 Page: 2 of 23

3 8.15 Completion of Work Under the Multiple Permits to Work Disciplinary Action Associated Documents Appendix Emergency Management...23 Document Number: PRO Version Date: 19/11/2012 Page: 3 of 23

4 1. Purpose The (PTW) procedure defines the minimum requirements to provide a safe system of Work when plant is taken from service for breakdown, maintenance or capital work and when Work is not controlled as Pre-Approved Work at Seqwater operational sites. The system also provides a trigger for the use of other permits for high risk work (2nd Tier Permits) such as hot work, work at heights, confined spaces work, excavation, fault finding, HV, and grid mesh, handrail and flooring removal. This procedure is a documented system that provides a notification of intent and an approval process, to undertake a specific scope of Work. 2. Scope The PTW process forms part of the Site Access and Works Control System (SAWCS) and covers Seqwater employees, contractors and sub-contractor employees engaged in operational, maintenance, inspection, construction, commissioning, decommissioning or alteration activities, that are not controlled as Pre-Approved Work, carried out at Seqwater owned and operated sites. All principal contractors shall abide by this procedure or submit a Safety Management Plan for endorsement by the Seqwater Workplace Health and Safety and Environment Departments. Any submitted Safety Management Plan must, as a minimum, achieve the intent of this procedure. 3. Definitions TERM 2 nd Tier Permits 2 nd Tier Permit Authority Access Officer DEFINITION Any permit used at Seqwater owned and operated sites to manage specific High Risk hazards, e.g. hot work, work at heights, confined spaces work, excavation, fault finding, HV, and grid mesh, handrail and flooring removal. A Worker holding the appropriate licences, tickets and industry regulated competencies relevant to the 2nd tier task they are performing. They approve and issue the relevant 2nd Tier Permit. The officer in control of dams, natural areas, facilities or water treatment plants who is nominated to maintain the responsibilities of this procedure. The Access Officer in responsible for assessing and approving/rejecting access requests and PTW s. They must ensure the proposed work does not produce conflicts in operational and maintenance requirements for the site and identify area specific and process hazards that the Worker may not be aware of. Document Number: PRO Version Date: 19/11/2012 Page: 4 of 23

5 TERM Additional Isolator Applicant Break in work CIS De-isolation Equipment Identification Tag Emergency DEFINITION Isolations are discipline specific. Isolations and de-isolations must only be performed within the Workers training, qualifications and competency e.g. Only licensed electricians may perform electrical isolations within an electrical exclusion zone. As a result, Permit Recipients will require additional resources to carry out isolations when working with energy sources requiring multi discipline isolations. Additional Isolators work only under the direction of the Permit Recipient or the Pre-Approved Worker. Person applying for access and or PTW from the Access Officer. The Applicant may be requesting access on behalf of the Worker or requesting access for themselves and their work party. Any time a Permit Recipient or Permit User of a PTW needs to leave a job for any period of time other than for meal and ablution breaks. Corporate Information System The process of re-energising hazardous energy sources Equipment Identification Tags are used to formally identify equipment (in the field) and associate it to Pre-Approved Work or a particular PTW. Equipment Identification Tags are placed by the Pre-Approved Worker or Permit Recipient prior to the commencement of any work under the control of a PTW. Equipment Identification Tags should be removed by the Worker-in- Charge or Permit Recipient upon the completion of the task. Equipment Identification Tags are green in colour. An emergency is the sudden, unexpected, or impending situation that may cause injury, loss of life, damage to property, and/or interference with the normal activities of a worker or operations and which, therefore, requires immediate attention and remedial action. e.g. fire, flood, medical emergency. Sources of energy that have the potential to cause injury, property damage or impact on the integrity of water supply. These sources may include: Hazardous Energy HV Electrical energy Influx of water or liquids Material/substances under pressure High Voltage Rotating or moving parts Release of toxic or caustic substances Potential energy Document Number: PRO Version Date: 19/11/2012 Page: 5 of 23

6 TERM Isolation Instruction Inch and Test Isolation Point JSEA Level 3 Manager Operational Site Permit Board Permit Recipient DEFINITION A documented instruction on the isolations required to be performed in order to safely conduct tasks. It contains explicit instructions to: Identify isolation points Positively isolate Discharge stored energy Lock and Tag out Test for dead, prove for dead De-isolate Inch and Test The Isolation Instruction is developed by the Permit Recipient, and reviewed by the Access Officer prior to use. The process of functional testing of equipment during commissioning. The Inch and Test Program may require the partial or full de-isolation of equipment and is recorded on the Isolation Instruction. A point at which an Isolation Lock and Tag can be applied to effect positive isolation. Job Safety and Environmental Analysis Seqwater Managers directly responsible for the day to day operation of water production facilities and plant. Any Seqwater owned and/or operated site. A board consisting of a lockable compartment and document holder that also provides multiple lockout capability Permit Boards provide the security for keys from Isolation Locks used to positively isolate equipment. Permit boards are used for the retention and displaying of documents associated to the / Pre-Approved Work (PTW form, 2 nd Tier Permits, Isolation Instructions, Work Order, etc). Permit boards are a common personal lockout point for all Workers to apply their Personal Danger Locks and Tags, protecting themselves from hazardous energy. Permit Boards may also be used for Pre-Approved Work where there are multiple isolations and there is a need for Isolation Lock keys to be secured in a central location. Any worker formally trained and assessed competent to complete tasks and accept conditions listed on the. The Permit Recipient in charge of the Work. They are responsible for applying for access, coordinating the PTW and any isolations. Document Number: PRO Version Date: 19/11/2012 Page: 6 of 23

7 TERM Permit Recipient Tag PTW Permit User Positively Isolated Positive Isolation Hardware RTHA Second Person Shall Should Test for Dead, Prove for Dead Work Worker DEFINITION A white tag applied by a Permit Recipient (with their Personal Danger Tag) to their Personal Danger Lock identifying them as the recipient of the corresponding PTW. A formal document used to identify the controls to be implemented to provide a safe workplace and safe systems of work. Any worker who has been trained and assessed competent to complete the work tasks and works under the direct supervision of the Permit Recipient. A complete physical separation of energy sources preventing energy transmission using a current isolation switch, isolating valve or device. Equipment is not positively isolated if the energy can be activated by another means while isolated. The shrouds (hardware) used in the positive isolation of valves, fuses, circuit breakers, electric leads and plugs. Real Time Hazard Assessment. A documented hazard assessment, or infield review, performed at the intended place of work prior to a PTW being issued, or during tasks where there is a change in conditions. A person trained in and assessed as competent in the Energy Tag and Lockout Procedure and the SAWCS process. Isolations are always confirmed by a Second Person cross checking each isolation point including de-isolations and re-isolations as required for testing/inching and PTW cancellation. To be interpreted as mandatory. Used in an advisory or discretionary sense. The test conducted by a Permit Recipient/ Pre-Approved Worker to test for dead, Prove for Dead after attaching Isolation Locks and Tags to an isolation point. This process ensures that the plant and equipment cannot be started and is documented in the Isolation Instruction Any task that is conducted on an operational site outside of an administration, meeting or office environment. The term Work excludes courier drivers, mail delivery, waste collection, security personnel. A Seqwater employee or business partner authorised and inducted to carry out work at an operational site. The term Worker may encompass Permit Recipients, Permit Users and Pre-Approved Workers 4. Roles and Responsibilities 4.1 Level 3 Manager Level 3 Managers are responsible for: Document Number: PRO Version Date: 19/11/2012 Page: 7 of 23

8 1. Ensuring that a PTW program is established and maintained for the protection of all personnel and assets within their jurisdiction, at Seqwater owned and operated sites. 2. Ensuring personnel are trained and assessed in the SAWCS process (SPE ) and competent to perform the PTW roles and processes. 3. Authorising the forced removal of any padlock used under the PTW system as outlined in the Energy Tag and Lockout procedure (PRO-00014), where required. 4. Ensuring PTW system hardware needs are readily available for field application. 4.2 Manager, Workplace Health and Safety The Manager, Workplace Health and Safety is responsible for: 1. Developing processes and systems for auditing and providing a training program that enables effective field application of this procedure. 2. Reviewing safety management plans submitted by principal contractors for approval. 3. Ensuring audits are conducted at regular intervals to monitor the PTW process and ensure continuous improvement. 4.3 Supervisor Supervisors are responsible for: 1. Assigning work to Workers via the CIS Work Order System 2. Ensuring Workers have the relevant competencies to carry out the assigned work 3. Controlling the keys to Out of Service Locks that are in use 4. Assembling lists of Pre-Approved Work 4.4 Permit Recipient Permit Recipients are responsible for: 1. Abiding by the requirements of this procedure at all times when Working at Seqwater operational sites. 2. Ensuring that they and their Permit Users have the relevant competencies to carry out the assigned work. 3. Ensuring a JSEA is developed (Refer to TEM-00013) for the proposed works in conjunction with the work party. Is reviewed, understood and accepted by the work party and is reviewed by the Access Officer and additional controls added where appropriate. 4. Obtaining a full understanding and ensuring that all Permit Users have a full understanding of the requirements and restrictions imposed by the PTW and any required 2nd Tier Permits, including the boundary of the work area. 5. Ensuring Isolation Instructions are available for the required isolations, and where not available, to develop the Isolation Instruction. 6. Performing isolations by securing each point with an Isolation Lock and Tag and or coordinating multi disciplined isolations as per the Isolation Instruction. 7. Ensuring a Second Person cross checks each isolation, de-isolation and reisolation as required for testing/inching and PTW cancellation. 8. Administering the PTW process, ensuring all sections of the PTW are completed in accordance with this procedure. Document Number: PRO Version Date: 19/11/2012 Page: 8 of 23

9 9. Closing the PTW and handing all documentation over to the Supervisor. 4.5 Second Person The Second Person is responsible for: 1. Abiding by the requirements of this procedure at all times when Working at Seqwater operational sites. 2. Ensuring they have competencies in the Energy Tag and Lockout Procedure (PRO-00014) and the SAWCS process (SPE-00215). 3. Cross checking each isolation point including de-isolations and re-isolations as required for testing/inching and PTW Closure. 4.6 Access Officer Access Officers are responsible for: 1. Abiding by the requirements of this procedure at all times when Working at Seqwater operational sites. 2. Reviewing the JSEA with the Permit Recipient, to ensure conflicts do not occur in operational and maintenance requirements for the site and identifying area specific and process hazards that the Permit Recipient may not be aware of (e.g. other workgroups in the area, chemical storage facilities, changed conditions, etc). 3. Confirming the competencies of the work party undertaking the PTW. 4. Issuing the Site Access approval and managing the Access Log (FRM-00426) to the Permit Recipient to allow site access. 5. Signing local PTW Activations or issuing the PTW Activation Number from the Access Log to the Permit Recipient. 6. Signing local PTW Cancellations or issuing the PTW Cancellation Number from the Access Log to the Permit Recipient. 4.7 Permit User Permit Users are responsible for: 1. Abiding by the requirements of this procedure at all times when Working at Seqwater operational sites. 2. Holding the appropriate licences, tickets and industry regulated competencies to perform the task (e.g. rigger, crane operator, etc). 3. Obtaining from the Permit Recipient, a full understanding of the requirements of and restrictions imposed by the JSEA, PTW and any 2nd Tier Permits. 4. Complying at all times with the requirements of: the JSEA the PTW any 2nd Tier Permits 4.8 2nd Tier Permit Authority The 2nd Tier Permit Authority is responsible for: 1. Abiding by the requirements of this procedure at all times when Working at Seqwater operational sites. 2. Reviewing the requirements of the PTW to ensure the correct 2nd Tier Permits have been allocated to the task. Document Number: PRO Version Date: 19/11/2012 Page: 9 of 23

10 3. Ensuring controls are adequate for the hazard and are implemented prior to the commencement of work. 4. Holding the appropriate licences, tickets and industry regulated competencies relevant to the 2nd tier task they are performing. 5. Approving and issuing the relevant 2nd Tier Permit. Document Number: PRO Version Date: 19/11/2012 Page: 10 of 23

11 5. Process Flow Document Number: PRO Version Date: 19/11/2012 Page: 11 of 23

12 6. Function 6.1 A PTW is issued to: Communicate the impacts and implications of the work being undertaken Ensure all hazards are identified and the associated risks are adequately controlled to reduce the risk to an acceptable level. Detail how equipment should be positively isolated and worked on safely. Identify and record the task being undertaken and the people carrying them out. Ensure workers are aware of plant or equipment isolation and availability. 6.2 A PTW is required for the following activities: Work requiring the isolation of hazardous energy or substances (Removing a plug in device fed from a GPO is not deemed an isolation unless it is part of process control) Work within an electrical exclusion zone (refer to QLD Electrical Safety Act 2002). For the following activities that have recorded a high uncontrolled /inherent risk score using the Seqwater JSEA (Refer to TEM-00013) o Tasks that have the potential to impact on the water treatment process, equipment or adjacent work activities. o Tasks that have the potential to result in a physical change to the work environment (e.g. scaffolding, excavation). o Tasks that have the potential to impact the environment (e.g. noise, dust, vibration, light, soil disturbance (excavation), possible contamination by oil, paint or other chemical). o Tasks where there is a risk of exposure to dangerous goods or hazardous chemicals. For work that falls into the above categories where personnel are not assessed competent under the Seqwater Pre-Approved Work process. Or as directed by an Seqwater representative. 6.3 A PTW is not required for: Pre-Approved tasks where at least one worker has been assessed as competent. Tasks that do not impact on others or Seqwater s ability to supply water to customers. Tasks that do not impact on others or Seqwater s ability to release water from infrastructure during flood events. Work performed in maintenance workshops, except when a 2nd Tier Permit or hazardous energy isolations are required. Emergency situations where the Access Officer has provided verbal clearance to the worker or other persons (i.e. emergency services, etc) requesting access to the area, however the Energy Tag and Lockout process shall be observed. Minor tool changes and adjustments and other minor servicing activities, if they: o Take place during normal production operations and do not require the removal or bypass of a guard; or o Are routine, repetitive and integral to the use of the equipment. o Office work o Safety inspections or audits. ( Will require an RTHA and if required a JSEA) Document Number: PRO Version Date: 19/11/2012 Page: 12 of 23

13 7. Hardware & Software 7.1 The hardware used in the PTW process includes: HARDWARE Book-fast 2nd Tier Permits Book-fast JSEA RTHA Cards Permit Boards Permit Recipient Tag Equipment Identification Tag Information Tag Isolation Lock and Tag Personal Danger Lock and Tag Out of Service Lock and Tag DESCRIPTION Written record of work approval Written record of 2 nd Tier activities Written record of job hazards and their controls Real Time Hazard Assessment record Secure Isolation Lock keys and associated paperwork Identifies the Permit Recipient on the Permit Board Identifies the equipment to be worked on Displays information relevant to the equipment Secures isolation points Secures isolation lock keys in the Permit Board and identifies Workers working on the PTW Identifies defective equipment and secures isolation keys in the Permit Board while there is a break in work In addition, a multitude of positive isolation hardware is available at operational sites. Further information on the listed hardware is available in the Energy Tag and Lockout Procedure. 8. Process 8.1 Application for a Work is generally planned in advance allowing appropriate time for the management of plant output to minimise disruption to services. To begin the process the Permit Recipient or Applicant acting on their behalf sends the request for Site Access and PTW via a MS Outlook Calendar Appointment addressed to the appropriate Access Officer at least 48 hours in advance of the planned start date, where possible by: 1. Searching the Access Officer Register (REG-00538) for the appropriate Access Officer 2. Generating a MS Outlook Calendar Appointment addressed to the appropriate Access Officer Document Number: PRO Version Date: 19/11/2012 Page: 13 of 23

14 3. The Appointment should contain the following information: a. A description of the work (may include Work Order Number) b. The location c. The time and duration for access d. A message containing relevant information for the Access Officer to approve your application, e.g. PTW. 4. Attach the required supporting documentation if available e.g. JSEA, Isolation Instruction etc and send the outlook meeting request If the Applicant/ Permit Recipient is unable to send an outlook meeting request they may use the Access Officer Group telephone number to contact the relevant Access Officer. The relevant information above must be provided verbally. If there is no JSEA and or Isolation Instruction, one must be drafted on arrival to site before a PTW Activation Number can be issued. 8.2 Call outs/ Breakdowns / Reactive Work In the case where work is unscheduled (i.e. a breakdown/callout), the PTW process must still be followed by the submission and review of a JSEA however: 1. The Access Officer may grant approval for access verbally via the call out and record it in the Access Log at a later date 2. Review of the JSEA may be accepted by the signature of the Access Officer on the JSEA and recorded in the Site Access Log at a later date 3. Approval and closure of the PTW may be granted by the signature of the Access Officer on the PTW and recorded in the Access Log at a later date 8.3 Approval for Work The Access Officer assesses the application by reviewing the JSEA and taking into account: 1. The type, priority and timing of the work. 2. Production and maintenance plans. 3. The items of plant and equipment that would require isolation and the impact this would have on operations. 4. Confirm with the Supervisor the training and competency of those nominated to conduct the work. 5. The impact of 2nd Tier Permits on operations. The Access Officer notifies the applicant of acceptance or rejection of the application Where a conflict with other works arises and or, there is a lack of information in the application, the Access Officer may reject the Application. Where a rejection occurs, the Access Officer identifies the issues with the Applicant and may suggest an appropriate re-scheduling time. 8.4 Arrival at Site Entrance Every Seqwater Operational Site will have a sign located at the entrance showing the Access Officers contact details, see below: Document Number: PRO Version Date: 19/11/2012 Page: 14 of 23

15 On arrival at the operational site entrance the Permit Recipient shall: 5. Contact the Access Officer to notify them of their arrival. Where there is limited phone coverage, contact shall be made with the Access Officer prior to arriving on site. 6. Where the access has not been pre-arranged the Permit Recipient must provide all the information required from 8.1 above and wait for the Access Officer to approve access. The Access Officer shall: 1. Where the Site Access has not been pre-arranged, assess the application for access following 8.1 above. 2. Confirm access approval for the Permit Recipient in the Access Log and allow access into the site for sign in (mandatory) and induction (if not previously). 8.5 Arrival on Site Once inside the Operational Site the Permit Recipient must: 1. Ensure they and the working party sign in; and complete the induction requirements if not previously inducted. 2. If there are no sign in facilities i.e. remote site, the Permit Recipient must inform the Access Officer of the date and time of arrival for inclusion in the Access Log. 3. Conduct an RTHA (Refer to GDE-00089) 4. Develop a JSEA (Refer to TEM-00013) for the Work if not already done 5. Develop an Isolation Instruction (Refer to TEM-00077) if not already done 6. Undertake a review of the JSEA with the Access Officer and implement any additional controls. Document Number: PRO Version Date: 19/11/2012 Page: 15 of 23

16 The Access Officer shall: 1. If there are no sign in facilities i.e. remote site, the Access Officer must enter the date and time of arrival in the Access Log. 2. Review the JSEA and Isolation Instruction with the Permit Recipient to: Ensure the proposed Work does not produce conflicts in operational and maintenance requirements for the site. Identify area specific and process hazards that the Worker may not be aware of (e.g. other workgroups in the area, chemical storage facilities, changed conditions, etc). Add any necessary controls to the JSEA. 3. Access to Work may be denied based on an inadequate JSEA, conflicting priorities, and or a lack of information in the application. 4. Where a rejection occurs, identify the issues with the Permit Recipient. This may include suggesting an appropriate re-scheduling time. 8.6 PTW Activation When the Permit Recipient is ready to have the PTW activated they carry out the following tasks: 1. Fill out the PTW 2. Review the JSEA with the work party 3. Fill out any 2nd Tier Permits as required 4. Confirm controls are in place for 2nd Tier permits if required 5. Attach the green Equipment Identification Tag to the equipment work is proposed for, where appropriate 6. Contact the Access Officer to request a signature or a PTW Activation number. A PTW can be activated by either the signature of the Access Officer or a PTW Activation Number. The PTW Activation Number is generated from the Access Log. The Access Officer must carry out the following tasks before activating the PTW: 1. Review the JSEA and check for work conflicts that impact or may be impacted upon by the work proposed under the PTW. 2. Confirm controls are in place for 2nd Tier permits if required. 3. Confirm there is an isolation Instruction if required. The Access Officer then signs the PTW or issues the PTW Activation Number and the Permit Recipient records the number on the PTW to confirm the permit is activated. If there are no Isolations required, the Permit Recipient locks their Personal Danger Lock and Tag and Permit Recipient Tag onto the Permit Board. 8.7 Undertaking Isolations Isolations are discipline specific. Isolations must only be performed within the Worker s discipline specific training, qualifications and competency. As a result, Permit Recipients will require Additional Isolators when working with energy sources requiring multi discipline isolations. Document Number: PRO Version Date: 19/11/2012 Page: 16 of 23

17 Additional Isolators work only under the direction of the Permit Recipient. If isolations are required, the Permit Recipient must undertake a RTHA for the isolations before any are performed. Then they must, carry them out personally, and or coordinate the isolations by following the Isolation Instruction explicitly to: 1. Identify the Isolation Points. 2. Where no effective isolation hardware exists they must submit a work request to install a suitable device and an alternative means of isolation shall be established until the issue can be rectified. 3. Isolate the energy source. 4. Discharge or release stored energy. 5. Lock and tag out the Isolation Points. 6. Sign the Isolation Tags and the relevant sections of the Isolation Instruction. 7. Have isolations checked by a Second Person and have that Worker initial the Isolation Tags and sign the relevant sections of the Isolation Instruction. 8. Test for dead, prove for dead. 9. Secures the Isolation Lock keys in the Permit Board. 10. Locks the Permit Board with their Personal Danger Lock, Tag and Recipient Tag. Once this is complete the energy sources are deemed Positively Isolated. The Permit Recipient then secures the PTW on the Permit Board with the JSEA, Isolation Instruction, 2nd Tier Permits and other relevant documents. Refer to the Energy Tag & Lockout Procedure (PRO-00014) for further explanation of positively Isolating energy sources. 8.8 Issuing 2nd Tier Permits 2nd Tier Permits are required for the following high risk work activities: Confined space work Hot work Trenching and excavation High voltage Fault finding Work at height Grid Mesh, Hand Rail and Flooring Removal If a 2nd Tier Permit is required the 2nd Tier Permit Authority must fill out the required permits and implement the appropriate controls as described in the JSEA for the work. 8.9 Carrying out Work Under an Activated Once all the controls are in place for the work as described in the JSEA the Permit Recipient ensures; 1. The Permit Users sign on to the PTW. 2. The Permit Users lock their personal danger tags and locks onto the Permit Board. 3. The work party carry out a RTHA for the work. Document Number: PRO Version Date: 19/11/2012 Page: 17 of 23

18 4. The Permit Recipient signs the PTW Acceptance section of the PTW form 5. The Permit Recipient signs the Permit User section of the PTW 6. The work party then proceed with the work. 7. If an emergency occurs during the course of the work, follow the steps outlined in the Appendix below Changes to the Work Under the If there is a change to the task and or work conditions after the PTW has commenced (e.g. an emergency, 2nd Tier Permit is required): 1. Work shall immediately cease. 2. The Permit Recipient will immediately contact the Access Officer and in consultation they will determine if the change alters the Scope of Work that the original PTW was issued under. Where the Scope of Work has changed a new PTW shall be obtained. Where there is no change in the Scope of Work but new hazards have been introduced to the job (i.e. 2nd Tier Permit), the JSEA must be reviewed and updated and additional controls implemented prior to the re-commencement of work Break in Work A break in work is any prolonged break in the work other than meal and ablution breaks. The most common example of a break in work is the end of a shift. When a break in work occurs the following takes place: 1. Permit Recipient leaves all isolations in place. 2. Permit Users remove their Personal Danger Locks and Tags from the Permit Board. 3. Permit Users sign off the PTW. 4. Permit Recipient places an Out of Service Lock and Tag onto the Permit Board, explaining the reason for the delay or break in work. 5. Permit Recipient removes his Personal Danger Lock, Tag and Recipient Tag from the Permit Board. 6. The Permit Board remains on site if break is less than one day if the break is longer than 24hrs the PTW board remains at the operational control room. 7. The key to the Out of Service Lock stays with the Permit Recipient if the break is not longer than 24hrs. 8. The key to the Out of Service Lock stays with the Supervisor if the break is longer than a day. For a break in work and a change of Permit Recipient refer to below Change of Permit Recipient From time to time a change in Permit Recipient may be required to complete work under a PTW. Changes to Permit Recipients may occur under the following conditions: Document Number: PRO Version Date: 19/11/2012 Page: 18 of 23

19 Change in Permit Recipient, no Break in Work: 1. Permit Recipient informs Access Officer of change. 2. New Permit Recipient signs onto PTW. 3. New Permit Recipient attaches their Personal Danger Lock and Tag and Permit Recipient Tag to the Permit Board. 4. Old Permit Recipient signs off PTW. 5. Old Permit Recipient removes their Personal Danger Lock and Tag and Permit Recipient Tag from the Permit Board. New Permit Recipient informs all Permit Users of change Change in Permit Recipient, Break in Work: 1. Permit Recipient leaves all isolations in place. 2. Permit Users sign off PTW. 3. Permit Users remove their Personal Danger Locks and Tags from the Permit Board. 4. Permit Recipient places an Out of Service Lock and Tag onto the Permit Board, explaining the reason for the delay or break in work. 5. Permit Recipient signs off the PTW and notifies the Access Officer. 6. Permit Recipient removes their Personal Danger Lock, Tag and Recipient Tag. 7. The Permit Board remains on site if break is less than 24hrs. If the break is longer than 24hrs the PTW board remains at the operational control room. 8. The key to the Out of Service Lock stays with the Supervisor Change in Permit Recipient, Recommencing Work: When the new Permit Recipient is ready to recommence work under the PTW he must: 1. Reapply for site access using the steps outlined above. 2. Review the JSEA for the PTW and implement any controls. 3. Lock his Personal Danger Lock, Tag and Recipient Tag on the Permit Board. 4. Sign onto the PTW. 5. Remove the Out of Service Lock and Tag. Once all the controls are in place for the work as described in the JSEA; 1. The Permit Users lock their Personal Danger Locks and Tags onto the Permit Board. 2. The work party carry out a RTHA and then proceed with the work De-Isolating De-Isolating is the process of removing Isolation Locks and Tags from Isolation Points and re-energising equipment. De-isolating is done at the end of Work and or for Inching and Testing. The following process is followed: 1. Permit Recipient contacts the Access Officer to discuss the implications of Deisolating 2. Access Officer ensures the proposed De-isolation does not produce conflicts in operational and maintenance requirements for the site. Document Number: PRO Version Date: 19/11/2012 Page: 19 of 23

20 3. Access Officer Identifies area specific and process hazards that the Permit Recipient may not be aware of (e.g. other workgroups in the area, chemical storage facilities, changed conditions, etc). 4. Permit Recipient confirms all work has ceased on the equipment and the equipment is ready to be De-isolated. 5. Permit Recipient assembles Additional Isolators as required. 6. Where the Workers who placed the Isolation Locks and Tags cannot be located, the Permit Recipient must assemble Additional Isolators with discipline specific training, qualifications and competency for the De-isolations. 7. Permit Recipient considers all 2nd Tier Permit controls before any attempt to reenergise equipment is made. 8. Permit Recipient undertakes a RTHA (Refer to GDE-00089) for the de-isolation with the Working Party 9. Permit Users then remove their Personal Danger Locks and Tags, sign off the PTW form and remain clear of the area throughout the De-isolation. 10. Permit Recipient removes their Personal Danger Lock, Tag and Recipient Tag 11. Permit Recipient confirms all Persons are in a position of safety before any attempt to re-energise equipment is made. 12. Permit Recipient is in control of the Isolation Lock keys and must carry out the Deisolations personally, and or coordinate the De-isolations by following the Isolation Instruction explicitly to: a. Identify the Isolation Points. b. Remove the Isolation Locks and Tags and sign the relevant sections of the Isolation Instruction. c. Have De-isolations checked by a Second Person and have that Worker sign the relevant sections of the Isolation Instruction. d. De-Isolate the energy sources. e. Recharge the energy sources Inching and Testing If Inching and Testing is required the process below is followed: 1. Permit Recipient must temporarily suspend the PTW by contacting the Access Officer and filling out the Inching and Testing section of the PTW. 2. Permit Users remove their Personal Danger Locks and Tags from the Permit Board and sign off the PTW 3. Permit Recipient removes their Personal Danger Lock and Tags from the Permit Board and signs off the PTW (User Section) 4. Permit Recipient de-isolates the required isolation following 8.13 above 5. Permit Recipient performs a RTHA (Refer to GDE-00089) prior to commencing the testing/inching 6. Permit Recipient follows the Inching and Testing Program on the Isolation Instruction. Once the testing/inching is completed: 1. Permit Recipient either completes work under the PTW following 8.15 below or; Document Number: PRO Version Date: 19/11/2012 Page: 20 of 23

21 2. Permit Recipient contacts the Access Officer to discuss the implications of reisolating the equipment 3. Work party review the JSEA for the PTW and implement any controls. 4. Permit Recipient re-isolates following 8.7 above. 5. Permit Users lock their Personal Danger Locks and Tags onto the Permit Board and sign back onto the PTW 6. Permit Recipient locks their Personal Danger Lock and Tags onto the Permit Board and signs back onto the PTW 7. Work party carry out a RTHA and then recommences the work 8.15 Completion of Work Under the On completion of work the following steps are taken: 1. Permit Recipient confirms all work has finished and all equipment has been de- Isolated where required. 2. Permit Recipient ensures the area has been left safe and clear of tools, equipment and rubbish. 3. Permit Recipient ensures all Permit Users have removed their Personal Danger Locks and Tags and have signed off the PTW if not already done. 4. Permit Recipient removes their Personal Danger Lock, Tag and Recipient Tag if not already done. 5. Permit Recipient signs the PTW Closure section of the PTW. 6. Permit Recipient contacts Access Officer and requests the PTW Cancellation Number. 7. If Access Officer is satisfied that the work area has been left clean and the equipment has been returned to service satisfactorily they sign the PTW Cancellation section of the PTW or issue the PTW Cancellation Number from the Access Log. 8. Permit Recipient records PTW Cancellation Number on PTW if issued. 9. Permit Recipient surrenders all PTW paperwork, including the JSEA, RTHAs, 2nd Tier Permits and Isolation Instruction to the Supervisor for review. 10. Supervisor files all relevant documentation in CIS. 9. Multiple Permits to Work From time to time, multiple work parties may need to work under the same master isolations for their PTWs e.g. plant shutdowns. In this instance multiple Permit Boards may be used following the process below: 1. The Permit Recipient undertakes the master isolation following 8.7 above and secures the master Permit Board with their Personal Danger Lock and Tag and Permit Recipient Tag. 2. The 2nd Permit Recipient locks an Isolation Lock and Tag to the master Permit Board and secures the Isolation Lock key inside the 2nd Permit Board with their Personal Danger Lock and Tag and Permit Recipient Tag. An Isolation Instruction noting the PTW of the Master Board must be attached to this Permit Board 3. The 3rd Permit Recipient locks an Isolation Lock and Tag to the 2nd Permit Board and secures the Isolation Lock key inside the 3rd Permit Board with their Personal Document Number: PRO Version Date: 19/11/2012 Page: 21 of 23

22 Danger Lock and Tag and Permit Recipient Tag. An Isolation Instruction noting the PTW of the Master Board must be attached to this Permit Board This process can continue on to support as many Permit Boards as required. Refer to the diagram below for a description of the process. 10. Disciplinary Action Unauthorised removal of Personal Danger and/or Isolation Locks and Tags and failure to follow correct Isolation Instructions has the potential to cause serious injury or death and/or serious equipment damage. Individuals found to have removed another person s Personal Danger and/or Isolation Lock and Tag or failed to follow the correct Isolation Instruction for isolating equipment will be subject to investigation and potentially the disciplinary action outlined below: Seqwater internal disciplinary action. Penalties as outlined in Electrical Safety and Work Health and Safety Legislation. Document Number: PRO Version Date: 19/11/2012 Page: 22 of 23

23 11. Associated Documents SPE Site Access and Works Control System Overview PRO Operational Site Access Authority Procedure PRO Pre-Approved Work Procedure PRO Energy Tag and Lockout Procedure REG Access Officer Register FRM Access Log Form GDE Conduct a RTHA Guidance Note TEM Job Safety and Environmental Analysis Template TEM Isolation Instruction Template ERP Incident Emergency Response Plan - Responsibilities 12. Appendix 12.1 Emergency Management An emergency is the sudden, unexpected, or impending situation that may cause injury, loss of life, damage to property, and/or interference with the normal activities of a worker or operations and which, therefore, requires immediate attention and remedial action. No further Work shall be performed on that plant/equipment until cleared to return to work. All PTWs are deemed suspended immediately Contact Emergency Services on 000, if required Make the area safe where possible Emergency Services do not require an Access approval Notify the Access Officer for assistance Administer first aid where required until relieved by trained medical relief and supply any relevant details NOTE: Emergency Services have control of the site on arrival. Post emergency: Verbal approval shall be gained from Emergency Services/Seqwater Person-in- Control when it is safe to re-enter the site. Where necessary maintain the state of the site to conduct internal/external investigations. PTW shall be re-assessed and re-issued prior to re-commencement of work. Where a Worker becomes overdue in their communication with the Access Officer refer to Corporate - Incident Emergency Response Plan Responsibilities (ERP-00022). Document Number: PRO Version Date: 19/11/2012 Page: 23 of 23

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

Procedure. Work Health and Safety General construction. Document number: PRO-00005. Description Process Owner Approved for issue. Rev no.

Procedure. Work Health and Safety General construction. Document number: PRO-00005. Description Process Owner Approved for issue. Rev no. Procedure Work Health and Safety General construction Document number: PRO-00005 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE 1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and

More information

WORKING IN CONFINED SPACES GUIDELINES

WORKING IN CONFINED SPACES GUIDELINES WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

WORKING IN THE ELECTRIFIED AREA

WORKING IN THE ELECTRIFIED AREA Network Safety Management System SPECIFICATION SAF/SPC/5178/ELE/NET WORKING IN THE ELECTRIFIED AREA Version 1.0 Effective Date: 12 October 2014 AURIZON COMMERCIAL-IN-CONFIDENCE SAF/SPC/5178/ELE/NET Working

More information

Corporate Standard. Contractor Management

Corporate Standard. Contractor Management Corporate Standard Contents Purpose... 2 Scope... 2 Definitions... 2 Background... 3 Specific Requirements... 4 Responsibilities... 11 Review Date... 11 References... 11 Date Issued July 2010 Management

More information

Corporate Standard. Contractor Management

Corporate Standard. Contractor Management WORK HEALTH & SAFETY CORPORATE STANDARD Accountability Head of People and Culture Corporate Standard Contractor Management 14/6/12 TABLE OF CONTENTS Requirements\Controlled s - Restricted Access\5. Works

More information

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety

More information

SUPPLY CHAIN PREQUALIFICATION PACKAGE

SUPPLY CHAIN PREQUALIFICATION PACKAGE SUPPLY CHAIN PREQUALIFICATION PACKAGE 2015 PREQUALIFICATION AS AN APPROVED SUBCONTRACTOR / SUPPLIER In order for your company to be registered as an approved Vendor with StructureTone Limited, we require

More information

Procedure. Work Health and Safety Incident Notification. Document number: PRO-00388. Description Process Owner Approved for issue. Rev no.

Procedure. Work Health and Safety Incident Notification. Document number: PRO-00388. Description Process Owner Approved for issue. Rev no. Procedure Work Health and Safety Incident Notification Document number: PRO-00388 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004 Estates Division Imperial College London Room 503 Sherfield Building South Kensington Campus London SW7 2AZ, UK Tel: +44 (0)20 7594 9832 Fax: +44 (0)20 7594 9050 r.mayne@imperial.ac.uk www.imperial.ac.uk

More information

Control of Hazardous Energy (Lockout / Tagout)

Control of Hazardous Energy (Lockout / Tagout) WAUKESHA COUNTY TECHNICAL COLLEGE Control of Hazardous Energy (Lockout / Tagout) Release Date: March 26, 2012 Revision Date: March 26, 2012 Revision Level: 1 TABLE OF CONTENTS Purpose... 1 Scope... 1 Responsibilities...

More information

Page85. Lock-out Tag-out Plan

Page85. Lock-out Tag-out Plan Page85 Lock-out Tag-out Plan Page86 Lock-out / Tag-Out Plan Table of Contents 1. Policy 2. Purpose 3. Scope 4. General Procedures 5. Application of Control Procedure 6. Release from Control Procedure 7.

More information

Guide Document for Development of WHS Management Plans

Guide Document for Development of WHS Management Plans DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.147 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) SECTION: 2400

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.147 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) SECTION: 2400 OSHA REGULATION: 29 CFR 90.7 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) DATE: 0/5/2008 DATE: /2/202 A. POLICY. This procedure follows requirements set forth in 29 CFR 90.7. 2. It is the policy

More information

ASBESTOS REMOVAL LICENCE ASBESTOS NOTIFICATIONS

ASBESTOS REMOVAL LICENCE ASBESTOS NOTIFICATIONS GUIDE FOR APPLICANTS ASBESTOS REMOVAL LICENCE ASBESTOS NOTIFICATIONS TABLE OF CONTENTS INTRODUCTION... 2 WHY YOU NEED A LICENCE... 2 WHY YOU NEED TO NOTIFY... 2 LICENCE TYPES... 2 SCOPE... 2 WHO MAY APPLY

More information

Health and safety policy

Health and safety policy 1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and

More information

Health and Safety Policy and Procedures

Health and Safety Policy and Procedures Health and Safety Policy and Procedures Health & Safety Policy & Procedures Contents s REVISION AND AMENDMENT RECORD : Summary of Change Whole Policy 4.0 05 Nov 08 Complete re-issue Whole Policy 4.1 10

More information

Asbestos removal and licensing

Asbestos removal and licensing Applicant Guide Asbestos removal and licensing Includes: Asbestos removal and asbestos assessor licence and notifications of asbestos removal work, asbestos fibres and emergency demolition of structures

More information

Accident/Incident Investigation & Reporting Procedure

Accident/Incident Investigation & Reporting Procedure Accident/Incident Investigation & 1. Overview The recognises its obligation to ensure that all accidents and incidents are reported, recorded and investigated. We are committed to identifying corrective

More information

GHD EPCM Standard operating procedure Working at height May 2013 v1

GHD EPCM Standard operating procedure Working at height May 2013 v1 GHD EPCM Standard operating procedure Working at height May 2013 v1 Table of contents 1. Purpose 2. Scope 3. Duty of care 4. Lifesaving rules; An overview 5. Roles and responsibilities 4.1 Operating centre

More information

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Owner Name Title Signature Steve White Head of Network Control and Operations Date 16 February 2016 Authoriser Name

More information

Contractor Environment, Health and Safety Management Plan

Contractor Environment, Health and Safety Management Plan EHSMS10 Contractor and Supplier EHS Management Contractor Environment, Health and Safety Management Plan Purpose Guidelines Record Keeping This template provides an example to Santos Contractors of the

More information

Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147

Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Contents I. Introduction II. Scope and Application III. Definitions IV. Lockout/Tagout Manual V. Energy Control Procedures 1. Applying Energy

More information

Golden Safety Rules booklet. No one gets hurt, no incidents

Golden Safety Rules booklet. No one gets hurt, no incidents Golden Safety Rules booklet No one gets hurt, no incidents The Golden Safety Rules exist to keep you safe There s nothing more important than your safety and that of your workmates. That s why we ve adopted

More information

Management of Contractors and Suppliers Procedure

Management of Contractors and Suppliers Procedure Management of Contractors and HSE P1101 Table of Content 1 DOCUMENT CONTROL... 2 2 PURPOSE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 ROLES AND RESPONSIBILITIES... 5 6 PROCESS DETAILS... 9 6.1 Confirm Need

More information

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES

WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES WHS UNIT WORKPLACE HEALTH AND SAFETY AUDITING GUIDELINES Contents 1 Purpose... 1 2 Scope... 1 3 Definitions... 1 4 Responsibilities... 1 4.1 WHS Unit... 1 4.2 Auditor(s)... 1 4.3 Managers of Faculties

More information

RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016

RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 June 2016 RMM 306 Lockout/Tagout (LOTO) Program for the Control of Hazardous Energy Page 2 3 Related Documents 3.1 Occupational Health and Safety Act, R.S.O. 1990 3.2 Regulations for Industrial Establishments, R.R.O.

More information

4.05e WHS Guidelines for Incident Investigation Procedures Page 1 of 7

4.05e WHS Guidelines for Incident Investigation Procedures Page 1 of 7 Page 1 of 7 1 Purpose It is a legal requirement under the NSW Work Health and Safety Act 2011 and NSW Work Health and Safety Regulation 2011 to identify hazards, assess the risk of those hazards, implement

More information

INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations...

INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations... March 2006 INTRODUCTION... 3 1.0 Purpose... 4 2.0 Policy... 4 Exception for Short-Term Workplace Visits... 4 Relevant Legislation and Regulations... 5 Definitions... 5 Contractor Safety Coordination Overview...

More information

Contractor Safety Management

Contractor Safety Management 1.0 Introduction Memorial University will ensure that a diligent contractor management process is established. This procedure establishes requirements for contract administration and oversight of contractor

More information

ASBESTOS MANAGEMENT PLAN

ASBESTOS MANAGEMENT PLAN ASBESTOS MANAGEMENT PLAN PREPARED BY: Scott Gregory: Estates - Property Services DATE: 18/04/2014 STATUS: Draft ISSUE: 2014 (02) September 2014 NEXT REVISION DATE: April 2014 Contents 1.0 Introduction

More information

WHS Policies and Procedures Package

WHS Policies and Procedures Package WHS Policies and Procedures Package The following is an extract to highlight the style and layout of this publication, as well as a snapshot of the content. Some samples may not be included in their entirety

More information

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM

GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM FEBRUARY 2016 2 Contents Introduction... 4 Scope and objectives... 5 Scope... 5 Objectives... 5 Responsibilities... 5 The role of the licensee

More information

SITE CONTRACTOR PROCEDURES

SITE CONTRACTOR PROCEDURES SITE CONTRACTOR PROCEDURES Asset Collection Type B Assets are considered High risk ; the site activities must be in accordance with Graysonline contractor procedures and are to be collected by appointment

More information

Customer Installation Safety Plan. March 2015

Customer Installation Safety Plan. March 2015 Customer Installation Safety Plan March 2015 Document History Issue No. Date Approved By Summary of Changes 1 June 2014 Chief Engineer Updated and revised in line with requirement for biennial review under

More information

Policy for the Management of Asbestos in Buildings

Policy for the Management of Asbestos in Buildings in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably

More information

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY 1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment

More information

Asbestos Removal and Assessor Licensing Information

Asbestos Removal and Assessor Licensing Information Asbestos Removal and Assessor Licensing Information January 2013 Version 1.0 - GB366 1 2 Contents Introduction 5 Why you need a licence 5 Why you need to notify 5 Licence types 5 Class A asbestos removal

More information

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK INSTRUCTION ISOLATION OF A TREATED WATER STORAGE POINT ON THE WATER NETWORK

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK INSTRUCTION ISOLATION OF A TREATED WATER STORAGE POINT ON THE WATER NETWORK ISOLATION OF A TREATED WATER STORAGE POINT ON Document Title: Document Reference: Work Instruction Isolation of a Treated Water Storage Point on the Water Network DOM-WN-WIN-00000301 Approved By: Asset

More information

Health & Safety Management System Manual

Health & Safety Management System Manual Health & Safety Management System Manual Document Information Document Number Description HSMSM This manual describes the Health & Safety Management System elements of the Integrated Management System

More information

Excavation & Trenching Procedure

Excavation & Trenching Procedure Excavation & Trenching 1. Overview The will ensure, as far as is reasonably practicable, that the conduct of work relating to excavation and trenching will not be harmful to the health and safety of employees

More information

Asbestos licensing and notification guide for applicants

Asbestos licensing and notification guide for applicants Asbestos licensing and notification guide for applicants Use this guide if you are: applying for an asbestos removal work licence applying for an asbestos assessor licence notifying of asbestos removal

More information

Safety Systems Review Facilities Management Guidance and specification Version 1 2014

Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Safety Systems Review

More information

Guidelines for. the employment EXTERNAL COMPANIES

Guidelines for. the employment EXTERNAL COMPANIES Guidelines for the employment of EXTERNAL COMPANIES on the grounds of Institut für Mikroelektronik Stuttgart Allmandring 30a 70569 Stuttgart Contents 1. Purpose and objective... 3 1.1 General directions...

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Procedure Approved: 09/07/2013 Next Review: 09/07/2015 1. Overview The District council of Mount Remarkable Council is committed to engaging quality Contractors who have a sound understanding and commitment

More information

Tremline Pty Ltd trading as The Hills Bark Blower

Tremline Pty Ltd trading as The Hills Bark Blower JSA No: Rev: 10011 Date: 10010 ABN 1 07 880 6 Website: wwwbarkblowercomau Job Number Start Time: Vehicle : Max Length Hose Date: Company Name: Product: Quantities Depth Job site address: Description of

More information

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015 WORK AT HEIGHT STFC Safety Code No 9 Rev. 1.4, Issued April, 2015 Note - This document may have been superseded by a more recent version. Revisions 1 Initial Launch November 2007 1.1 Amendments to training

More information

The Electrical Contractor Safety Program Guide

The Electrical Contractor Safety Program Guide The Electrical Contractor Safety Program Guide September 2013 Electrical Hazard Warning Sign Disclaimer Whilst this guide endeavors to provide general information on work health and safety issues relating

More information

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS

AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS Conducted By GASKIN CONSTRUCTION SERVICES PTY LTD TABLE OF CONTENTS SECTIONS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

EVENT APPLICATION FORM MAJOR EVENT (Over 50 Attendees)

EVENT APPLICATION FORM MAJOR EVENT (Over 50 Attendees) DCBW Event Form 1 File Number: Record Number: 1. EVENT ORGANISER DETAILS Organisation: Address: EVENT APPLICATION FORM MAJOR EVENT (Over 50 Attendees) Contact Person: Phone: After Hours: E-mail: Position

More information

Hazard/Incident Recording, Reporting and Investigation

Hazard/Incident Recording, Reporting and Investigation Hazard/Incident Recording, Reporting and Investigation Power and Water Corporation Procedure 1 Purpose... 1 2 Scope... 1 3 References... 2 4 Roles and Responsibilities... 2 5 Definitions... 6 6 Records...

More information

The Management of Asbestos containing Materials

The Management of Asbestos containing Materials The Management of Asbestos containing Materials Status Owner Approval by University Court Draft Head of Estates and Building 1 Purpose... 1 2 Scope... 3 3 Principles... 4 4 Procedure... 5 5 Accountabilities...

More information

Conditions of accreditation as an assessor for high risk work classes

Conditions of accreditation as an assessor for high risk work classes Conditions of accreditation as an assessor for high risk work classes. Contents Section 1 - Purpose... 3 Section 2 - Conditions of accreditation... 3 General requirements... 4 Conduct as an assessor...

More information

To establish a process to control all UON Health and Safety Management System Framework

To establish a process to control all UON Health and Safety Management System Framework UON Health and Safety Procedure: HSP 9.1 Records, Documents and Document Control 1. Purpose To establish a process to control all UON Health and Safety Management System Framework policies, elements, procedures,

More information

Management of Health and Safety for Work and Services Contractors Policy June 2010

Management of Health and Safety for Work and Services Contractors Policy June 2010 June 2010 Contents 1. Introduction 3 2. Policy Statement 4 3. Policy Objectives 5 4. Application 6 5. Organisational Responsibilities 7 6. Glossary of Terms 11 7. Authorised Directors Appendix 1 2 www.surrey.ac.uk

More information

Guide for applicants for asbestos removal and asbestos assessor licences and notifications

Guide for applicants for asbestos removal and asbestos assessor licences and notifications Guide for applicants for asbestos removal and asbestos assessor licences and notifications of asbestos removal work, asbestos fibres and emergency demolition of structures containing asbestos March 2013

More information

Noosa Jazz Festival Terms and Conditions Food and Market Stalls

Noosa Jazz Festival Terms and Conditions Food and Market Stalls Noosa Jazz Festival Terms and Conditions Food and Market Stalls Welcome to the Noosa Jazz Festival! As Noosa Shire s second longest-running event, the Noosa Jazz Festival has a proven track record of delivering

More information

Vendor Management Program

Vendor Management Program The Corporation of the City of Kawartha Lakes is committed to the provision of a safe and healthy work environment for its employees, contractors and visitors. To promote this type of environment, the

More information

SAFETY and HEALTH MANAGEMENT STANDARDS

SAFETY and HEALTH MANAGEMENT STANDARDS SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents

More information

CONTRACT CONDITIONS FOR LOGISTICS (2014)

CONTRACT CONDITIONS FOR LOGISTICS (2014) CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member

More information

This procedure applies to all DECS employees, students and others in worksites, schools, preschools and departmental offices. 1.0 PURPOSE...

This procedure applies to all DECS employees, students and others in worksites, schools, preschools and departmental offices. 1.0 PURPOSE... OCCUPATIONAL HEALTH SAFETY AND WELFARE INJURY / INCIDENT REPORTING and INVESTIGATION PROCEDURE SCOPE This procedure applies to all DECS employees, students and others in worksites, schools, preschools

More information

LOCK-OUT / TAG-OUT SAFETY TRAINING

LOCK-OUT / TAG-OUT SAFETY TRAINING LOCK-OUT / TAG-OUT SAFETY TRAINING Introduction Welcome to Lock-out Tag-out Training "So I m on the job one day, doing some repair on a cutting machine.replacing a guide on the table. Pretty routine everything

More information

WHS record keeping requirements

WHS record keeping requirements WHS record keeping requirements The table below provides details of the record keeping requirements in the Model Work Health and Safety Regulation, covering the following areas: Air-borne contaminant levels

More information

Six steps to Occupational Health and Safety

Six steps to Occupational Health and Safety Six steps to Occupational Health and Safety This booklet gives basic guidelines for workplace health and safety systems to help industry in NSW comply with the "duty of care" principle outlined in the

More information

Owner-User Pressure Equipment Integrity Management Requirements

Owner-User Pressure Equipment Integrity Management Requirements the pressure equipment safety authority Owner-User Pressure Equipment Integrity Management Requirements AB-512 Edition 2, Revision 0 Issued 2015-06-25 Owner-user Pressure Equipment Integrity Management

More information

LOCK-OUT/TAG-OUT PROGRAM I. Purpose

LOCK-OUT/TAG-OUT PROGRAM I. Purpose LOCK-OUT/TAG-OUT PROGRAM I. Purpose This procedure establishes requirements for the lockout of energy isolating devices. It should be used to ensure that the machine or piece of equipment is isolated from

More information

LOCKOUT/TAGOUT PROGRAM. Table of Contents

LOCKOUT/TAGOUT PROGRAM. Table of Contents Western University of Health Sciences IIPP SUB-PROGRAM LOCKOUT/TAGOUT PROGRAM Table of Contents 1.0 INTRODUCTION 1 2.0 PURPOSE 1 3.0 RESPONSIBILITIES 1 Supervisors 1 Employees 1 4.0 TRAINING 2 5.0 WRITTEN

More information

WHS CONTRACTOR MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE MANAGEMENT PROCEDURE 1. OVERVIEW The Flinders Ranges Council as part of its commitment under its WHS Contractor Management Policy, recognises its obligation to: Ensure, so far as is reasonably practicable,

More information

WORKPLACE REHABILITATION & RETURN TO WORK QUEENSLAND

WORKPLACE REHABILITATION & RETURN TO WORK QUEENSLAND WORKPLACE REHABILITATION & RETURN TO WORK QUEENSLAND POLICY STATEMENT Kelly Services is committed to the prevention of work-related injuries and illnesses by providing a safe working environment through

More information

No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974

No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974 The Police Treatment Centres Health and Safety Legal Compliance Register No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974 2.

More information

Incident Investigation Procedure

Incident Investigation Procedure Incident Investigation Procedure Document Number 001001 Date Approved 27 November 2012 1 Introduction When a serious incident occurs there shall be a review of the system which is in place to manage the

More information

Procedure: OHS CONTRACTOR MANAGEMENT

Procedure: OHS CONTRACTOR MANAGEMENT Procedure: OHS CONTRACTOR MANAGEMENT. Purpose This procedure outlines the occupational health and safety (OHS) requirements for the management of contractors engaged to perform tasks or services for Greater

More information

1. Purpose... 3. 2. Scope... 3. 3. Roles and responsibilities... 3

1. Purpose... 3. 2. Scope... 3. 3. Roles and responsibilities... 3 Contents 1. Purpose... 3 2. Scope... 3 3. Roles and responsibilities... 3 4. Procedure... 4 4.1 Overview... 4 4.2 Activities not to be conducted alone... 4 4.3 Minimising or eliminating the need for remote

More information

Construction and Civil Work Management

Construction and Civil Work Management STANDARD LME-12:001901 Uen Rev A Contents 1 Introduction... 3 2 Definitions... 3 3 Requirements... 4 3.1 General... 4 3.2 Responsibilities... 4 3.3 OHS Safety Plan... 5 3.4 Start of Construction Phase...

More information

Communication of Health and Safety Policy and Information

Communication of Health and Safety Policy and Information Modules 1 4 1. Communication of Health and Safety Policy and Information 2. Allocation of Responsibility/Accountability for Health and Safety 3. Purchasing Controls 4. Contractors Communication of Health

More information

CO-LOCATION SPACE SCHEDULE OF SERVICES Schedule 1

CO-LOCATION SPACE SCHEDULE OF SERVICES Schedule 1 CO-LOCATION SPACE SCHEDULE OF SERVICES Schedule 1 1. THIS SCHEDULE - INTERPRETATION 1.1 The terms of this Co-Location Space Schedule of Services ( Schedule 1 ) apply together with, in addition to and form

More information

KUC HSEQ MS Element 7 Compliance Procedure Supplier and Contractor Management Effective Date: 08 /12 Document Number: HSEQSOP07-001 Rev: 01

KUC HSEQ MS Element 7 Compliance Procedure Supplier and Contractor Management Effective Date: 08 /12 Document Number: HSEQSOP07-001 Rev: 01 PURPOSE: SCOPE: This Element provides requirements associated with procured materials, equipment, services, and labor to ensure HSEQ risks are managed effectively. The Element is supported by the KUC Contractor

More information

section 5 machine guarding and lockout

section 5 machine guarding and lockout section machine guarding and lockout This section covers ways to physically protect people working in and around machinery. It includes information on: machinery guards lockout systems emergency stop confined

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

Project & Task Work Health and Safety Risk Management Procedure

Project & Task Work Health and Safety Risk Management Procedure Project & Task Work Health and Safety Risk Management Procedure Related Policy Work Health and Safety Policy Responsible Officer Executive Director Human Resources Approved by Executive Director Human

More information

CONTRACTOR INDUCTION HANDBOOK

CONTRACTOR INDUCTION HANDBOOK CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with

More information

SUB CONTRACTORS AGREEMENT

SUB CONTRACTORS AGREEMENT DATED NR EVANS AND SON LIMITED and SUB CONTRACTORS AGREEMENT NR EVANS & SON LIMITED LLWYN YR EOS CROSS HANDS BUSINESS PARK LLANELLI CARMARTHENSHIRE SA14 6RA CONTRACT TERMS AND CONDITIONS SUB-CONTRACTORS

More information

CCE-TRK-SPN-010 Specification for Movement Monitoring of Railway Track

CCE-TRK-SPN-010 Specification for Movement Monitoring of Railway Track Reference No. CCE-TRK-SPN-010 Version 1.0 Operative Date 02/08/2011 Status LIVE Prepared by Nick West, Colin Hedderly Checked by Cathal Mangan Approved by Éamonn Ballance CCE DEPARTMENT TECHNICAL SPECIFICATION

More information

SAFETY AND HEALTH PROGRAM

SAFETY AND HEALTH PROGRAM PROGRAM NUMBER NO. PAGES 05-005 10 REVISION ISSUE DATE Revision 2 11/1/2005 SAFETY AND HEALTH PROGRAM Confined Space Entry 1.0 INTRODUCTION Confined Space Entry is a serious workplace hazard, capable of

More information

ASBESTOS MANAGEMENT POLICY

ASBESTOS MANAGEMENT POLICY ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...

More information

Lockout / Tagout Program

Lockout / Tagout Program Lockout / Tagout Program Table of Contents Page Scope... 2 Definitions... 2 Authorization... 3 Responsibilities... 4 Compliance and Enforcement... 4 When to Lockout/Tagout (LOTO)... 5 Lockout Procedure...

More information

OHSMS Implementation Guide

OHSMS Implementation Guide OHSMS Implementation Guide Developed by the Employee Health Unit, Department of Education and Early Childhood Development and Marsh Pty Ltd. Published by the Employee Health Unit, Department of Education

More information

Lockout - Tagout. Control of Hazardous Energy OSHA Standard 1910.147

Lockout - Tagout. Control of Hazardous Energy OSHA Standard 1910.147 Lockout - Tagout Control of Hazardous Energy OSHA Standard 1910.147 You will learn Purpose of Lockout-Tagout Requirements for LOTO Types of Hazardous Energy Procedures for LOTO Types of Energy Electrical

More information

Contractor s Safe Working Agreement

Contractor s Safe Working Agreement Contractor s Safe Working Agreement This statement provides details on how I/we, the Trade Contractor will manage the health and safety hazards associated with my/our work. ASSESSING WORKPLACE HEALTH AND

More information

Handbook 16. Handbook 16. AC electrified lines. GE/RT8000/HB16 Rule Book

Handbook 16. Handbook 16. AC electrified lines. GE/RT8000/HB16 Rule Book GE/RT8000/HB16 Rule Book Uncontrolled When Printed Handbook 16 AC electrified lines Handbook 16 Issue 3 September 2015 Comes into force 05 December 2015 This handbook is for those personnel who need to

More information

Implementation and Customer Services ( ICS") Installation Services Standard Terms and Conditions of Supply. (Effective September 2013)

Implementation and Customer Services ( ICS) Installation Services Standard Terms and Conditions of Supply. (Effective September 2013) Implementation and Customer Services ( ICS") Installation Services Standard Terms and Conditions of Supply 1. General (Effective September 2013) This web page content defines the standard terms and conditions

More information

How To Monitor Safety Management System Performance

How To Monitor Safety Management System Performance Guidance Note Performance standards and indicators Advice for operators of major hazard facilities on developing meaningful and useful performance standards and indicators for the Safety Management System

More information

Administrative Procedure. Asbestos

Administrative Procedure. Asbestos Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour

More information

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD Birchall Road Knowsley Industrial Estate Liverpool L33 7TG TABLE OF CONTENTS STATEMENT OF SAFETY POLICY... 3 STATEMENT OF INTENT... 4 HEALTH & SAFETY

More information

BWC Division of Safety and Hygiene

BWC Division of Safety and Hygiene BWC Division of Safety and Hygiene A SAMPLE LOCKOUT/TAGOUT PROCEDURE A good Lockout/Tagout Procedure, at a minimum, should contain the following elements: 1. All maintenance personnel shall be provided

More information