1 Ageing and life extension April 7th workshop
2 Background NPD recommended NORSOK AGn to start developing guidelines for life extension (2000). NPD initiated a PhD study on ageing and life extension of offshore facilities (2002) NPD proposed to establish working groups in ISO TC67 (2002). Ageing rigs initiative from HSE and NPD (2004) PSA gave ageing and life extension main priority (2005) PSA requested an overview from operators of facilities and their status with respect to design life and need for life extension (2006). PSA requested an initiative from OLF towards developing procedures for life extensions (2006)
3 Facilities on the Norwegian continental shelf Number Installation year /04/2010 3
4 Strategy Improve handling of applications for life extensions. - To be submitted 1 year before end of design life period as stated in the PDO (Plan for development and operation). Improve regulation and standards for life extensions. Increase the knowledge and competency about ageing and aspects of ageing that may reduce safety. - R&D projects, evaluation of industry activity, overview of other industries handling of ageing and life extension. Increase the awareness related to ageing and life extension challenges in our industry. Establish database on facilities with installation date, design life, and life extensions.
5 Main priorities of the PSA R&D to better understand aspects of ageing that may reduce safety of facilities. - SINTEF, Cranfield University / Ocean Structures, Aalborg University, etc In cooperation with the operators association (OLF) develop standards and guidelines for life extension. Developing a data base with information on installation date, design life and other issues concerning life extension for facilities in Norwegian petroleum activities. Development of internal procedures and check-lists for consideration of life extension applications. Participating in and organising workshops, conferences, meeting etc. to inform about issues related to ageing and life extension. Collaborating with relevant authorities (NMD, HSE, MMS, SodM, etc.)
6 Main Document OLF guideline No. 122 Published in June 2008 Sub- Documents Permanente structures Offshore Structures Published May 2008 Drilling and Well Systems Check List Published in May 2008 Drilling systems and Well integrity, including conductors, BOP and down hole equipment Export and intra field Pipelines and risers. Transport Systems Process Systems Emergency Shutdown, Evacuation, Barriers, Fire and Gas Detection and other safety systems. Living Quarters, Escape Ways, Material and Chemicals Handling, Control Rooms, Man machine interfaces. Technical Safety Systems,,Working Environment and Risk management Underwater installations Consent Applications for Life Extension of Facilities are submitted to the Petroleum Safety Authority (PSA) Norway and Norwegian Petroleum Directorate (NPD).
7 Life extension applications Åsgard C (2005) until 2018 Ula (2005) until 2028 Ekofisk 2/4-B (2005) until 2015 Statfjord A (2007) until 2028 Valhall QP, PCP & DP (2007), QP until 2010, PCP and DP till 2015 Hod (2008) until 2015 Norpipe oil (2008) until 2028 Gyda (2009) until 2030 Veslefrikk A & B (2009) until 2020 Ekofisk (2009), - 2/4-H and 2/4-Q until 1 Sept 2013, - 2/4-C until 1 Sept 2013 (2028), - 2/4-FTP until 31 Dec 2015, - 2/4-BS01, 2/4-W and 2/4-SF until 31. Dec 2012, - 2/4-A until 31 Dec 2016, - 8 pipeline between 2/4-C and 2/4-B until 2028, - 12 pipeline for water injection from 2/4-K to 2/4-W until 31 Dec 2012 (2028) Norpipe gas and B11 (2009) until
8 Major challenges Decisions are not made when application is submitted. - Plans to study health and safety issues on the facility are described, rather than concluding on what the operator will do with respect to health and safety in the life extension period. - Applications are being submitted before it has been decided whether a life extension will be funded by the production license. - Several solutions to identified health and safety issues are still being put on the table when applications are being submitted. Lack of standards for application and comparison
9 Main priorities of the PSA R&D to better understand aspects of ageing that may reduce safety of facilities. - SINTEF, Cranfield University / Ocean Structures, Aalborg University, etc In cooperation with the operators association (OLF) develop standards and guidelines for life extension. Developing a data base with information on installation date, design life and other issues concerning life extension for facilities in Norwegian petroleum activities. Development of internal procedures and check-lists for consideration of life extension applications. Participating in and organising workshops, conferences, meeting etc. to inform about issues related to ageing and life extension. Collaborating with relevant authorities (NMD, HSE, MMS, SodM, etc.)
10 Evaluation of facility History: -Original design and fab -Actural degradation and trends -Incidents -Inspecion results -Changes to facility As-is condition: -Evaluate condition -Collect information (design, fabrication, installation & operation) -Identify deviations and gaps from regulations -New knowledge Future challanges: -Ageing-related failure modes and ageing of barriers -Changes to environment -Spare parts -Competence Future use: -Planned changes and modifications to facility -Planned changes in operation of the facility -Changes in risk due to modifications Ageing relevant for this SSC? * Maintenance according to existing plans and methods. Guiding documents and principles: -Present regulation -Risk reduction -ALARP -BAT -Continuous improvement Assess integriy: -Analyse and assess safety in life extension -Evaluate mitigations Criticality evaluation: -Main safety functions? -Barrier? -Inspectable? Make Decisions: -Mitigating measures -Operational restrictions -Future maintenance Maintenance that account for ageing, system effects of ageing, and the increasing likelihood of failures due to ageing. Documentation of technical and operational integrity. Plan for implementation of measures and modifications. Maintenance plan and system of KPI s and acceptance levels. 12/04/
11 Is it possible to inspect and mitigate? Knowledge? Good Some Poor Replace Measures? Some No
12 AGEING MANAGEMENT A. Material degradation B. Obsolescence C. Organisational issues - Material properties - Operation conditions - Environmental conditions - Maintenance practices - Equipment out of date - New needs - New technology - New requirements - Reorganisation - Ageing of personnel - Transfer of knowledge 12/04/
13 Structure of Contents Ageing and life extension management General part Analyses of material degradation Obsolescence and organisational issues Specific part Wells Pipelines Risers Subsea production systems Topside process equipment Safety systems Material handling and cranes Challenges and Lacks of knowlege 13
14 Knowledge gaps (SINTEF report) Understanding and assessing degradation mechanisms and modelling of degradation mechanisms for various materials and equipment. Developing and applying reliable methods for subsea inspection and monitoring. Understanding and increasing awareness of common cause failures of equipment due to ageing. Assessing the effects of and utilising methods for monitoring of facility loads. Understanding ageing of electronic equipment and cabling. Optimising test interval for safety systems with respect to material degradation due to ageing. Understanding the results of testing, inspection and monitoring of process equipment with respect to degradation mechanisms. Understanding the consequences of combining old and new equipment. Assessing the effects of subsidence on relevant SSC, such as structure, helideck and free fall lifeboats. 14
15 Recommended further research and development (SINTEF report) Analyses of degradation mechanisms of critical systems, comprising: - Modelling of main degradation mechanisms, also considering the combined effect of various degradation mechanisms, common cause failures and effect of operational conditions. - Development of systems for data collection and use of field experience with degradation failures. Developing a general guideline for design of the life extension processes encompassing the entire facility. Improving maintenance management systems for ageing and life extension so that all three ageing aspects are being processed in parallel, in order to - evaluate and improve the operator s maintenance systems prior to and during life extension. - Improve awareness and overall knowledge of the SSC on the facility, e.g. combinations of old and new equipment, availability of spare parts, common cause failures, new types of operation and new technology. 15
16 Further work in the PSA Evaluate needs for updating rules and regulations. Collaborate with operators and operators association to update regulation and standards. Further development of the SISU data base Further studies related to working environment on ageing facilities International standardisation and further collaboration with authorities in the UK, US, etc. Continuation of presenting and interchanging findings and results in relevant forums
17
18 Myth 1: Why life extension it s just continuing normal operation. 12/04/
19 Myth 2: Life extension is just maintenance. AGEING MANAGEMENT A. Material degradation B. Obsolescence C. Organisational issues - Material properties - Operation conditions - Environmental conditions - Maintenance practices - Equipment out of date - New needs - New technology - New requirements - Reorganisation - Ageing of personnel - Transfer of knowledge 12/04/
20 Myth 3: If the facility is safe today, it is also safe tomorrow 12/04/
21 Myth 4: Life extension is not a safety issue, it is just a cost issue. Partly true, but misleading It will cost to keep the safety to the expected level (mitigations, repair, improvements, maintenance). Safety is the primary factor! 12/04/
22 Myth 5: There is no statistics that indicate that ageing is a problem. There is a lot of evidence that ageing is a problem, including: - Crack history on ageing ships and rigs - Subsidence - Accidental damages - Corrosion - Etc. 12/04/
Subsea Standard & Rules What is Subsea?
Subsea Standard & Rules What is Subsea? MEK4450 Standards and Rules Bjørn Søgård, Anders Husby Goals General knowledge of subsea development and production systems Understand the building blocks forming
More informationGoliat Barrier Management
Goliat Barrier Management ESRA Norge; March 25, 2015 www.eninorge.com Eni: Ole Rekdal Safetec: Helene Ness Hansen PL 229 Goliat Location and Partnership License awarded in 1997 Present licensees Eni Norge
More informationRefleksjoner rundt alvorlige hendelser i petroleumsindustrien i et risikostyringsperspektiv
Refleksjoner rundt alvorlige hendelser i petroleumsindustrien i et risikostyringsperspektiv Presentasjon i Tekna-uken 2012 Professor II Jan Erik Vinnem Universitetet i Stavanger jev@preventor.no Overview
More informationOFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017
STRATEGIC CONTEXT OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017 1 This strategy sets out how HSE s Energy Division will regulate health and safety of the offshore oil and gas industry operating on the
More information- Translation from Norwegian -
Page 1 of 63 Guidelines for plan for development and operation of a petroleum deposit (PDO) and plan for installation and operation of facilities for transport and utilisation of petroleum (PIO). 4 February
More information13. FPSO Operational Problems Don Smith, OGP
OGP Marine Risks Workshop Proceedings 13. FPSO Operational Problems Don Smith, OGP FPSO Operational Problems Don Smith OGP Analysis of Accident Statistics for Floating Monohull and Fixed Installations
More informationANNUAL REPORT 2008. The Draugen field that is operated by Norske Shell started production in 1991 and is operated from Kristiansund.
ANNUAL REPORT 2008 BP Norge AS (BPN) is owned by BP Global Investments Ltd and Amoco Norway Oil Company. Both are part of the BP Group which itself is one of the largest integrated Oil & Gas Companies
More informationSjøoffiserskonferansen i Bergen. Welcome! INNOVATION FOR WORLD CLASS CUSTOMERS. Innovation Technology Reliability. xervo.dk
Sjøoffiserskonferansen i Bergen Welcome! INNOVATION FOR WORLD CLASS CUSTOMERS xervo.dk Kent Lynggaard Country Manager Norway Xervo Company Profile Set the scene Working with the Rules & Regulations Lifeboat
More informationNORSOK STANDARD Z-013 Rev. 2, 2001-09-01. Risk and emergency preparedness analysis
NORSOK STANDARD Z-013 Rev. 2, 2001-09-01 Risk and emergency preparedness analysis This NORSOK standard is developed by NTS with broad industry participation. Please note that whilst every effort has been
More informationRisk management and major accident potential in a safe late phase. Experience from Supervisory Activities.
Risk management and major accident potential in a safe late phase. Experience from Supervisory Activities. Ingvill Hagesæther Foss Director of supervisory activities Kjell Arild Anfinsen Supervision Coordinator
More informationPRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA
PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA Table of content 1. INTRODUCTION... 2 1.1. Purpose of document... 2 1.2. Det norske oljeselskap... 2 1.3. HSE... 2 2. ABOUT THE IVAR AASEN FIELD... 2 2.1.
More informationAOG 2015 Acoustic System to Monitor Wellhead Fatigue in Real-time. March 12 th 2015. www.pulse-monitoring.com
AOG 2015 Acoustic System to Monitor Wellhead Fatigue in Real-time March 12 th 2015 Agenda Monitoring method currently used Online monitoring New generation wireless monitoring Benefits of active monitoring
More informationDEEPWATER HORIZON. Summary report
1 Summary report DEEPWATER HORIZON Lessons learned and follow-up A Norwegian Oil Industry Association (OLF) report with contributions from the Norwegian Clean Seas Association for Operating Companies (NOFO)
More informationANNUAL REPORT 2007. Page 1
ANNUAL REPORT 2007 BP Norge AS carries out exploration and production of oil and gas from the Norwegian Continental Shelf. The company's head office is in Stavanger. Profit The petroleum revenues for 2007
More informationGuidelines the DNV way
Guidelines the DNV way for safe service elastomers in oil & gas Jon Huse Guidelines the DNV way for safe service elastomers Content: What is a DNV-guideline? Examples of DNV-guidelines - Qualification
More informationAPPLICATION OF IEC 61508 AND IEC 61511 IN THE NORWEGIAN PETROLEUM INDUSTRY
1 of 159 APPLICATION OF IEC 61508 AND IEC 61511 IN THE NORWEGIAN PETROLEUM INDUSTRY 2 of 159 Table of content FOREWORD...5 1 INTRODUCTION...6 1.1 SCOPE AND PURPOSE OF DOCUMENT...6 1.2 RISK REDUCTION, SIS
More informationAnnouncement on Providing Guarantee for the Subsidiary Company - Offshore Oil Engineering (Qingdao) Co., Ltd. by Offshore Oil Engineering Co., Ltd.
Announcement on Providing Guarantee for the Subsidiary Company - Offshore Oil Engineering (Qingdao) Co., Ltd. by Offshore Oil Engineering Co., Ltd. Important Notes The board of directors and all the directors
More informationThe oil fields in the NCS are located in the North Sea, Norwegian Sea, and Barents Sea.
A.2 Norway Volumes of Associated Gas Flared on Norwegian Continental Shelf Norway is a major oil producer, and its oil fields are located offshore in the Norwegian Continental Shelf (NCS). 81 In 2002,
More informationwww.ntos.no Hydraulic Solutions keep your operations running specialist services
www.ntos.no Hydraulic Solutions keep your operations running specialist services rental products MAINTAINS A HIGH LEVEL OF PERFORMANCE NTOS designs and installs hydraulic solutions for the international
More informationRISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES
RISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES Eivind Okstad and Per Hokstad SINTEF Industrial Management, Dept. of Safety and Reliability, N-7465 Trondheim,
More informationKP4: AGEING & LIFE EXTENSION (ALE) INSPECTION PROGRAMME 1 YEAR ON
KP4: AGEING & LIFE EXTENSION (ALE) INSPECTION PROGRAMME 1 YEAR ON PRESENTATION OUTLINE What is KP4? What have we achieved so far? Supporting activities; external events, web page, network and technical
More informationLIFE EXTENSION ISSUES FOR AGEING OFFSHORE INSTALLATIONS
Proceedings of OMAE2008 27 th International Conference on Offshore Mechanics and Arctic Engineering 15-20 June 2008, Estoril, Portugal OMAE2008-57411 LIFE EXTENSION ISSUES FOR AGEING OFFSHORE INSTALLATIONS
More informationIntegrated Barrier Analysis in Operational Risk Assessment in Offshore Petroleum Operations
Integrated Barrier Analysis in Operational Risk Assessment in Offshore Petroleum Operations Jan Erik Vinnem Preventor/Stavanger University College, Bryne, Norway Terje Aven Stavanger University College,
More informationRECOMMENDED GUIDELINES FOR THE APPLICATION OF IEC 61508 AND IEC 61511 IN THE PETROLEUM ACTIVITIES ON THE NORWEGIAN CONTINENTAL SHELF
RECOMMENDED GUIDELINES FOR THE APPLICATION OF IEC 61508 AND IEC 61511 IN THE PETROLEUM ACTIVITIES ON THE NORWEGIAN CONTINENTAL SHELF No.: 070 Date effective: 1.02.2001 Revision no.: 01 Date revised: NA
More informationSafety Integrity Level (SIL) Studies Germanischer Lloyd Service/Product Description
Safety & Risk Management Services Safety Integrity Level (SIL) Studies Germanischer Lloyd Service/Product Description Germanischer Lloyd Service/Product Description Safety Integrity Level (SIL) Studies
More informationTechnology services for existing facilities
part of Aker Kristian Risdal SVP C&T MMO 2010 Aker Solutions MMO - Field life solutions 1992 Tie-in 1997 Decommissioning 1999 Satellite tie-in 1998 Platform integrity Statfjord B 2001 Compression modification
More informationPSA Well Integrity Survey, Phase 1 summary report - o o. Begrenset Fortrolig. Strengt fortrolig. Rapport. Gradering Offentlig o Unntatt offentlighet
Rapport Rapporttittel PSA Well Integrity Survey, Phase 1 summary report - Rapport nummer Gradering Offentlig o Unntatt offentlighet o o Begrenset Fortrolig o Strengt fortrolig Involverte Organisasjonsenhet
More informationCommon IT solutions for The Norwegian Continental Shelf (NCS)
Semantic Days Conference 2013 Sola strand Hotel, Stavanger, Norway Common IT solutions for The Norwegian Continental Shelf (NCS) Dr. Thore Langeland Strategic Advisor, EPIM Mobile: +47 9095 1756 Email:
More informationThe Norwegian Petroleum Directorate Annual Report. Offshore Norway 2001
The Norwegian Petroleum Directorate Annual Report Offshore Norway 2001 Preface Norwegian Petroleum Directorate Annual Report Offshore Norway 2 0 0 1 A NEW OIL NORWAY The 2001 oil and gas year was marked
More informationForebyggende arbeid i letefasen What do we do to prevent major accidents during exploration drilling?
Forebyggende arbeid i letefasen What do we do to prevent major accidents during exploration drilling? HSE seminar for small and new operators and licensees Per Olav Sætre, November 8 th 2012 Lundin Norway
More informationHSE DIRECTIVE 10 HELICOPTER OPERATIONS
HSE DIRECTIVE 10 HELICOPTER OPERATIONS Directive owner per 01.01.2016 Gunn Elin Hellegaard HELI. OPS.. Please consult the asset s HSE instructions for potential installation specific requirements 1 GENERAL
More informationSWEDBANK SUMMIT. Det norske presentation. Oslo, 20 March 2014
SWEDBANK SUMMIT Det norske presentation Oslo, 20 March 2014 Building a company for the future Strong production growth Current production ~4,000 boepd (Jette, Atla, Jotun, Varg) Ivar Aasen and Johan Sverdrup
More informationAlways finding new solutions. modulesolutions.no
Always finding new solutions. modulesolutions.no modulesolutions.no we can work it out Contents The company 3 Our driving force 4 Our solutions 5 Our capabilities 6 Our areas of expertise 8 Modules 9 Rental
More informationHow to find field candidates for enhanced recovery by water additives on the NCS
How to find field candidates for enhanced recovery by water additives on the NCS Enhanced Recovery by water additives FORCE Seminar 8. 2. 27 Jan Bygdevoll, Principal Engineer, NPD Why is a field a candidate
More informationImproving pre-operational production efficiency estimates
Improving pre-operational production efficiency estimates ESRA seminar 28 th January 2015 Classification: Internal Production efficiency (PE) 100% Estimated production loss PE Production efficiency (PE)
More informationA Renewed Life Cycle Approach to FPSO by DNV
A Renewed Life Cycle Approach to FPSO by DNV 2011 FPSO JIP Forum Kenneth Vareide, Director of Operations Life Cycle Approach to FPSO: Some Key Success Criteria Newbuilding Project vs. Operation Integrated
More informationNorwegian Operators Conference 2014. Bernd Schrimpf Managing Director Wintershall Norge AS Stavanger 19 th November 2014
Norwegian Operators Conference 2014 Bernd Schrimpf Managing Director Wintershall Norge AS Stavanger 19 th November 2014 New transaction with Statoil Shares in development project Aasta Hansteen (24%),
More informationMOD2013 Muligheter i riggreparasjonsmarkedet Jonn Berget, Westcon Group, 16.03.13
MOD2013 Muligheter i riggreparasjonsmarkedet Jonn Berget, Westcon Group, 16.03.13 1. Short Update Westcon 2. Rig Market 3. Why Westcon? V Business Lines Westcon Group Yards Power & Automation Lifting Techniques
More informationControl of Major Accident Hazards
Appendix 2 Ageing Plant: Site Operator Self-Assessment Question Set 1. This appendix contains a question set to help operators assess compliance against Managing Ageing Plant: A Summary Guide. 2. In the
More informationDetermination of Flared Gas Volumes Offshore Norway. By Stig Arvid Knutsson Principal Engineer Fiscal Metering Norwegian Petroleum Directorate
Determination of Flared Gas Volumes Offshore Norway By Stig Arvid Knutsson Principal Engineer Fiscal Metering Norwegian Petroleum Directorate Presentation Outline Regulatory requirements Flaring of Associated
More informationBirth of a Norwegian. giant
EICT package for Det norske s Ivar Aasen project Birth of a Norwegian giant In 2008, Det norske discovered hydrocarbons in the Ivar Aasen field some 180 kilometers off the Norwegian coast. When the plan
More informationThe Norwegian Model: Evolution, performance and benefits
The Norwegian Model: Evolution, performance and benefits Ola Borten Moe Minister of Petroleum and Energy Olje- og energidepartementet regjeringen.no/oed Our largest industry Norwegian Oil and Gas Activities
More informationKey Programme 4 (KP4) Ageing and life extension
An interim report by the Offshore Division of HSE s Hazardous Installations Directorate November 2012 1 of 15 pages Contents Glossary 3 Summary 4 Introduction 5 KP4 inspection programme interim findings
More informationNew Solutions for Cost Challenges in the Oil & Gas Industry
OIL & GAS New Solutions for Cost Challenges in the Oil & Gas Industry Norwegian Business Delegation to Australia Etienne Romsom February 2015 1 SAFER, SMARTER, GREENER The market trends for the oil and
More informationSubsea processing. Oslo 8. September 2011 Håvard Eidsmoen, Statoil 2011-08-11
Subsea processing Oslo 8. September 2011 Håvard Eidsmoen, Statoil Content Introduction/Motivation Why subsea processing? Overview of technologies, applications and examples Boosting Separation Compression
More informationBP NORGE AS. Annual Accounts 2010
BP NORGE AS Annual Accounts 2010 BP NORGE AS INCOME STATEMENT NOK 1 000 Notes 2010 2009 Operating income Petroleum income 2 7 423 582 5 622 751 Other income 3 128 843 42 330 Total operating income 7 552
More informationHSE information sheet. Fire and explosion hazards in offshore gas turbines. Offshore Information Sheet No. 10/2008
HSE information sheet Fire and explosion hazards in offshore gas turbines Offshore Information Sheet No. 10/2008 Contents Introduction.. 2 Background of gas turbine incidents in the UK offshore sector...2
More informationThe Norwegian continental shelf - 2005
The Norwegian continental shelf - 2005 Director General Gunnar Berge The Norwegian Petroleum Directorate, 12 January 2006 Exploration in 2005 Twelve exploration wells started Nine wildcat wells and three
More informationWintershall Norge ASA Maria Development Project. Maria Åpenbaring - Nytt felt og Nye muligheter i Haltenbanken området
Wintershall Norge ASA Maria Development Project Maria Åpenbaring - Nytt felt og Nye muligheter i Haltenbanken området E. Braune/ Norskehavskonferansen Stjørdal 8. mars 2012 1 Wintershall - Core Regions
More informationNORSOK STANDARD RISK AND EMERGENCY PREPAREDNESS ANALYSIS
NORSOK STANDARD RISK AND EMERGENCY PREPAREDNESS ANALYSIS Z-013 Rev.1, March 1998 This NORSOK standard is developed by NTS with broad industry assistance. Please note that whilst every effort has been made
More informationICHEME SYMPOSIUM SERIES NO. 139 A METHODOLOGY FOR CONCEPT RISK ASSESSMENT OF OFFSHORE DEVELOPMENTS
A METHODOLOGY FOR CONCEPT RISK ASSESSMENT OF OFFSHORE DEVELOPMENTS FK Crawley, Dr MM Grant, MD Green WS Atkins Consultants Limited, 20 N Claremont St., Glasgow G3 7LE This paper describes a simple means
More informationReport from Axess AS February 2013. Magazine
Report from Axess AS February 2013 Magazine safe lifting operations Leder General Manager, Børge Gjeldvik A LIFTING OPERATION IS NOT SIMPLY A LIFTING OPERATION client oriented and solution focused organization
More informationDet norske oljeselskap - Our first diving operation. Annual Conference The Norwegian Oil and Gas Association Stavanger, Norway 13.03.
Det norske oljeselskap - Our first diving operation Annual Conference The Norwegian Oil and Gas Association Stavanger, Norway 13.03.13 Diving Operations our starting point Det norske started out with a
More informationNorSeaGroup2011web 26-01-11 12:05 Side 1. The leading provider of supply bases and integrated logistic solutions to the offshore industry
2011web 26-01-11 12:05 Side 1 The leading provider of supply bases and integrated logistic solutions to the offshore industry 1 1 2011web 26-01-11 12:05 Side 2 10 supply bases - 1 contract With 10 strategically
More informationSubsea Integrity and Efficiency Conference. Securing and Enhancing UK Brownfield Production from Subsea Control Systems. Alan Peek - 01 Dec 2015
Subsea Integrity and Efficiency Conference Securing and Enhancing UK Brownfield Production from Subsea Control Systems Alan Peek - 01 Dec 2015 1 Introduction The Challenge For Us All Low oil price and
More informationHEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT STANDARDS. OCTOBER 2011- ISSUE No 01. Doc No: HSEC MS 001
HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT S OCTOBER 2011- ISSUE No 01 Doc No: MS 001 Introduction Celtique Energie is in the business of exploring for oil and gas in proven basins in Europe.
More informationEconomic commentaries
No. 4 2013 Economic commentaries Monetary Policy The effect of a fall in oil prices on the turnover of Norwegian enterprises An analysis based on Norges Bank s regional network By Anna Sandvig Brander,
More informationPart 0 - Classification and Surveys Classification and Surveys I-0 2016-01
Code Edition I - Ship Technology Part 0 - Classification and Surveys Classification and Surveys I-0 2016-01 Part 1 - Seagoing Ships Chapter 1 - Hull Structures I-1-1 2016-01 Chapter 1 - Hull Structures
More informationFPS new entrant coordination process
FPS new entrant coordination process Technical studies are normally necessary to determine whether access to FPS is possible, at what cost, requiring what modifications and to understand any specific risks.
More informationTechnical & Engineering: OIL & GAS
Providing Qualified Professionals Be Exceptional About us Recruitment Process Compliance Client Support Payroll Control Our Clients Oil & Gas Industry Contact About us Cordant Technical & Engineering Recruitment
More informationYear Client & Destination Description Photo
Year Client & Destination Description Photo Shell Engineering, procurement and construction (EPC) CCR building comprising 5 modules for Toucan facility upgrade project. TAQA Bratani Workfox The Netherlands
More informationScana Offshore Technology
Scana Offshore Technology 1 Presentasjon NFLB Vinterkonferansen 2009 Januar 2009 Scana Industry Group Structure 2 Steel Area Marine Area Oil & Gas Area Scana Steel Björneborg AB Scana Volda AS Scana Offshore
More informationSilverPipe. Pipeline Integrity Management Software. Lene B. Synnestvedt December 2011
Pipeline Integrity Management Software Lene B. Synnestvedt - Background DNV Software s Pipeline Integrity Management Software 2 The Industry s Challenges - and Opportunities Increasingly more global, complex
More informationSend your email directly to oseghaleokohue@chesssubseaengineering.com
Welcome to Chess Engineering Virtual Office - EVO Our engineering virtual office assistants are highly trained and provide a number of engineering support services depending on your EPIC business needs.
More informationApplication of real-time monitoring
Application of real-time monitoring NCR August 25th 2015 Trond Lilleng Senior Advisor Integrated Operations TEX FOT OT FO Statoil ASA Mobile: +47 91183884 Email: trlil@statoil.com Disclaimer: The comments
More informationThe Norwegian Experience
The Norwegian Experience Jerusalem, January 23 rd 2012 www.agr.com 1 About the presenters Eivind Reiten Chairman AGR CEO Hydro from 2001 to 2009 Minister of Oil & Energy from 1989 to 1990 Minister of Fishery
More informationBEST PRACTICE FOR THE DESIGN AND OPERATION OF HIGH HAZARD SITES
BEST PRACTICE FOR THE DESIGN AND OPERATION OF HIGH HAZARD SITES Lyn Fernie and Jo Fearnley AK EHS & Risk, Aker Kvaerner Engineering Services Ltd, Ashmore House, Stockton on Tees, TS18 3RE. The idea of
More informationRiser less Light Well Intervention (RLWI) - "A success for reducing OPEX - cost and increasing oil recovery for subsea completed fields"
Classification: Internal Status: Draft Riser less Light Well Intervention (RLWI) - "A success for reducing OPEX - cost and increasing oil recovery for subsea completed fields" Underwater Technology Conference
More informationAsset Integrity - Process Safety Management
Asset Integrity - Process Safety Management Commit to Process Safety Understand Hazards & Risks Manage Risk Learn from experience Process safety culture Compliance with standards Process safety competency
More informationPIPELINES AND ONSHORE FACILITIES. ruc FACTS 127
14 PIPELINES AND ONSHORE FACILITIES ruc 2011 FACTS 127 EUROPIPE ll 12 10 8 6 4 2 0 2 4 6 8 62 Norne Skarv Åsgard Heidrun Kristin 66 FAROE ISLANDS Ormen Lange Draugen Njord HALTENPIPE 64 60 58 56 THE ORKNEYS
More informationTECHNICAL INFORMATION
Page: 1/6 This checklist recognizes the major accident hazards found by experience of previous HAZID studies. It is not intended to be totally exhaustive and feedback from users should be incorporated
More informationOil & Gas UK I N D E X. December 2009
Oil & Gas UK I N D E X December 09 THE OIL & GAS UK INDEX 1 Summary The Oil & Gas UK Index The Oil & Gas UK Index is a new quarterly index which measures changes in activity and business confidence across
More informationTECHNIP IN NORWAY GENERAL PRESENTATION
TECHNIP IN NORWAY GENERAL PRESENTATION Technip Technip Among the top five major players in the field of oil, gas and petrochemical engineering, construction and services Global corporation with entities
More informationCertification of Materials and Components
OIL & GAS Certification of Materials and Components Standardisation of the industry s approach to quality control and assurance processes Martin Fowlie 12th February 2015 1 DNV GL 2013 12th February 2015
More informationSUPPLY CHAIN CODE OF PRACTICE. Streamlining processes and increasing value for the oil and gas industry
SUPPLY CHAIN CODE OF PRACTICE Streamlining processes and increasing value for the oil and gas industry About The Supply Chain Code of Practice The Supply Chain Code of Practice (SCCoP) outlines a set
More informationSAFETY ENVIRONMENTAL MANAGEMENT SYSTEM (SEMS) STANDARDS MANUAL TABLE OF CONTENTS
SAFETY ENVIRONMENTAL MANAGEMENT SYSTEM (SEMS) STANDARDS MANUAL NXY000-080-SF-ST-0000-0001 Proponent: Brad Koskowich Issue Date: Nov. 2011 Approver: Rick Johnston Audit Date: Mar 2014 Ross Sommer Competency
More informationHIPPS Application in the Gulf of Mexico. Christopher Lindsey-Curran BP Senior Subsea Engineer
HIPPS Application in the Gulf of Mexico Christopher Lindsey-Curran BP Senior Subsea Engineer Agenda Introduction and background HIPPS overview Codes and standards System design Regulatory issues Conclusions
More informationFormer Station 12 and SpecTec. SFI Group System. Product Description
Former Station 12 and SpecTec SFI Group System Product Description Version 05-2001 Table of Contents 1. INTRODUCTION 2 2. BACKGROUND, PURPOSE & ADVANTAGES 2 2.1 Background 2 2.2 Purpose & Advantages 2
More informationINTERTEK S ASSET INTEGRITY MANAGEMENT PROGRAM (AIM)
INTERTEK S ASSET INTEGRITY MANAGEMENT PROGRAM (AIM) Intertek AIM is a strategic management system consisting of specialized expertise, resources methodologies, and tools to assist production and process
More informationNORSOK STANDARD S-006 Rev 2, December 2003
NORSOK STANDARD S-006 Rev 2, December 2003 HSE evaluation of contractors This NORSOK standard is developed with broad petroleum industry participation by interested parties in the Norwegian petroleum industry
More informationDANISH ENERGY AGENCY S GUIDELINES ON SAFETY- AND HEALTH RELATED CONDITIONS ON OFFSHORE INSTALLATIIONS, ETC. HEALTH & SAFETY CASES
DANISH ENERGY AGENCY S GUIDELINES ON SAFETY- AND HEALTH RELATED CONDITIONS ON OFFSHORE INSTALLATIIONS, ETC. HEALTH & SAFETY CASES REV. 0 December 2012 TABLE OF CONTENT TABLE OF CONTENT... 2 DOCUMENT CONTROL...
More informationANNUAL OFFSHORE STATISTICS & REGULATORY ACTIVITY REPORT 2013/2014
ANNUAL OFFSHORE STATISTICS & REGULATORY ACTIVITY REPORT 2013/2014 Date of release: December 2014 1 Preface HSE is responsible for regulating health & safety matters offshore. The Health and Safety at Work
More informationAMOS SFI. Group System. Product Description
AMOS SFI Group System Product Description 1. INTRODUCTION 1 2. BACKGROUND, PURPOSE AND ADVANTAGES 1 2.1 Background 1 2.2 Purpose and Advantages 1 2.3 Scope 2 3. THE PROBLEMS SFI CAN SOLVE 2 3.1 Controlling
More informationCMD 2008 Kongsberg Gruppen ASA. Kongsberg Maritime. Kongsberg Maritime Capital Markets Day September 2008. Status and Prospects for the future
Kongsberg Maritime Capital Markets Day September 28 Kongsberg Maritime Status and Prospects for the future Strategic direction /2/ Kongsberg Maritime Business segment description Segments and sub segments
More informationCreating a robust asset management strategy to optimise asset performance and improve asset reliability
N o v e m b e r, 2 0 1 5 Creating a robust asset management strategy to optimise asset performance and improve asset reliability Nick Tompkins Technical Manager Asset Management November, 2015 1 Asset
More informationLicensing system in Norway. Steinar Njå Norwegian Petroleum Directorate
Licensing system in Norway Steinar Njå Norwegian Petroleum Directorate Licensing system in Norway Discretionary system The Government invites companies to apply for exclusive rights to petroleum activities
More informationStep to the future Life Cycle Information
Step to the future Life Cycle Information LCI Leader Marianne Kalvenes/Mona Nøstvold Classification: Open STEP projects improving our efficiency End-to-end well delivery Standard well design, equipment
More informationTopsides, Floaters & Onshore Facilities
Topsides, Floaters & Onshore Facilities KVAERNER PARTNER Kvaerner is a specialised engineering, procurement and construction (EPC) company. As a preferred partner for oil and gas operators, Kvaerner is
More informationThe Technology Challenge. Agenda - The Technology Challenge
The Technology Challenge British and Norwegian Oil and Gas Industry Collaboration Conference R. Rasmus Sunde Executive Vice President London, October 26, 2005 Agenda - The Technology Challenge Overall
More informationEfficient Operations for Maintenance
Efficient Operations for Maintenance Business challenges Through Absoft s unrivalled experience of optimising operations and maintenance processes for operators, drilling and oilfield service companies,
More informationOFFSHORE FIELD DEVELOPMENT
OFFSHORE FIELD DEVELOPMENT OPTIONS & STRATEGY By: Nguyen Ngoc Hoan M.Sc of Petroleum Engineering Hoannn@pidc.com.vn PRESENTATION CONTENT Field Development Consideration Field Development Options & Strategy
More informationPolicy and Legal Status -
Policy and Legal Status - - CO 2 Storage in European and Norwegian context 2 Policy and Legal CONTENTS International Politics International law European law Norway Summing up This is it! 3 Classification:
More informationOil and Natural Gas Analysis at Norges Bank. Pål Winje ( International Department), workshop on modeling and forecasting oil prices, 22 March 2012
Oil and Natural Gas Analysis at Norges Bank Pål Winje ( International Department), workshop on modeling and forecasting oil prices, 22 March 212 The Norwegian Petroleum Sector as a Share of Macroeconomic
More informationCubility - Facilities and offices
MudCube by Cubility Cubility - Facilities and offices Head office and sales offices Cubility s head office is located in Sandnes, Norway A major part of the oil and gas activity in the North Sea is operated
More informationJIP Offshore Leak Detection
OIL & GAS JIP Offshore Leak Detection Fjernmåling tidlig deteksjon av akutt forurensning Heidi Hægeland Halvorsen BEREDSKAPSFORUM 2014 1 DNV GL 2013 BEREDSKAPSFORUM 2014 SAFER, SMARTER, GREENER DNV GL
More informationStoring of CO 2 offshore Norway, Criteria for evaluation of safe storage sites
Storing of CO 2 offshore Norway, Criteria for evaluation of safe storage sites Eva Halland Norwegian Petroleum Directorate Trondheim CCS Conference June 14-16, 2011 1 29.06.2011 Storing of CO 2 offshore
More informationStructural integrity management framework for fixed jacket structures
Health and Safety Executive Structural integrity management framework for fixed jacket structures Prepared by Atkins Limited for the Health and Safety Executive 2009 RR684 Research Report Health and Safety
More informationOG21 - Oil and Gas in the 21st Century for the 21st Century Strategy DoCument
OG21 - Oil and Gas in the 21st Century Norway s Technology Strategy for the 21st Century Strategy DoCument Oil and gas for the 21 st Century og21 c/o The research council of norway stensberggata 26 PO
More informationRisk Based Asset Management
Document number Risk Based Asset Management turning policy into operational excellence Dave Oesterholt DNV GL Oil & Gas - Groningen Office, NL Monday, 2 December 2013 Location Groningen, NL: Gas Consulting
More informationCapability maturity model for maintenance management
Capability maturity model for maintenance management CAPABILITY MATURITY MODEL FOR MAINTENANCE MANAGEMENT CAPABILITY MATURITY MODEL FOR MAINTENANCE MANAGEMENT October 2007 Published by ENERGY INSTITUTE,
More information