Common InfraBIM requirements YIV2015

Size: px
Start display at page:

Download "Common InfraBIM requirements YIV2015"

Transcription

1 Common InfraBIM requirements YIV2015 Vol 1.0 MANAGING MODEL BASED PROJECT Quality control Interaction and collaboration Supervision and coordination Infra modeling Coordination of disciplines Gathering of initial data Planning, construction, asset management Jari Niskanen WSP Finland Oy English version 1.0

2 Document version history Version Date Author Description Jari Niskanen Guideline English version

3 CONTENT 1 INTRODUCTION Planning a model-based project Planning phases in Finnish planning system Modeling plan Modeling extent and level of accuracy GOALS WITH MODELING AND PURPOSE of USE MODEL PROCESS DESCRIPTION Actors Cooperation and data exchange between actors Schedule Model description document and list of contents Quantity and cost management quality assurance utilization principals of model in different project phases... 10

4 1 INTRODUCTION This document describes management of projects which use modeling. Use of modeling effects project organization, phasing, schedule, approach and exchange of information. Project responsible shall be able to evaluate how information modeling can be used to maximize the added value and how modeling contributes to achieve overall project objectives.

5 2 PLANNING A MODEL-BASED PROJECT 2.1 Planning phases in Finnish planning system Workflow in an infra project can be described with following diagram. Time spam of project from its first phases to the end can be long. On the other hand, modeling planning can start at any project phase. Starting point in this document is, that an information modeling plan has to be made regardless of project phase. Contents of modeling plan document vary depending on project phase, but these differences are not dealt with in this context. Data delivered to orderer in infra project Edited from source: Lehtovirta Final product in documentbased, main contract form project Preliminary design report, preliminary drawings General design report, complement drawings, electronic data Road design, complement drawings, electronic data Construction design Drawings Work specification Design data to be implemented at sites Working drawings Investment requirements and preliminary design General plan Early design phases, Road, street or railway design Construction design Construction Final product in model-based, cooperation form project Preliminary design model General design model Construction design model 3D-objects Required data Initial data model Initial data model Initial data model Road, street or railway model Implementation model As built drawings Operation and maintenance Maintenance manual Picture 1. Produced material per project phase. As built model Asset management model Interface to archiving and administration systems

6 2.2 Modeling plan In initiation stage of project, the project responsible makes model plan, which shows: general goals of modeling and purpose of use; what the project or process needs the model for process description o project actors, roles (responsibilities) and tasks o cooperation and exchange of data o schedule modeling extent and level of detail cost calculation/administration; procedures quality assurance principles of model utilization in relation to project phase o design, construction, implementation o use, administration, maintenance o purchase and contracting techniques Model plan is an appendix document in design contract. Other central documents in engineering procurement as design principals and design program are closely related to it. Most of data shown in modeling plan belongs more naturally in design plan, but it s more suitable to keep these as separate documents, as long as model documents and design documents have different content and contractual position in construction. 2.3 Modeling extent and level of accuracy Requirements for modeling extent and level of accuracy are based on earlier specified goals and purpose of use. When specifying and documenting the modeling accuracy and it s extent, we can lean on specifications in other parts in this requirement and instruction documentation. Requirements concerning the modeling extent and level of accuracy are recommended to be documented in the corresponding form of design program. Factors affecting the extent and level of accuracy are specified and documented with designing principals, design program and modeling plan. In goal situations, obligations and requirements of modeling are outlined through design principals and program. General modeling requirements offers a foundation which may be relied on in documents. Design principals Design program Modeling plan document General modeling requirements Picture 1. Definition of design and modeling task.

7 3 GOALS WITH MODELING AND PURPOSE OF USE MODEL Project goals set on modeling are documented in modeling plan document. General goals are for example benefits in securing execution of project, increase productivity and efficiency in construction, improve quality in design and construction, more cost effective controllability of project, benefits offered by model in understanding and its contents and form a picture of project etc. Purpose of use for modeling is described in the modeling plan document. These can be for instance: Description: communication with outside interest groups Description: internal communication and transfer of data in a design or construction project Clash detection between disciplines Clash detection between existing structures and designs Ease the determination of construction qualities: link quality requirements for construction parts to model Improve quality of procurement: construction project defined with model reduces risks for tenderer and leads to better tenders Production scheduling and production control: linking model to schedule with project division and cost control with a model containing quantity data (4D and 5D modeling) Life cycle information management: needed data for operation, management and maintenance systems in an easy accessible form; as built model utilized in maintenance manual or it s user interface Visualization helps understanding content solutions in design producing explicit, understandable and higher quality data of design situation. When central features of solutions are portrayed explicit enough in model, visualization supports also design, management, control and decision-making. Visualization can serve apart from project group and users, also outside interest groups like authorities \, Part 10, In model-based procurement, models are part of contract documents. With help of models the intelligibility of designs increases, service providers risk decreases and client gets more profitable and higher quality tenders. With help of a model, efficiency can also be sought in dividing project in different procurement packages. Quality requirements for construction shown in model, improves the client possibilities to state the quality of construction. At the moment it ś not clear how modeling technology will support this goal in the future. If the goal is to use the produced data from design and construction for the needs of management and maintenance, this shall be taken into account in procurement phase of construction. Parties responsible for maintenance should have a possibility reserved to affect the contents of a modeling plan document. 4 PROCESS DESCRIPTION Process description contains actors in project, their role in project organization as well as their tasks and responsibilities regarding producing or using the model. In addition, cooperation between actors and exchange of information as well as schedule of project is described.

8 4.1 Actors Most central actor in a project is the client. The client is responsible for project financing, decision-making and management and makes also the decisions and procurement concerning modeling. The client is responsible for project preparations and implementation and receives the final design for their own archives and administration systems. The client can use outside technical experts as support for procurement and quality assurance (contract control). The client's user role to the model is typically a viewing user. Technical experts must have access to use full-scale tools (programs) for checking the model. Project manager appointed by service provider is responsible for modeling management. Project manager can delegate tasks regarding modeling management to model coordinator, but can t delegate responsibilities regarding modeling, like compatibility of designs (discipline models). Project manager s user role is viewing user. Model coordinators ensure that different areas are consistent and compatible. Technical designers are responsible of their own modeling discipline and a model coordinator ensures the combined model is updated according to modeling plan document. To confirm compatibilities, responsibilities can be delegated in many different ways: to many actors, principal designer (road, railway, street) or project manager (who is ultimately responsible for everything). Model coordinator should have tools to consolidate and control models. Infra model controller is client's controller and responsible for client s quality assurance tasks. Designers draw their own designs following design principals, design program and model plans of their own discipline. Designer follows quality assurance tasks. The designer uses needed tools to make and modify the model of their own discipline and applicable tools for controlling the combined model. 4.2 Cooperation and data exchange between actors The modeling plan document describes cooperation between actors from modeling point of view. Process shall be interwoven with other project work as smoothly as possible. 4.3 Schedule Schedule of modeling follow the schedule of design, where the modeling tasks are added. When scheduling a model for a project, the attention should be drawn especially to following matters: creation of initial data models and delivery well in advance preparation of visualization model in such a way it supports communication and meetings in the project division of project in a way, that it supports modeling and utilization of model 5 MODEL DESCRIPTION DOCUMENT AND LIST OF CONTENTS Model description document describes central initial data per design area, purpose of model, content, coverage, modeling methods and level of accuracy as well as possible limits and deviations from general requirements. With help of the report other parts can interpret the general construction of model, naming practices and degree of readiness. Model description document is updated always when the model is released for other users.

9 Material division in model description document shall follow the principle, where design model and initial data model are separated and initial data model only consist of data of existing conditions. Out of initial data and model is prepared a listing; model content list with an equivalent structure as an infra model report. The document shows the purpose of files, possible limitations as well as if needed, mistakes in description in comparison with theoretical geometry model. An inspection of documents can be made with help of the table (mark the particular row in the table) before forward delivery to other parties or being generated in to combined model. Table 1. Example on contents of model description in railway plan. 0 General 3 Railway model 3C Constructions and systems 1 Raw material 3C1 Traffic lanes 1A Terrain model 3C1.1 Railway 1B Ground model 3C Railway constructions 1B1 Geotechnical soundings 3C Drainage 1C Constructions and systems 3C Equipment 1D Map and GIS 3C1.1.9 Service roads 1E Other data 3C Crossing 3C Existing constructions 2 Initial data 3C1.2 Road network 2A Terrain model 3C2 Foundation 2B Ground model 3C2.1 Preloading 2B1 Rock face 3C2.2 Surcharge loading 2B2 Soil type surface. 3C2.3 Replacement of soil Peat, lower surface 2B3 Soil type surface. 3C2.4 Work-time abutment wall Clay, lower surface 2B4 Soil type surface. 3C2.5 Pile slab Loam, lower surface 2C Constructions and systems 3C2.6 Loading berm 2D Map and GIS 3C3 Bridges 2E Other data 3C3.1 New bridges 3C3.2 Existing bridges Model description document is more specifically described in part 2 in this set of instruction. 6 QUANTITY AND COST MANAGEMENT Quantity and cost management is described in part 8 in this instruction document, Quantity and cost estimates. How to link models to cost management is at this stage technically unsolved. Nowadays it s essential to keep cost effects up-to-date in the design phase. Modeling benefits are multiplied, if the model can be linked to other functions as production control and cost management. At time of writing, there aren t any established ways to deal with model-based quantity and cost management or for instance connect project and construction part calculation systems totally into model-based design systems.

10 7 QUALITY ASSURANCE The client receives and accepts the model (models) produced in the project. The client has to ensure, that resources, knowledge and methods needed for this are sufficient. Quality assurance is mainly based on service provider s inspection of produced models and it s documentation. In addition the client can implement a separate quality assurance procedure. Quality assurance is described in part 8 8 UTILIZATION PRINCIPALS OF MODEL IN DIFFERENT PROJECT PHASES Modeling is used differently in different design phases. In the early phases the central factors are for example to find out the technical implementation, reliable definition of investment and maintenance costs as well as confirm acceptability of design. Central element in modeling is the combined model, which supports the implementation of solutions. The combined model is a virtual portrayal of all discipline models. Virtual model can function as a support to confirm the acceptability of design. Work flow of utilization of virtual model in design phase.

11 Picture 2. Use of modeling as a controlling tool and support in interaction. Utilizing model in construction phase is portrayed in following work flow. Design is made to varying extent, for instance depending on procurement model. In principle, the designer is however always also involved in the construction phase. Construction phase has produced model-based designs from different disciplines and produced combined-models of them. From this entity is produce data for the needs of construction including machine control and on site measurements., As construction progresses, specified initial data as well as changes to design solutions at work site are delivered to designer, who up-dates the designs and the combined model. An administrator has to be appointed before start of construction phase. Most naturally it is the designer. Model coordinator at site is responsible for producing the model for construction.

12 Picture 3. Utilizing models in construction phase is portrayed in following work flow. The role of model coordinator and responsibility limitations should be defined before start of construction project. Subject significance depends on project procurement model: in the so called integrated implementation models the significance decreases (picture doesn t take side on procurement model; model-based design may have been made separately before construction phase or it can be made as part of procurement within the frameworks of a traditional contract or an alliance type ). Operation and maintenace Picture 4. Utilization of infra model in operation and maintenance phase.

13 English version 1.0

A Conceptual Methodology and Practical Guidelines for Managing Data and Documents on Hydroelectric Projects

A Conceptual Methodology and Practical Guidelines for Managing Data and Documents on Hydroelectric Projects A Conceptual Methodology and Practical Guidelines for Managing Data and Documents on Hydroelectric Projects Alan Hodgkinson SoftXS GmbH Alpensrasse 14 CH-6300 Zug Switzerland Joseph J Kaelin Pöyry Infra

More information

Tekla Structures More than a detailing tool. Precast concrete

Tekla Structures More than a detailing tool. Precast concrete Tekla Structures More than a detailing tool Precast concrete Much more Than a detailing tool a Tekla Structures is much more than design and detailing software: it is the most accurate and comprehensive

More information

RoadBIM Seminar 11.09.2013 Tallinn

RoadBIM Seminar 11.09.2013 Tallinn RoadBIM Seminar 11.09.2013 Tallinn Ongoing Finnish InfraBIM Activities and the Finnish Inframodel Juha Hyvärinen, Senior Scientist VTT Technical Research Centre of Finland 3 Background Building Information

More information

Energy Efficiency Agreement between the Ministry of Trade and Industry and the Municipality of (2008 2016)

Energy Efficiency Agreement between the Ministry of Trade and Industry and the Municipality of (2008 2016) Dnro 7202/804/2008 Unofficial translation Energy Efficiency Agreement between the Ministry of Trade and Industry and the Municipality of (2008 2016) 1 The starting points and grounds for the agreement

More information

Foreword. Version 1.0 27.03.2012 Parties to the COBIM project

Foreword. Version 1.0 27.03.2012 Parties to the COBIM project Series 12 author Insinööritoimisto Olof Granlund Oy: Markku Jokela, Tuomas Laine, Reijo Hänninen Foreword The publication series Common BIM 2012 is the result of a broadbased development project entitled

More information

Inframodel 3 (4-5) InfraFINBIM / buildingsmart Infra Seminar 19 November 2013. Juha Hyvärinen, Senior Scientist

Inframodel 3 (4-5) InfraFINBIM / buildingsmart Infra Seminar 19 November 2013. Juha Hyvärinen, Senior Scientist InfraFINBIM / buildingsmart Infra Seminar 19 November 2013 Inframodel 3 (4-5) Juha Hyvärinen, Senior Scientist VTT Technical Research Centre of Finland 2 The Finnish Inframodel To improve information exchange

More information

InfraBIM Tiina Perttula 19.11.2013

InfraBIM Tiina Perttula 19.11.2013 InfraBIM Tiina Perttula 19.11.2013 The Finnish Transport Agency FTA Is a multidisciplinary expert organisation specialising in transport Responsible for the Finnish transport infrastructure and the overall

More information

New Business Models in Construction

New Business Models in Construction New Business Models in Construction Results of the Finnish BIM Survey 2013 CIB BIM & IDDS Seminar, Tokyo 1.11.2013 Dipl. Ing. Helena Soimakallio, M. Sc. (CE), B. Sc. (BA), M. aff. ASCE Managing Director

More information

Tietomallintamisen läpimurto infra-alalla - tietomallintamisella automaatioon

Tietomallintamisen läpimurto infra-alalla - tietomallintamisella automaatioon PRE-ohjelman tulosseminaari, Dipoli, Otaniemi 18.11.2013 Tietomallintamisen läpimurto infra-alalla - tietomallintamisella automaatioon Rauno Heikkilä Oulun yliopisto Development of Infra Construction Technologies

More information

Professional Engineers Providing Structural Engineering Services In Buildings

Professional Engineers Providing Structural Engineering Services In Buildings GUIDELINE Professional Engineers Providing Structural Engineering Services In Buildings 1995 Published by Association of Professional Engineers of Ontario Revised 12/11/98 CONTENTS INTRODUCTION...3 PART

More information

Model based quality assurance process in a infra construction. Case Riippa-Eskola RU2 double rail project

Model based quality assurance process in a infra construction. Case Riippa-Eskola RU2 double rail project Model based quality assurance process in a infra construction project Case Riippa-Eskola RU2 double rail project M. Jaakkola a and P. Toppi a a Destia Ltd, Development of Infra construction, Finland E-mail:

More information

COBIM. Series 1. General part. Common BIM Requirements 2012. v 1.0

COBIM. Series 1. General part. Common BIM Requirements 2012. v 1.0 COBIM v 1.0 Common BIM Requirements 2012 Series 1 General part Foreword The publication series Common BIM Requirements 2012 is the result of a broad-based development project entitled COBIM. The need for

More information

Project Management Manual Update 2006. Transportation Department City of Edmonton

Project Management Manual Update 2006. Transportation Department City of Edmonton Project Management Manual Update 2006 Transportation Department City of Edmonton Project Management Manual for Transportation Projects EXECUTIVE SUMMARY This document has been updated to fulfill the requirements

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

Development of the BIM based process for Dredging Works

Development of the BIM based process for Dredging Works The 31st International Symposium on Automation and Robotics in Construction and Mining (ISARC 2014) Development of the BIM based process for Dredging Works R. Heikkilä a, T. Leinonen b, H. Paukkeri c and

More information

Getting More Value from your BIM Process with Autodesk Collaboration and Data Management Products

Getting More Value from your BIM Process with Autodesk Collaboration and Data Management Products Autodesk Vault Professional 2014 Getting More Value from your BIM Process with Autodesk Collaboration and Data Management Products Building Information Modeling (BIM) is a process that relies on intelligent

More information

NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013

NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 NETLIPSE NETWORK MEETING 27-28.5.2013 Seppo Mäkinen Finnish Transport Agency 27.5.2013 Mainroad 4 Järvenpää Lahti PPP Project 1997 2012 FINLAND 27.5.2013 27.5.2013 Seppo Mäkinen Mainroad 4 Järvenpää -

More information

Series 600: Earthworks

Series 600: Earthworks Series 600: Volume 4 home page 1 General Where the Contractor has obligations in respect of classification of earthworks materials then these obligations include sampling and testing in accordance with

More information

GIS Solutions for FTTx Design. David Nelson, GISP

GIS Solutions for FTTx Design. David Nelson, GISP GIS Solutions for FTTx Design David Nelson, GISP Telecom GIS Manager, Black & Veatch Agenda Intro to GIS Telecom GIS Vision GIS Strategy Project Execution Mobile Online Services Dashboards Client Deliverables

More information

TechnicalNotes. Terramodel Software for Construction

TechnicalNotes. Terramodel Software for Construction TechnicalNotes Terramodel Software for Construction INTEGRATED SOFTWARE FOR IMPROVED CONSTRUCTION PROCESSES Today s construction industry demands high accuracy and maximum efficiency throughout the construction

More information

14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003

14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003 14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003 A CASE STUDY OF THE IMPACTS OF PRELIMINARY DESIGN DATA EXCHANGE ON NETWORKED PRODUCT DEVELOPMENT PROJECT CONTROLLABILITY Jukka Borgman,

More information

Engineering Council of South Africa

Engineering Council of South Africa Government Gazette No. 26180, 2 April 2004 Page 1 of 30 Board Notice 42 of 2004 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the

More information

Built Environment Process Reengineering (PRE)

Built Environment Process Reengineering (PRE) RAKENNETTU YMPÄRISTÖ Tarvitaanko tätä palkkia? Built Environment Process Reengineering (PRE) RYM SUMMIT 2013 Kimmo Laatunen, Infra FINBIM Built Environment Process Innovations Reengineering 3.12.2013 Built

More information

No. 132. Land Use and Building Act (132/1999, amendment 222/2003 included) Chapter 1. General provisions. Section 1 General objective of the Act

No. 132. Land Use and Building Act (132/1999, amendment 222/2003 included) Chapter 1. General provisions. Section 1 General objective of the Act NB: UNOFFICIAL TRANSLATION FINLAND No. 132 Land Use and Building Act (132/1999, amendment 222/2003 included) In accordance with the decision of Parliament the following is enacted: Chapter 1 General provisions

More information

Sage 300 ERP 2014. What's new. Being connected helps get more done

Sage 300 ERP 2014. What's new. Being connected helps get more done Sage 300 ERP 2014 What's new Being connected helps get more done Get more done by connecting your business, providing a better customer experience, and increasing revenue. Sage 300 ERP (formerly Sage ERP

More information

TENDER DOCUMENT PROCEDURE FOR MAJOR WORKS CONTRACTS USING AS 2124 1992 GENERAL CONDITIONS OF CONTRACT

TENDER DOCUMENT PROCEDURE FOR MAJOR WORKS CONTRACTS USING AS 2124 1992 GENERAL CONDITIONS OF CONTRACT TENDER DOCUMENT PROCEDURE FOR MAJOR WORKS CONTRACTS USING AS 2124 1992 GENERAL CONDITIONS OF CONTRACT MAIN ROADS Western Australia Tender Document Procedure Page 1 of 18 Document 07/4351 Issued 9/03/2011

More information

Summary of Stakeholder Report. Action 1, BIOGASSYS, Decision making tools for the establishment and expanding of biogas production and consumption

Summary of Stakeholder Report. Action 1, BIOGASSYS, Decision making tools for the establishment and expanding of biogas production and consumption Summary of Stakeholder Report Action 1, BIOGASSYS, Decision making tools for the establishment and expanding of biogas production and consumption Table of content Introduction... 2 Background... 2 Purpose...

More information

Civil Engineering and Architecture (CEA) Detailed Outline

Civil Engineering and Architecture (CEA) Detailed Outline Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of

More information

USABILITY OF A FILIPINO LANGUAGE TOOLS WEBSITE

USABILITY OF A FILIPINO LANGUAGE TOOLS WEBSITE USABILITY OF A FILIPINO LANGUAGE TOOLS WEBSITE Ria A. Sagum, MCS Department of Computer Science, College of Computer and Information Sciences Polytechnic University of the Philippines, Manila, Philippines

More information

WORKSHOP PEDAGOGY. Operating environment of workshops. Information for stakeholders and partners. PRINCIPLES OF COACHING IN WORKSHOPS

WORKSHOP PEDAGOGY. Operating environment of workshops. Information for stakeholders and partners. PRINCIPLES OF COACHING IN WORKSHOPS WORKSHOP PEDAGOGY PEDAGOGIC PRINCIPLES OF COACHING IN WORKSHOPS Operating environment of workshops A workshop is a flexible environment in which coaching, different kinds of activities, work and learning

More information

Get to know your Autodesk Design and Creation Suites 2014

Get to know your Autodesk Design and Creation Suites 2014 Get to know your Design and Creation Suites 2014 Design and Creation Suites 2014 offer more tools and cloud services so you can take advantage of smoother workflows, better access to project information,

More information

JOB DESCRIPTION POSITION TITLE:

JOB DESCRIPTION POSITION TITLE: Halifax Regional Municipality JOB DESCRIPTION POSITION TITLE: Design Engineering Technologist BUSINESS UNIT: Transportation and Public Works Services DIVISION: Design & Construction Services SECTION: Design

More information

Instructions for Writing a Thesis for the Master s Degree

Instructions for Writing a Thesis for the Master s Degree Instructions for Writing a Thesis for the Master s Degree Seinäjoki University of Applied Sciences 2013 2 FOREWORD The present instructions for writing a thesis are applied by all the Master s Degree programmes

More information

Graduate route 3 candidate guidance

Graduate route 3 candidate guidance Assessment of Professional Competence (APC) August 2007 Graduate route 3 candidate guidance www.joinricsineurope.eu Contents Page Section one Introduction 3 Entry requirements Section two The Assessment

More information

Spatially Enabling an Asset Management Database

Spatially Enabling an Asset Management Database Spatially Enabling an Asset Management Database John Woollett, GIS Manager (Operations) Tube Lines Ralph Diment Intergraph UK Helen Neaves Intergraph UK Bruce Aquila Intergraph Introduction Background

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

Improving Data Quality: Empowering Government Decision Makers with Meaningful Information for Better Decision Flow in Real-Time

Improving Data Quality: Empowering Government Decision Makers with Meaningful Information for Better Decision Flow in Real-Time WHEN DATA CLICKS, KNOWLEDGE FLOWS. WHITE PAPER Improving Data Quality: Empowering Government Decision Makers with Meaningful Information for Better Decision Flow in Real-Time HOW INQUISIENT S PLATFORM

More information

Workflow and Process Analysis for CCC

Workflow and Process Analysis for CCC Section 3.6 Design Workflow and Process Analysis for CCC This tool introduces the importance of workflow and process improvement in a community-based care coordination (CCC) program, describes the value

More information

Built Environment Process Reengineering (PRE): Infra FINBIM

Built Environment Process Reengineering (PRE): Infra FINBIM RAKENNETTU YMPÄRISTÖ Tarvitaanko tätä palkkia? (PRE): Infra FINBIM buildingsmart and Infra FINBIM - Nordic Workshop in Helsinki November 30th 2011 30.11.2011 Built Built Environment Process Innovations

More information

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.

More information

How To Manage Transportation Asset Management

How To Manage Transportation Asset Management 1 TRANSPORTATION ASSET MANAGEMENT THE NEW BUSINESS MODEL FOR TRANSPORTATION AGENCIES Presented at the AASHTO Subcommittee on Transportation Finance Policy Business Meeting Irvine, California June 26, 2012

More information

SOLUTIONS FROM VIANOVA SYSTEMS

SOLUTIONS FROM VIANOVA SYSTEMS NovapointDCM & QuadriDCM Sydhavna, Oslo - Statens vegvesen/vianova SOLUTIONS FROM VIANOVA SYSTEMS The transport infrastructure industry worldwide is restructuring to meet increasing demands for shorter

More information

COMPANY... 3 SYSTEM...

COMPANY... 3 SYSTEM... Wisetime Ltd is a Finnish software company that has longterm experience in developing industrial Enterprise Resource Planning (ERP) systems. Our comprehensive system is used by thousands of users in 14

More information

Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations

Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations The implementation of the AASHTO LRFD Bridge Design Specifications

More information

integrated operational management

integrated operational management VISIONLINK integrated operational management The VisionLink fleet, asset and site productivity management solution from Trimble tells you where your equipment is, what it's doing and how it's performing.

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

use of OpenBIM Hospitals in Denmark Norway and Espoo Hospital in Finland DENMARK - FINLAND - NORGE

use of OpenBIM Hospitals in Denmark Norway and Espoo Hospital in Finland DENMARK - FINLAND - NORGE use of OpenBIM Hospitals in Denmark Norway and Espoo Hospital in Finland Agenda Introduction to speakers Introduction to hospital projects Reasons for using BIM Processes Break Organization Implementation

More information

COBIM. Series 8. Use of models for visualization. Common BIM Requirements 2012. v 1.0

COBIM. Series 8. Use of models for visualization. Common BIM Requirements 2012. v 1.0 COBIM v 1.0 Common BIM Requirements 2012 Series 8 Use of models for visualization Foreword The publication series Common BIM Requirements 2012 is the result of a broadbased development project entitled

More information

STANDARD OPERATING PROCEDURES QUALITY ASSURANCE AND QUALITY CONTROL 04

STANDARD OPERATING PROCEDURES QUALITY ASSURANCE AND QUALITY CONTROL 04 STANDARD OPERATING PROCEDURES SOP QUALITY ASSURANCE AND QUALITY CONTROL 04 SAMPLING Sampling for inspection and control of soil treatment depth during demining machine usage 04.02 DOMAIN: HUMANITARIAN

More information

Gestão Integrada de Projectos. Arquitectura

Gestão Integrada de Projectos. Arquitectura Gestão Integrada de Projectos Prática Integrada como Visão Holística do Projecto (EXTENDED ABSTRACT) João Ricardo Vieira Lourenço Dissertação para obtenção do Grau de Mestre em Arquitectura JÚRI Presidente:

More information

Work Type Definition and Submittal Requirements

Work Type Definition and Submittal Requirements Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials

More information

Transportation Management. Transportation Procurement. Transportation Planning & Execution. Fleet Management. Audit, Payment & Claims

Transportation Management. Transportation Procurement. Transportation Planning & Execution. Fleet Management. Audit, Payment & Claims Transportation Management Transportation Procurement Transportation Planning & Execution Fleet Management Audit, Payment & Claims Transportation Management Everyday, you are charged with making sure your

More information

Space Project Management

Space Project Management EUROPEAN COOPERATION FOR SPACE STANDARDIZATION Space Project Management Configuration Management Secretariat ESA ESTEC Requirements & Standards Division Noordwijk, The Netherlands Published by: Price:

More information

Documents pertaining to safety control of nuclear facilities. 1 General 3. 2 Submission of documents 3. 3 Document structure and contents 3

Documents pertaining to safety control of nuclear facilities. 1 General 3. 2 Submission of documents 3. 3 Document structure and contents 3 GUIDE 11 Sept. 1995 YVL 1.2 Documents pertaining to safety control of nuclear facilities 1 General 3 2 Submission of 3 3 Document structure and contents 3 3.1 Document structure 3 3.2 Document contents

More information

Improving supply chain management information systems in public administration using a new theory

Improving supply chain management information systems in public administration using a new theory www.ijcsi.org 102 Improving supply chain management information systems in public administration using a new theory Hind LAHMIDANI Omar EL BEQQALI Department of Science and Technologies of Information

More information

Sage 300 ERP 2014 Get more done.

Sage 300 ERP 2014 Get more done. Get more done. Get more done by connecting your business, providing a better customer experience, and increasing revenue. Sage 300 ERP (formerly Sage ERP Accpac) is the foundation for your business to

More information

BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY

BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY MR. ALVIN WONG-KAM MAN Building Services Engineering Graduate Gammon Skanska Limited E-mail: alvin.wong@gammonskanska.com Do a 2-Dimensional

More information

5047P Architectural and Engineering Services for the Cambie Fire Hall and Ambulance Station Project- Addendum #2

5047P Architectural and Engineering Services for the Cambie Fire Hall and Ambulance Station Project- Addendum #2 January 23, 2013 Business and Financial Services Department Finance Division Telephone: 604-276-4218 Fax: 604-276-4162 Attention: To All Proponents Dear Bidders: Re: 5047P Architectural and Engineering

More information

Client Consultancy. Description of services December 2003. The Danish Council of Practising Architects (PAR)

Client Consultancy. Description of services December 2003. The Danish Council of Practising Architects (PAR) Description of services December 2003 Client Consultancy The Danish Council of Practising Architects (PAR) The Association of Consulting Engineers in Denmark (FRI) PAR and FRI Description of services for

More information

1Current. Today distribution channels to the public have. situation and problems

1Current. Today distribution channels to the public have. situation and problems 1Current situation and problems Today distribution channels to the public have proliferated. The time when purchases were made at grocery stores which held all kinds of goods in a small space has long

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT Characteristic of Construction Industry One of the biggest sector as * total turnover is more than $3,9 trillion annually * 7 million employee (USA) Affects vast and different industries:

More information

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY

MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY GUIDE YVL A.3 / 2 June 2014 MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Management system 6 3.1 Planning, implementation, maintenance, and improvement of the management

More information

INTRUSION PREVENTION AND EXPERT SYSTEMS

INTRUSION PREVENTION AND EXPERT SYSTEMS INTRUSION PREVENTION AND EXPERT SYSTEMS By Avi Chesla avic@v-secure.com Introduction Over the past few years, the market has developed new expectations from the security industry, especially from the intrusion

More information

Forensic engineering of a bored pile wall

Forensic engineering of a bored pile wall NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Forensic engineering of a bored pile wall Willem Robert de Bruin Geovita AS, Norway,

More information

Framework Agreement on the Improvement of Energy Efficiency in Industries

Framework Agreement on the Improvement of Energy Efficiency in Industries 18/804/2007 Unofficial translation Framework Agreement on the Improvement of Energy Efficiency in Industries 1 Parties The parties to this Energy Efficiency Agreement on the Improvement of Energy Efficiency

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

EUROPASS DIPLOMA SUPPLEMENT

EUROPASS DIPLOMA SUPPLEMENT EUROPASS DIPLOMA SUPPLEMENT TITLE OF THE DIPLOMA (ES) Técnico Superior en Proyectos de Obra Civil TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Higher Technician in Civil Works Projects --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

More information

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning

More information

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344

Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING

More information

FutureWorks Nokia technology vision 2020: personalize the network experience. Executive Summary. Nokia Networks

FutureWorks Nokia technology vision 2020: personalize the network experience. Executive Summary. Nokia Networks Nokia Networks FutureWorks Nokia technology vision 2020: personalize the network experience Executive Summary White paper - Nokia Technology Vision 2020: Personalize the Network Experience CONTENTS Aligning

More information

BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi

BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value Professor Mustafa Alshawi Improving Project Performance Current Project Portfolio 1.83 B UAED ($500M) Award Winning

More information

A COMPARISON OF PRINCE2 AGAINST PMBOK

A COMPARISON OF PRINCE2 AGAINST PMBOK Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the

More information

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents 2004R0552 EN 04.12.2009 001.001 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B REGULATION (EC) No 552/2004 OF THE EUROPEAN PARLIAMENT

More information

The Verdura Wall check with your local building department

The Verdura Wall check with your local building department The Verdura Wall The Verdura Wall by Soil Retention Products, Inc of Carlsbad, California can be constructed as a gravity retaining structure or a geosynthetic reinforced segmental retaining wall, depending

More information

Vertex BD. Leading Software Solution for Cold Formed Steel Construction

Vertex BD. Leading Software Solution for Cold Formed Steel Construction Vertex BD Leading Software Solution for Cold Formed Steel Construction Architectural Design Framing Engineering Detailing Production One Tool Does It All Leading Software for CFS Construction Vertex BD

More information

Airport safety and security solutions. Tailored intelligent solutions to protect passengers, assets and infrastructure. Answers for infrastructure.

Airport safety and security solutions. Tailored intelligent solutions to protect passengers, assets and infrastructure. Answers for infrastructure. Airport safety and security solutions Tailored intelligent solutions to protect passengers, assets and infrastructure Answers for infrastructure. Check in for safety and security Today s megatrends such

More information

Strategic Plan for Control Period 5, 2014 2019. Issue Two 2015-2016

Strategic Plan for Control Period 5, 2014 2019. Issue Two 2015-2016 Infrastructure Standards Committee Strategic Plan for Control Period 5, 2014 2019 Issue Two 2015-2016 Approved by the Infrastructure Standards Committee 05 March 2015 ISCC/020 Email: enquirydesk@rssb.co.uk

More information

Quality Control and Quality Assurance Guide

Quality Control and Quality Assurance Guide Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...

More information

Design of Network Educating Information System Based on Use Cases Driven Shenwei Wang 1 & Min Guo 2

Design of Network Educating Information System Based on Use Cases Driven Shenwei Wang 1 & Min Guo 2 International Symposium on Social Science (ISSS 2015) Design of Network Educating Information System Based on Use Cases Driven Shenwei Wang 1 & Min Guo 2 1 College of Electronic and Control Engineering,

More information

Sage 300 ERP 2014 Get more done.

Sage 300 ERP 2014 Get more done. Sage 300 ERP 2014 Get more done. Get more done by connecting your business, providing a better customer experience, and increasing revenue. New web and mobile functionality: driving better customer experiences

More information

Streamline your design-to-cost processes with Autodesk Navisworks

Streamline your design-to-cost processes with Autodesk Navisworks Quantification in Autodesk Navisworks 2015 Streamline your design-to-cost processes with Autodesk Navisworks Contents Overcome data disarray....................................................................................

More information

Quality Assurance/Quality Control Plan. Division of Transportation Solutions

Quality Assurance/Quality Control Plan. Division of Transportation Solutions Quality Assurance/Quality Control Plan Division of Transportation Solutions January 2009 Table of Contents MISSION STATEMENT 3 GENERAL POLICY 3 QA/QC RESPONSIBILITIES 4 PROJECT DESIGNER 4 DELDOT S PROJECT

More information

BIM in Finland today. TOMI HENTTINEN M.Sc. (Archit.) SAFA Gravicon Oy, CEO buildingsmart Finland, Chair FINLAND

BIM in Finland today. TOMI HENTTINEN M.Sc. (Archit.) SAFA Gravicon Oy, CEO buildingsmart Finland, Chair FINLAND BIM in Finland today TOMI HENTTINEN M.Sc. (Archit.) SAFA Gravicon Oy, CEO buildingsmart Finland, Chair GRAVICON BIM SERVICES BIM Manager Specifications and Supervision for BIM projects BIMwise WEB-Based

More information

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc) Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-57 Requirements for an Excavation and Lateral Support Plan Building

More information

Intergraph Roadway Information Management Solution. Title Title. Title Title. A White Paper

Intergraph Roadway Information Management Solution. Title Title. Title Title. A White Paper Intergraph Roadway Information Management Solution A White Paper Security, Government & Infrastructure, a division of Intergraph Title Title Title Title Table of Contents 1. Introduction... 1 2. Intergraph

More information

Project Management Standards: A Review of Certifications/Certificates

Project Management Standards: A Review of Certifications/Certificates Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in

More information

Post-Merger Integration at Sachtleben

Post-Merger Integration at Sachtleben Post-Merger Integration at Sachtleben The seamless merging of operational business processes and systems by BearingPoint In just ten months, BearingPoint brought together the key operational processes,

More information

INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING CONTENTS

INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING CONTENTS INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING (Effective for audits of financial statements for periods beginning on or after December 15, 2004) CONTENTS Paragraph Introduction...

More information

05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246

05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 CIVIL ENGINEERING ASSOCIATE, 7246 Summary of Duties: Performs professional civil engineering work in researching,

More information

Guidelines for Cost Estimate Template

Guidelines for Cost Estimate Template Guidelines for Cost Estimate Template Date: December 11, 2014 Version: 1 Public Information Table of Contents Overview... 1 Protecting / Unprotecting the Spreadsheet... 1 Entry and Formula Fields... 1

More information

INTERNATIONAL STANDARD ON ASSURANCE ENGAGEMENTS (ISAE) 3402 ASSURANCE REPORTS ON CONTROLS AT A SERVICE ORGANIZATION

INTERNATIONAL STANDARD ON ASSURANCE ENGAGEMENTS (ISAE) 3402 ASSURANCE REPORTS ON CONTROLS AT A SERVICE ORGANIZATION INTERNATIONAL STANDARD ON ASSURANCE ENGAGEMENTS (ISAE) 3402 ASSURANCE REPORTS ON CONTROLS AT A SERVICE ORGANIZATION (Effective for service auditors assurance reports covering periods ending on or after

More information

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

Autodesk Solutions for Environmental Engineering. Engineering a better environment

Autodesk Solutions for Environmental Engineering. Engineering a better environment Autodesk Solutions for Environmental Engineering Engineering a better environment Better Engineering, Faster Design and deliver environmental engineering projects better, faster, and more economically.

More information

Guidelines for Writing Reports in Engineering Engineering Faculty, Monash University

Guidelines for Writing Reports in Engineering Engineering Faculty, Monash University Guidelines for Writing Reports in Engineering Engineering Faculty, Monash University Key features of reports Reports: are designed for quick and easy communication of information are designed for selective

More information

Introduction to Fractions

Introduction to Fractions Section 0.6 Contents: Vocabulary of Fractions A Fraction as division Undefined Values First Rules of Fractions Equivalent Fractions Building Up Fractions VOCABULARY OF FRACTIONS Simplifying Fractions Multiplying

More information

Design-Bid-Build versus Design-Build: The client s choice

Design-Bid-Build versus Design-Build: The client s choice Design-Bid-Build versus Design-Build: The client s choice Ruben Favié Eindhoven University of Technology (email: r.favie@tue.nl) Job Sijbers Eindhoven University of Technology (email: jobsijbers@hotmail.com)

More information

Role in the project (e.g. Prime Engineering Consultant or Contractor), and summary of professional Duties : Name Professional Duties Contract Awarded?

Role in the project (e.g. Prime Engineering Consultant or Contractor), and summary of professional Duties : Name Professional Duties Contract Awarded? PROPOSAL FORM FOR SINGLE PROJECT PROFESSIONAL INDEMNITY NOTE: THIS IS A PROPOSAL FOR A CLAIMS MADE POLICY Note : Please provide any necessary explanations or additional details by attachment to this Proposal

More information