1 IT Session 3: Resourcing Creating a Resource Library It is possible within the software to include resources as you go on, but it is better to set up a separate resource library and link this to your developing project plan. The reasons for this will be discussed during the session. Assuming that you have started the software, ensure that you have employed your template file as you should now do automatically at the start of any session with this planning software! You ought to have a blank project on the screen if not, click File, New. Now, using File, Save as, save the blank project as Resources.mpp as this is going to become our Resource Library or Resource Pool. The table below represents the team of resources for our project along with their rates and working week: Resource Library Name Number Hourly Working week Rate Resource A 1 14 Normal 5 day Resource B 1 20 Normal 5 day Resource C 2 12 Normal 5 day Resource D 1 8 M, T, W, Th only Click on View, Resource Sheet to give you the following screen: From the table above enter each of the resources in the Resource Name column on a new line in the Resource Sheet. Just enter the names to start with; the numbers and hourly rates will be dealt with next. As you enter each resource, you will notice that a lot of additional default information is inserted as well. We will discuss this. After entering all of the resources, it should look like the illustration on the next page: 28

2 Now enter the number of resources in the Max Units column and the hourly rates into the Std Rate column so that it looks like: numbers of resources and hourly rates entered In order to sort out the different working week for Resource D, select Tools, Change Working Time to give the following dialog box: Now from the drop down list at the top of the dialog box, select Resource D as shown: 29

3 Now click on the F (for Friday) on the calendar so that the column is highlighted and change their status to Nonworking time as shown: Click on the F here to highlight the column Change this setting from Use default to Nonworking time Note the times disappear from these cells here Select OK. Save the file as a precaution. Please note there should be NO TASKS in this project it should only contain resources. This will be discussed further in the session. In order to undertake the next part of the process you must have the Simple.mpp file saved from the last session. Borrowing this file from someone else is likely to cause you problems! Select File, Open and open the Simple.mpp project. We are now going to link the two files, so be particularly careful at this point. Ensure you are in the Simple project and not the Resources one ( but don t close it ). Select Tools, Resource Sharing, Share Resources as shown on the next page: 30

4 This will give the following: Change the settings to those shown below and select OK. This has now converted the Resoures file into a resource pool. The merits of this will be discussed. 31

5 The resource assignments for the Simple project are as follows: Simple Project Task Resource Number G1 Resource A 1 G2 Resource B&D 1 for both G3 Resource C 2 G4 Resource A 1 G5 Resource C 2 G6 Resource D 1 F1 Resource D 1 F2 Resource D 1 F3 Resource C 2 F4 Resource D 1 E1 Resource C 1 E2 Resource B 1 E3 Resource D 1 E4 Resource A 1 E5 Resource C 2 To assign the resources in the software, firstly, click on the task G1 and then click on the button with 2 people on as shown below: Click on task G1 to start with and then click on the button showing 2 people If you have linked the two files correctly, the dialog box that appears should look like the one shown on the following page. If it doesn t look like this, ask! 32

6 Click in the Units column next to Resource A. Either using the small scroller that appears, or by simply typing, put 1 in this column. Click on the Assign button. You will notice that a tick appears on the left hand side of Resource A and the dialog box remains present. This is to make the process of assigning resources to tasks a little easier. Now click on task G2 and assign both Resource B and D to this task so that when you have completed it, the Assign Resources dialog box looks like this: Continue assigning the resources as laid out in the table on page 32. Click the Close on this dialog box once you have finished doing the assignments. The screen of your Simple project now ought to look something like that on the next page. 33

7 You should see that the resources have been assigned and their names have appeared to the right hand side of the tasks on the gantt chart. Press F9 to calculate. If you have developed the project correctly, you might expect that the fact that one of the resources only worked a 4-day week might have an impact on the duration of the project. This does depend on what we mean when we stipulate the duration of the task; do we mean 5 day s duration or do we mean 5 day s worth of work? This concept will be explored further in the session along with some ways of viewing just how busy the resources are at this point and the developing costs. 34

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

Resource Allocation in MS Project

Resource Allocation in MS Project Resource Allocation in MS Project Calendars The project calendar determines the working days and hours available to your project, In addition each resource can have their unique calendars to mark time

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

Project Management: Intermediate Microsoft Project 2010

Project Management: Intermediate Microsoft Project 2010 Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project

More information

Project Management Quick Reference Guide for MS Project 2010

Project Management Quick Reference Guide for MS Project 2010 Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides

More information

Creating a New Project

Creating a New Project Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

Excel 2013 What s New. Introduction. Modified Backstage View. Viewing the Backstage. Process Summary Introduction. Modified Backstage View

Excel 2013 What s New. Introduction. Modified Backstage View. Viewing the Backstage. Process Summary Introduction. Modified Backstage View Excel 03 What s New Introduction Microsoft Excel 03 has undergone some slight user interface (UI) enhancements while still keeping a similar look and feel to Microsoft Excel 00. In this self-help document,

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

Resource Management with Microsoft Project Professional 2010

Resource Management with Microsoft Project Professional 2010 Resource Management with Microsoft Project Professional 2010 Greg Bailey Founder & CEO SharkPro Software greg.bailey@sharkprosoftware.com 1 Copyright 2011 SharkPro Software Corporation Microsoft Project

More information

Using Microsoft Office to Manage Projects

Using Microsoft Office to Manage Projects (or, Why You Don t Need MS Project) Using Microsoft Office to Manage Projects will explain how to use two applications in the Microsoft Office suite to document your project plan and assign and track tasks.

More information

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated.

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated. Microsoft Project Pro Steps to completing Project Pro Assignments PART B. (These instructions include all you need to know about adjusting your project in Microsoft Project Pro 2013 and may include instructions

More information

Word 2010: Mail Merge to Email with Attachments

Word 2010: Mail Merge to Email with Attachments Word 2010: Mail Merge to Email with Attachments Table of Contents TO SEE THE SECTION FOR MACROS, YOU MUST TURN ON THE DEVELOPER TAB:... 2 SET REFERENCE IN VISUAL BASIC:... 2 CREATE THE MACRO TO USE WITHIN

More information

The purpose of this document is to describe how to connect Crystal Reports with BMC Remedy AR System using ODBC.

The purpose of this document is to describe how to connect Crystal Reports with BMC Remedy AR System using ODBC. UCL INFORMATION SERVICES DIVISION CRYSTAL REPORTS INTEGRATING WITH REMEDY The purpose of this document is to describe how to connect Crystal Reports with BMC Remedy AR System using ODBC. 1. Install BMC

More information

Lesson 6 - Managing Resources in a Project Plan

Lesson 6 - Managing Resources in a Project Plan Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

Excel 2010: Create your first spreadsheet

Excel 2010: Create your first spreadsheet Excel 2010: Create your first spreadsheet Goals: After completing this course you will be able to: Create a new spreadsheet. Add, subtract, multiply, and divide in a spreadsheet. Enter and format column

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step

More information

Online Appointments (Patients)

Online Appointments (Patients) Online Appointments (Patients) Overview Once the patient has registered and activated their account they can use the modules available at the practice. This section of the user guide details how the patient

More information

Beginning Microsoft Project

Beginning Microsoft Project Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND

More information

How to Create Database in Microsoft Excel 2003

How to Create Database in Microsoft Excel 2003 Step 1: Getting start How to Create Database in Microsoft Excel 2003 Install Microsoft Excel 2000 or 2003 in your computer, press start program files click Microsoft Excel 2003 After click MS-Excel it

More information

Microsoft Word 2010 Mail Merge (Level 3)

Microsoft Word 2010 Mail Merge (Level 3) IT Services Microsoft Word 2010 Mail Merge (Level 3) Contents Introduction...1 Creating a Data Set...2 Creating the Merge Document...2 The Mailings Tab...2 Modifying the List of Recipients...3 The Address

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

Project Management Dashboard Pro v5 Documentation

Project Management Dashboard Pro v5 Documentation Project Management Dashboard Pro v5 Documentation Installation There is NO installation required. It s just a macro enabled excel file that opens if you have Excel 2007, 2010, 2013 and 2016 on your Windows

More information

Excel Reports User Guide

Excel Reports User Guide Excel Reports User Guide Copyright 2000-2006, E-Z Data, Inc. All Rights Reserved. No part of this documentation may be copied, reproduced, or translated in any form without the prior written consent of

More information

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010 Produced by Flinders University Centre for Educational ICT PivotTables Excel 2010 CONTENTS Layout... 1 The Ribbon Bar... 2 Minimising the Ribbon Bar... 2 The File Tab... 3 What the Commands and Buttons

More information

Microsoft Project Server 2010 Project Manager s Guide for Project Web App

Microsoft Project Server 2010 Project Manager s Guide for Project Web App Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web

More information

Create a new investment form and publish it to a SharePoint 2013 forms library

Create a new investment form and publish it to a SharePoint 2013 forms library Create a new investment form and publish it to a SharePoint 2013 forms library Step 1, create two new document libraries in the root site of your a collection 1) Open SharePoint Designer 2013 2) Create

More information

Using Microsoft Project 2000

Using Microsoft Project 2000 Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL

More information

Create a PivotTable or PivotChart report

Create a PivotTable or PivotChart report Page 1 of 5 Excel Home > PivotTable reports and PivotChart reports > Basics Create or delete a PivotTable or PivotChart report Show All To analyze numerical data in depth and to answer unanticipated questions

More information

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan. 2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone

More information

Creating an Excel Database for a Mail Merge on a PC. Excel Spreadsheet Mail Merge. 0 of 8 Mail merge (PC)

Creating an Excel Database for a Mail Merge on a PC. Excel Spreadsheet Mail Merge. 0 of 8 Mail merge (PC) Creating an Excel Database for a Mail Merge on a PC Excel Spreadsheet Mail Merge 0 of 8 Creating an Excel Database for a Mail Merge on a PC 1. To create a database for a mail merge you will first need

More information

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado

More information

Mail Merge Creating Mailing Labels 3/23/2011

Mail Merge Creating Mailing Labels 3/23/2011 Creating Mailing Labels in Microsoft Word Address data in a Microsoft Excel file can be turned into mailing labels in Microsoft Word through a mail merge process. First, obtain or create an Excel spreadsheet

More information

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 Contents Contents INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 IMPORT UPDATES 12 CUSTOM TEXT FIELDS MAPPING 13

More information

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,

More information

INFOPATH FORMS FOR OUTLOOK, SHAREPOINT, OR THE WEB

INFOPATH FORMS FOR OUTLOOK, SHAREPOINT, OR THE WEB INFOPATH FORMS FOR OUTLOOK, SHAREPOINT, OR THE WEB GINI COURTER, TRIAD CONSULTING Like most people, you probably fill out business forms on a regular basis, including expense reports, time cards, surveys,

More information

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider www.bluepecantraining.com :: 0800 6124105 :: info@bluepecan.co.

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider www.bluepecantraining.com :: 0800 6124105 :: info@bluepecan.co. Excel Pivot Tables 1 Table of Contents Pivot Tables... 3 Preparing Data for a Pivot Table... 3 Creating a Dynamic Range for a Pivot Table... 3 Creating a Pivot Table... 4 Removing a Field... 5 Change the

More information

Lab 1 Introduction to Microsoft Project

Lab 1 Introduction to Microsoft Project Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features

More information

The first thing to do is choose if you are creating a mail merge for printing or an e-mail merge for distribution over e-mail.

The first thing to do is choose if you are creating a mail merge for printing or an e-mail merge for distribution over e-mail. Create a mail or e-mail merge Use mail or e-mail merge when you want to create a large number of documents that are mostly identical but include some unique information. For example, you can use mail merge

More information

To create a histogram, you must organize the data in two columns on the worksheet. These columns must contain the following data:

To create a histogram, you must organize the data in two columns on the worksheet. These columns must contain the following data: You can analyze your data and display it in a histogram (a column chart that displays frequency data) by using the Histogram tool of the Analysis ToolPak. This data analysis add-in is available when you

More information

A guide to setting up pay periods (including week 53) PM00104.0315/1

A guide to setting up pay periods (including week 53) PM00104.0315/1 A guide to setting up pay periods (including week 53) PM00104.0315/1 Within this document you will find instructions for creating new pay periods and amending existing pay periods for the 2015/2016 tax

More information

Using MS Project in Translation Projects Management

Using MS Project in Translation Projects Management Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

Mac Outlook Calendar/Scheduler and Tasks

Mac Outlook Calendar/Scheduler and Tasks Introduction Schedule an event and/or meeting. Schedule all-day and recurring events. Assign tasks to another user and use special shortcut keys. Contents Introduction Contents Calendar View Edit an appointment

More information

Advanced Excel 10/20/2011 1

Advanced Excel 10/20/2011 1 Advanced Excel Data Validation Excel has a feature called Data Validation, which will allow you to control what kind of information is typed into cells. 1. Select the cell(s) you wish to control. 2. Click

More information

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Computer Lab # 1 Time Management (with Microsoft Project 2007) Lab Manual (with master s

More information

A simple three dimensional Column bar chart can be produced from the following example spreadsheet. Note that cell A1 is left blank.

A simple three dimensional Column bar chart can be produced from the following example spreadsheet. Note that cell A1 is left blank. Department of Library Services Creating Charts in Excel 2007 www.library.dmu.ac.uk Using the Microsoft Excel 2007 chart creation system you can quickly produce professional looking charts. This help sheet

More information

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010.

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010. Page 1 of 8 Excel 2010 Home > Excel 2010 Help and How-to > Getting started with Excel Search help More on Office.com: images templates Basic tasks in Excel 2010 Here are some basic tasks that you can do

More information

Microsoft Access from creating new Database to Queries

Microsoft Access from creating new Database to Queries www.shamskm.com Microsoft Access from creating new Database to Queries Let s say, you have an Excel sheet that contains infos for 9 boreholes: - their x and y coordinates, and - layer depths (each borehole

More information

MAIL MERGE MADE EASY A STEP-BY-STEP GUIDE FOR LABELS OR EMAIL MERGES

MAIL MERGE MADE EASY A STEP-BY-STEP GUIDE FOR LABELS OR EMAIL MERGES MAIL MERGE MADE EASY A STEP-BY-STEP GUIDE FOR LABELS OR EMAIL MERGES WHY MAIL MERGE? Labels: Mail merge in Office lets you convert your contact list data into a sheet of mailing labels, with complete control

More information

Getting Started with Access 2007

Getting Started with Access 2007 Getting Started with Access 2007 1 A database is an organized collection of information about a subject. Examples of databases include an address book, the telephone book, or a filing cabinet full of documents

More information

Computer Training Centre University College Cork. Excel 2013 Pivot Tables

Computer Training Centre University College Cork. Excel 2013 Pivot Tables Computer Training Centre University College Cork Excel 2013 Pivot Tables Table of Contents Pivot Tables... 1 Changing the Value Field Settings... 2 Refreshing the Data... 3 Refresh Data when opening a

More information

APPLYING BENFORD'S LAW This PDF contains step-by-step instructions on how to apply Benford's law using Microsoft Excel, which is commonly used by

APPLYING BENFORD'S LAW This PDF contains step-by-step instructions on how to apply Benford's law using Microsoft Excel, which is commonly used by APPLYING BENFORD'S LAW This PDF contains step-by-step instructions on how to apply Benford's law using Microsoft Excel, which is commonly used by internal auditors around the world in their day-to-day

More information

Accounts Receivable: Importing Remittance Data

Accounts Receivable: Importing Remittance Data Updated December 2015 Contents...3 Getting Started...3 Configuring the Excel Spreadsheet...3 Importing the Data...5 2015 ECi Software Solutions, Inc. This feature lets you import check remittance information

More information

Project Day Numbering

Project Day Numbering Project Day Numbering How to format a Microsoft Project schedule to use Project Dates instead of Calendar Dates 2009 Celeris Systems, Inc. Jim Aksel, PMP, PMI SP, MVP Celeris Systems, Inc. Project Date

More information

In This Issue: Excel Sorting with Text and Numbers

In This Issue: Excel Sorting with Text and Numbers In This Issue: Sorting with Text and Numbers Microsoft allows you to manipulate the data you have in your spreadsheet by using the sort and filter feature. Sorting is performed on a list that contains

More information

Every project requires communication and collaboration and usually a lot of

Every project requires communication and collaboration and usually a lot of Collaborating on Projects with SharePoint CHAPTER 25 Every project requires communication and collaboration and usually a lot of both. With small project teams, you and your team members may interact in

More information

Microsoft Excel 2013: Using a Data Entry Form

Microsoft Excel 2013: Using a Data Entry Form Microsoft Excel 2013: Using a Data Entry Form Using Excel's built in data entry form is a quick and easy way to enter data into an Excel database. Using the form allows you to: start a new database table

More information

Outlook Web App User Guide

Outlook Web App User Guide Outlook Web App User Guide Outlook Web App (OWA) is the new version of the webmail system that enables you to access your email from home, or wherever you have an Internet connected computer. There are

More information

Computer Training Centre University College Cork. Excel 2013 The Quick Analysis Tool

Computer Training Centre University College Cork. Excel 2013 The Quick Analysis Tool Computer Training Centre University College Cork Excel 2013 The Quick Analysis Tool Quick Analysis Tool The quick analysis tool is new to Excel 2013. This tool enables the user to quickly access features

More information

Excel 2003: Ringtones Task

Excel 2003: Ringtones Task Excel 2003: Ringtones Task 1. Open up a blank spreadsheet 2. Save the spreadsheet to your area and call it Ringtones.xls 3. Add the data as shown here, making sure you keep to the cells as shown Make sure

More information

Integrating Microsoft Word with Other Office Applications

Integrating Microsoft Word with Other Office Applications Integrating Microsoft Word with Other Office Applications The Learning Center Staff Education 257-79226 http://www.mc.uky.edu/learningcenter/ Copyright 2006 Objectives After completing this course, you

More information

SharePoint How To s / Team Sites 1of 6

SharePoint How To s / Team Sites 1of 6 SharePoint How To s / Team Sites of 6 SharePoint Server 007 Team Sites are Web sites created from a template and designed for team collaboration. They are hosted on the corporate network. Team Sites are

More information

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1 IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break

More information

1. Introduction. P2O is automatically loaded when you open Ms Project (2010 or 2013). The add-in can be found under the M5 Tools menu. 2.

1. Introduction. P2O is automatically loaded when you open Ms Project (2010 or 2013). The add-in can be found under the M5 Tools menu. 2. 1. Introduction Project 2 Outlook (P2O) will help Microsoft Project users to improve project communication by exporting MS Project tasks and information to MS Outlook Task or Appointments. Users don t

More information

Email Mail Merge Using Thunderbird. Bob Booth February 2009 AP-Tbird2

Email Mail Merge Using Thunderbird. Bob Booth February 2009 AP-Tbird2 Email Mail Merge Using Thunderbird. Bob Booth February 2009 AP-Tbird2 University of Sheffield Contents 1. Introduction... 3 2. Installing the Mail Tweak Plug-In... 4 2.1 DOWNLOADING MAIL TWEAK... 4 2.2

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

How To Use Excel 2010 On Windows 7 (Windows 7) On A Pc Or Mac) With A Microsoft Powerbook (Windows Xp) On Your Computer Or Macintosh (Windows) On Windows Xp (Windows 2007) On Microsoft Excel 2010

How To Use Excel 2010 On Windows 7 (Windows 7) On A Pc Or Mac) With A Microsoft Powerbook (Windows Xp) On Your Computer Or Macintosh (Windows) On Windows Xp (Windows 2007) On Microsoft Excel 2010 ISBN 978-1-921780-70-7 CREATE AND PRODUCE SPREADSHEETS BSBITU202A/BSBITU304A Excel 2010 Supporting BSBITU202A Create and Use Spreadsheets and BSBITU304A Produce Spreadsheets in the Business Services Training

More information

FrontPage 2003: Forms

FrontPage 2003: Forms FrontPage 2003: Forms Using the Form Page Wizard Open up your website. Use File>New Page and choose More Page Templates. In Page Templates>General, choose Front Page Wizard. Click OK. It is helpful if

More information

Business Objects Version 5 : Introduction

Business Objects Version 5 : Introduction Business Objects Version 5 : Introduction Page 1 TABLE OF CONTENTS Introduction About Business Objects Changing Your Password Retrieving Pre-Defined Reports Formatting Your Report Using the Slice and Dice

More information

How To Make Email Templates More Powerful In Ec.Org

How To Make Email Templates More Powerful In Ec.Org EMAIL TEMPLATE RESTRUCTURING OVERVIEW This document describes the restructuring of stored email templates in release 6.0, version 2012-01. The primary reason this restructuring was implemented was so that

More information

Here is a Trial Balance sample, generated and exported into an Excel spreadsheet, by an accounting software*

Here is a Trial Balance sample, generated and exported into an Excel spreadsheet, by an accounting software* Here is a Trial Balance sample, generated and exported into an Excel spreadsheet, by an accounting software* (*) It should be straightforward to put the trial balance produced by accounting software into

More information

Monthly Payroll to Finance Reconciliation Report: Access and Instructions

Monthly Payroll to Finance Reconciliation Report: Access and Instructions Monthly Payroll to Finance Reconciliation Report: Access and Instructions VCU Reporting Center... 2 Log in... 2 Open Folder... 3 Other Useful Information: Copying Sheets... 5 Creating Subtotals... 5 Outlining

More information

Importing of Clients, Contacts & Leads

Importing of Clients, Contacts & Leads Importing of Clients, Contacts & Leads The Import function can be found within the Client module of the Key. It enables client data previously input into Trigold, Mortgage Brain MBL or from other formatted

More information

MS Project Tips and Tricks

MS Project Tips and Tricks MS Project Tips and Tricks ELLEN LEHNERT, MVP, PMP, MCT, MCITP CONSULTANT/INSTRUCTOR LEHNERTCS, LLC WWW.LEHNERTCS.COM ELLEN@LEHNERTCS.COM Ellen Lehnert, MVP, PMP, MCT, MCITP Background in teaching, Business

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Module 1. Project item activities, Gantt Chart & Utilization Sheet Contents...

More information

Setting Preferences in QuickBooks

Setting Preferences in QuickBooks Setting Preferences in QuickBooks The following preferences should be set in Quickbooks: Setting QuickBooks to Display the Lowest Sub-Account Number The Default setting in QuickBooks for displaying Account

More information

How to Create Your Own Crystal Report

How to Create Your Own Crystal Report How to Create Your Own Crystal Report Step 1 Figure out what table you need to use for your report. Click on Resources, then File Layouts and Program Information. Click on File Layouts to see the available

More information

MINI-GUIDE: Work with Packages in Kitomba

MINI-GUIDE: Work with Packages in Kitomba MINI-GUIDE: Work with Packages in Kitomba Packages allows you to bundle services and retail together and offer them to your clients as a package for a reduced time and/or cost! Use Packages to entice your

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Lukos Web TimeSheet Quick Start Guide - GBPS

Lukos Web TimeSheet Quick Start Guide - GBPS Lukos Web TimeSheet Quick Start Guide - GBPS Entering Data in a Timesheet This guide provides a visual overview of the steps required to enter and submit time using a Standard 2.0 (Smart Interface) timesheet.

More information

Create Charts in Excel

Create Charts in Excel Create Charts in Excel Table of Contents OVERVIEW OF CHARTING... 1 AVAILABLE CHART TYPES... 2 PIE CHARTS... 2 BAR CHARTS... 3 CREATING CHARTS IN EXCEL... 3 CREATE A CHART... 3 HOW TO CHANGE THE LOCATION

More information

Creating a Gradebook in Excel

Creating a Gradebook in Excel Creating a Spreadsheet Gradebook 1 Creating a Gradebook in Excel Spreadsheets are a great tool for creating gradebooks. With a little bit of work, you can create a customized gradebook that will provide

More information

IST 195 Lab 12 Introduction to Microsoft Project

IST 195 Lab 12 Introduction to Microsoft Project IST 195 Lab 12 Introduction to Microsoft Project Microsoft Project is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans,

More information

Making an online form in Serif WebPlus

Making an online form in Serif WebPlus Making an online form in Serif WebPlus Before you begin your form, it is a very good idea to plan it out on a piece of paper. Decide what information you wish to collect, and which type of fields will

More information

Rational Team Concert. Scrum Project Management Tutorial

Rational Team Concert. Scrum Project Management Tutorial Rational Team Concert Scrum Project Management Tutorial 1 Contents Contents... 2 1. Introduction... 3 2. Terminology... 4 3. Project Area Preparation... 4 3.1 Adding Users and specifying Roles... 5 3.2

More information

So you want to create an Email a Friend action

So you want to create an Email a Friend action So you want to create an Email a Friend action This help file will take you through all the steps on how to create a simple and effective email a friend action. It doesn t cover the advanced features;

More information

Western PeopleSoft Financials Expense Reports, Cash Advances and Manager Approval

Western PeopleSoft Financials Expense Reports, Cash Advances and Manager Approval Content 1. Create a Cash Advance 2. Create an Expense Report 3. View Expense Reports 4. Manager Approvals 5. My System Profile 6. Delegate Entry Authority by Individual 7. View Payment History To access

More information

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create.

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create. What is Excel? Applies to: Excel 2010 Excel is a spreadsheet program in the Microsoft Office system. You can use Excel to create and format workbooks (a collection of spreadsheets) in order to analyze

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

Setting up Microsoft Outlook to reject unsolicited email (UCE or Spam )

Setting up Microsoft Outlook to reject unsolicited email (UCE or Spam ) Reference : USER 191 Issue date : January 2004 Updated : January 2008 Classification : Staff Authors : Matt Vernon, Richard Rogers Setting up Microsoft Outlook to reject unsolicited email (UCE or Spam

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

Using Pivot Tables in Microsoft Excel 2003

Using Pivot Tables in Microsoft Excel 2003 Using Pivot Tables in Microsoft Excel 2003 Introduction A Pivot Table is the name Excel gives to what is more commonly known as a cross-tabulation table. Such tables can be one, two or three-dimensional

More information