1 PART 1 - GENERAL SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. RELATED SECTIONS Division 16 Section "Basic Electrical Materials and Methods" for general and installation materials and methods. Division 16 Section "Fuses." SUBMITTALS Product Data: For each product and component specified. Shop Drawings: For each switchboard. Show dimensioned plans and elevations, including required clearances and service space, component and device lists, and a single-line diagram showing main- and branch-bus current ratings and short-time and short-circuit ratings of switchboard. Include the following: Descriptive documentation of optional barriers specified for electrical insulation and isolation. Schedule of features, characteristics, ratings, and factory settings of individual protective devices. Wiring Diagrams: Details of wiring for power and control and differentiating between manufacturerinstalled and field-installed wiring. Samples: Of mimic bus with specified finish, for color selection. Qualification Data: For firms and persons specified in "Quality Assurance" Article. Reports of Field Tests and Observations: Certified by testing agency. Manufacturer field service report. Certificates for field testing agency, signed by Contractor, certifying that agency complies with requirements specified in "Quality Assurance" Article below. Report of Field Tests and Observations: Certified by testing agency. Maintenance Data: For switchboards to include in the maintenance manuals specified in Division 1. Include detailed manufacturer's written instructions on adjusting overcurrent protective devices. QUALITY ASSURANCE Testing Agency Qualifications: In addition to the requirements specified in Division 1 Section "Quality Control," an independent testing agency shall meet OSHA criteria for accreditation of testing laboratories, Title 29, Part 1907, or shall be a full-member company of the InterNational Electrical Testing Association. Testing Agency's Field Supervisor: Person currently certified by the InterNational Electrical Testing Association or National Institute for Certification in Engineering Technologies, to supervise on-site testing specified in Part 3. Listing and Labeling: Provide switchboard assemblies specified in this Section that are listed and labeled. The Terms "Listed" and "Labeled": As defined in the National Electrical Code, Article 100. Listing and Labeling Agency Qualifications: A "Nationally Recognized Testing Laboratory" as defined in OSHA Regulation Comply with NFPA 70. Comply with NEMA PB 2. Product Selection for Restricted Space: Drawings indicate maximum dimensions for switchboard equipment, including clearances between switchboard and adjacent surfaces and items. Switchboards having equal performance characteristics and complying with indicated maximum dimensions may be considered. DELIVERY, STORAGE, AND HANDLING Deliver in shipping splits of lengths that can be moved past obstructions in delivery path. Store so condensation will not occur on or in switchboards. Provide temporary heaters as required to avoid condensation. Handle switchboards according to NEMA PB 2.1. Use only factory-installed lifting provisions. PROJECT CONDITIONS Verify dimensions by field measurements. Determine suitable path for moving switchboard into place considering Project conditions. Verify clearance requirements. Locate switchboard to meet installation tolerances.
2 Revise locations and elevations from those indicated as required to suit Project conditions. PART 2 - PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by the following: General Electric Co.; Electrical Distribution and Control Division. Square D Co. 2.2 MANUFACTURED UNITS A. Front-Connected, Front-Accessible Switchboard: Fixed, individually mounted main device, panel-mounted branches, and sections rear aligned. Ratings: Provide nominal system voltage, continuous main-bus amperage, and short-circuit current ratings as indicated on schedules. 2.3 FABRICATION AND FEATURES A. Enclosure Finish for Indoor Units: Factory-applied finish in manufacture's standard gray finish over a rust-inhibiting primer on treated metal surface. Barriers: Between adjacent switchboard sections. Service Conditions: NEMA PB 2, usual service conditions. Bus Transition and Incoming Line Pull Sections: Matched and aligned with basic switchboard. Hinged Front Panels: Allow access to breaker, metering, accessory, and blank compartments. Pull Box on Top of Switchboard: Include the following features: Adequate ventilation to maintain air temperature in pull box within same limits as switchboard. Removable covers forming top, front, and sides. Top covers at rear are easily removable for drilling and cutting. Bottom of insulating, fire-resistant material with separate holes for cable drops into switchboards. Cable supports arranged to facilitate cabling and adequate to support cables indicated, including those for future installation. Buses and Connections: 3 phase, 4 wire, except as otherwise indicated. Features as follows: Phase- and Neutral-Bus Material: Hard-drawn copper of 98 percent conductivity with feeder circuitbreaker line connections. Load Terminals: Silver-plated copper bus extensions equipped with compression connectors for outgoing circuit conductors 400 amp frame and above. Ground Bus: 1/4-by-2-inch (6-by-50-mm) minimum size, drawn-temper copper of 98 percent conductivity; equipped with pressure connectors for feeder- and branch-circuit ground conductors. For busway feeders, extend insulated equipment grounding cable to busway ground connection and support cable at intervals in vertical run. Contact Surfaces of Buses: Silver plated. Main Phase Buses, Neutral Buses, and Equipment Ground Buses: Uniform capacity the entire length of the switchboard main and distribution sections. Provide for future extensions from both ends. Isolation Barrier Access Provisions: Permit checking bus bolt tightness. Neutral Buses: 100 percent of the ampacity of the phase buses, except as indicated, and equipped with approved pressure connectors for outgoing circuit neutral cables. Bus extensions for busway feeder neutral bus is braced. 2.4 OVERCURRENT PROTECTIVE DEVICES A. Enclosed, Molded-Case Circuit Breaker: NEMA AB 1, handle lockable. Characteristics: Frame size, trip rating, number of poles, and auxiliary devices as indicated and interrupting capacity rating to meet available fault current. Application Listing: Appropriate for application, including switching fluorescent lighting loads or heating, air-conditioning, and refrigerating equipment. Circuit Breakers, 200 A and Larger: Trip units interchangeable within frame size. Circuit Breakers, 400 A and Larger: Field-adjustable short-time and continuous current settings. Current-Limiting Trips: Where indicated, let-through ratings less than NEMA FU 1, Class RK-5. Lugs: Compression lugs and power-distribution connectors for number, size, and material of conductors indicated. Shunt Trip: Where indicated.
3 Future Devices: Where indicated, equip compartments with mounting brackets, supports, bus connections, and appurtenances designed for overcurrent protective device types and ampere ratings indicated. 2.5 INSTRUMENTATION A. Instrument Transformers: NEMA EI 21.1, IEEE C57.13, and the following: Potential Transformers: Secondary voltage rating of 120 V and NEMA accuracy class of 0.3 with burdens of W, X, and Y. Current Transformers: Ratios as indicated and accuracy class and burden suitable for connected relays, meters, and instruments. Control Power Transformers: Dry type, mounted in separate compartments for units larger than 3 kv. Current Transformers for Neutral and Ground-Fault Current Sensing: Ground/neutral sensor current transformers located as indicated. Connect secondaries to ground overcurrent relays to provide selective tripping of bus tie and main breaker. Coordinate with feeder breaker ground-fault protection. Multifunction Digital Metering Monitor: Microprocessor-based unit suitable for 3- or 4-wire systems and with the following features: Switch selectable digital display of the following values with maximum accuracy tolerances as indicated: Phase Currents, Each Phase: Plus or minus 1 percent. Phase-to-Phase Voltages, 3 Phase: Plus or minus 1 percent. Phase-to-Neutral Voltages, 3 Phase: Plus or minus 1 percent. Megawatts: Plus or minus 2 percent. Megavars: Plus or minus 2 percent. Power Factor: Plus or minus 2 percent. Frequency: Plus or minus 0.5 percent. Megawatt Demand: Plus or minus 2 percent; demand interval programmable from 5 to 60 minutes. Accumulated Energy, Megawatt Hours: Plus or minus 2 percent. Accumulated values unaffected by power outages up to 72 hours. Mounting: Display and control unit flush or semiflush mounted in instrument compartment door. 2.6 CONTROL POWER A. Control Circuits: 120 V, supplied through secondary disconnect devices from control power transformer. Electrically Interlocked Main and Tie Circuit Breakers: 2 control power transformers in separate compartments with interlocking relays, connected to the primary side of each control power transformer at the line side of the associated main circuit breaker. 120-V secondaries connected through automatic transfer relays to effect a fail-safe automatic transfer scheme. Provide Kirk Key override. Control Power Fuses: Primary and secondary fuses for current-limiting and overload protection of transformer and fuses for protection of control circuits. Control Wiring: Factory installed, complete with bundling, lacing, and protection. Provide flexible conductors for No. 8 AWG and smaller, for conductors across hinges, and for conductors for interconnections between shipping units. 2.7 ACCESSORY COMPONENTS AND FEATURES A. Accessory Set: Include tools and miscellaneous items as required for overcurrent protective device test, inspection, maintenance, and operation. Portable Test Set: Arranged to permit testing of all functions of solid-state trip devices without removal from switchboard. Include relay and meter test plugs suitable for testing switchboard meters and switchboard class relays. Circuit-Breaker Removal Apparatus: Portable, floor-supported, roller-base, elevating carriage arranged for movement of breakers in and out of compartments for present and future breakers. 2.8 IDENTIFICATION A. Nameplates and label products are specified in Division 16 Section "Basic Electrical Materials and Methods." Compartment Nameplates: Engraved laminated-plastic or metal nameplate for each compartment, mounted with corrosion-resistant screws.
4 PART 3 - EXECUTION 3.1 EXAMINATION A. Examine elements and surfaces to receive switchboard for compliance with installation tolerances and other conditions affecting performance of switchboards. Do not proceed with installation until unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Install switchboards level and plumb as indicated, according to manufacturer's written instructions and NEMA PB 2.1. Support switchboards on concrete housekeeping bases, 4-inch (100-mm) nominal thickness. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from switchboard units and components. Operating Instructions: Frame and mount printed, basic operating instructions for switchboards, including control and key interlocking sequences and emergency procedures. Fabricate frame of finished wood or metal and cover instructions with clear acrylic plastic. Mount on the front of switchboards. Provide Framed and mounted One-Line of building electrical system near switchboard. 3.3 CONNECTIONS A. Connect switchboards and components to wiring systems and to ground as indicated and instructed by manufacturer. Tighten electrical connectors and terminals, including screws and bolts, according to manufacturer's published torque tightening values. Where manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B. 3.4 IDENTIFICATION A. Identify field-installed wiring and components and provide warning signs as specified in Division 16 Section "Basic Electrical Materials and Methods." Install compartment nameplates. 3.5 FIELD QUALITY CONTROL A. Prepare for acceptance tests as follows: Make insulation-resistance tests of each switchboard bus, component, and connecting supply, feeder, and control circuits. Make continuity tests of each circuit. Notify Owner of test. Testing Agency: Provide the services of switchboard vendor testing agency to perform specified acceptance testing. Acceptance Testing: After installing switchboards and after electrical circuitry has been energized, demonstrate product capability and compliance with requirements. Procedures: Perform each visual and mechanical inspection and electrical test stated in NETA ATS, Sections 7.1, , 7.9, 7.10, 7.11, and 7.14 as appropriate. Certify compliance with test parameters. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, remove and replace with new units, and retest. 3.6 ADJUSTING A. Set field-adjustable switches and circuit-breaker trip ranges as indicated. 3.7 CLEANING A. Upon completion of installation, inspect interior and exterior of switchboards. Remove paint splatters and other spots, dirt, and debris. Touch up scratches and mars of finish to match original finish. 3.8 DEMONSTRATION A. Startup Services: Engage a factory-authorized service representative to demonstrate and train Owner's maintenance personnel as specified below: To identify each switchboard location.
5 To instruct in function, operation, and maintenance of each component. To instruct in each distinct procedure and schedule related to servicing and preventive maintenance. 3.9 PROTECTION A. Temporary Heating: Apply temporary heat to maintain temperature according to manufacturer's written instructions. End of this Section
SECTION 262413 SWITCHBOARDS
PART 1 - GENERAL... 1 1.1 RELATED DOCUMENTS... 1 1.2 SUMMARY... 1 1.3 DEFINITIONS... 1 1.4 SUBMITTALS... 2 1.5 QUALITY ASSURANCE... 3 1.6 DELIVERY, STORAGE, AND HANDLING... 3 1.7 PROJECT CONDITIONS...
More informationSubmit shop drawings for equipment provided under this section Shop drawings shall indicate:
Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,
More informationSECTION 16341 MEDIUM VOLTAGE SWITCHGEAR
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, apply to this Section. 1.2 SUMMARY A. This Section includes metal-enclosed
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation
Basis of Design This section applies to the design relating to low voltage switchboards. Design Criteria UW Class N1 facilities main switchboards shall be rear accessible. The main, tie and feeder breakers
More information2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.
2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to
More informationBERTHOLD ELECTRIC GENERATOR CONNECTION CABINET
BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET Berthold Electric Company s Generator Connection Cabinet provides a quick and convenient station to connect a portable generator to a facility s main service
More informationPREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to:
PREFACE UL developed the Dead-Front Switchboard Marking Guide for code authorities, electric utilities, contractors, installers, users, designers, and other interested parties to aid in understanding deadfront
More informationSample - No Commercial Use
COMPLETE REVISION October 2010 Electrical PIP ELSSG01 Design and Fabrication of Low-Voltage Metal-Enclosed AC Power Circuit Breaker Switchgear PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort
More informationMCC Ratings. Voltage Rating
MCC Ratings In addition to the various ratings of individual components used in motor control centers, the overall ratings of the motor control center must also be considered. Voltage Rating Motor control
More informationMEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4
CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,
More informationAll work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.
DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,
More informationCircuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services
Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination
More informationSECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated
More informationLearning Module 13: Panelboards and Switchboards. 101 Basic Series
Learning Module 13: Panelboards and Switchboards 101 Basic Series What You Will Learn We ll step through each of these topics in detail: Introduction 4 Definitions 4 Similarities Between Panelboards and
More informationSWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions
SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS POWER DISTRIBUTION RACKS IN A MISSION CRITICAL SYSTEM MODULES IN A MISSION CRITICAL SYSTEM UPS Convertor Main Inverter Load Battery BPC UPS & BATTERY
More information3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance
SPECIFICATION FOR LOW VOLTAGE SWITCHBOARD SEN I N D E X Description 10 STANDARD TECHNICAL REQUIREMENTS 11 Standards 12 General Operating Conditions 13 General Description Of Switchboard 131 Structure 132
More informationSOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings
*** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not
More informationELECTRIC METERING COMMERCIAL & INDUSTRIAL
ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS
More informationMETER REQUIREMENTS GENERAL REQUIREMENTS SECTION D
12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section
More informationSection 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services
Section 9: Power Distribution Equipment Bill Brown, P.E., Square D Engineering Services Introduction Power Distribution Equipment is a term generally used to describe any apparatus used for the generation,
More informationSECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT
SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION A. The Work specified in this Section consists of designing, furnishing and installing factory-assembled
More informationUnified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to
More informationELECTRIC UTILITY SERVICE EQUIPMENT REQUIREMENTS COMMITTEE, EUSERC
ELECTRICAL SERVICE REQUIREMENTS ELECTRIC UTILITY SERVICE EQUIPMENT REQUIREMENTS COMMITTEE, EUSERC TABLE OF CONTENTS TITLE SECTION NO. List of Approved Electric Utility Service Equipment Requirements Committee
More informationPower Management Module 2. Installation
Power Management Module 2 30 300 kva Installation Table of Contents Safety... 1 Safety Instructions... 1 Certification Standards Three Phase... 1 Product Safety... 2 Special Precautions... 2 System Description...
More informationLVA Take Offs in Bid Manager
Electrical Sales and Distributor Training Low Voltage Assemblies (LVA) LVA Take Offs in Bid Manager This job aid helps to define some of the common selection questions that are encountered when configuring
More informationSUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches
SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches PART 1 GENERAL 1.01 Scope Optional Standby Power Generator Systems A. Furnish and install automatic transfer switches
More informationD. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.
SECTION 263354 STATIC UPS TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. System start-up services. 2. Battery charging. 3. Load bank testing. 4. Battery load testing. 5.
More informationSchneider Electric Services: life-cycle solutions for electrical distribution equipment. Scopes of Work for Electrical Acceptance Testing
Scopes of Work for Electrical Acceptance Testing Schneider Electric Services: life-cycle solutions for electrical distribution equipment Make the most of your energy SM Scopes of Work for Electrical Acceptance
More informationEast Central College 14434.03 HANSEN HALL LEVEL 300/400 RENOVATIONS PACKAGE
SECTION 260519 - BUILDING WIRE AND CABLE PART 1 - GENERAL 1.1 WORK INCLUDES A. Base and Alternate Bids: 1. Contractor Provide: a. Building wire and cable as shown on drawings or specified including feeders,
More informationCity of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov
City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov PHOTOVOLTAIC PERMITTING GUIDELINES The information provided in this document is general and is intended only as a
More informationThis section applies to the design and installation of transformers.
ELECTRICAL: TRANSFORMERS BASIS OF DESIGN This section applies to the design and installation of transformers. Design Criteria 13.8-kV equipment shall be 15-kV class. Coordinate with short-circuit studies
More informationHyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
More informationIntroduction. Upon completion of Basics of Switchboards you should be able to: Explain the role of switchboards in a distribution system
Table of Contents Introduction... 2 Distribution Systems... 4 Switchboard Definition... 9 Switchboard Construction... 12 Service Entrance Equipment... 18 Service Section... 20 Switchboard Grounding...
More informationSECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)
SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2
More informationSECTION 26 05 19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
SECTION 26 05 19 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationB. Related Sections: 1. Section 26 05 33 - Raceway and Boxes for Electrical Systems.
SECTION 262726 - WIRING DEVICES PART 1 - GENERAL 1.1 SUMMARY A. Section includes wall switches; wall dimmers; receptacles; multioutlet assembly; and device plates and decorative box covers. B. Related
More informationSecondary Unit Substations
14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically
More informationShort Circuit Current Calculations
Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that
More informationSURGE PROTECTIVE DEVICES (SPDs) LOW VOLTAGE AC INTEGRATED SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS SECTION 16671A SECTION 16671A
SURGE PROTECTIVE DEVICES (SPDs) INTEGRATED UNITS LOW VOLTAGE AC SURGE PROTECTION FOR ELECTRICAL DISTRIBUTION SYSTEMS PART 1 GENERAL 01 02 03 SCOPE The Contractor shall furnish and install the Surge Protective
More informationSECTION 26 09 26 LOW VOLTAGE LIGHTING CONTROLS
SECTION 26 09 26 LOW VOLTAGE LIGHTING CONTROLS PART 1 - GENERAL 1.01 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section
More informationSpecification Guide. for RVAC. Direct Replacement. AC Medium Voltage. Circuit Breakers
Specification Guide for RVAC Direct Replacement AC Medium Voltage Circuit Breakers Table of Contents 1.0 General Work Scope...3 2.0 Standards...3 3.0 Supplier Qualifications...4 4.0 Circuit Breaker Element
More informationA. Shop Drawing submittals shall include, but not be limited to, the following:
SECTION 26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical
More informationARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013
ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 READ CAREFULLY These instructions are intended to cover good practices in
More informationSwitchgear and Metal-Enclosed Bus
Section 18 Switchgear and Metal-Enclosed Bus 180. SWITCHGEAR ASSEMBLIES 180A. General Requirements for All Switchgear. This rule covers general requirements for all switchgear. Examples of switchgear found
More informationELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
More informationWhat are the basic electrical safety issues and remedies in solar photovoltaic installations?
What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic
More informationAMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5
AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC
More informationPrimary and Secondary Electrical Distribution Systems
Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility
More informationHOUSTON COMMUNITY COLLEGE HCC ALIEF CAMPUS MAIN BUILDING, FIRST, SECOND & FOURTH FLOORS RENOVATION ISSUE DATE: 10.17.12
SECTION 27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes grounding and bonding products, design requirements and installation for communications
More informationSECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word
More informationSECTION 26 1316 MEDIUM-VOLTAGE FUSIBLE INTERRUPTER SWITCHGEAR
SECTION 26 1316 MEDIUM-VOLTAGE FUSIBLE INTERRUPTER SWITCHGEAR PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
More informationCOMPARISON OF ANSI/IEEE AND IEC REQUIREMENTS FOR LOW- VOLTAGE SWITCHGEAR
COMPARISON OF ANSI/IEEE AND IEC REQUIREMENTS FOR LOW- VOLTAGE SWITCHGEAR Copyright Material IEEE Paper No. PCIC 2003-13 Eddie Wilkie Eaton Cutler-Hammer 3990 Old Tasso Road NE Cleveland, TN 37312 USA Abstract
More informationSECTION 23 81 43 HEAT PUMPS
SECTION 23 81 43 HEAT PUMPS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Packaged rooftop heat pumps. 1.2 REFERENCES A. American Society of Heating, Refrigerating and Air-Conditioning Engineers:
More informationBussmann. All-In-One Module. Bussmann Power Module Switch. How to configure Part Numbers: Step 1: Select Switch Amperage 1
How to configure Part Numbers: Step : Select Switch Amperage Power Module Switch Rating (Amps) Power Module Switch Catalog No. 30 3 60 6 00 200 2 400 4 Step 2: Select Options Needed 5 Bussmann Power Module
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design
Basis of Design This section applies to the design, installation and integration of metering and monitoring equipment, including: hardware installed in the electrical service and distribution equipment,
More informationPIP ELSSG02 Design and Fabrication of Medium Voltage Metal-Clad Switchgear from 4.76 kv to 38 kv
Electrical Design and Fabrication of Medium Voltage Metal-Clad Switchgear from 4.76 kv to 38 kv Table of Contents 1. Introduction...2 1.1 Purpose... 2 1.2 Scope... 2 2. References...2 2.1... 2 2.2 Industry
More informationInstallation Instructions
H5HK Series Installation Instructions 3 Phase Electric Heater Kits 7.5 and 0 TON Package A/C Systems Description Installation of 08/40V and 480V H5HK 3 Phase Heater Kits in 7.5 and 0 TON Packaged Air Conditioners.
More informationPREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to:
PREFACE Because of changes in installation codes, the increasing complexity of the equipment involved, and other factors, more and more markings are being used on electrical heating and cooling equipment.
More informationAtlanta Chapter IEEE Industry Applications Society
Atlanta Chapter IEEE Industry Applications Society Electrical Equipment Room Design Considerations presented at the Sheraton Buckhead Hotel Atlanta, Georgia November 20, 2006 Outline 1. Definitions 2.
More informationRoof Top Air Conditioner INSTALLATION AND OPERATING INSTRUCTIONS
Roof Top Air Conditioner INSTALLATION AND OPERATING INSTRUCTIONS Ducted System RECORD THIS UNIT INFORMATION FOR FUTURE REFERENCE: Model Number: Serial Number: Date Purchased: This manual must be read and
More informationSECTION 16346A METAL-CLAD MEDIUM VOLTAGE ARC RESISTANT SWITCHGEAR
METAL-CLAD MEDIUM VOLTAGE ARC RESISTANT SWITCHGEAR PART 1 GENERAL 1.01 SCOPE A. The Contractor shall furnish and install the equipment as specified herein and as shown on the contract drawings. 1.02 RELATED
More informationSECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines
PART 1 -- GENERAL 1.1 WORK OF THIS SECTION SECTION 16720 - City of San Diego, CWP Guidelines A. The WORK of this Section includes providing manual and automatic fire alarm and smoke detection systems meeting
More informationMEDIUM VOLTAGE METAL CLAD SWITCHGEAR
MEDIUM VOLTAGE METAL CLAD SWITCHGEAR PART 1 - GENERAL 1.1 DESCRIPTION This section specifies the furnishing, installation, connection and testing of the medium voltage switchgear. 1.2 SWITCHGEAR FEATURES
More informationMCR1900 Media Converter 19-Slot Chassis
MCR1900 Media Converter 19-Slot Chassis Installation Guide Part #5500304-11 Copyright Statement This document must not be reproduced in any way whatsoever, either printed or electronically, without the
More informationCalMod Design-Build Electrification Services
SECTION 28 16 00 INTRUSION DETECTION SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION A. This section describes the detailed technical requirements for the Intrusion Detection System (IDS), where the Contractor
More informationFAQs-Main switchboard design criteria
FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard
More informationINSTALLATION INSTRUCTIONS
LIGHTING CONTROL PANELS 4 AND 8 RELAYS INSTALLATION INSTRUCTIONS INSTALLATION OVERVIEW The installation instructions contained in this document are provided as a guide for proper and reliable installation.
More informationInstallation. Smart-UPS VT MGE Galaxy 3500. Maintenance Bypass Panel. 10-40 kva 400 V
Installation Smart-UPS VT MGE Galaxy 3500 Maintenance Bypass Panel 10-40 kva 400 V Contents Safety.................................................. 1 Save these instructions...................................
More informationThe following components are common to most cubicles; this example is an ABB HK cubicle.
4.0 CIRCUIT BREAKER CUBICLE Learning Objectives The circuit breaker cubicle is the component of the switchgear that holds the circuit breaker, and the controls and cabling for the distribution system.
More informationSan Diego Area Chapter International Code Council
San Diego Area Chapter International Code Council Code Reference Subject Page 90.7 110.14 110.26 11 0.26(E) (2) Approval of Electrical Equipment Torque Requirements Electrical Equipment Rooms Outdoor dedicated
More information2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE
2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE PAGE 1 OF 5 This Reference provides a very comprehensive list of aspects of a solar PV installation that could be reviewed, clarifying
More informationExtend the Life of Existing Switchgear
Extend the Life of Existing Switchgear January 2011/1910DB1002 by Hal Theobald, Product Manager Schneider Electric USA, Inc. Make the most of your energy SM Summary Introduction... p 3 Maintenance Requirements...
More informationGROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264
BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used
More informationOil and Coolant Circulating Heating System. Model - OCSM
Oil and Coolant Circulating Heating System Model - OCSM Installation & Operation Manual 216280-000 REV 2 Identifying Your System The HOTSTART heating system is designed to heat fluids for use in marine
More informationE2 Series Electric Furnaces
E2 Series Electric Furnaces Service Manual Table of Contents Electrical Requirements... 10 Codes, Specifications Requirements... 10 Connection Supply Service Wires... 10 Furnace Sequence of Operation...
More informationHow To Plan Out An Array Of Solar Panels
CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013
More informationSECTION 16426C ARC RESISTANT DRAWOUT SWITCHGEAR (MAGNUM DS) LOW VOLTAGE
ARC RESISTANT DRAWOUT SWITCHGEAR (MAGNUM DS) LOW VOLTAGE PART 1 GENERAL 1.01 1.02 1.03 1.04 SCOPE The Contractor shall furnish and install, where indicated on the drawings, a deadfront type, arc resistant
More informationQuestions and Answers for Heating and A/C Contractors
1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded
More informationMini Power-Zone Unit Substation Product Description. Product Description. Features. Typical Applications
Product Description Product Description The Mini Power-Zone Unit Substation from Schneider Electric is a miniaturized version of our Power-Zone Unit Substation. Included are: Circuit Breaker Sealed Step-Down
More informationCAT ATC POWER BREAKER & POWER CASE SWITCH AUTOMATIC TRANSFER SWITCH
CAT ATC POWER BREAKER & POWER CASE SWITCH AUTOMATIC TRANSFER SWITCH Cat transfer switches are designed for a variety of standby power applications. They provide flexibility, reliability and value in a
More informationA Comparison of Contemporary Electrical Distribution Equipment Standards. San Francisco IEEE Industry Applications Society May 26, 2009
A Comparison of Contemporary Electrical Distribution Equipment Standards San Francisco IEEE Industry Applications Society May 26, 2009 What are Standards? Clearly defined performance characteristics Based
More informationSECTION 15750 PACKAGED ROOFTOP AIR CONDITIONING UNITS
SECTION 15750 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for roof mounted, self-contained units, with electric cooling, and electric or reverse refrigeration cycle (heat pump) heating
More informationMTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation
MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability
More informationRequirements for Electrical Installations
ARTICLE 110 Requirements for Electrical Installations INTRODUCTION TO ARTICLE 110 REQUIREMENTS FOR ELECTRICAL INSTALLATIONS Article 110 sets the stage for how you ll implement the rest of the NEC. This
More informationIRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
More informationD Youville College July 31, 2008 New Academic Building Cannon Design Project No. 002935.00
SECTION 22 6119 - COMPRESSED-AIR EQUIPMENT FOR LABORATORY AND HEALTHCARE PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Packaged, oilless scroll air compressors. 1.2 DEFINITIONS A. Actual Air: Air
More informationParallel Redundant Uninterruptible Power Supply
9 315 Parallel Redundant Uninterruptible Power Supply Installation/Operation Manual 164202013 Rev. D ------------------------------------------------------------------------ ------------------------------------------------------------------------
More informationETC TWO STAGE ELECTRONIC TEMPERATURE CONTROL
RANCO INSTALLATION INSTRUCTIONS ETC TWO STAGE ELECTRONIC TEMPERATURE CONTROL Relay Electrical Ratings PRODUCT DESCRIPTION The Ranco ETC is a microprocessor-based family of electronic temperature controls,
More informationElectrical Grounding. Appendix C
Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment
More informationMini Power-Zone Unit Substation
Catalog 7440CT0901 2009 Class 7440 CONTENTS Description............................................. Page Product Description...........................................2 General Information...........................................3
More informationPart 1 System Modeling & Studies for Existing Systems
Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures
More informationSECTION 26 29 23 VARIABLE FREQUENCY DRIVES
SECTION 26 29 23 VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 SCOPE A. Furnish and install individual freestanding variable frequency AC drives (VFD) as shown on the Drawings and specified herein. 1.02
More informationMike Holt s Illustrated Guide to. Rule 220.87, Articles 445, 700, 701, and 702. Based on the 2011 NEC
Mike Holt s Illustrated Guide to NEC Requirements for Generators and Standby Power Systems Rule 220.87, Articles 445, 700, 701, and 702 Based on the 2011 NEC Extracted from Mike Holt s Illustrated Guides
More informationAddendum #2 Contract UK-11-13
Addendum #2 Contract UK-11-13 Utilities Kingston Purchase and Replacement of Switchgear at Kingston Hydro Substation MS11 March 25, 2011 Delivered to: All RFP recipients Total number of pages: Nine (9)
More informationElectronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600
Electronic Trip Circuit Breaker Basics Circuit Breaker Application Guide Class 0600 Data Bulletin 0600DB1104 03/2012 Retain for future use. Electronic Trip Circuit Breaker Basics 0600DB1104 Table of Contents
More informationFFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid
Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars Presented By: Greg Pelster & Robert Schmid FFI Ferrie, Franzmann Industries LOW VOLTAGE SWITCHGEAR & LOW VOLTAGE
More informationWE-350 Series ¼ Turn Electric Actuator
WE-350 Series ¼ Turn Electric Actuator Operation and Installation Manual Pg 1 (Rev. 020113) Table of Contents 1.0 General 1.1 Pre-Installation Inspection 1.2 Storage 1.3 Features & General Information
More informationUtility Distribution Systems
Utility Distribution Systems 6/2012 A0011037 1 WARRANTY This equipment is warranted to be free from defects in materials and workmanship, under normal use and service, for a period of 12 months from date
More informationSWITCHGEAR. EGP Switchgear
SWITCHEA EP Switchgear Cat generator set paralleling switchgear has been designed to integrate with Cat EMCP3 generator set controls. Now you can get greater efficiency, reliability and dependability all
More informationArc Flash Hazards. Electrical Hazards. Dan Neeser Field Application Engineer DanRNeeser@Eaton.com. Electrical Hazards 2/18/2015. Shock.
Arc Flash Hazards Dan Neeser Field Application Engineer DanRNeeser@Eaton.com Electrical Hazards Electrical Hazards Shock Arc Flash Arc Blast 2 1 Arcing Fault Basics 35,000 F Radiant Heat & UV Speed of