Data Migration Assessment
|
|
|
- Jordan Cobb
- 9 years ago
- Views:
Transcription
1 Data Migration Assessment
2 Table of Content 1 Executive Summary Scope of Work Approach for Data Migration Assessment Key Findings Consequences Recommendations Scope of Work Methodology for Data Migration Assessment Limitations Approach and Methodology Approach Data Migration Fundamentals Methodology Chronology of Events Findings and Consequences Assessment of the EFI Data Migration Analysis Phase Key Findings Assessment of the EFI Data Migration Design Phase Key Findings Assessment of the EFI Data Migration Build Assessment of the EFI Data Migration Testing Key Findings Assessment of the EFI Data Migration for Key Findings Appendix Documents Examined List of Meetings P a g e
3 1 Executive Summary 1.1 Scope of Work The scope of this Data Migration Assessment was to review the process that was performed for the migration of claim and treatment data for the EFI Programme. It therefore includes assessing key tasks in the analysis, design and testing of the data migration. Accenture has reviewed the timeline, methodology and sequence of events from the start of the data migration effort in 2009 until the EFI+DMI System went into operation in September This report is based on review of the documents listed in Appendix 6.1 from the data migration process for the EFI Programme. The purpose of the review has not been to consider who is responsible for the decisions taken during the project execution. The report does therefore not include a legal review of the contractual obligations in the EFI and DMI contracts and the report can thus not be used to conclude whether or to what extent any of the parties involved in the project execution can be held legally responsible for their involvement in the project. The assessment is made based on our experience and on assumption that the conclusions in the assessment are representative also for the data migration documents that have not been reviewed. 1.2 Approach for Data Migration Assessment The assessment has been conducted by examining key documents and conducting interviews with key people involved in the data migration for the EFI Programme. The documents reviewed and the interviews conducted are listed in Appendix 6.1. The examination of documents started with the original requirements for data migration and ended with a report describing the deficiencies in data in the EFI+DMI System after go-live. Interviews were conducted in order to clarify facts in the documents reviewed. Accenture s Delivery Methodology for Data Migration was used as a reference for generally accepted IT industry normal practices of data migration projects. For each stage of the methodology, we have assessed the facts as evidenced by the documents reviewed versus a normal practice approach. Accenture did review the documents listed in Appendix 6.1, which cover: Original Requirements for data migration Strategy and planning documents Status reports Meeting notes correspondence, including attachments Results from our EFI Technical Analysis 2 P a g e
4 Accenture did not review: Detailed design documentation, e.g. field mappings or program logic Test case documents Contract documents not specifically related to data migration 1.3 Key Findings Accenture s assessment has identified the following: Scope, Planning and Management of Data Migration A comparison of the strategy and planning documents for data migration with the status reports from the migration trials revealed that: Not all the entry/exit criteria for the migration trials, as stated in the plan, were adhered to during the execution of the data migration trials The end-to-end testing of EFI and DMI with the migrated data was not completed Data Cleansing Cleansing of source data with deficiencies prior to migration is a vital task according to the methodology. Although there was a clean-up list defined and the data cleansing activity was tracked, we found that: Status green had been reported although there were a number of unfinished activities listed The data cleansing still did not prevent data with e.g. incorrect amounts from being migrated Data Migration Testing Accenture s Methodology for Data Migration calls for repeated migration trials of all the relevant data until the migration trials are successful - before migrating data to production. Our analysis of the plan, the summary status reports from the migration trials and post migration status reports found that: None of the data migration trials (PK1, PK2, PK3, PK4) were on a full scale (100% of source system data) the most extensive migration trial, PK4, was limited to ~49% the amount of data in the production migration The summary status reports for each of the migration trials (PK1, PK3, PK4) reported that the trials were completed, although there were listed remaining defects that were still to be fixed As the EFI Modtag Fordring (MF) component, as well as EFI+DMI, were under development and testing during the migration trials, it is a fact that neither the application used for migration (MF) nor the target System (EFI+DMI) were tested in their final state with the migrated data. The testing was therefore inconclusive and 3 P a g e
5 invalid, as it was done on earlier versions of MF, EFI and DMI than the versions used during the production and production Only limited testing of the migrated data was performed in a test phase (pilot) between PK4 and go-live. The end-to-end testing of EFI with the migrated data that was described in the plan was not performed Deployment / Go-live A review of the summary status report from the last migration trial PK4, revealed that: The scope of PK4 had been reduced and had not covered 100% of all data to be converted. Only ~49% of source data was attempted converted in PK4 The exit criteria for PK4 had been reduced compared to those listed for PK2 in the plan. PK4 would not have passed the exit criteria if they had been used as specified in the plan The summary status report from PK4 still concluded with a recommendation that PK4 be approved and that the project could continue to the production migration, with prioritized risk reduction actions and defect corrections The steering committee of the EFI Programme made the go-live decision following the PK4 summary status report recommendation 4 P a g e
6 Figure 1 Accenture Data Migration Methodology and highlighted shortcomings in the EFI migration project. In Summary The diagram above illustrates the major tasks of data migration according to Accenture s Methodology for Data Migration. The callouts in yellow indicate where our findings from the data migration of EFI and DMI deviated from the methodology s approach. The evidence is clear that Less than half of the combined body of data in all source systems were ever included in migration trials prior to the production. The validation of incoming data was not sufficient to prevent incorrect claims being migrated The migrated data was not tested end-to-end with the EFI+DMI system before the production migration These facts are the most important deficiencies of the data migration project and constituted a high level of risk that the data migration would not be successful. 5 P a g e
7 1.4 Consequences The consequences of the EFI data migration were: Data was migrated into the EFI+DMI System that could not be processed correctly by the system. As the EFI+DMI system had not been thoroughly tested with the migrated data it could not be expected that it would be able to process the migrated data correctly The EFI+DMI System was designed to handle data without deficiencies and Modtag Fordring did not include sufficient data validation to ensure that only correct and complete data was entered into EFI. For instance claims were placed on treatments where the claim type treatment combination is not allowed As of 2 years post go-live it has not been possible to enable much of the disabled automated functionality originally intended in EFI, due to a variety of functionality and data related issues which are still not fixed, e.g. incorrect expiration dates on claims 1.5 Recommendations In order to recover large portions of the affected data, with a view at one point to continue operation with new systems, a data cleansing exercise should be performed to detect and correct data issues introduced by the data migration or subsequent operation. The data cleansing should be aligned with other functional and technical changes being planned, and will require more focus on clear requirements and testing. The data cleansing will be complex and lengthy, and is likely to be able to resolve only a portion of the known data issues. 6 P a g e
8 2 Scope of Work The scope of this data migration assessment was to review the process that was performed for the migration of claims and treatments data for the EFI Programme. It therefore includes assessing key tasks in the analysis, design and testing of the data migration. Accenture has reviewed the timeline, methodology and sequence of events from the start of the data migration effort in 2009 until the EFI+DMI System went into operation in September Methodology for Data Migration Assessment The assessment has been conducted by examining key documents and conducting interviews with key people involved in the data migration for the EFI Programme. The documents reviewed and the interviews conducted are listed in Appendix 6.1. The examination of documents started with the original contracted requirements for data migration and ended with a report describing the deficiencies in data in EFI after go-live The interviews were conducted in order to clarify facts in the documents reviewed. Accenture did review the documents listed in Appendix 6.1, which cover: Contract documents concerning the data migration Strategy and planning documents Status reports Meeting notes correspondence, including attachments Results from our EFI Technical Analysis Report and Technical Report Accenture did not review: Detailed design documentation, e.g. field mappings or program logic Test case documents Contract documents not specifically related to data migration Accenture s assessment of the data migration process documents: Started with the documents made available to us from the EFI Programme at the start of the assessment We have requested and obtained a number of additional documents based on document references found in the first documents we reviewed Our examination of documents has not been exhaustive, but focused on obtaining a logical sequence of documents describing the EFI data migration from start to end 7 P a g e
9 The main focus of this data migration assessment were: To assess the production data migration that was done in Aug/Sep 2013 to migrate claims and treatments from the source systems into EFI and DMI before EFI and DMI were put into production in Sep 2013 To examine the critical tasks that were performed in preparing for the data migration, including the validation of the data migration through testing 2.2 Limitations The scope of this data migration assessment was to review the process that was performed for the migration of claims and treatments data for the EFI Programme. It therefore includes assessing key tasks in the analysis, design and testing of the data migration. Accenture has reviewed the timeline, methodology and sequence of events from the start of the data migration effort in 2009 until the EFI+DMI System went into operation in September This report is based on review of the documents listed in Appendix 6.1 from the data migration process for the EFI Programme. The purpose of the review has not been to consider who is responsible for the decisions taken during the project execution. The report does therefore not include a legal review of the contractual obligations in the EFI and DMI contracts and the report can thus not be used to conclude whether or to what extent any of the parties involved in the project execution can be held legally responsible for their involvement in the project. The report is made based on our experience and assumption that the conclusions in the report are representative also for the data migration documents that have not been reviewed. 8 P a g e
10 3 Approach and Methodology 3.1 Approach Accenture s approach for this assessment was: Review of the documentation as listed in the Appendix Accenture s Delivery Methodology for Data Migration was used as a baseline of the tasks that should be performed in a data migration process and for which we looked for documented evidence that had been done For each stage of the methodology we have assessed the facts as evidenced by the documents reviewed Develop a preliminary report with findings, including references to the documents reviewed Conduct interviews with key individuals who had been involved in the data migration process, as listed in the Appendix, to answer key questions and to ensure that essential relevant documentation had been located and reviewed Review all findings with stakeholders 3.2 Data Migration Fundamentals This section briefly describes the fundamentals of data migration. Data are the valuable business records, which are the reason for a business to exist. Data migration involves movement and transformation of data from a source system and format into a format that another system can process. Typically, the target system includes different functionality or changed processes that require changes to the data. Data from legacy source systems usually requires a clean-up effort (e.g. correcting addresses, deduplicating), which usually is performed in the legacy source systems prior to migration. The data to be migrated is then extracted from the source system and mapped and transformed, as needed, into the required format that can be loaded into the target system. With large amounts of data to be migrated, the extraction, transformation and loading requires use and configuration of ETL software or custom coded software to be built for the job. This migration software must be thoroughly tested prior to performing the data migration. Because of the variations normally found in source data and the complexity of mapping and transformation, the migration effort usually requires a number of trial runs before everything works for all the data, this is called migration trials. The ultimate goal of data migration is to ensure that the target system will be able to process the migrated data correctly. This requires that: The target system must first have completed testing with prepared (controlled) test data, this is a prerequisite for the following step Then the target system must be tested with the migrated data to validate that it is in fact capable of processing the migrated data correctly 9 P a g e
11 The testing described in the previous paragraph is normally a test of all relevant business scenarios from start to finish; normally referred to as case based testing or end-to-end testing. The term data is often used instead of and interchangeably with data migration. 3.3 Methodology Accenture s Delivery Methodology (ADM) for Data Migration is used as a reference for generally accepted industry practices of data migration. The methodology is organised into a five-step process with a standard set of tasks to be performed. A: Data Migration Analysis A1: Identify and agree on data migration requirements, approach and responsibilities. Systematic breakdown of high-level requirements into detailed requirements that are traced back to the high-level requirements, in the form of a Requirements Traceability Matrix A2: Define the scope of data to be migrated, and migration rules. Data profiling of 100% of the data to be migrated, to assess data quality, volume and number of variants A3: Define and agree on any data clean-up to be performed, prior to migration A4: Define the total migration approach, which includes all relevant aspects of the data migration (all data sources, all variants). Decide on single migration (big bang), phased or incremental approach B: Data Migration Design B1: Design how each item of data is to be mapped and migrated from source to target B2: Design how the migration will be validated through testing B3: Define non-functional aspects (i.e. performance / available time window for the full migration to be processed) C: Data Migration Build C1: Build and test the migration programs D: Data Migration Testing D1: Testing of the new system with prepared test data (precondition for the next steps) D2: Repeated trial migrations, until all data migration procedures and jobs are working as intended for all the data to be migrated D3: Testing of the new system processes (end-to-end) with the migrated data E: Data Migration E1: Go-live decision E2: Final migration run E3: controls, to confirm that the migration has been successful in the production environment. 10 P a g e
12 4 Chronology of Events Based on our review of all the documentation and interviews listed in the Appendix we have drawn the following high-level timeline for the data migration of the EFI Programme from start to finish. ID Task Name 2008 Q Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1 Migration Strategy (EFI) 2 Migration Trial 1 (PK1) 3 4 Migration Strategy for EFI+DMI (no documented strategy found) Migration Build 5 Migration baseline documentation 6 Migration Trial 2 (PK2) 7 Migration Trial 3 (PK3) 8 Migration Trial 4 (PK4) 9 Migration 10 Data Validation 11 Go Live Decision Figure 2 EFI Data Migration Timeline Based on Accenture experience with comparable projects, we have the following comments to the timeline: The initial migration trial seems short, only ~ 2 months. With a data migration of this scale, approx months would have been expected for the initial task, as it should involve profiling of all the data to be migrated, definition of migration rules etc. With a data migration of this scale, we would have expected ~10 data migration trials. Each of these would have the following characteristics: Would be full scale, including all the data to be migrated The final 2-4 data migration trials would be essentially identical to the production migration, in order to fine-tune the migration approach before the production migration According to Accenture s data migration methodology, the final task is Confirm migrated data, as data validation is done as an integral part of the data migration trials, not as a separate activity afterwards 11 P a g e
13 In a data migration project of this scale, according to Accenture s methodology and experience, the timeline and activities would have been more in line with what is indicated below. ID 1 Task Name Migration Strategy & Analysis Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2 Migration Design 3 4 Migration Build Migration Trial 1 5 Migration Trial 2 6 Migration Trial 3 7 Migration Trial 4 8 Migration Trial 5 (end to end w app) 9 Migration Trial 6 (end to end w app) 10 Migration Trial 7 (end to end w app) 11 Migration Trial 8 (identical to live) 12 Migration Figure 3 Expected Data Migration Timeline According to the Data Migration Methodology, the total data migration effort would run in parallel with systems development for most of the duration of the project. However, we normally would have recommended a more concentrated project effort to reduce the timeline to e.g. 2 2½ years in order to reduce the risk of scope changes during the migration. The remainder of the document deals with the assessment of the data migration work that was done, as evidenced by the documents reviewed and the interviews conducted. The report has been structured according to the phases of the Data Migration Methodology. 12 P a g e
14 5 Findings and Consequences 5.1 Assessment of the EFI Data Migration Analysis Phase This section describes Accenture's assessment of the analysis phase of the EFI data migration project. We identified the following documents as the most relevant for the assessment of the analysis phase: Ref.# Category (used for sorting) Document title 2 Contract L21 Underbilag - EFI Konvertering.doc 3 Strategy Konvereteringsstrategi v1.2.pdf 4 Plan Konverteringsplan EFI v09 CSC KONV 7 PK2 Opsamlingsskema for test PK2.docx 9 PK Oprydningsliste til IU 10 PK3 05 b KFL_Prøvprøvekonvertering 3 afrapportering v0_2 [DOK ] ( _1).DOCX 17 PK4 16 Prøvekonvertering 4 afrapportering v0_3 [DOK ] ( _1).DOCX Produktionskonvertering afrapportering v0_8 ( ).docx Bilag B - Tværgående konverteringsmangler ( _2) (2).docx Table 1 Overview over Relevant Documents for Assessment of Analysis Phase Information in the documents listed above was compared to what is to be expected in the analysis phase of a data migration project, based on ADM for data migration. Our assessment focused on answering the following key questions: Were the requirements [1] sufficient to define the scope of work? Was there a documented data migration approach, and was this appropriate to manage the work? Was all the data and variants to be migrated identified and analysed during the analysis phase? And was the need for data cleansing appropriately addressed? Key Findings Data Migration Requirements Based on our review of the original requirements for data migration the EFI Programme, as listed in [1], Section 1.2, it is our observation that these were few and high-level. According to interview 3, the only detailing of requirements that was made are in the form of mapping rules which are documented in Excel documents per treatment type and in the 13 P a g e
15 Informatica portal, plus specified data formats that the source system owners were to deliver data in to the migration team. It is our evaluation that the detailing of the original requirements [1] were lacking the hierarchical breakdown structure which is required for defining all the tests that are necessary in order to validate the full data migration effort. Data Conversion Strategy and Planning Based on our review of the data strategy [3], data plan [4] the production migration report [34], our observations are that: The initial strategy only covered EFI Separate data strategy documents for EFI and DMI had been developed prior to EFI and DMI being gathered into one organization [34], Section 1.1. (Our document review has not identified the data strategy document for DMI) There was a change to the strategy [34], Section 1.1 after PK1: SKAT wanted to introduce the principle of taking the debts directly from the claimants (our translation). The strategy document [3] was not updated with the modified strategy, but it was reflected in the plan [4] The data plan describes an overall time plan for data migration trials, organization of the data migration effort and entry and exit criteria for the data migration trials It is our evaluation that although the strategy document was not updated, the planning document [4] for the migration trials was updated and contained the basic high-level information required for managing the migration trials Analysis of All Data and Variants to be Migrated According to interview 3, data profiling had only been done on external data, not SKAT data. It is our evaluation that: Not all data and variants that were to be migrated were identified in the migration trial PK1, before subsequent migration trials were executed. According to [30] PK1 was insufficient because the data in KMD-IND lacked the details that was wanted in EFI (split of claims in main claim and sub-claims (interest, fees)). None of the migration trials PK2, PK3, PK4 were on 100% of the data, as the number of source systems and the volume of the data that was included increased for every trial, but PK4 still didn t cover all the data to be migrated 14 P a g e
16 Need for Data Cleansing of the Source Systems A data clean-up list [9] was defined, but according to interview 3 this covered only SKAT internal data. Data clean-up status was tracked [9], but although a number of areas were marked as green there were still unfinished clean-up tasks listed. It is our evaluation that data cleansing of the source systems was insufficient or not done, because e.g. fields with incorrect values were migrated to EFI+DMI, according to [46]. 5.2 Assessment of the EFI Data Migration Design Phase This section describes Accenture s assessment of the design phase of the EFI data migration project. We identified the following documents as the most relevant for the assessment of the design phase: Ref.# Category (used for sorting) Accenture deliverable Document title Produktionskonvertering afrapportering v0_8 ( ).docx Bilag B - Tværgående konverteringsmangler ( _2) (2).docx Technical Report.docx Table 2 Most Relevant Documents for Assessment of Design Phase Information in the documents listed above was compared to what is to be expected in the design phase of a data migration project, based on ADM for Data Migration. Our assessment focused on answering the following key questions: Did the data migration design documents include the necessary controls to secure that only quality data was migrated and all non-conforming data written to error logs? What data controls were designed into Modtag Fordring, the part of EFI through which the vast majority of claims were migrated? (Modtag Fordring is the interface through which claimants submit their claims to EFI+DMI) Key Findings Based on our examination of the documents it is observed that the design documentation has not been sufficient to prevent invalid data from being inserted into EFI because it was discovered, after the production migration that crucial details were missing such as decisions for salary deductions [46]. According to the final report [34], Section 1.1, claims were migrated using the Modtag Fordring application, where it was temporarily allowed to accept historic claims as part of the migration. Treatments (indsatser) were migrated using the ETL tool Informatica. This is consistent with statements from interview 3, where the Konsortium stated that claims were migrated using the Modtag Fordring interface, where an exception flag had 15 P a g e
17 been added to the Web service message to Modtag Fordring to also accept historic claims. Validation in MF is based on a number of things [see Technical Report]: WSDL and/or XSD validation on the enterprise service bus (ESB) Matrix configurations, which are rules matrices for e.g. which claimants are allowed to submit which types of claims Administrator configuration, which is based on super user configuration of the system via the user interface. E.g. selecting which fields are on different types of claims, and whether they are mandatory Accenture have shown in our Technical Report [57], that Modtag Fordring does not include validations to ensure that only valid claims can enter the system. E.g. when MF was used to load claims in the migration, claims were accepted and put on a treatment for which the claim type was not justified. There is no sanity checking on key fields, e.g. to ensuring that dates are in a proper time sequence for the claim to be in a valid state, and the amount of debt is not sanity checked [46]. 5.3 Assessment of the EFI Data Migration Build No specific comments. 5.4 Assessment of the EFI Data Migration Testing This section describes Accenture s assessment of the testing of the EFI data migration project. We identified the following documents as the most relevant for the assessment of the testing that was done: Ref.# Category (used for sorting) Document title 3 Strategy Konvereteringsstrategi v1.2.pdf 4 Plan Konverteringsplan EFI v09 CSC KONV 5 PK1 Prøvekonvertering 1 afrapportering PK2 Opsamlingsskema for test PK2.docx 10 PK3 05 b KFL_Prøvprøvekonvertering 3 afrapportering v0_2 [DOK ] ( _1).DOCX 12 FKT FKT reduktion og færdiggørelse.docx 17 PK4 16 Prøvekonvertering 4 afrapportering v0_3 [DOK ] ( _1).DOCX 34 Produktionskonvertering afrapportering v0_8 ( ).docx 16 P a g e
18 46 Table 3 Relevant Documents for Assessment of Testing Bilag B - Tværgående konverteringsmangler ( _2) (2).docx Information in the documents listed above was compared to what is to be expected in the testing of a data migration project, based on ADM for Data Migration. Our assessment focused on answering the following key questions: Was the pre-condition on a stable, tested EFI+DMI System met? Did the migration trials cover 100% of the data to be migrated, and did the trials continue until they were successful? Had the system passed end-to-end testing with the migrated data? Key Findings Testing with Prepared Test Data It is our observation from the trial migration reports PK1, PK3 and PK4 that EFI+DMI and Modtag Fordring were not thoroughly tested and were not stable during the migration trials. It is our evaluation that since the target system was not stable and tested during the migration trials, the validation of data migration that was performed during each of the trials were inconclusive in terms of what would work in the production system. Migration Trials None of the migration trials PK1, PK2 (we have not seen this report, however it is stated [10] that this was the case), PK3 and PK4 represented a complete data migration trial, hence, there was no full migration trial performed prior to the production data migration. Mapping rules for treatments were adjusted after each migration trial, also after PK4 [3]. In the final migration trial - PK4, the following was the result as stated in [17]: ~9.3 million out of ~19.1 million claims attempted to be migrated (49% of total claims) EFI rejected a significant number of claims, for multiple reasons including a lack of AKR functionality (customers that could not be reconciled with CPR or CVR) The balances in EFI and DMI did not reconcile, post migration There was a high probability that EFI would automatically mail 600,000 debtors immediately Payment ability (BeBB) calculations were not usable Assignment of automatic treatments were not usable o As a direct result of this testing, most automated functionality was disabled before go-live (the pilotspor was used instead) A number of remaining defects were listed 17 P a g e
19 The summary status reports for each of the migration trials (PK1, PK3, PK4) [5, 10, 17] reported that the trials were completed, although there were listed remaining defects that were still to be fixed. (The summary status report for PK2 has not been identified). Testing with the Migrated Data Based on our examination, testing on migrated data was written into the strategy [3], Section , and [4], Section 4: A regression test on migrated data, where selected test cases from test of functionality (FKT) is applied on migrated data, in order to validate that migrated data supports the EFI-functionality. The final regression test is to validate that migrated data will function in EFI-processes (our translation). End-to-end testing of EFI+DMI with migrated data had not been completed prior to go-live, hence it had not been proven that EFI+DMI were able to process the migrated data correctly from being received through Modtag Fordring and processed through all the variations of treatments and claimants. According to interview 4, the migration team only checked that the migrated data had been imported correctly into EFI, by checking the fields using EFI screens. This is not according to the strategy or the plan, where it is stated that an end-to-end test with migrated data was to be performed. According to [34], Section 1.3.1: It was only in the pilot that it has been possible to do functional testing of migrated data. Functional testing was performed to a limited degree in the Pilot (our translation). The pilot test was a test between PK4 and the go-live. Based on a review of a letter [12], there was a decision by the EFI project manager to limit the amount of functional testing in order to meet the September 1 st 2013 deadline for golive. Although scope reduction is a common thing to do in order to meet a set go-live date, it is Accenture s evaluation that two very risky decisions were taken: Retesting of fixed defects were not to be done before go-live. This is extremely risky as the need to retest defect corrections is common practice in any testing effort (regression test). Reduction of the end-to-end testing was to be compensated by a pilot and other relevant activities, but there is no description of what kind of activities that were intended to compensate for the lack of sufficient testing. The evidence is clear on the fact that less than half of the combined body of data in all source systems were ever included in migration trials prior to the production migration. That and the fact that the migrated data was not tested end-to-end in EFI+DMI are the single most important deficiencies of the data migration project. There is no way to predict how data will behave in a system if it has not been tested sufficiently, i.e. through testing end-to-end business processes on an amount of data which represents all the data variants that will come from the source systems. 18 P a g e
20 5.5 Assessment of the EFI Data Migration for This section describes Accenture s assessment of the EFI production data migration. We identified the following documents as the most relevant for the assessment of the production migration: Ref.# Category (used for sorting) Document title 4 Plan Konverteringsplan EFI v09 CSC KONV 5 PK1 Prøvekonvertering 1 afrapportering PK2 07 Konverteringsstyregruppe møde opd [DOK ] ( _1).PPTX 10 PK3 05 b KFL_Prøvprøvekonvertering 3 afrapportering v0_2 [DOK ] ( _1).DOCX 17 PK4 16 Prøvekonvertering 4 afrapportering v0_3 [DOK ] ( _1).DOCX 18 PK4 31 Afrapportering PK4 [DOK ] ( _1).PPTX 24 PK4 09 Referat EFI_DMI konvertering [DOK ] ( _1).DOCX bilag 1 - mail fra SKAT af Bilag 2 - mail fra SKAT af Produktionskonvertering afrapportering v0_8 ( ).docx Bilag B - Tværgående konverteringsmangler ( _2) (2).docx Table 4 Relevant Documents for Assessment of Migration Information in the documents listed above was compared to what is to be expected in the production migration phase of a data migration project, based on ADM for Data migration. Our assessment focused on answering the following key questions: On what basis was the go-live decision made? Was the final data migration run successful? Key Findings Go-live Decision The plan [4] Section 5, 6 and 7 defined exit criteria for migration trials. The commonly accepted and sole purpose of defining exit criteria is that unless these criteria are met, the activity is not to be regarded as completed. Based on our examination of the 19 P a g e
21 PK4 summary status report [17] it is observed that a complete migration trial of data from all sources was not completed, because Udbetaling Danmark (UDK) was not participating. Based on our examination of the trial migration reports from PK1, PK3 and PK4 [5, 10, 17] and the summary status report from the production [34] it is our observation that: None of the 4 migration trials tested a full load of data from all sources The exceptions (data migration defects) listed in PK3 and PK4 were not managed to a conclusion before moving on to the next trial migration. Overall status green was set for each of the migration trials despite the fact that there were remaining deficiencies and when the identified exceptions had been assigned to be fixed, without waiting till after the exceptions had been fixed and retested. Despite the above shortcomings, the status report from PK4 [17], Section : concluded with: It is recommended to finalize and approve migration trial 4 and it is recommended that the production migration can be performed on the current basis plus risk evaluated and prioritized defect corrections and changes (our translation). It is our evaluation that the team should not have recommended to the steering group of the EFI Programme that the data migration could proceed to the production migration. Each of the deficiencies listed above should have mandated a clear no-go decision, according to Accenture s Data Migration Methodology. Final Migration Run The status report from the production migration [34] lists a substantial number of defects that were detected during go-live: Claims from DMO with incorrect liability Transports with incorrect payment period Missing expiration dates from DMO Errors in calculation of payment ability Expiration dates for RIS claims erroneous due to PEF rules in DMI Accenture has done profiling of the migrated data in EFI and DMI which shows that the length of time since a payment was last received on migrated claims is so long that in our opinion they are effectively not being collected. It was the decision of the project s steering group [28, 29] to move claims into EFI where it was known that subsequent manual tasks were necessary in order to process the claims correctly. 20 P a g e
22 6 Appendix 6.1 Documents Examined The following table lists the documentation examined for the data migration assessment. All documents in the list have been examined and where it is especially relevant to explicitly reference a document, and sections of a document, this has been done in the text of the report. Ref. # 1 Category (used for sorting) Original requirement Document title 1. EFI 02 Leverandørens kravopfyldelse S v1_00 s 2 Contract L21 Underbilag - EFI Konvertering.doc 3 Strategy Konvereteringsstrategi v1.2.pdf 4 Plan Konverteringsplan EFI v09 CSC KONV 5 PK1 Prøvekonvertering 1 afrapportering PK2 33 Imødegåelse af trusler mod EFI go-live i maj 2013 klh [DOK ] ( _1).PPTX 7 PK2 Opsamlingsskema for test PK2.docx 8 PK2 07 Konverteringsstyregruppe møde opd [DOK ] ( _1).PPTX 9 PK Oprydningsliste til IU 10 PK3 05 b KFL_Prøvprøvekonvertering 3 afrapportering v0_2 [DOK ] ( _1).DOCX 11 PK3 01 EFI stg ekstra PK oplæg v2 [DOK ] ( _1).PPTX 12 FKT FKT reduktion og færdiggørelse.docx 13 FKT Kopi af ANH FKT oplæg uge 16og17 v3.xlsx 14 FKT ANH FKT oplæg uge 16og17.xlsx 15 FKT Stormøde docx 16 PK4 17 PK4 11 Konverteringsstyregruppe møde [DOK ] ( _1).PPTX 16 Prøvekonvertering 4 afrapportering v0_3 [DOK ] ( _1).DOCX 18 PK4 31 Afrapportering PK4 [DOK ] ( _1).PPTX 19 PK4 32 Drejebog PK4 gennemløb_0_4 (DOK ) ( _1).XLSX 21 P a g e
23 20 PK4 08 Konverteringsstyregruppe møde [DOK ] ( _1).PPTX 21 PK4 Konverteringsstyregruppe møde pptx 22 PK4 23 PK4 24 PK4 25 PK Referat EFI_DMI konvertering [DOK ] ( _1).DOCX 04 Referat EFI_DMI konvertering [DOK ] ( _1).DOCX 09 Referat EFI_DMI konvertering [DOK ] ( _1).DOCX 10 Konverteringsstyregruppe møde [DOK ] ( _1).PPTX Trusler mod opstart og ibrugtagning af EFI - oktober 2013 til udlevering Imødegåelse af trusler mod EFI go-live i september bilag 1 - mail fra SKAT af Bilag 2 - mail fra SKAT af Bilag 3 - MF_TEST_resultat_ Brev til SKAT Konvertering Afstemningsrapport EFI produktionskonverterig Notat.docx Produktionskonvertering afrapportering v0_3x.docx Produktionskonvertering afrapportering v0_8 ( ).docx VS Idriftsættelse - forberedelse af konvertering mm.msg 02 BEO_KonverteringsPostscripts [DOK ] ( _1).DOCX 03 Konvertering Post-Skript BOB V [DOK ] ( _1).DOCX 15 Idriftsættelsesstg defect status slides [DOK ] ( _1).PPTX 17 Referat EFI_DMI idriftsættelse [DOK ] ( _1).DOCX 28 EFI DMI - Hovedtidsplan opstart v3 [DOK ] ( _1).PPTX 34 Idriftsættelsesstyregruppe etablering v02 juli 2013 [DOK ] ( _1).PPTX 22 P a g e
24 Verdensbillede.pptx b Teknisk konvertering referat eftermiddag [DOK ] ( _1).DOCX b Teknisk konverteringsproces rev maj12 [DOK ] ( _1).DOCX 45 EFI DMI prodkonvertering afrapportering v01.pptx 46 Bilag B - Tværgående konverteringsmangler ( _2) (2).docx 47 Dag til dag Cutover plan - EFI xlsx 48 Processer i lukkeperioden EFI (3).docx 49 Kopi af ANH FKT oplæg uge 16og17 v FKT reduktion og færdiggørelse SKMI0168S PA EFI-statusrapportering - SKAT systemmodernisering fase 2 v juli_UdfordringerttilLøsningnu_ved samletchefgruppe_forretning_teknik_projekt-pb.xlsx EFI Review - Mgmt præsentation - v Imødegåelse af trusler mod EFI go-live i maj 2013pptx Imødegåelse af trusler mod EFI go-live i september Bilag_2_EFI leverancer 57 Accenture deliverable Technical Report.docx 58 Other BEBB Kunde.docx 59 Other REV Diverse planer for EFI.msg 60 Other 06 b Fordringer_analyse_konklusion_v1_41_kommenteret[1] [DOK ] ( _1).DOCX 61 Other 27 b liste_man_tina (DOK ) ( _1).XLSX 62 Other 27 b mapningstabel_henlaeggelser_v08_2013_06_21_efter_prod_kon v (DOK ) ( _1).XLSX 63 Other Oplæg til workshop V4.pptx 64 Other Copy of SKMI0168S PA EFI-statusrapportering - SKAT systemmodernisering fase 2 v3 2.xls 65 Ministry of Finance Bilag_2_EFI leverancer ( ).pdf Table 5 Documents Examined 23 P a g e
25 6.2 List of Meetings The following interviews were conducted with stakeholders in the EFI data migration project: Interview 1 Interview 2 Interview 3 Interview 4 Table 6 List of Meetings 24 P a g e
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for
ájoƒ ùdg á«hô dg áµلªÿg Yesser Overall SDLC Process Definition
ájoƒ ùdg á«hô dg áµلªÿg Yesser Overall SDLC Process Definition Version 0.6 - Page 3 / 43 Table of Contents 1. Process Introduction... 5 1.1. Process Scope... 5 1.2. Process Objectives and Benefits... 5
How To Implement An Enterprise Resource Planning Program
ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing
POLAR IT SERVICES. Business Intelligence Project Methodology
POLAR IT SERVICES Business Intelligence Project Methodology Table of Contents 1. Overview... 2 2. Visualize... 3 3. Planning and Architecture... 4 3.1 Define Requirements... 4 3.1.1 Define Attributes...
Data Conversion Best Practices
WHITE PAPER Data Conversion Best Practices Thomas Maher and Laura Bloemer Senior Healthcare Consultants Hayes Management WHITE PAPER: Data Conversion Best Practices Background Many healthcare organizations
The management of testing and test deliverables is detailed in the Test Management procedure (Reference 1).
Guidance Testing Guidelines Purpose This document provides guidelines for testing changes to the BSC Software, Systems and Processes. It also provides a high level view of test procedures that are followed
1 What does the 'Service V model' represent? a) A strategy for the successful completion of all service management projects
1 What does the 'Service V model' represent? a) A strategy for the successful completion of all service management projects b) The path to Service Delivery and Service Support for efficient and effective
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Fixed Scope Offering for Oracle Fusion HCM. Slide 1
Fixed Scope Offering for Oracle Fusion HCM Slide 1 Today s Business Challenges Adopt leading Global HCM practices. Streamline the HCM processes and achieve measurable efficiencies. Achieve HR excellence
System Build 2 Test Plan
System Build 2 Test Plan Version 1.0 System Build 2 Test Plan Author s Signature Your signature indicates that this document has been prepared with input from content experts and is in compliance with
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
This alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed by the IIBA.
Red River College Course Learning Outcome Alignment with BABOK Version 2 This alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed
Quality Assurance - Karthik
Prevention is better than cure Quality Assurance - Karthik This maxim perfectly explains the difference between quality assurance and quality control. Quality Assurance is a set of processes that needs
Smart Metering Implementation Programme
Smart Metering Implementation Programme BPDG Sign-Off for Process Cycle 1 Process Review Summary 25 August 2011 Agenda BPDG model approach for Process Cycle 1 sign-off Agenda for future meetings (1 September
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
Procedure for Assessment of System and Software
Doc. No: STQC IT/ Assessment/ 01, Version 1.0 Procedure for Assessment of System and Software May, 2014 STQC - IT Services STQC Directorate, Department of Electronics and Information Technology, Ministry
EMR Implementation Planning Guide
EMR Implementation Planning Guide A Ten-Step Guide to Planning for Successful Implementation of an Electronic Medical Record (EMR) System 1 Contents Purpose of this guide... 3 Step 1: Establishing the
Free ITIL v.3. Foundation. Exam Sample Paper 1. You have 1 hour to complete all 40 Questions. You must get 26 or more correct to pass
Free ITIL v.3. Foundation Exam Sample Paper 1 You have 1 hour to complete all 40 Questions You must get 26 or more correct to pass Compliments of Advance ITSM www.advanceitsm.com 1. What is the main reason
Single Electricity Market
Single Electricity Market SEM R2.0.0 INTRA-DAY TRADING MARKET TRIAL APPROACH COPYRIGHT NOTICE All rights reserved. This entire publication is subject to the laws of copyright. This publication may not
ERP Test Plan. Revised 7/5/10. SYSTEM TEST PLAN and PEOPLESOFT FMS TEST SCRIPTS. 2010 SpearMC Consulting. Page 1 of 15
SYSTEM TEST PLAN and PEOPLESOFT FMS TEST SCRIPTS Page 1 of 15 INTRODUCTION The Oracle Implementation project team will implement Oracle applications package at client site. The intent of this document
ISTQB Certified Tester. Foundation Level. Sample Exam 1
ISTQB Certified Tester Foundation Level Version 2015 American Copyright Notice This document may be copied in its entirety, or extracts made, if the source is acknowledged. #1 When test cases are designed
The Software Development Life Cycle (SDLC)
Document ID: Version: 2.0 1 / 22 2 TABLE OF CONTENTS INTRODUCTION... 4 THE SDLC WATERFALL... 4 ALLOWED VARIATIONS... 5 OTHER SDLC MODELS... 6 REFERENCES... 7 GENERIC STAGE... 8 KICKOFF PROCESS... 8 INFORMAL
Presentation: 1.1 Introduction to Software Testing
Software Testing M1: Introduction to Software Testing 1.1 What is Software Testing? 1.2 Need for Software Testing 1.3 Testing Fundamentals M2: Introduction to Testing Techniques 2.1 Static Testing 2.2
Capacity Plan. Template. Version X.x October 11, 2012
Template Version X.x October 11, 2012 This is an integral part of infrastructure and deployment planning. It supports the goal of optimum provisioning of resources and services by aligning them to business
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
BAL2-1 Professional Skills for the Business Analyst
1 BAL2-1 Professional Skills for the Business Analyst OVERVIEW This course trains participants to help business clients articulate their needs and wants, and to document them clearly, concisely, and completely.
Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce
Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO
TEST PLAN Issue Date: <dd/mm/yyyy> Revision Date: <dd/mm/yyyy>
DEPARTMENT OF HEALTH AND HUMAN SERVICES ENTERPRISE PERFORMANCE LIFE CYCLE FRAMEWORK CHECKLIIST TEST PLAN Issue Date: Revision Date: Document Purpose The purpose of
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
Clinical Risk Management: Agile Development Implementation Guidance
Document filename: Directorate / Programme Document Reference NPFIT-FNT-TO-TOCLNSA-1306.02 CRM Agile Development Implementation Guidance v1.0 Solution Design Standards and Assurance Project Clinical Risk
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
The ITIL v.3. Foundation Examination
The ITIL v.3. Foundation Examination ITIL v. 3 Foundation Examination: Sample Paper 3, version 3.0 Multiple Choice Instructions 1. All 40 questions should be attempted. 2. There are no trick questions.
The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements.
CAPACITY AND AVAILABILITY MANAGEMENT A Project Management Process Area at Maturity Level 3 Purpose The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision
CMMI KEY PROCESS AREAS
CMMI KEY PROCESS AREAS http://www.tutorialspoint.com/cmmi/cmmi-process-areas.htm Copyright tutorialspoint.com A Process Area is a cluster of related practices in an area that, when implemented collectively,
Milestone Deliverables
Milestone Deliverables The Hands-On Approach To Implementing ERP Projects By Peter Gross Pemeco Inc. 416 Wood Avenue Montréal, Québec H3Y 3J2 Canada Pemeco Inc. Serving Business Since 1978 Table of Contents
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
CalMod Design-Build Electrification Services
SECTION 01800 SYSTEMS INTEGRATION AND INTEGRATOR REQUIREMENTS PART 1 GENERAL DESCRIPTION A. This section specifies the system-wide integration requirements for the Caltrain Electrification system, i.e.
Big Data-Challenges and Opportunities
Big Data-Challenges and Opportunities White paper - August 2014 User Acceptance Tests Test Case Execution Quality Definition Test Design Test Plan Test Case Development Table of Contents Introduction 1
Project Implementation Process (PIP)
Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
INTERNAL AUDIT DIVISION AUDIT REPORT 2013/020. Audit of the Umoja software system (SAP) implementation
INTERNAL AUDIT DIVISION AUDIT REPORT 2013/020 Audit of the Umoja software system (SAP) implementation Overall results relating to effective implementation and configuration of the SAP system were initially
Data Migration through an Information Development Approach An Executive Overview
Data Migration through an Approach An Executive Overview Introducing MIKE2.0 An Open Source Methodology for http://www.openmethodology.org Management and Technology Consultants Data Migration through an
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
SECTION 4 TESTING & QUALITY CONTROL
Page 1 SECTION 4 TESTING & QUALITY CONTROL TESTING METHODOLOGY & THE TESTING LIFECYCLE The stages of the Testing Life Cycle are: Requirements Analysis, Planning, Test Case Development, Test Environment
EU CUSTOMS BUSINESS PROCESS MODELLING POLICY
EUROPEAN COMMISSION MASP Revision 2014 v1.1 ANNEX 4 DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Processes and Project Management Brussels, 03.11.2014 TAXUD.a3
Configuration Management - The Big Picture
Configuration Management - The Big Picture Consists of: 1. Product s aligned to system development life cycle comprised of hardware and software configuration items described by specifications, design
Roles: Scrum Master & Project Manager
Roles: Scrum Master & Project Manager Scrum Master: Facilitate collaborative meetings Track team performance Remove impediments (Risk, Issue) Validate team alignment to Agile framework and scope Drive
Mergers and Acquisitions: The Data Dimension
Global Excellence Mergers and Acquisitions: The Dimension A White Paper by Dr Walid el Abed CEO Trusted Intelligence Contents Preamble...............................................................3 The
Oracle Insurance Policy Administration System Quality Assurance Testing Methodology. An Oracle White Paper August 2008
Oracle Insurance Policy Administration System Quality Assurance Testing Methodology An Oracle White Paper August 2008 Oracle Insurance Policy Administration System Quality Assurance Testing Methodology
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
Commonwealth of Massachusetts IT Consolidation Phase 2. ITIL Process Flows
Commonwealth of Massachusetts IT Consolidation Phase 2 ITIL Process Flows August 25, 2009 SERVICE DESK STRUCTURE Service Desk: A Service Desk is a functional unit made up of a dedicated number of staff
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition
Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Topics for Discussion PMI Foundational Standards Harmonization of PMI s Foundational Standards Top 10 changes
Fixed Scope Offering for Implementation of Taleo
Fixed Scope Offering for Implementation of Taleo Mindtree limited 2015 All third party identities used within this presentation are copyrighted properties of the respective companies. Viewers and users
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
CMMI: Specific Goals and Practices
Software Engineering for Outsourced & Offshore Development CMMI: Specific Goals and Practices PeterKolb Software Engineering CMMI Process Areas for R&D Projects Slide 2 Content Management in Projects Project
Attachment 7 Requirements Traceability Matrix (RTM) ATMS RFP. New York State Department of Transportation Advanced Traffic Management System
Attachment 7 Requirements Traceability Matrix (RTM) ATMS RFP New York State Department of Transportation Advanced Traffic Management System i 1. INTRODUCTION This Requirements Traceability Matrix (RTM)
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Software Engineering. Session 3 Main Theme Requirements Definition & Management Processes and Tools Dr. Jean-Claude Franchitti
Software Engineering Session 3 Main Theme Requirements Definition & Management Processes and Tools Dr. Jean-Claude Franchitti New York University Computer Science Department Courant Institute of Mathematical
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Fundamentals of Information Systems, Fifth Edition. Chapter 8 Systems Development
Fundamentals of Information Systems, Fifth Edition Chapter 8 Systems Development Principles and Learning Objectives Effective systems development requires a team effort of stakeholders, users, managers,
4.13 System Testing. Section 4 Bidder's Products, Methodology, and Approach to the Project. 4.14 System Training
Section 4 Bidder's Products, Methodology, and Approach to the Project 4.1 FACTS II Requirements Summary 4.11 Interfaces 4.2 Functional Requirements 4.12 System Development 4.3 Technical Requirements 4.13
Project Management Life Cycle (PMLC)
Project Management Life Cycle (PMLC) Page 2 Project Management Life Cycle (PMLC) Introduction PMLC Working Group IT Business Process Management(BPM) IT Project Management Office (PMO) Finance System Support
WHITE PAPER ON TECHNICAL DEVELOPMENT APPROACH FOR SAP IMPLEMENTION PROJECTS
WHITE PAPER ON TECHNICAL DEVELOPMENT APPROACH FOR SAP IMPLEMENTION PROJECTS Author Chandra Kumar Meda Table of Contents 1. Objectives and Scope of White Paper... 2 2. Project Phases... 3 3. Methodology...
Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions
Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage
VA ICJIS. Program Management Plan
VA ICJIS Program Management Plan 1 08/29/01 Program Management Plan VA Integrated Criminal Justice Information System (ICJIS) Program 1. Introduction. The Commonwealth of Virginia Integrated Criminal Justice
ITIL A guide to service asset and configuration management
ITIL A guide to service asset and configuration management The goal of service asset and configuration management The goals of configuration management are to: Support many of the ITIL processes by providing
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
INFORMATION TECHNOLOGY GUIDELINE
COMMONWEALTH OF PENNSLVANIA DEPARTMENT OF HUMAN SERVICES INFORMATION TECHNOLOG GUIDELINE Name Of Guideline: System Development Methodology (SDM) Domain: Business Date Issued: 03/01/1999 Date Revised: 03/29/2016
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) Project Status Report Week Ending: 09-19-2012 Page - 1 Executive Summary The Executive Summary provides an executive level review of general project activities,
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
Final Audit Report. Audit of the Human Resources Management Information System. December 2013. Canada
Final Audit Report Audit of the Human Resources Management Information System December 2013 Canada Table of Contents Executive summary... i A - Introduction... 1 1. Background... 1 2. Audit objective...
How to Implement MDM in 12 Weeks
White Paper Master Data Management How to Implement MDM in 12 Weeks Tuesday, June 30, 2015 How to Implement Provider MDM in 12 Weeks The Health Insurance industry is faced with regulatory, economic, social
Requirements Definition and Management Processes
Software Engineering G22.2440-001 Session 1 Sub-Topic 1 Requirements Definition & Management Processes and Tools Dr. Jean-Claude Franchitti New York University Computer Science Department Courant Institute
UCPath Project Status Report
UCPath Project Status Report Report Date August 23, 2013 Project Director Anthony Lo [email protected] Executive Sponsors Nathan Brostrom Peter Taylor Project Summary Tony Lo has resigned as Project
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Kern Health System CORE Software Professional Services RFP Responses to Questions/Request for Explanation
Kern Health System CORE RFP Responses to Questions/Request for Explanation Kern Health Systems (KHS) has prepared the following responses to questions received regarding the CORE Request for Proposal (RFP).
Data Migration for Legacy System Retirement
September 2012 Data Migration for Legacy System Retirement A discussion of best practices in legacy data migration and conversion. (415) 449-0565 www.gainesolutions.com TABLE OF CONTENTS The Importance
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
Project Plan for <project name>
Note: Text displayed in blue italics is included to provide guidance to the author and should be deleted or hidden before publishing the document. This template can be used at it is, or to complete and
Cost of Poor Quality:
Cost of Poor Quality: Analysis for IT Service Management Software Software Concurrent Session: ISE 09 Wed. May 23, 8:00 AM 9:00 AM Presenter: Daniel Zrymiak Key Points: Use the Cost of Poor Quality: Failure
IT Service Management tools - Acquisition and implementation
IT Service Management tools - and implementation Christian F. Nissen, CFN People A/S ITIL and PRINCE2 are Registered Trade Marks of Axelos in the United Kingdom and other countries COBIT is a registered
ITS Projects Systems Engineering Process Compliance Checklist
ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying
Introducing Agility into a Phase Gate Process
B E S T P R A C T I C E S W H I T E P A P E R Introducing Agility into a Phase Gate Process Jenny Stuart, Vice President of Consulting, Construx Software Version 1.1, June 2011 Contributors Earl Beede,
Appendix <<1>> System Status Report for System template
Document Template Document Number ESS-0004799 Date Sep 3, 2013 Revision 1 (2) State Preliminary Appendix System Status Report for System template Authors Reviewers Approver Name Affiliation European
Key performance indicators
Key performance indicators Winning tips and common challenges Having an effective key performance indicator (KPI) selection and monitoring process is becoming increasingly critical in today s competitive
SC121 Umoja Contractor & Consultant Services Overview. Umoja Contractor & Consultant Services Overview Version 7
SC121 Umoja Contractor & Consultant Services Overview Umoja Contractor & Consultant Services Overview Version 7 Last Copyright Modified: United 14-August-13 Nations 1 Agenda Course Introduction Module
CA Gen. Change Management
CA Gen Change Management Introduction Reduced software product life cycles and increasingly diverse requirements are leading companies to review and improve their software development processes. These
Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases
Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor
How To Build A New System For A College
Application Development Methodology The main objective of Enterprise Applications is to design, develop, and maintain quality software. This document out lines the requirements for requesting new systems,
Datalynx Project Delivery Methodology and PCTM Methodology For Legacy Data Cleansing & Migration
Datalynx Project Delivery Methodology and For Legacy Data Cleansing & Migration Title: Datalynx for Migrating Legacy Data Revision: V1.4 Copyright 2014 - Datalynx Pty Ltd. All rights reserved. www.datalynx.com.au
WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101
WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101 Prepared by: Phillip Bailey, Service Management Consultant Steve Ingall, Head of Service Management Consultancy 60 Lombard Street London EC3V 9EA
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
