RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR

Size: px
Start display at page:

Download "RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR"

Transcription

1 RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Suo-Motu In the matter of Determination of Benchmark Capital Cost for Solar PV and Solar Thermal Power Projects for FY and resultant Generic Levellised Tariff. Coram : Shri D.C. Samant, Chairman Shri S.K. Mittal, Member Shri S. Dhawan, Member Date of hearing: Date of Order: ORDER BACKGROUND 1. In accordance with the provisions of Electricity Act, 2003 and National Tariff Policy notified by Govt. of India (GoI), the Commission under its RERC (Terms and Conditions for Determination of Tariff) Regulations, 2009 had incorporated the enabling provisions for determination of generic tariff for solar power projects. 2. Commission had issued the last Tariff Order on , wherein, Commission had determined generic tariff for solar power plants, which was applicable for solar PV plants (SPV), where PPA was signed on or before and getting commissioned on or before and solar thermal plants, where PPA was signed on or before and getting commissioned on or before The tariff as per the above mentioned Order is given in the following table: Page 1 of 27

2 Table-1: Solar Tariffs in Rajasthan as per Tariff Order dated S. No. Particulars Tariff (`/kwh) if AD benefit is not availed Tariff (`/kwh) if AD benefit is availed Solar Photo Voltaic (PV) Power Plants commissioned by Solar Thermal Power Plants commissioned by Roof Top Solar PV installations and other small solar PV power generation plants covered in MNRE s scheme or Rajasthan Solar Energy Policy to be commissioned by Small Solar Thermal Power generation plants covered in MNRE s scheme or Rajasthan Solar Energy Policy to be commissioned by CERC has issued Order on (Petition No. 243/SM/2012 (Suo-Motu) in the matter of determination of generic levellised generation tariff for FY of various RE sources which include the category of Solar Photo Voltaic (PV) and Solar Thermal Power Projects. CERC in the above Order has determined a generic tariff of `8.75 per unit (`7.87 per unit if AD benefit is availed) in respect of solar PV projects and a generic tariff of `11.90 per unit (`10.69 per unit if AD benefit is availed) for solar thermal projects whose PPAs would be signed by and which is to be commissioned on before in the case of solar PV projects and on or before in the case of solar thermal projects. Draft Tariff Order 4. The Commission undertook an exercise to determine Benchmark Capital Costs for Solar PV and Solar Thermal Power Projects and resultant Generic Levellised Tariff for the MW scale solar plants where PPAs would be signed on or before and to be commissioned on or before in the case of solar PV plants and to be commissioned on or before in the case of solar thermal plants. Page 2 of 27

3 5. In the draft tariff order issued on , Commission considered it appropriate to retain the financial norms, as stipulated in Part III of RERC Tariff Regulations, 2009 i.e. debt : equity ratio, RoE, depreciation and O&M escalation that are applicable for the tariff determination of other RE sources like wind/bio-mass and were used for tariff order dt for both Solar PV and Solar thermal projects. Parameters like auxiliary consumption, CUF and de-ration were proposed to be retained as adopted in the Tariff Order dated The summary of Norms and Parameters considered in the draft order is as under: Table-2: Summary of key normative parameters for solar PV projects in the draft Tariff Order. S.No. Parameter Value Capital cost `7.60 crore per MW for FY Capacity Utilization Factor 20% with a deration of 0.5% every (CUF) year after second year. 3 Interest on term loan 13.00% p.a 4 Interest on working capital 12.50%p.a. 5 O&M Expenses `11.63 lakhs/mw for FY with an escalation of 5.72% p.a. plus 0.3% of depreciated project cost in each year towards insurance. 6 Auxiliary consumption 0.25% Table-3: Summary of key normative parameters for solar thermal projects in the draft Tariff Order. S.No. Parameter Value Capital cost ` crore per MW for FY Capacity Utilization 23% with a deration of 0.25% every Factor (CUF) year after fourth year. 3 Interest on term loan 13.00% p.a 4 Interest on working 12.50% p.a. capital 5 O&M Expenses ` lakhs /MW for FY with an escalation of 5.72% p.a. plus 0.3% of depreciated project cost in each year towards insurance. Page 3 of 27

4 S.No. Parameter Value Auxiliary consumption 6.5% Applicable Tariff for Solar PV and Solar Thermal Projects (as in draft order) 6. As per the draft tariff order on , the generic tariff levellised for 25 years for two different technologies (Solar PV & Solar thermal) and for Roof Top and small solar plants worked out as per the said norms is summarized as follows: Table- 4: Summary of Tariff for Solar PV and Solar Thermal projects in the draft Tariff Order. S. No. Particulars Tariff (`/kwh) if AD benefit is not availed Tariff (`/kwh) if AD benefit is availed Solar Photo Voltaic (PV) Power Plants commissioned by Solar Thermal Power Plants commissioned by Roof Top Solar PV installations and other small solar PV power generation plants to be commissioned by Small Solar Thermal Power generation plants to be commissioned by Publication of Draft Order and stakeholder s comments/suggestions 7. A public notice was published in the following newspapers inviting comments/suggestions of stakeholders on the Draft order dated and the said order was also placed on Commission s website: (1) The Times of India published on (2) Dainik Bhaskar published on (3) Dainik Navjyoti published on In response to the same, written comments/suggestions were received from the following stakeholders: (1) Rudraksh Energy, (2) Power & Energy Consultants (PEC), Page 4 of 27

5 (3) Sh. Shanti Prasad, (4) Torrent Power Limited (TPL), (5) Reliance Power Limited (RPL), and (6) First Solar Power India (P) Limited (FSPIL). 9. A public hearing on the Draft Order was held on Sh. Shanti Prasad, one of the stakeholders, has offered the comments in respect of terms and conditions for roof top PV installations. He has stated that his comments being in respect of net sale of solar power to Discom may not be directly related to draft order, but are relevant in promoting roof top solar installations. He observed that if deemed fit, the same may be considered through Suo-motu approach paper to enable stakeholders to offer comments. 11. His comments, not being related to draft order, have not been considered in this order. The comments/suggestions received from other stakeholders have been dealt with in the following paras. Capital Cost Stakeholder s comments/suggestions 12. Sh. D.S.Agarwal, on behalf of Rudraksh Energy, submitted that they agree with the capital cost of ` 7.60 Cr/MW, however, requested Commission to clarify/confirm whether this MW cost excludes the cost of transmission line from the Solar Plant to RVPN s 132 kv or 220 kv GSS, receiving power. Further, he also requested to clarify whether this MW cost is for 1 MWP i.e. installed modules capacity or 1 MW AC output of the solar plant requiring about 1.1 MW capacity of Modules. 13. Power & Energy Consultants have submitted that both types of lands i.e. Private and Government land are being used for solar PV projects in Rajasthan. In case of Government land, although initial Page 5 of 27

6 cost of land (10% of DLC) is low, however it takes quite long time and therefore, additional cost of follow up is incurred till possession of the land is taken. In addition to this, the developer has to pay annual lease rental to Government of Rajasthan which has not been considered in annual expense. Further, the land development and infrastructure cost in case of revenue land is also higher. Therefore, cost of land and land development should be considered as minimum of ` Lakh/MW. They also submitted that with present exchange rate of Rs. 59 per US$ (in place of Rs per US$), the cost of 1 MW PV Module may be taken as Rs. 354 Lakhs or higher. As the US $ is expected to further appreciate, the stakeholders observed that after including Rs Lakh per MW as grid connectivity charges, the total capital cost for Solar PV project should be considered as Rs. 817 Lakh per MW. 14. Reliance Power Ltd. submitted about the key difference between RERC and CERC Order in respect of capital cost saying that as per RERC Order, land is reckoned cheaper in Rajasthan and de-ration of module has not been considered as part of capital cost. These two factors in their view, will not result in reduction of capital cost from ` 8.00 Cr/MW (CERC) to ` 7.60 Cr/MW (RERC). They have further submitted that the DLC rate considered by RERC for cost of land varies from place to place. Hence, it would be appropriate to consider land cost as per CERC norms. 15. Reliance Power Limited also requested to consider the registration charges payable by Developer to RRECL as part of Project Cost. They further submitted that Solar PV and Solar Thermal sites are generally located in remote area with little basic amenities available in the vicinity. For developers developing large capacities (>25 MW) it becomes imminent to develop suitable living conditions at the site by developing a township with Page 6 of 27

7 appropriate amenities for attracting staff during project construction and also during O&M period. Hence, it is recommended to have Townships also as part of the Capital Cost. Reliance Power Limited also submitted that in case of Solar PV, module price is noted in USD/Wp and hence, exchange rate variation has significant impact on the overall project cost. Since Rupee has experienced depreciation in the past few months and has reached the level of Rs /USD and is not expected to regain the levels of Rs /USD, hence Rs /USD may be considered as exchange rate for working out capital cost for FY The module cost, at exchange rate of Rs. 60/USD, may be considered as Rs. 360 Lakhs. In light of above, Reliance Power Ltd. requested for benchmark Capital cost for Solar PV projects as Rs Cr./MW. 16. Torrent Power in their written comments have submitted that PV insights report on Solar Module spot price (last updated on ), reveals that the Average price for Silicon Solar Module is USD per Watt (against USD per Watt of draft Tariff Order) and Average price for Thin Film Solar Module is USD per Watt ( against USD per Watt of draft Tariff Order) as under: Table-5: Solar Module weekly Spot Price (USD per Watt) Item High Low Average Avg. Chg Avg. Chg % Silicon Solar Module % Thin Film Solar Module % (The average change in the table is being carried out after comparison with Table-5 in the Draft Order) Torrent Power based on above, requested to consider the average price of PV module as USD per watt for working out the Capital cost. Torrent Power submitted that as per Reserve Bank of India, last six months average of USD to INR is Rs per USD compared to Rs per USD. Further, the current USD to INR exchange rate is near to Rs. 60 per USD, which has significantly Page 7 of 27

8 impacted the module price. They requested to consider module price of Rs. 439 Lakhs/MW ( USD per Watt * XRs per USD) due to upward change in spot prices and exchange rate. 17. Torrent Power has submitted that Directorate General of Antidumping and Allied Duties (DGAD) has initiated an investigation on imports of Solar cells whether or not assembled partially or fully in Modules or Panels or on glass or some other suitable substrates, originating in or exported from Malaysia, China PR, Chinese Taipei and United States of America in November 2012 to determine the existence, degree and effect of any alleged dumping and to recommend the amount of anti-dumping duty, which if levied, would be adequate to remove the injury to the domestic industry and hence, there are chances of increase of price of module. 18. First Solar Power India (P) Ltd have submitted that Commission has provided reference to the cost of power conditioning unit approved by CERC in its Order for However, CERC in its explanatory Memo for benchmark capital cost norms for solar technology for had decreased the PV inverter cost from ` 98 Lakh/MW in to ` 60 Lakh/MW for which was a sharp decease of 39%. However, the current spot market prices of power conditioning units (inverters) are higher than the prices specified by CERC. The stakeholder has also submitted the table showing spot prices and contract prices for PV inverters as follows: Table-6: PV Inverter prices Item High Low Avg Chg Chart PV Inverter Price (Per Watt) (0 %) (Source: Page 8 of 27

9 Further, they have submitted that the average spot price for PV inverter on June 26, 2013 was $0.21/W. It is noteworthy that the average contract price for inverters during the last six months has been in the range of $0.21/W to $0.23/W. Therefore, even if lowest spot price of $0.15/W is considered for determination of inverter prices in , it works out as ` 90 Lakh/MW. Thus, they requested to increase the cost of inverter from ` 60 Lakh/MW to ` 90 Lakh/MW. 19. First Solar Power India(Private) Limited submitted that Commission while determining the benchmark capital cost for Solar PV projects for the year , did not consider inverter replacement cost. Photovoltaic inverters come with a typical 5 year warranty, with a provision for a 10 year extended warranty. Therefore, it is imperative to replace the inverter after years of operation. Considering a replacement after completion of 12 years, the present value of replacement comes at approx. Rs 25 Lakh/MW which should be considered while determining the capital cost of the project. 20. Torrent Power submitted that Commission in the Draft Order has considered the one time cost of the Power conditioning unit at Rs. 60 Lakh per MW in the Capital cost of the Solar PV Project. The power conditioning unit/inverter generally comes with a warranty of 5 years and also various EPC contractors recommend that inverters are to be replaced during 12 th to 15 th year of operation to ensure proper transmission of Power. Further, GERC in its Solar Tariff Order dated has considered cost of inverter replacement at 3.81% of the capital cost during 13 th year. They requested Commission to consider additional Power conditioning unit replacement cost of Rs. 60 Lakhs per MW during the 13 th year of operation while working out the tariff. Page 9 of 27

10 21. Power Energy Consultants also submitted that capital cost of Solar Thermal Project should also be revised based on recent Exchange Rate of ` per US$ ( in place of ` as per US$). 22. Reliance Power Limited submitted that only one solar thermal project has been commissioned in India as per media reports (Godavari Green Energy Limited: Project cost of ` 790 Crores for 50 MW i.e. ` 15.8 Cr/MW). The capital cost for FY should not be less than ` Cr/MW (capital cost FY ). Apart from the above, capital cost should be minimum ` Cr/MW for FY (=` Cr/MW+` 0.25Cr/MW towards township). Commission s Analysis and Decision 23. Commission clarifies that benchmark capital cost specified by the Commission excludes the cost of transmission line from solar plant to RVPN s 132 kv or 220 kv GSS, receiving power, which is to be borne by a Solar developer. As regards the clarification about Capital cost benchmark, whether Capital cost per MW is for 1 MWp i.e. installed module capacity or 1 MW AC output of a solar plant, it is stated that capital cost benchmark for a solar PV plant refers to cost per MW of the output. 24. Regarding the comments of the stakeholders to consider the cost of land as Rs Lakh/MW same as considered by CERC, Commission would like to state that it is also mentioned in the draft order that Capital Cost arrived by CERC is in All India Context. However, the situation varies from State to state. The land used by Solar developers for setting up their Solar Projects in the State is mostly Govt. land; which is being allotted at concessional rate of 10% of the DLC rate (agriculture land) as per the provisions of Rajasthan Land Revenue (Allotment of Land for setting up of Power plant based on Renewable Energy Sources) Rules, 2007 as Page 10 of 27

11 amended from time to time. In addition to this, the land used by Solar developer for setting up their Solar projects is mostly a wasteland virtually having negligible commercial utility. Therefore, in view of the above, Commission considers it appropriate not to make any changes in Capital cost norm for a Solar plant on account of land cost. 25. One of the developers has requested for considering township as a part of the Capital cost for both Solar PV and Solar Thermal. Commission would like to clarify that capital cost norms for Solar projects (both Solar PV and Solar thermal) are generic norms and are applicable for both small and large scale projects and small projects do not need a separate colony. The large projects on the other hand have the benefit of economies of scale. In view of the above, Commission, therefore, is not inclined to accept the said contentions. 26. One of the stakeholders has furnished the solar module spot price (updated on ) showing higher average prices for Silicon Solar module (0.731 $/Watt against 0.667$ considered in the draft order) and thin film solar module ($ 0.664/W against 0.620$/W considered in the draft order) referred in the Commission s draft order. It is clarified that the price information was analyzed to capture the cost trend of PV modules. It is mentioned that PV insight reports (last updated on ) indicates average price for Silicon Solar module as $/W and average price for thin film solar module as $/W, which are lower than suggested by the stakeholder. It is clarified that while specifying the benchmark capital cost, the future spot price trends cannot be lost sight of. Considering that solar module prices were almost at the same level even as on as indicated in the draft Page 11 of 27

12 order, Commission is, therefore, of the view that no change is required in the Capital cost benchmark norm on this account. 27. One of the stakeholders apprised that on insistence of Solar manufacturers Association, Directorate General of Antidumping and Allied Duties (DGAD) has initiated an investigation of imports of Solar cells and expressed that, if any antidumping duty is levied, there are chances of increase of price of modules. Any change in the capital cost bench mark purely based on speculation of imposition of antidumping duty can not be agreed. 28. One of the stakeholders has requested to increase the inverter price from ` 60 Lakh/MW to ` 90 Lakh/MW in view of spot prices revealed by PV energy trend. Some stakeholders have submitted that since Photo voltaic inverters come with a typical five year warranty, with a provision for a ten year extended warranty, it is, therefore, to be replaced after years of operation for which present value of replacement cost of approximately ` 25 Lakh/MW may be considered in capital cost. CERC in their order dated in the matter of determination of the benchmark capital cost norm for solar PV and Solar thermal power projects applicable during FY , has also observed that some of the inverter manufacturers have started manufacturing in the country. CERC even after considering the replacement cost of inverter after 12 to 15 years, has considered ` 60 Lakh/MW as reasonable cost. Therefore, in view of the above, no change is required in the Capital cost benchmark norm on this account. 29. Several stakeholders have requested that capital cost for solar PV and solar thermal may be revised on account of foreign exchange rate variation. Commission would like to state that though Commission has not specified the breakup of capital cost Page 12 of 27

13 benchmark, however, the capital benchmark norms specified are broadly based on benchmark specified by CERC for FY CERC in their order has considered average currency exchange rate of past six months for arriving at the module cost instead of considering the prevailing exchange rate. Accordingly, they had considered exchange rate at ` 54.32/US $. Further, it is mentioned that the variation in exchange rate is affected by the prevailing general economic scenario, therefore, is amenable to change either way in future course. Sometimes exchange rates also exhibit abnormal variations. Thus, the suggestions of stakeholders of considering prevailing exchange rate for arriving at module cost cannot be accepted. Commission has, on the other hand, considered average rate of exchange for past six months of Rs 57.62/US$ (1 st March 2013 to 30 th August 2013), which is the most recent trend of six months period, to smoothen out abnormal exchange rate variations and accordingly, the cost of PV Module increases by ` Lakh (= [(57.62/ )*325.92). In light of this, total capital cost for solar PV Projects has been increased by Rs Lakh by rounding off. 30. One of the stakeholders has cited that based on media reports, the capital cost of a commissioned solar thermal project i.e. Godavari Green Energy Ltd., is coming to ` 15.8 Cr./MW. They have also submitted that capital cost for FY should not be less than ` Cr./MW (capital cost for FY ), it should be minimum ` Cr./MW. Commission would like to state that presently Commission is determining the generic capital cost benchmark, where, unless a significant reliable and validated data relating to cost of the commissioned projects is available, it would not be appropriate to change the benchmark norm based on data of a specific project. In view of this, Commission considers it appropriate to retain the capital cost benchmark norm for solar Page 13 of 27

14 thermal projects as proposed in the draft order i.e. ` Cr./MW for FY , including connectivity charges of ` 2.00 Lakh/MW. Capacity Utilisation Factor (CUF) Stakeholder s comments/suggestions 31. Rudraksh Energy in their written submissions requested that it may be clarified whether the CUF of 20% considered for solar projects is with the module capacity of 1 MWP (installed Module capacity) or 1 MW AC output corresponding to about 1.1. MW DC. 32. Reliance Power Limited submitted that based on 21 prominent locations in Rajasthan where projects are being executed, they have calculated the average CUF, considering GHI data based on Meteonorm. The average CUF for these locations is 19% for thin film and 18.30% for crystalline. They have requested that CUF should be considered as 19% as per CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulation, Reliance Power Limited, regarding CUF of Solar Thermal, has submitted that CUF of 23% has been considered on resource DNI map published by MNRE in Based on actual DNI data collected at sites across India, all Solar Thermal developers are experiencing approximately 15% drop in DNI in comparison to the data published earlier by MNRE. Based on actual DNI data collected, the Commission should consider revising the CUF from 23% to 20%. Commission s Analysis and Decision 34. As far as CUF of solar PV plants is concerned, it is mentioned that CUF of plants operating in the state is lower than 20% at some locations and more than 20% at other locations. Further, Page 14 of 27

15 Commission also observes that throughout the country geographic and climatic conditions vary and it is difficult to expect the same CUF norm for different locations in the country. Commission considers it appropriate to retain the benchmark norm of CUF as 20%. In case of solar thermal plants, in absence of actual data of full one year, Commission is of the views that no change is required for benchmark CUF and accordingly, benchmark CUF of 23% would continue to remain applicable. De-ration Stakeholder s comments/suggestions 35. PEC submitted that as per the international guarantees/warrantees given by the manufacturers, degradation up to 90% is allowed by tenth year and 80% by 25 th year. Considering this, the de-rating should be taken as 1% per annum from 2 nd to 11 th year and thereafter, 0.70% per annum till 25 th year. 36. Reliance Power Limited submitted that most of the PV module manufacturers provide a warranty of 1% degradation from 2 nd year onwards. Hence, the same may be considered in the tariff determination. Commission s Analysis and Decision 37. Commission would clarify that in the initial 3-4 years of operation, there is no considerable de-ration to be accounted for, as the same is more or less covered in the manufacturer s guaranteed output of the solar modules. Therefore, Commission considers it appropriate to retain de-ration of 0.50% per annum after two years for solar PV modules. Page 15 of 27

16 Auxiliary Consumption Stakeholder s comments/suggestions 38. Reliance Power Ltd submitted that auxiliary power is required for air-conditioning in inverter and control rooms, cleaning water softening and pumping system, security night lighting and general office lights and fans. Also, based on experience of operational plants, the observed auxiliary consumption is between 1% to 2%. Hence, Auxiliary consumption may be considered at a nominal value of 1% of gross generation. Commission s Analysis and Decision 39. Commission recognizing the requirement of solar plant has allowed auxiliary consumption of 0.25%. Further, Commission has also considered de-ration separately to account for the reduction in generation with passage of time and also, in absence of reliable actual operational data, Commission presently, is not inclined to make any change in auxiliary consumption benchmark for solar PV projects on this account. Operation and Maintenance (O& M) Expenses Stakeholder s comments/suggestions 40. Reliance Power Ltd submitted that the key reason for escalation in O&M expenses is attributable to the manpower costs and the general scenario of a higher inflation. The escalation of 5.72% considered by the Commission in O&M expenses is not reflective of the actual price rise due to higher WPI and increased manpower cost. Lack of skilled manpower availability within the country and consequently hiring of experts during O&M of the plants results in higher O&M expenses for solar thermal projects. Thus, due to higher escalation and expert requirement, O&M expenses should be increased to Rs 18 Lakh/MW from Rs Lakh/MW. Page 16 of 27

17 Commission s Analysis and Decision 41. Commission observes that there is hardly any operational experience of MW scale thermal power projects in India to establish the norms for O&M expenses. Commission, therefore, considering an annual escalation of 5.72% over O&M Expenses of Rs Lakh/MW approved for FY with 0.3% towards insurance cost every year on the depreciated value of the assets, arrived at the figure of Rs Lakh/MW for FY in the draft order. Accordingly, Commission does not consider it appropriate to make any change in the O&M expenses benchmark for solar thermal projects. Applicability of Rate of Surcharge Stakeholder s comments/suggestions 42. Torrent Power submitted that in the Fiscal Budget 2013, the surcharge rate on MAT and Corporate tax for AY (FY ) has been increased from 5% to 10% for those companies whose total income exceeds Rs 10 Crore rupees, therefore, the surcharge rate of 10% may be considered for the corporate tax and MAT during the useful life of the project. Commission s Analysis and Decision 43. As regards the suggestion of applying surcharge rate of 10% for corporate tax and MAT, it may be mentioned that the most of the plants getting commissioned in the State for supply of power to distribution companies are typically of size 5 to 10 MW and annual taxable income of such plants relevant for levellised tariff would be less than 10 Crores. Therefore, these would not be subjected to said increased surcharge rate of 10%. In light of the above, Commission considers it appropriate to retain a surcharge rate of 5% in the tariff computations of generic tariff for FY Page 17 of 27

18 Other issues 44. The stakeholders have also furnished comments on the issues not covered as above. The same have been covered in the following paras. Other issues-transmission Charges Stakeholder s comments/suggestions 45. Reliance Power Ltd submitted that Rajasthan has high solar irradiation and barren land, which offers good potential to be utilised by Developers to set up solar power projects for sale to other States. In case of interstate sale of power, the developer has to use the transmission system of the host State to connect to PGCIL network. While CERC has exempted Solar Power from transmission charges and losses on the CTU network, whereas the inter-state developer has to bear the transmission charges. Since CUF of solar plants is lower (20% for PV, 23% for Solar Thermal as per RERC) as compared to 80%-90% of thermal power plats, the impact on per unit basis is high for solar power plants. These charges and losses form a significant portion. In order to encourage solar power plants in the State of Rajasthan, the matter may be taken up to issue an Order to waive off the transmission charges and losses in line with CERC. In absence of this, it is likely that the project will be set up in the host states, where the demand is, which will deprive the State of Rajasthan from investments and associated benefits. Commission s Analysis and Decision 46. As regards the waiving off the transmission charges and losses for solar power projects in line with CERC, Commission would like to observe that this matter relates to amendment in tariff regulations and falls outside of the purview of this order. Page 18 of 27

19 Other issues-applicable Tariff for Solar PV Plants Stakeholder s comments/suggestions 47. Rudraksh Energy submitted that in order to give relief to the Discoms/ Consumers during the initial years of the Tariff period, the alternate tariff (back loaded) with lesser tariffs of about Rs 6.25 and Rs 5.5 per unit for the first year with an annual escalation of about 3% (with and without AD) may be specified. Commission s Analysis and Decision 48. Commission observes that tariff design should be such which may ensure adequate cash flow stream to the developers in the initial years of the project when debt servicing cost is higher and at the same time, the interests of utility and consumers are protected by avoidance of cost burden during these years. Commission, therefore, has been specifying the levellised tariff for solar power projects commissioned during earlier years. Commission, therefore, considers it appropriate to continue with the past practice of specifying the levellised tariff. Other issues-tariff Based bidding Stakeholder s comments/suggestions 49. M/s Rudraksh Energy requested that: (1) Discoms and RREC, who may be purchasing Solar Power through Tariff based bidding may be directed to consider discount on both the tariffs i.e. with and without availing AD benefits as was done earlier under National Solar Mission (NSM) so that the competition is wider and not limited to the Companies availing AD benefits. (2) Discoms/ RREC while inviting Tariff based bidding, can ask for the Discount on such lower tariffs (6.25 and 5.5) with an annual escalation of about 3%. This tariff Model has been Page 19 of 27

20 adopted recently by TANGEDCO, Tamilnadu with an escalation of 5% for first 10 years. Commission s Analysis and Decision 50. Commission observes that both issues raised by the stakeholder related to the bidding said to be conducted by RREC. RREC, being a trading licensee, therefore, falls outside the domain of regulatory control of the Commission in respect of directions as suggested by the stakeholder. Therefore, Commission is unable to accept the suggestion of the stakeholder at this stage. Other issues-penal charges for recovery of wrongly claimed AD benefit Stakeholder s comments/suggestions 51. Rudraksh Energy submitted that the percentage mentioned for recovering the additional amount of wrongly claimed AD benefit by a power generator, the penal charges may be considered as 2.0% per month in place of proposed 1.50% per month. Commission s Analysis and Decision 52. Commission would like to state that penal charges of 1.50% per month for recovering the additional amount of wrongly claimed AD benefit by a power generator have been specified for wind power projects (order dated ) and therefore, Commission considers it appropriate to continue with the same for Solar power projects also. Metering Stakeholder s comments/suggestions 53. Rudraksh Energy requested the Commission to clarify as to how the transmission losses shall be accounted for, in case Metering for billing purpose is done at RVPN s GSS/Discom s Sub-station. Page 20 of 27

21 Commission s Analysis and Decision 54. As the metering is now to be done at Generator s bus bar, the issue of accounting for losses in case of metering at RVPN/Discom s sub-station doesn t arise. Interest on Term Loan Stakeholder s comments/suggestions 55. Reliance Power submitted that while interest rate reflects the current market scenario, Banks also charge a one time upfront/processing fee of around 1.50% of debt amount, which may be considered instead of 1% of capital cost considered by CERC. RERC has considered 1% in line with CERC and same may be considered as part of Financing Charges and thus, part of Project Cost. Commission s Analysis and Decision 56. Commission would like to state that Capital cost has been specified only on the lumpsum basis broadly based on total capital cost specified by CERC keeping in view the overall situation and no break up was specified. In light of this, the contention of the stakeholders is not acceptable. Rooftop and Small Solar PV and thermal systems: Applicable Tariff (as in draft Order) Stakeholder s comments/suggestions 57. Rudraksh Energy in their written suggestions have submitted that Roof top PV and small solar projects are generally installed as distributed generation projects, throughout the state in every district with varying solar radiation (from 18 to 20% CUF). Besides this the capital cost per MW is higher and the grid availability is lower. In view of this, a higher tariff may be provided for smaller projects and at least two separate tariff for the State, as provided in the case of Wind Projects, so that Solar Plants are installed in Page 21 of 27

22 Districts other than Jodhpur, Jaisalmer, Bikaner, Nagore also, which will save Transmission cost as well as losses. 58. First Solar Power India (P) Ltd submitted that for roof top projects, capital cost is higher than the capital cost considered for grid connected solar PV projects on account of battery cost involved in small rooftop systems. MERC has provided Rs 0.5/kWh for solar rooftop plants over and above the tariff approved for grid connected solar power plants. Therefore, Commission may notify increased benchmark capital cost and tariff for small solar rooftop projects taking into account the cost of battery. Commission s Analysis and Decision 59. Commission would like to state that for setting up of a MW scale power plant, a set of preliminary works are required to be done, which also include land acquisition and development etc. For a typical green field grid connected solar PV MW scale project, the cost components towards land, civil and general works, preliminary and preparative expenses taken together come in the vicinity of 15-17%. For roof top solar PV systems such expenses would be lower. However, CUF for roof top PV systems would be lower as such systems may be located predominantly in the areas having lesser solar radiation when compared with western Rajasthan, which has better solar radiation potential and also due to impact of shading of trees/adjoining buildings. In view of such consideration, Commission has been specifying the same tariff for Rooftop PV Systems as applicable to the MW scale projects. In light of the above position, Commission considers it appropriate to continue with the past practice of specifying same tariff for both roof top PV and small solar plants and MW scale PV projects. Page 22 of 27

23 Summary of Norms for Solar Thermal projects 60. Considering the stakeholder comments and the Commission s analysis and decisions on the same, the summary of the final main parameters for Solar PV and Solar thermal tariff determination are given below: Table-7: Summary of key normative parameters for solar PV projects S.No. Parameter Value Capital cost `7.80 crore per MW for FY Capacity Utilisation Factor 20% with a deration of 0.5% every (CUF) year after second year 3 Interest on term loan 13.00% p.a. 4 Interest on working capital 12.50% p.a. 5 O&M Expenses `11.63 Lakh/MW for FY with an escalation of 5.72% p.a. plus 0.3% of depreciated project cost in each year towards insurance. 6 Auxiliary Consumption 0.25% The complete tariff parameters/assumptions along with detailed computations for the generic tariff for solar PV tariff are given at Annexure-1. Table-8: Summary of key normative parameters for solar thermal projects S.No. Parameter Value Capital cost ` Crores per MW for FY Capacity Utilisation Factor (CUF) 23% with a deration of 0.25% every year after fourth year. 3 Interest on term loan 13.00% p.a. 4 Interest on working capital 12.50% p.a. 5 O&M Expenses ` Lakh /MW for FY with an escalation of 5.72% p.a. plus 0.3% of depreciated project cost in each year towards insurance. 6 Auxiliary Consumption 6.5% Page 23 of 27

24 The complete tariff parameters/assumptions along with detailed computations for the generic tariff for solar thermal tariff are given at Annexure-2. Applicable Tariff for Solar PV Plants 61. Considering the parameters discussed above, the generic tariff for Solar PV plants is being determined as ` 8.33/kWh, as per calculation sheet placed at Annexure-1. This tariff is levellised tariff for 25 years and applicable for plants commissioned without availing benefit of AD. The tariff would be lower by ` 1.02/kWh if AD benefit is availed i.e. the tariff would be ` 7.31/kWh. This tariff would be applicable for solar PV plants where PPA is signed on or before and which get commissioned on or before Applicable Tariff for Solar Thermal projects 62. Considering the parameters discussed above, the generic tariff for the solar thermal power plants is being determined as ` 11.37/kWh, as per calculation sheet given at Annexure-2. This tariff is levellised for 25 years and applicable for plants commissioned without availing benefit of AD. The tariff would be lower by ` 1.40/kWh if AD benefit is availed i.e. the tariff would be ` 9.97/kWh. This tariff would be applicable for solar thermal plants where PPA is signed on or before and which get commissioned on or before Guidelines for Metering, Billing and other Requirements 63. The guidelines laid down as per order dtd as regards (i) Metering and Billing arrangement; (ii) Technical requirements; and (iii) General Terms and Conditions are being retained and would be suitably incorporated in the PPA. Conclusion Page 24 of 27

25 64. The generic tariff levellised for 25 years for two different technologies (solar PV & solar thermal) and for Roof Top and small solar plants is summarized as under: Table- 9: Summary of tariff for Solar PV and Solar Thermal projects S. No. Particulars Tariff (`/kwh) if AD benefit is not availed Tariff (`/kwh) if AD benefit is availed Solar Photo Voltaic (PV) Power Plants commissioned by Solar Thermal Power Plants commissioned by Roof Top Solar PV installations and other small solar PV power generation plants to be commissioned by Small Solar Thermal Power generation plants to be commissioned by Both the tariff mentioned in the above table i.e. with or without availing AD benefit would be a valid tariff for purchase of Solar Power by distribution licensees from solar generation plants set up in Rajasthan. 66. For a solar power generator claiming the higher tariff worked out as above for projects not availing Accelerated Depreciation benefit, Commission considers it appropriate to lay down modalities as under: (1) The PPA should include an undertaking of the solar power generator that Accelerated Depreciation benefit would not be availed for the generating plant/unit; (2) The first bill raised by the solar power generator shall be accompanied by an undertaking that Accelerated Depreciation benefit shall not be claimed. Based on this, the applicable tariff would be allowed; Page 25 of 27

26 (3) The claims of energy charges as per applicable tariff may be entertained based on the said undertaking upto the due date of filing of Income Tax Return of the relevant financial year. This would mean 30 th September, 2014 for payment for the financial year and for the first six months (upto 30 th September) of financial year and so on; (4) After filing of Income Tax Return a certificate from a Chartered Accountant (CA) that Accelerated Depreciation has not been claimed would have to be submitted or in the alternative a copy of Income Tax Return filed with Income Tax Department wherein Accelerated Depreciation has not been claimed along with verification of Tax Consultant may be furnished; (5) As Income Tax Return is required to be filed in the next year, the payment of amount corresponding to non-availment of Accelerated Depreciation in respect of energy supplied in the month of October onwards of the financial year following the financial year of commissioning of the plant would be made only after the said certificate/copy of Income Tax Return is furnished; (6) For the energy supplied in the months of October onwards, the methodology as given in sub-paras (4) & (5) above be followed. Commission also considers it appropriate that undertaking of the power generator in PPA saying that benefit of Accelerated Depreciation would not be availed should also include an undertaking that in case it is found that benefit of Accelerated Depreciation has been claimed, the licensee would be entitled to Page 26 of 27

27 recover the additional amount wrongly claimed by power generator along with penal 1.50% per month. 67. A solar power generator not availing CDM benefit would need to give an annual undertaking that CDM benefit has not been availed. However, if CDM benefit is availed, it would have to be shared with distribution licensee as envisaged in Regulation 42 of RERC Tariff Regulations Grid connectivity charges are governed by regulation 89(2) of current MYT Regulations and therefore, Connectivity ` 2.00 Lakh per MW, would be payable. 69. If the capacity in excess of RPO is to be contracted, the licensee must obtain prior approval of the Commission based on reasons and full justification before contracting for capacity in excess of RPO requirement. 70. The metering shall be at the generator premises as provided in CEA Metering Regulations. 71. Copy of this Order be sent to the State Government, Central Electricity Authority (CEA), MNRE,RREC, Distribution Licensees and be also placed on the Commission s web site. (S. Dhawan) Member (S.K. Mittal) Member (D.C. Samant) Chairman Page 27 of 27

28 TARIFF DETERMINATION FOR SOLAR PHOTO VOLTAIC POWER PLANTS LOCATED IN RAJASTHAN Annexure-1 Levelised Tariff (Rs/kWh) without AD 8.33 Accelerated Depreciation benefit(rs/kwh) 1.02 Levelised Tariff (Rs/kWh) with AD 7.31 S. No. Assumption Head Sub-Head Sub-Head (2) Unit Base Case (SPV) 1 Power Generation Capacity 2 Project Cost Installed Power Generation Capacity MW 1 CUF % 20.00% Deration p.a. after 2nd year % 0.50% Auxiliary Consumption % 0.25% Tariff Period Years 25 Life of Power Plant Years 25 Capital Cost/MW Including Land & Connectivity charges Rs Lakh/MW Sources of Fund Debt: Equity Debt % 70.00% Equity % 30.00% Total Debt Amount Rs Lakh Total Equity Amout Rs Lakh Funding Options-1 (Domestic Loan Source-1) Loan Amount Rs Lakh Moratorium Period years 0 Repayment Period(incld Moratorium) years 12 Intrest Rate % 13.00% Funding Options-2 ( Equity Finance ) Equity amount Rs Lakh 234 Return on Equity % p.a 16.00% Discount Rate (CERC Notification ) 13.10% 4 Financial Assumptions Fiscal Assumptions Income Tax (11th year onwards) % 30.90% MAT Rate (for yr-1) yr-2 ) % 20.01% 19.06% MAT Rate (for yr-2 to yr-10) 19.06% 80 IA benefits Yes/No Yes Depreciation Depreciation Rate(upto 12-yrs) % 5.28% Depreciation Rate(after 12-yrs) % 2.05% Years for 5.28% SLM rate years 12 5 Working Capital For Fixed Charges O&M Charges Months 1 Maintenance Spare (% of O&M expenses) 15.00% Receivables for Debtors Months 1.5 Intrest On Working Capital % 12.50% 6 Operation & Maintenance Expenses Power plant Rs Lakh per MW Rs Lakh/MW Insurance charges % of depreciated capital cost % 0.30% O & M Expenses Escalation % 5.72%

29 Annexure-1 contd TARIFF DETERMINATION FOR SOLAR PHOTO VOLTAIC POWER PLANTS LOCATED IN RAJASTHAN Units Generation Unit Year---> Aux Consumption % 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% 0.25% Installed Capacity MW Deration factor % 0.50% Generation MU Cost of generation Unit Year---> O&M Expenses Rs Lacs Depreciation Rs Lacs Interest on term loan Rs Lacs Interest on working Capital Rs Lacs Return on Equity Rs Lacs Total Cost of generation Rs Lacs Per unit Cost of generation Rs/kWh Levellised cost of generation (Rs/kWh) (25 yrs) 8.33 Note(s): 1. Levellised tariff has been worked out by carrying out levelisation over 25 years and Discount Rate has been considered as 13.10% as per CERC Notification Figures may not tally exactly on account of rounding off.

30 Determination of Accelerated Depreciation Benefit for Solar PV Power Projects Depreciation amount 90% Book Depreciation rate 5.28% Tax Depreciation rate 80% Additional depreciation rate applicable during first year 20% Income Tax 32.45% 30.90% Capital Cost Rs Lakh/MW Years > Unit Book Depreciation % 2.64% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 5.28% 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Book Depreciation Rs Lakh Accelerated Depreciation Opening % % 50.00% 5.00% 1.00% 0.20% 0.04% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Allowed during the year % 50% 45.00% 4.00% 0.80% 0.16% 0.03% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Closing % 50.00% 5.00% 1.00% 0.20% 0.04% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Accelrated Deprn. Rs Lakh Net Depreciation Benefit Rs Lakh (9.98) (34.94) (39.94) (40.93) (41.13) (41.17) (41.18) (41.18) (41.18) (41.18) (41.18) (41.18) (41.18) (41.18) (41.18) (22.46) Tax Benefit Rs Lakh (3.09) (10.80) (12.34) (12.65) (12.71) (12.72) (12.73) (12.73) (12.73) (12.73) (12.73) (12.73) (12.73) (12.73) (12.73) (6.94) Energy generation MU Per unit benefit Rs/Unit (0.18) (0.62) (0.72) (0.74) (0.75) (0.75) (0.75) (0.76) (0.76) (0.77) (0.77) (0.77) (0.78) (0.78) (0.79) (0.43) Discounting Factor,DF Applicable DF Levellised AD benefit 1.02 Rs/kWh Note(s): 1. In the above calculations, depreciation for the first year has been considered as 50%(=50% of (80%+20%) and for second year as 90%(=80%+50% of 20%) as per CERC methodology. 2. Generation for the first year has been considered as 50% of normative generation for second half of the financial year. 3. Figures may not tally exactly on account of rounding off.

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4,

More information

KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001

KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001 KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001 Present: Shri M.R.Sreenivasa Murthy Chairman Shri Vishvanath Hiremath Shri K. Srinivasa

More information

DRAFT ORDER (SUO-MOTU)

DRAFT ORDER (SUO-MOTU) Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: mercindia@mercindia.org.in

More information

Consultative Paper on Comprehensive Tariff Order on Solar Power. (Comments/Suggestions are invited on or before 31.08.2013)

Consultative Paper on Comprehensive Tariff Order on Solar Power. (Comments/Suggestions are invited on or before 31.08.2013) TAMIL NADU ELECTRICITY REGULATORY COMMISSION Consultative Paper on Comprehensive Tariff Order on Solar Power (Comments/Suggestions are invited on or before 31.08.2013) 1. Introduction 1.1 The importance

More information

TARIFF DETERMINATION METHODOLOGY FOR THERMAL POWER PLANT

TARIFF DETERMINATION METHODOLOGY FOR THERMAL POWER PLANT TARIFF DETERMINATION METHODOLOGY FOR THERMAL POWER PLANT 1. Background The Electricity Act 2003 has empowered the Central Electricity Regulatory Commission (CERC) to specify the terms and conditions for

More information

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes

More information

all that you want to know About Rajasthan Solar Energy

all that you want to know About Rajasthan Solar Energy all that you want to know bout Rajasthan Solar Energy Policy, 2014 General 01 Registration Land Timelines Fee & Charges 06 08 11 13 all that you want to know bout Rajasthan Solar Energy Policy, 2014 Rajasthan

More information

Draft Solar Power Tariff - Ground Mounted Grid Connected and Solar Rooftop with Net Metering Regulations - 2014

Draft Solar Power Tariff - Ground Mounted Grid Connected and Solar Rooftop with Net Metering Regulations - 2014 Draft Solar Power Tariff - Ground Mounted Grid Connected and Solar Rooftop with Net Metering Regulations - 2014 JERC invites suggestions / comments/inputs / objections on above draft Regulations of Joint

More information

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com Draft ver2 Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com 1 TABLE OF CONTENTS S.No Contents Page No 1. PREAMBLE 3 2. OBJECTIVES 3 3. OPERATIVE

More information

S. No. Year Obligation expressed as percentage of energy consumption (%) 1 2011-12 6.00 2 2012-13 7.10 3 2013-14 8.20

S. No. Year Obligation expressed as percentage of energy consumption (%) 1 2011-12 6.00 2 2012-13 7.10 3 2013-14 8.20 Background paper for prescribing Renewable Purchase Obligation (RPO) for Captive consumption of CPP & open access consumers in the State for the period ending March, 2017 and related amendment in regulations:

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7. PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.2010 In the matter of : Determination of generic levellised generation

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No. 52 of 2013 Date of Order: 14.11.2013 In the matter of: Petition under Section 86 (1) (b) and 86 (1)

More information

BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA

BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA Quorum: Case No. HERC/PRO-51 of 2014 Date of hearing: 22.07.2014 Date of order : 22.07.2014 Shri

More information

PFS Web Conference Frequently Asked Questions

PFS Web Conference Frequently Asked Questions PFS Web Conference Frequently Asked Questions 1. About PFS and its performance Q: Kindly brief about PTC India Financial Services? A: PTC India Financial Services Limited, also known as PFS, is one of

More information

Guidelines for Solar Grid Power Projects

Guidelines for Solar Grid Power Projects Guidelines for Solar Grid Power Projects NTPC Ltd. NTPC Vidyut Vyapar Nigam Ltd. AGENDA 1 2 3 NTPC / NVVN at a glance Broad Guidelines for Selection of Solar Power Developers Elements of PPA NTPC Limited

More information

G.O.MS.No. 8 Dated 12.02.2015 Read the following:-

G.O.MS.No. 8 Dated 12.02.2015 Read the following:- GOVERNMENT OF ANDHRA PRADESH ABSTRACT ENERGY, INFRASTRUCTURE & INVESTMENT DEPARTMENT - Development of Solar Power in Andhra Pradesh Andhra Pradesh Solar Power Policy, 2015 Orders Issued. ------------------------------------------------------------------------------------------------------------

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION

KERALA STATE ELECTRICITY REGULATORY COMMISSION KERALA STATE ELECTRICITY REGULATORY COMMISSION Notification No. 2096/KSERC/CT/2014 Dated, Thiruvananthapuram 10 th June 2014. In exercise of the powers conferred under sections 66, 86 (1) (e) and 181 of

More information

RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR

RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR NOTIFICATION 23 rd December, 2010 No.RERC/Secy/Reg. 82 : In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity Act,

More information

a) Whether there is a need to revisit the existing approach for debt: equity ratio or to continue with the existing composition?

a) Whether there is a need to revisit the existing approach for debt: equity ratio or to continue with the existing composition? Summary of the comments and suggestions received on Approach Paper on Terms and Conditions of Tariff Regulations for the tariff period 1.4.2014 to 31.3.2019 ( Ref No. 20/2013/CERC/Fin(Vol-I)/Tariff Reg/CERC

More information

Overview of Rooftop Solar PV Green Bank Financing Model

Overview of Rooftop Solar PV Green Bank Financing Model Overview of Rooftop Solar PV Green Bank Financing Model Sponsored by The Connecticut Clean Energy Finance and Investment Authority and The Coalition for Green Capital Developed by Bob Mudge & Ann Murray,

More information

Delhi Solar Energy Policy, 2015

Delhi Solar Energy Policy, 2015 DRAFT VERSION FOR PUBLIC COMMENT Delhi Solar Energy Policy, 2015 GOVERNMENT OF NCT OF DELHI DELHI SECTRETARIAT, I.P. ESTATE, NEW DELHI- 110002 10 September 2015 NOTIFICATION The Government of NCT of Delhi

More information

Generation Cost Calculation for 660 MW Thermal Power Plants

Generation Cost Calculation for 660 MW Thermal Power Plants P P IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 1 Issue 10, December 2014. Generation Cost Calculation for 660 Thermal Power Plants 1 1* 2 Vilas S. MotghareP P,

More information

THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE

THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE PRESENTATION BY : MR KESHAV PRASAD MEMBER, DELEGATION OF THE CONFEDERATION OF INDIAN INDUSTRY (CII) & CHIEF OPERATING OFFICER, IL&FS ENERGY

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Sources) Regulations, 2012 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI No. : L-1/94/CERC/2011 Dated: 06.02.2012 NOTIFICATION In exercise of powers conferred under Section 61 read with Section 178

More information

Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014

Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Table of Contents 1- PREAMBLE - 1 2- OBJECTIVES - 1 3- OPERATIVE PERIOD - 1 4- IMPLEMENTATION PLAN - 2 5- ELIGIBLE ENTITIES - 2 6- TARGETS

More information

To whom application is to be filed

To whom application is to be filed SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED 6-1-50, Corporate Office/Mint Compound/Hyderabad 063. www.tssouthernpower.com, email:seipc@tssouthernpower.com As per TELANGANA SOLAR POWER POLICY

More information

RAJASTHAN ELECTRICITY REGULATORY COMMISSION

RAJASTHAN ELECTRICITY REGULATORY COMMISSION RAJASTHAN ELECTRICITY REGULATORY COMMISSION In the matter of amendments in: I. RERC (Renewable Energy Obligation) Regulations, 2007. II. RERC (Renewable Energy Certificate and Renewable Purchase Obligation

More information

Case No. 100 of 2014. Smt. Chandra Iyengar, Chairperson Shri Vijay L. Sonavane, Member ORDER (SUO-MOTU)

Case No. 100 of 2014. Smt. Chandra Iyengar, Chairperson Shri Vijay L. Sonavane, Member ORDER (SUO-MOTU) Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: mercindia@merc.gov.in Website:

More information

Marketing Methodology of Solar PV Power Packs

Marketing Methodology of Solar PV Power Packs Marketing Methodology of Solar PV Power Packs Somasekhar. G, Bharathi.G, and GirijaEureka.M* Department of Management Studies Madanapalle Institute of Technology & Science Post Box No: 14, Angallu, Madanapalle-

More information

Success in Scaling-up Solar Energy in Rajasthan, India

Success in Scaling-up Solar Energy in Rajasthan, India Success in Scaling-up Solar Energy in Rajasthan, India Shreemat Pandey Principal Secretary to Chief Minister Rajasthan, India 1. Introduction Solar power is attractive because it is abundant and offers

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. SM/354/2013 (Suo-Motu)

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. SM/354/2013 (Suo-Motu) CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. SM/354/2013 (Suo-Motu) Coram: 1. Shri Gireesh B. Pradhan, Chairperson 2. Shri M. Deena Dayalan, Member 3. Shri A. K. Singhal, Member 4.

More information

Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur, Dated March 29, 2011

Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur, Dated March 29, 2011 Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur, Dated March 29, 2011 Chhattisgarh State Electricity Regulatory Commission (Terms and conditions for determination

More information

CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2009

CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2009 CERC (Terms and Conditions for Tariff determination from Renewable Statement of Objects and Reasons 1. Introduction 1.1 The Electricity Act, 2003 (hereinafter referred to as the Act ) under Section 79

More information

SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems

SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems Contents Introduction 3 How solar PV power systems work 4 Solar modules 5 Is solar power

More information

RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14

RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14 RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14 In the matter of Determination of Annual Revenue Requirement (ARR) & Retail Supply

More information

NEW CERC REGULATIONS TO ENCOURAGE INVESTMENT, EFFICIENCY IN POWER SECTOR

NEW CERC REGULATIONS TO ENCOURAGE INVESTMENT, EFFICIENCY IN POWER SECTOR ICRA Rating Feature January 2009 NEW CERC REGULATIONS TO ENCOURAGE INVESTMENT, EFFICIENCY IN POWER SECTOR Contact Anjan Ghosh Head, Corporate Ratings aghosh@icraindia.com +91-22-30470006 Sabyasachi Majumdar

More information

TELANGANA SOLAR POWER POLICY 2015

TELANGANA SOLAR POWER POLICY 2015 TELANGANA SOLAR POWER POLICY 2015 1 GLOSSARY COD CII GoTS GoI MNRE MoP NCE NOC NSM PCB PPA PV R&D REC RPPO RLDC SGST SLDC SPC SPP SPV SRP Scheduled Commercial Operations Date Confederation of Indian Industry

More information

Tamil Nadu Electricity Regulatory Commission

Tamil Nadu Electricity Regulatory Commission 1 Tamil Nadu Electricity Regulatory Commission No 19A, Rukmini Lakshmipathy Salai, Egmore, Chennai - 600 008. Phone:044-28411376, Website:http://www.tnerc.tn.nic.in/ Public Notice 1. The Tamil Nadu Generation

More information

Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd.

Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd. Financing of Renewable Energy in India: Implications for Policy Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd.org CPI analyzes the effectiveness of policies relevant to climate change

More information

Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013

Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013 Dated: 23 rd April, 2015 Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013 Present: Hon ble Mr. Rakesh Nath, Technical Member Hon ble Mr. Justice Surendra Kumar, Judicial

More information

Grid Connected Solar Power in India. Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India

Grid Connected Solar Power in India. Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India Grid Connected Solar Power in India Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India Indian Power Sector (31 March 2012) Thermal Hydro Nuclear Renewable 1,31,353 MW

More information

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY 1. OBJECTIVE : 1.1. This procedure shall provide guidance to the entities to implement

More information

Existing Wind Power Policies and Incentives

Existing Wind Power Policies and Incentives Existing Wind Power Policies and Incentives Consultation on National Wind Energy Mission January 9, 2014 New Delhi Wind Power Progress (in MW) Potential (at 80 m) : 1,02,000 Achievement so far : 20,150

More information

Financial Analysis of Solar Photovoltaic Power plant in India

Financial Analysis of Solar Photovoltaic Power plant in India Financial Analysis of Solar Photovoltaic Power plant in India M. Ganga Prasanna, S. Mahammed Sameer, G. Hemavathi Department of Management Studies MadanapalleInstitute of Technology& Science Post Box No:

More information

No. 22/9/2009-NSM (ST) भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र ऱय / Ministry of New & Renewable Energy ***** Office Memorandum

No. 22/9/2009-NSM (ST) भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र ऱय / Ministry of New & Renewable Energy ***** Office Memorandum No. 22/9/2009-NSM (ST) भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र ऱय / Ministry of New & Renewable Energy ***** Office Memorandum Block-14, CGO Complex, Lodhi Road, New Delhi, dated 8 th

More information

Subject: Draft Scheme for development of Solar Parks and Ultra Mega Solar power projects circulation for comments reg.

Subject: Draft Scheme for development of Solar Parks and Ultra Mega Solar power projects circulation for comments reg. MOST IMMEDIATE No.30/18/2014-15-NSM भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र लय / Ministry of New & Renewable Energy (NSM Coord. Group) ***** Block 14, CGO Complex, Lodi Road, New Delhi-03,

More information

Regulations for Determination of Pipeline Tariff for Natural Gas Pipelines

Regulations for Determination of Pipeline Tariff for Natural Gas Pipelines Draft Regulations for Determination of Pipeline Tariff for Natural Gas Pipelines Petroleum & Natural Gas Regulatory Board, New Delhi November 29, 2007 Reader may please note that this document is the property

More information

Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC

Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC This agreement made at on this day of Two thousand between M/s. (Solar Power Generator name and address) hereinafter called the

More information

Tamil Nadu Electricity Regulatory Commission

Tamil Nadu Electricity Regulatory Commission Tamil Nadu Electricity Regulatory Commission Consultative Paper on Procurement of Power from small hydro power (up to 5 MW) (Comments/Suggestions are invited on or before 31-03-2010) 1.0 Introduction 1.1

More information

A. 5MWp SPV Plant at Khimsar, Rajasthan. B. 5MWp SPV Plant Installed Technologies. D. 5MWp SPV Plant Challenges. E. 5MWp SPV Plant - Performance

A. 5MWp SPV Plant at Khimsar, Rajasthan. B. 5MWp SPV Plant Installed Technologies. D. 5MWp SPV Plant Challenges. E. 5MWp SPV Plant - Performance An overview & Performance Analysis of 5 MWp Solar PV Plant at Khimsar, Rj Rajasthan Reliance Industries Limited June 2, 2011 July 2010 Contents A. 5MWp SPV Plant at Khimsar, Rajasthan B. 5MWp SPV Plant

More information

DELIVERING BUSINESS ENERGY GO GREEN AND SAVE MONEY

DELIVERING BUSINESS ENERGY GO GREEN AND SAVE MONEY DELIVERING BUSINESS ENERGY CO M M E R C I A L S O L A R S O LU T I O N S GO GREEN AND SAVE MONEY PAY LESS FOR YOUR ELECTRICITY WHAT YOU SAVE ENERGYAID MODEL HOW YOU GET LOW COST ELECTRICITY Green electricity

More information

Karnataka Electricity Regulatory Commission. Discussion note on

Karnataka Electricity Regulatory Commission. Discussion note on Karnataka Electricity Regulatory Commission Discussion note on Draft KERC (Forecasting, Scheduling, Deviation settlement and related matters for Wind and Solar Generation sources) Regulations, 2015. 1.0.

More information

Technology Fact Sheet for Mitigation

Technology Fact Sheet for Mitigation Technology Fact Sheet for Mitigation Solar PV systems (>1MW) i Technology: Solar PV systems (>1MW) Sector : Energy Subsector : Technology characteristics Introduction Solar photovoltaic, or simply photovoltaic

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION

CENTRAL ELECTRICITY REGULATORY COMMISSION CENTRAL ELECTRICITY REGULATORY COMMISSION EXPLANATION FOR THE NOTIFICATION ON ESCALATION RATES DATED 04.04.2007 1. The Ministry of Power (MOP), vide its Notification dated, 19.01.2005, issued Guidelines

More information

*** Discussion Draft Not for Distribution ***

*** Discussion Draft Not for Distribution *** *** Discussion Draft Not for Distribution *** Draft PV Cash Flow Analysis Falmouth Wind Turbines Options Analysis Process December 3, 2012 Sustainable Energy Advantage, LLC Assumptions: Modeling Inputs

More information

Tamil Nadu WiNd ENErgy ProfilE

Tamil Nadu WiNd ENErgy ProfilE Tamil Nadu WiNd ENErgy ProfilE Wind energy in Tamil Nadu has witnessed tremendous growth propelling the State to the number one position in India in terms of renewables. However the challenge that remains

More information

DELHI ELECTRICITY REGULATORY COMMISSION

DELHI ELECTRICITY REGULATORY COMMISSION DELHI ELECTRICITY REGULATORY COMMISSION DELHI ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION AND RENEWABLE ENERGY CERTIFICATE FRAMEWORK IMPLEMENTATION) REGULATIONS, 2011 No. Dated:. NOTIFICATION

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Draft Maharashtra Electricity Regulatory Commission (Net Metering for Rooftop Solar Systems) Regulations, 2015 Electricity Act, 2003 No. MERC / Legal

More information

CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008

CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008 Titel: IBC SOLAR mit starken Ideen die Welt verändern Autor: Ort, 00. Monat 2008 CHANGING THE WORLD WITH COMPELLING IDEAS German Indian Renewable Energy Dialogue 1st of October 2008 2008 IBC SOLAR Agenda

More information

Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation

Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation Solar Energy Corporation of India (A Govt. of India Enterprise) NBCC Plaza, Tower-1, 4 th Floor, Pushp Vihar Sector-V,

More information

Solar Power Plants FAQs

Solar Power Plants FAQs Solar Power Plants FAQs Solar Power industry in India is gaining more and more prominence with each passing day. The domestic/off-grid industry is picking up speed too. Owing to the queries we are receiving

More information

Solar. for a brighter. future

Solar. for a brighter. future Solar for a brighter future Rajasthan Solar Energy Policy, 2014 Rajasthan Solar Energy Policy, 2014 Energy Department Government of Rajasthan Rajasthan, by virtue of its geography, enjoys the highest number

More information

ADB s Rooftop Solar Project. Aiming Zhou Senior Energy Specialist 15-19 June 2015 10 th Asia Clean Energy Forum

ADB s Rooftop Solar Project. Aiming Zhou Senior Energy Specialist 15-19 June 2015 10 th Asia Clean Energy Forum ADB s Rooftop Solar Project Aiming Zhou Senior Energy Specialist 15-19 June 2015 10 th Asia Clean Energy Forum 1. Project Summary 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 >27

More information

NOTICE OF INTENT Department of Revenue Policy Services Division. Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I.

NOTICE OF INTENT Department of Revenue Policy Services Division. Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I. NOTICE OF INTENT Department of Revenue Policy Services Division Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I.1907) Under the authority of R.S. 47:287.785, R.S. 47:295, R.S. 47:1511, and

More information

Wind Power Programme in India

Wind Power Programme in India Wind Power Programme in India Ministry of New & Renewable Energy 1 st August 2012, New Delhi 1 Renewable Power Sector in INDIA Share of Installed Renewable Capacity 13% 4% 13% 70% Wind Solar Hydro Biomass

More information

SMALL SOLAR. 2014 Nebraska Wind and Solar Conference and Exhibition. Guy C. Smith October 29, 2014

SMALL SOLAR. 2014 Nebraska Wind and Solar Conference and Exhibition. Guy C. Smith October 29, 2014 SMALL SOLAR 2014 Nebraska Wind and Solar Conference and Exhibition Guy C. Smith October 29, 2014 TYPES OF SOLAR PROJECTS Concentrated Solar Projects (CSP) Systems generate solar power using mirrors or

More information

Solar Provider Group LLC, 453 South Spring Street, Suite 804 Los Angeles, CA 90013 Phone: (805) 410-2571 Toll Free: 1 (888) 989-4677 Fax:

Solar Provider Group LLC, 453 South Spring Street, Suite 804 Los Angeles, CA 90013 Phone: (805) 410-2571 Toll Free: 1 (888) 989-4677 Fax: OVERVIEW This document outlines a proposed 630 kw system on the Overland parking structure for Sony Pictures Entertainment ("SPE") as part of Southern California Edison's ("SCE") Solar Photovoltaic Program

More information

IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND

IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY

More information

Government of Jharkhand Department of Energy. Notification

Government of Jharkhand Department of Energy. Notification Draft Jharkhand State Solar Power Policy 2015 Government of Jharkhand Department of Energy Notification No. ------ Date:./2015 Preamble: In order to reduce the dependence on fossil fuel based generation,

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION

KERALA STATE ELECTRICITY REGULATORY COMMISSION KERALA STATE ELECTRICITY REGULATORY COMMISSION Dated 24 th January 2014 NOTICE Notice is hereby given that Kerala State Electricity Regulatory Commission has published the Draft Kerala State Electricity

More information

Dated 2011. (1) Waverley Borough Council (2) [NAME OF OCCUPIER] Solar Agreement. relating to [ADDRESS OF PROPERTY]

Dated 2011. (1) Waverley Borough Council (2) [NAME OF OCCUPIER] Solar Agreement. relating to [ADDRESS OF PROPERTY] Dated 2011 (1) Waverley Borough Council (2) [NAME OF OCCUPIER] Solar Agreement relating to [ADDRESS OF PROPERTY] THIS AGREEMENT is made on Date between: (1) the Landlord Waverley Borough Council whose

More information

IREDA-NCEF REFINANCE SCHEME

IREDA-NCEF REFINANCE SCHEME IREDA-NCEF REFINANCE SCHEME REVIVAL OF THE OPERATIONS OF EXISTING BIOMASS POWER & SMALL HYDRO POWER PROJECTS AFFECTED DUE TO UNFORSEEN CIRCUMSTANCES SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA NCEF

More information

INDEX S. No. PARTICULARS Note:

INDEX S. No. PARTICULARS Note: INDEX S. No. PARTICULARS T1 Profit & Loss Account - Transmission Business T2 Profit & Loss Account - SLDC Business T3 Annual Revenue Requirement - Transmission Business T4 Annual Revenue Requirement -

More information

Is Overproduction Costing You?

Is Overproduction Costing You? Is Overproduction Costing You? A review of the impacts of solar resource data on financing and revenues for PV plants Presented by: Marie Schnitzer Vice President of Consulting Services Paul Thienpont

More information

Draft Jharkhand State Solar Power Policy 2015

Draft Jharkhand State Solar Power Policy 2015 Draft Jharkhand State Solar Power Policy 2015 Government of Jharkhand Department of Energy Notification No. ------ Date:./2015 Preamble: In order to reduce the dependence on fossil fuel based generation,

More information

H1 2014 LEVELISED COST OF ELECTRICITY - PV

H1 2014 LEVELISED COST OF ELECTRICITY - PV H1 2014 LEVELISED COST OF ELECTRICITY - PV JENNY CHASE 4 FEBRUARY 2014 LCOE OF PV, FEBRUARY 2014 1 PV EXPERIENCE CURVE, 1976-2013 (2013 $/W) 100 Cost per W (2013 $) 1976 10 1985 2003 2006 1 2012 2013 Q3

More information

OFFICE SPACE AVAILABLE FOR IT COMPANIES ON LEASE RENT AT NSIC STP COMPLEX, OKHLA INDUSTRIAL ESTATE, NEW DELHI

OFFICE SPACE AVAILABLE FOR IT COMPANIES ON LEASE RENT AT NSIC STP COMPLEX, OKHLA INDUSTRIAL ESTATE, NEW DELHI OFFICE SPACE AVAILABLE FOR IT COMPANIES ON LEASE RENT AT NSIC STP COMPLEX, OKHLA INDUSTRIAL ESTATE, NEW DELHI Details of available office space SL. PARTICULARS MODULES AREA IN TYPE OF STATUS NO. SQ. FT

More information

Using the sun to generate electricity

Using the sun to generate electricity Using the sun to generate electricity Image source: http://www.globalsolarcenter.com/files/2009/04/commercial-solar.jpg Solar panels information sheet What are the benefits? How does it work? What is the

More information

SOLAR TECHNOLOGY CHRIS PRICE TECHNICAL SERVICES OFFICER BIMOSE TRIBAL COUNCIL

SOLAR TECHNOLOGY CHRIS PRICE TECHNICAL SERVICES OFFICER BIMOSE TRIBAL COUNCIL SOLAR TECHNOLOGY CHRIS PRICE TECHNICAL SERVICES OFFICER BIMOSE TRIBAL COUNCIL SOLAR TECHNOLOGY Photovoltaics Funding Options Solar Thermal Photovoltaics 1. What are they and how do they work? 2. The Solar

More information

Review relating to Statutory Corporation

Review relating to Statutory Corporation Review relating to Statutory Corporation 6.2 Computerised energy billing system of Ranchi Electric Supply Circle of Jharkhand State Electricity Board Highlights Jharkhand State Electricity Board (JSEB)

More information

02 July 2015. VIPL Response to balancedata gaps 1 / Queries Set Case 36 of 2015 Data Gaps/Deficiencies on the Petition submitted by VIPL

02 July 2015. VIPL Response to balancedata gaps 1 / Queries Set Case 36 of 2015 Data Gaps/Deficiencies on the Petition submitted by VIPL Exhibit A VIPL Response to balancedata gaps 1 / Queries Set Case 36 of 2015 Data Gaps/Deficiencies on the Petition submitted by VIPL VIPL- Transmission: Determination of Capital Cost and Approval of ARR

More information

Renewable Energy Certificate Mechanism

Renewable Energy Certificate Mechanism Opportunities in Financing Renewable Energy Projects focusing on FiT and RECs Balawant Joshi Director, balawant@gmail.com, balawant.joshi@abpsinfra.com In this presentation.. Investment Potential for Renewable

More information

Modelling of Large- Scale PV Systems in Australia

Modelling of Large- Scale PV Systems in Australia Modelling of Large- Scale PV Systems in Australia By The Australian PV Association November 2011 AUTHORS: Graham Mills (APVA); Simon Franklin, Rob Passey & Muriel Watt (IT Power Australia); Anna Bruce

More information

Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading

Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading Target Clients v Renewable Energy Generators in India v RPO mandated entities in India v Investors seeking

More information

ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY / RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012

More information

U.S.A. and China Solar PV Market

U.S.A. and China Solar PV Market U.S.A. and China Solar PV Market & PPA Solar Project Development Kevin Gao VP, CA Solar LLC kevingao@casolarco.com Table of Content Solar Panel Pricing & Cost Trend USA Solar Market China Solar Market

More information

POWER PURCHASE AGREEMENT BETWEEN SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED

POWER PURCHASE AGREEMENT BETWEEN SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED POWER PURCHASE AGREEMENT BETWEEN SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED AND M/s. NCE SOLAR PPA No. This Power Purchase Agreement ( Agreement ) entered into on this day of 20 between Southern

More information

Report On Development of Conceptual Framework For Renewable Energy Certificate Mechanism for India

Report On Development of Conceptual Framework For Renewable Energy Certificate Mechanism for India Report On Development of Conceptual Framework For Renewable Energy Certificate Mechanism for India Submitted to Ministry of New and Renewable Energy (Government of India) Prepared by ABPS Infrastructure

More information

Solar for Homeowners. Bear Valley Solar Initiative (BVSI) Laura Williams, Project Manager. February, 11 2015

Solar for Homeowners. Bear Valley Solar Initiative (BVSI) Laura Williams, Project Manager. February, 11 2015 Solar for Homeowners Bear Valley Solar Initiative (BVSI) February, 11 2015 Laura Williams, Project Manager Our Mission: Accelerate the transition to a sustainable world powered by clean energy CSE Disclaimer

More information

DELHI TRANSCO LIMITED

DELHI TRANSCO LIMITED DELHI TRANSCO LIMITED SCHEDULE-22: Notes forming part of Accounts. 1. Delhi Electricity Reform (Transfer Scheme) Notification No. 2869 dated 20-11-01. In exercise of the Power conferred by Section 60 read

More information

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents Annexure-1-B ANNEXURE TO TARIFF ORDER PASSED BY MPERC For Financial Year 2006-07 MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS Table of Contents Sr No Particulars

More information

Solar for Businesses. Getting Started with Solar. Laura Williams, Renewables Project Manager. June 10, 2015

Solar for Businesses. Getting Started with Solar. Laura Williams, Renewables Project Manager. June 10, 2015 Solar for Businesses Getting Started with Solar June 10, 2015 Laura Williams, Renewables Project Manager Our Mission: Accelerate the transition to a sustainable world powered by clean energy What We Do

More information

For Empanelment of Registered Firms of Chartered Accountants for. conduct of Audit of Accounts and also Physical verification

For Empanelment of Registered Firms of Chartered Accountants for. conduct of Audit of Accounts and also Physical verification '... REQUEST FOR PROPOSAL (RFP) For Empanelment of Registered Firms of Chartered Accountants for conduct of Audit of Accounts and also Physical verification of Works executed by the Gram Panchayats of

More information

32/1/2013-14/PVSE(Part-II) Ministry of New and Renewable Energy SPV Off Grid Division

32/1/2013-14/PVSE(Part-II) Ministry of New and Renewable Energy SPV Off Grid Division Annexure-A 32/1/2013-14/PVSE(Part-II) Ministry of New and Renewable Energy SPV Off Grid Division Scheme: Installation of 10,000 nos. of solar photovoltaic water pumping systems for irrigation purpose implemented

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION. No. L-1/(3)/2009-CERC Dated the 7 th August 2009

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION. No. L-1/(3)/2009-CERC Dated the 7 th August 2009 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION No. L-1/(3)/2009-CERC Dated the 7 th August 2009 In exercise of powers conferred by section 178 of the Electricity Act, 2003 and all other

More information

Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency

Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Renewable Energy Strategy for 2020 and Regulatory Framework Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Objectives of the Agency Regulate, supervise, and control all matters

More information

HARNESS. Utilising solar energy to save money

HARNESS. Utilising solar energy to save money HARNESS Utilising solar energy to save money Why consider solar? No control over ever rising electricity prices Electricity costs have doubled over the last 10 years* What will your electricity bill be

More information

Virginia Solar Co-op FAQs

Virginia Solar Co-op FAQs Solar Basics How do solar panels work? Photovoltaic cells convert the energy from the sun into electricity and are arranged together to form solar panels. The inverters then convert the electricity generated

More information

Exposure Draft. Guidance Note on Accounting for Derivative Contracts

Exposure Draft. Guidance Note on Accounting for Derivative Contracts Exposure Draft Guidance Note on Accounting for Derivative Contracts (Last date of comments: January 21, 2015) Issued by Research Committee The Institute of Chartered Accountants of India (Set up by an

More information