02 July VIPL Response to balancedata gaps 1 / Queries Set Case 36 of 2015 Data Gaps/Deficiencies on the Petition submitted by VIPL
|
|
- Junior Webb
- 8 years ago
- Views:
Transcription
1 Exhibit A VIPL Response to balancedata gaps 1 / Queries Set Case 36 of 2015 Data Gaps/Deficiencies on the Petition submitted by VIPL VIPL- Transmission: Determination of Capital Cost and Approval of ARR for FY and Replies to Balance Data Gaps - Set 1 (Query No. is same as was provided in Response to data gaps submitted by VIPL (Ref: VIPL/MUM/ /MERC/VIPL-T/1dated 17 th July 2015)) 14. VIPL has submitted IDC and Financing cost of Rs Crores in the Petition as compared to an in-principle approved IDC of Rs Crore. VIPL should submit the detailed working of IDC and Financing cost including monthly loan drawl and corresponding documentary evidences justifying the significant increase in IDC & Financing expenses for the Project. VIPL should submit the detailed calculation of IDC for the in-principle approved capital cost and the IDC calculation for revised capital cost submitted in the Petition, in excel format with all linked formulas and assumptions considered for calculation. VIPL-T Response: VIPL would like to submit that the financing of the project was done on combined basis for Transmission &Generation assets.there was no separate financing for Transmission assets. In view of above, thefollowing methodology was adopted for calculations of IDC for Transmission schemes 1 & 2: 1) Firstly, IDC of entire project including Generation &Transmission was calculated as on commissioning dates of Transmission schemes 1& 2. 2) Further, total IDC as calculated above is apportioned betweengeneration &Transmission assets in the ratio ofvalue assets of Generation &Transmission respectively, as on the date of Capitalisation of Transmission schemes. Detailed workings for original and actual IDC based on the above methodology is enclosed in Annexure Query 14. The explanationrelated toincrease in IDC is providedunder query No-2 (Sr. No 4 in table) indata Gaps Set 1 (Exhibit A submitted vide letter Ref: VIPL/MUM/ /MERC/VIPL-T/1 dated 17th July 2015). 15. VIPL should submit the loan-wise details regarding opening and closing loan and actual interest paid for FY Further, VIPL should also submit loan-wise applicable rate of interest at the beginning of the year for FY and FY along with documentary evidence. 1
2 VIPL-T Response:VIPL wants to submit that, there has been certain revisions since the time the petition dated 18 th Feb 2015 (Ref: VIPL/MUM/FEB15/MERC/01) till the time clarifications were sought on data-gaps by the Hon ble Commission. The said revisions will affect Interest on Long-term loan capital and Interest on working capital leading to change in the Annual Revenue Requirement. The following are the revisionsrequired to be made 1) Rate of Interest on Long-term Capital for FY is to be revised as 14%. VIPL. VIPL submits that there was an inadvertent mistake in the interest rate used for computation of interest on long-term capital for FY The same is to be revised as 14% in place of 13.75% which was mentioned earlier. VIPL request Hon ble Commission to condone the same. 2) Rate of Interest on Long-term Capital for FY is to be revised as 12.5%. The Hon ble Commission may appreciate the fact that VIPL has managed to reduce the interest rate of long term debt significantly by refinancing the Rupee Term Debt. The refinancing transaction of the loan got completed post submission of the petition dated 18 th Feb 2015 (Ref: VIPL/MUM/FEB15/MERC/01). As per the Reserve Bank of India circular ref no DBOD.BP.BC.No.31/ / dated August 07, 2014 the long term debt of existing infrastructure projects may be refinanced with longer repayment period for reducing the interest liability of the projects. In order to take advantage of improved credit profile, VIPL re-financed majority of its domestic rupee loan taken for the project to avail the following benefits: Reduce the interest rate on domestic rupee loan from earlier 14.00% pa to 12.50% pa Reduction in the number of lenders in the consortium for better coordination w.r.t. compliance of financial and non-financial covenants and ease of obtaining of financing related approvals in future from lenders The abovechanges will result into changes in the following sections of the petition submitted on 18th Feb Interest on Loan Capital 5.8. The Petitioner submits that since the project was funded as part of total power station, there is no segregated source wise funding identified towards creation of the transmission asset. However, for the purpose of the Interest rate for the project, the Petitioner submits that interest rate as per Rupee loan availed for the VIPL project has been considered for transmission assets. The ECB loan and Buyer s credit availed for the VIPL project (Generation and Transmission project as a whole) has been fully allocated to VIPL Butibori Generation project 2
3 for which the Hon ble Commission has approved provisional tariff vide its order dated February 17, 2014 in case 91 of With regard to interest rate on debt considered as explained above, VIPL-T has considered the interest rate on Indian Loan for FY 14-15, based on norms specified in the MYT Regulations As per the Reserve Bank of India circular ref no DBOD.BP.BC.No.31/ / dated August 07, 2014 the long term debt of existing infrastructure projects may be refinanced with longer repayment period for reducing the interest liability of the projects. In order to take advantage of improved credit profile, VIPL re-financed majority of its domestic rupee loan taken for the project to avail the following benefits: Reduce the interest rate on domestic rupee loan from earlier 14.00% pa to 12.50% pa Reduction in the number of lenders in the consortium for better coordination w.r.t. compliance of financial and non-financial covenants and ease of obtaining of financing related approvals in future from lenders The working of the same is provided in the financial model submitted along herewith as Appendix As has been stated earlier, the assets under Scheme 1 have been charged, tested and ready to use/put to use on 29 th June However, the supply of power started from April 1, 2014, as per PPA, hence, the loan corresponding to 70% of project cost as provided in Clause 4.12 above has been considered as the loan admitted from 1 st April 2014 onwards In accordance of the above, the interest on loan capital is computed as in the table below: Table 1: Interest on Loan Capital UoM FY Estimated FY Estimated Opening Loan Balance* Rs. Crs Loan Drawl Rs. Crs - - Normative Loan Repayment Rs. Crs Closing Loan Balance Rs. Crs Interest Rate % 14% 12.50% Interest on Loan Capital Rs. Crs *Opening loan for FY specified above is the loan as on date of supply of power as per PPA calculated based on 70% of Capex as on date of commissioning less actual accumulated depreciation for FY & FY
4 Interest on Working Capital Interest on working capital has been calculated according to Clause 36.2(c) of MYT Regulations 2011 reproduced as under: (c) Rate of Interest on working capital shall be on normative basis and shall be equal to the State Bank Advance Rate (SBAR) of State Bank of India as on the date on which the application for determination of tariff is made Considering the above regulation, interest on working capital has been computed at the rate of % per annum for FY & FY 15-16, which is equivalent to SBAR as on date of submission of this petition. The SBAR over the years is provided in the table below: Table 2: SBAR over the years Date From Date To Number of Days Interest Rate 7-Nov Mar % 1-Apr Mar % Since VIPL-T is a new transmission licensee, it does not have any historical records to analyse and determine the nature of requirement of working capital in relation to stores, materials and supplies. Therefore, for the purpose of this petition 1% of opening GFA has been considered as annual requirement for stores for the relevant financial year Accordingly VIPL-T has considered the following assumptions while computing the working capital: Table 3: Working Capital Assumptions In Months O&M Expenses 1 Stores, Materials and Supplies 1 Revenue 1.5 Assumption for Stores 1% of GFA Interest on Working Capital FY 15 & FY % The table below provides the IoWC in accordance with MYT Regulations 2011: 4
5 Table 4: Interest on Working Capital UoM FY FY Normative Normative O&M Expenses Rs. Crs Stores Rs. Crs Expected Revenue from Transmission Rs. Crs Total Working Capital Requirement Rs. Crs Interest on Working Capital Rs. Crs Since the Petitioner is not envisaging any security deposit to be taken from the users of its transmission system, no interest on security deposit has been considered for the purpose of computation of Transmission ARR. Clause 5.29 of the petition is also revised as under: Based on the above parameters, the Projected Aggregate Revenue Requirement for VIPL-T for FY to is summarized in the table below: Table 5: Aggregate Revenue Requirement MYT Period FY FY Operation & Maintenance Expenses Depreciation Expenses Interest on Long-term Loan Capital Interest on Working Capital and on consumer security deposits Other Expenses - - Income Tax (FY 15, FY 16) Contribution to contingency reserves Total Revenue Expenditure Return on Equity Capital Aggregate Revenue Requirement Less: Non Tariff Income Less: Income from Other Business - - Aggregate Revenue Requirement from Transmission Tariff The financial model at Appendix 5 of the Petition submitted dated 18th Feb 2015 is revised and attached along with this response to data gaps as Annexure to Query 15 (A).Due to the above changes, the similar figures are required to be revised in F1. (c), F1. (d), F1. (i)of the petition submitted on 18th Feb
6 The details of the combined rupee term loan for the Project (Generation & Transmission combined) is as FY under. Rs Cr Opening Rupee Term Loan for Closing Rupee Term Loan Interest on Rupee Term Loan paid Interest Rate at the beginning of the year 14.00% The interest rate at the beginning of the year for FY is 12.5%. Loan document for the project are executed outside Maharashtra State and as per The Maharashtra Stamp Act (Bom.Act LX 1958) Section 18 and 19, pages 117 and 118,any document executed out of the state and subsequently such instrument or a copy of theinstrument has been received in the state, then the stamp duty is chargeable. VIPL thereforereiterates that the relevant pages of unsigned copy of loan agreement are being submittedfor interest rate applicable at the beginning of the year FY as Annexure 15 (B). The authenticity of the submissions vis-à-vis the original loan agreement has been verified bythe representatives of the Hon ble Commission during previous tariff proceedings. In this regard, minutes of meeting for the same is being attached herewith as Annexure to Query 15 (C). Similarly, as the loan documents for refinanced Rupee term loan are also executed outside Maharashtra, relevant pages of unsigned loan document is being attached herewith as Annexure to Query 15 (D) for determining the interest rate applicable at the beginning of FY If required, authenticity of the loan document can be verified by Representatives of Hon ble Commission as done in earlier proceedings. Base PLR applicable at the beginning of FY and FY for Axis Bank is attached herewith as Annexure Query 15 (E).. 6
Tamil Nadu Electricity Regulatory Commission
1 Tamil Nadu Electricity Regulatory Commission No 19A, Rukmini Lakshmipathy Salai, Egmore, Chennai - 600 008. Phone:044-28411376, Website:http://www.tnerc.tn.nic.in/ Public Notice 1. The Tamil Nadu Generation
More informationTrue up of Capitalization of FY 2006 and FY 2007, RoCE, Depreciation for the MYT Control Period and True up of FY 2011-12
Introduction 1.1 The Distribution Licensee, Tata Power Delhi Distribution Limited (TPDDL), has filed its Petition for approval of (i) True up for 2011-12 and truing up for controllable parameters, viz.,
More informationANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th & 5 th Floors, Singareni Bhavan, Red Hills, Hyderabad-500 004. O.P.No.
Between ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION 4 th & 5 th Floors, Singareni Bhavan, Red Hills, Hyderabad-500 004 O.P.No. 17 of 2009 Dated: 18.06.2011 Present Sri A. Raghotham Rao, Chairman Sri
More informationBEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA
BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA Quorum: Case No. HERC/PRO-51 of 2014 Date of hearing: 22.07.2014 Date of order : 22.07.2014 Shri
More informationa) Whether there is a need to revisit the existing approach for debt: equity ratio or to continue with the existing composition?
Summary of the comments and suggestions received on Approach Paper on Terms and Conditions of Tariff Regulations for the tariff period 1.4.2014 to 31.3.2019 ( Ref No. 20/2013/CERC/Fin(Vol-I)/Tariff Reg/CERC
More informationCENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 7/MP/2013
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 7/MP/2013 Coram: Dr. Pramod Deo, Chairperson Shri V.S.Verma, Member Shri M.Deena Dayalan, Member In the matter of Date of Hearing: 14.3.2013
More informationKERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4,
More informationJammu & Kashmir State Electricity Regulatory Commission
Jammu & Kashmir State Electricity Regulatory Commission Order on Annual Revenue Requirement for 3-Year Multi Year Tariff (MYT) period from FY 2013-14 to FY 2015-16 and Retail Tariff for FY 2013-14 for
More informationDetailed Vetting Report
Detailed Vetting Report Additional Supply Charge (ASC) and Incremental Additional Supply Charge (IASC) Amount for the period January 2007 to April 2007 1. The Commission issued the Tariff Order in Case
More informationBRIHANMUMBAI ELECTRIC SUPPLY AND TRANSPORT UNDERTAKING (BEST)
Before the Maharashtra Electricity Regulatory Commission Filing of the Petition for Aggregate Revenue Requirement and Tariff Proposal for FY 2011-12 under Maharashtra Electricity Regulatory Commission
More informationDRAFT ORDER (SUO-MOTU)
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: mercindia@mercindia.org.in
More informationDetermination of cost of power generation for Dongamahua captive power plant of Jindal Steel & Power Ltd. from FY 2011-12 till FY 2015-16.
Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur - 492 001 (C.G.) Ph.0771-4048788, Fax: 4073553 www.cserc.gov.in, e-mail: cserc.sec.cg@nic.in Petition No. 47
More informationCENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Coram: 1. Shri Bhanu Bhushan, Member 2. Shri R. Krishnamoorthy, Member In the matter of Petition No.33/2003 Approval of tariff in respect of Assam Gas
More informationBank Branch Audit Program / Illustrative Checklist Time & Manpower planning Sr. N. Designation &
Bank Branch Audit Program / Illustrative Checklist Time & Manpower planning Sr ame of the person Designation & Estimated time for work Initials of the Audit Program Sr o A B C General - Pre Audit Work
More informationJharkhand State Electricity Regulatory Commission
Final True up of JSEB for FY 2003-04 to FY 2010-11 and MYT Order for Generation Business for First Control Period (FY 2012-13 to FY2015-16) and Annual Revenue Requirement for FY 2011-12 & FY 2012-13 for
More informationBANK BRANCH AUDIT PLANNING
BANK BRANCH AUDIT PLANNING Banking Industry in India is developing and expanding day by day. The basic work culture in banks in India is fairly different as compared to banks in other countries. The customers
More informationSCHEDULE-17 SIGNIFICANT ACCOUNTING POLICIES 1. GENERAL BASIS OF PREPARATION
SCHEDULE-17 SIGNIFICANT ACCOUNTING POLICIES 1. GENERAL BASIS OF PREPARATION The financial statements have been prepared and presented under historical cost convention on accrual basis of accounting unless
More informationCapital Expenditure of Corporates: FY09-FY14
September 24, 2014 Economics RBI recently releaseda study on corporate investments which provides a picture on the envisaged capital expenditure (investment in fixed assets) of companies from the private
More informationTERMS AND CONDITIONS OF TARIFF REGULATIONS
TERMS AND CONDITIONS OF TARIFF REGULATIONS Approach Paper for Control Period 1.4.2014 TO 31.3.2019 Central Electricity Regulatory Commission 3 rd & 4 th Floor, Chandralok Building, 36, Janpath, New Delhi
More informationINDEX S. No. PARTICULARS Note:
INDEX S. No. PARTICULARS T1 Profit & Loss Account - Transmission Business T2 Profit & Loss Account - SLDC Business T3 Annual Revenue Requirement - Transmission Business T4 Annual Revenue Requirement -
More information1. What are the approximate rates for obtaining NHB refinance, NCD, RMBS, Bank loans, Deposits, CPs, ECB, any other instruments?
1. What are the approximate rates for obtaining NHB refinance, NCD, RMBS, Bank loans, Deposits, CPs, ECB, any other instruments? NHB Refinance Under Rural Housing Fund 1 : Interest rate on refinance =
More informationRAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14
RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14 In the matter of Determination of Annual Revenue Requirement (ARR) & Retail Supply
More informationallowed. Request for inclusion and consideration of ISO 2008:9001 quality certification. CMMI Level 5 : 10 Marks CMMI Level 3 : 07 marks ISO: 05
Corrigendum for the Tender for Web Based Project Monitoring Tool & MIS System Bidders Clarification Sl. Clause /Page no Tender Clause Clarification Sought Clarification No. 1 Page No:4 No consortium Consortium
More informationJammu & Kashmir State Electricity Regulatory Commission
Jammu & Kashmir State Electricity Regulatory Commission Order on Annual Revenue Requirement for Financial Year 2009-10 & Financial Year 2010-11 and Determination of Retail Tariffs for Financial Year 2010-11
More informationDR. HEDGEWAR AROGYA SANSTHAN GNCT OF DELHI KAKARDOOMA DELHI -110032
DR. HEDGEWAR AROGYA SANSTHAN GNCT OF DELHI KAKARDOOMA DELHI -110032 File No F4/Misc/2015-15/DHAS/ Dated CIRCULAR As per the provision of Section 192 of the Income Tax Act 1961, person responsible for paying
More information5:25 Flexible Structuring Scheme: Aligning Benefits
June 02, 2015 Ratings I. Genesis 5:25 Flexible Structuring Scheme: Aligning Benefits The development of core industries and infrastructure sector is pivotal for developing countries like India. Development
More informationIREDA-NCEF REFINANCE SCHEME
IREDA-NCEF REFINANCE SCHEME REVIVAL OF THE OPERATIONS OF EXISTING BIOMASS POWER & SMALL HYDRO POWER PROJECTS AFFECTED DUE TO UNFORSEEN CIRCUMSTANCES SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA NCEF
More informationSCHEDULE-17 SIGNIFICANT ACCOUNTING POLICIES 1. GENERAL BASIS OF PREPARATION
SCHEDULE-17 SIGNIFICANT ACCOUNTING POLICIES 1. GENERAL BASIS OF PREPARATION The financial statements have been prepared and presented under historical cost convention on accrual basis of accounting unless
More informationTARIFF DETERMINATION METHODOLOGY FOR THERMAL POWER PLANT
TARIFF DETERMINATION METHODOLOGY FOR THERMAL POWER PLANT 1. Background The Electricity Act 2003 has empowered the Central Electricity Regulatory Commission (CERC) to specify the terms and conditions for
More informationGeneration Cost Calculation for 660 MW Thermal Power Plants
P P IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 1 Issue 10, December 2014. Generation Cost Calculation for 660 Thermal Power Plants 1 1* 2 Vilas S. MotghareP P,
More informationHighlights Business Cross Section Domestic CASA Domestic Advances Retail Credit Components. 9 Months. Key Parameters Quarterly
Sl. No. Areas of Presentation Slide No Sl. No. Areas of Presentation Slide No 13 Financial 9 Months 14 Key Parameters Quarterly 24 15 Capital Adequacy (Basel III) 25 9 16 Earnings Per share, Book Value
More informationReview on Electricity Tariff in Peninsular Malaysia under the Incentive-based Regulation Mechanism (FY2014-FY2017)
Review on Electricity Tariff in Peninsular Malaysia under the Incentive-based Regulation Mechanism (FY2014-FY2017) Suruhanjaya Tenaga 19 th December 2013 1 The move towards better regulation: Suruhanjaya
More informationFinancial Performance and Financial Statement Projections
Financial Performance and Financial Statement Projections A. Introduction and Approach 1. The Georgian State Electrosystem (GSE), EA of the project, is a 100% state owned Limited Liability Company responsible
More informationSavings bank accounts- interest ing issues
Savings bank accounts- interest ing issues Ashish Das Division of Theoretical Statistics and Mathematics, Indian Statistical Institute, New Delhi 110016 and Department of Statistics, The University of
More informationMASTER CIRCULAR ON INTEREST RATES ON ADVANCES
MASTER CIRCULAR ON INTEREST RATES ON ADVANCES A. Purpose To consolidate the directives on interest rates on advances issued by Reserve Bank of India from time to time. B. Classification A statutory directive
More informationMaharashtra Budget Analysis 2016-17
The Minister of Finance of Maharashtra, Mr. Sudhir Mungantiwar, presented the Budget for Maharashtra for the financial year on March 18, 2016. Budget Highlights The Gross State Domestic Product of Maharashtra
More informationThe Straightforward. Consumer IVA Protocol. 2014 version
The Straightforward Consumer IVA Protocol 2014 version Effective from January 2014 1 IVA PROTOCOL Straightforward consumer individual voluntary arrangement hereinafter referred to as a Protocol Compliant
More informationPUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No. 52 of 2013 Date of Order: 14.11.2013 In the matter of: Petition under Section 86 (1) (b) and 86 (1)
More informationSECTION B7 FINANCIAL PROJECTIONS
B7.1 THE FINANCING PLAN SECTION B7 FINANCIAL PROJECTIONS B7.1.1 Cost of Capital The Company subscribes to the NERA reports on Cost of Capital for PR09 (January 2009) and on The Evidence for a Small Company
More informationExternal Commercial Borrowings
External Commercial Borrowings Neha Gupta Vinod Kothari & Company 1012 Krishna, 224 AJC Bose Road Kolkata- 7000017 Ph: 91-33-22817715/ 22811276 Email: neha@vinodkothari.com What is ECB? Source of funds
More informationSubject: -Submission of Income Details & proof of savings for the Financial Year 2014-15
CP No. Date To, The Incharge- F&A Division, Central Pollution Control Board, East Arjun Nagar, Shahadara, Delhi-110032 Sir, Subject -Submission of Income Details & proof of savings for the Financial Year
More informationKARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001
KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001 Present: Shri M.R.Sreenivasa Murthy Chairman Shri Vishvanath Hiremath Shri K. Srinivasa
More informationGUJARAT ELECTRICITY REGULATORY COMMISSION (GERC) Terms and Conditions of Tariff Notification No. 12 of 2005
GUJARAT ELECTRICITY REGULATORY COMMISSION (GERC) Terms and Conditions of Tariff Notification No. 12 of 2005 Gujarat Electricity Regulatory Commission In exercise of the powers conferred by Section 45(2),
More informationBharti Airtel Limited
Bharti Airtel Limited Registered Office: Bharti Crescent, 1, Nelson Mandela Road, Vasant Kunj, Phase II, New Delhi 110 070, India CIN: L74899DL1995PLC070609 T:+91-11-4666 6100, F:+91-11-4166 6137, Email
More information14 Paid Up Equity Share Capital 11,353 11,352 11,351 11,353 11,351 11,352 (Face Value of ` 10 each) 15 Reserve excluding Revaluation Reserve 740,298
STATEMENT OF CONSOLIDATED UNAUDITED RESULTS FOR THE QUARTER AND HALF YEAR ENDED 30TH SEPTEMBER 2012 Half Year Ended Year Ended 1 Income from Operation (a) Net Sales / Income from Operations (Net of Excise
More informationPROFORMA. 1) In respect of H.R.A. (Section 10(13) A of I.T. Act 1961 read with Rule 2A of I.T. Rules 1952) a) Actual HRA received Rs.
-2- ANNEXURE-I PROFORMA Calculation of Income tax for the Financial Year 2014-15 (A.Y.2015-2016) NAME : DESIGNATION : PERMANENT ACCOUNT NO. : PARTICULARS OF SALARY, ETC : Gross Income:- A 1. Salary for
More informationDRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015
DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes
More informationSUBMISSION ON THE AER'S DRAFT DISTRIBUTION DETERMINATION 2011-2015, APPENDIX P: DEBT RAISING COSTS
SUBMISSION ON THE AER'S DRAFT DISTRIBUTION DETERMINATION 2011-2015, APPENDIX P: DEBT RAISING COSTS 19 August 2010 119476207 This submission sets out CitiPower Pty (CitiPower) and Powercor Australia Limited's
More informationWebcast on Revised Schedule VI. CA. Pankajj Goel
Webcast on Revised Schedule VI CA. Pankajj Goel Overview Background and Applicability Significant Features Major Changes Structure of Revised Schedule VI Form of Balance Sheet Statement of Profit and Loss
More informationCoal India Ltd. Subdued e-auction realization impacted profitability BUY. Nov. 17, 2015
17-Nov-14 17-Dec-14 17-Jan-15 17-Feb-15 17-Mar-15 17-Apr-15 17-May-15 17-Jun-15 17-Jul-15 17-Aug-15 17-Sep-15 17-Oct-15 Coal India Ltd. Subdued e-auction realization impacted profitability Coal India Ltd.
More informationDelhi Electricity Regulatory Commission Viniyamak Bhawan, C Block, Shivalik, Malviya Nagar, New Delhi 17
Delhi Electricity Regulatory Commission Viniyamak Bhawan, C Block, Shivalik, Malviya Nagar, New Delhi 17 No. F. 11(1160)/DERC/2014-15/ Petition No. 53/2014 In the matter of: Petition seeking approval for
More informationODA. Direct investment in joint venture (JV)/wholly owned subsidiary (WOS) abroad under automatic route To
ODA Direct investment in joint venture (JV)/wholly owned subsidiary (WOS) abroad under automatic route To (Name and address of the For use by RBI only authorised dealer) Date of receipt : Inward No. Identification
More informationORISSA ELECTRICITY REGULATORY COMMISSION UNIT-VIII, BHUBANESWAR 751 012. Suo motu proceeding of Case No.44 of 2011
ORISSA ELECTRICITY REGULATORY COMMISSION UNIT-VIII, BHUBANESWAR 751 012 Suo motu proceeding of Case No.44 of 2011 The Commissioner-cum-Secretary, Department of Energy, Govt. of Orissa, Bhubaneswar have
More informationASSAM ELECTRICITY REGULATORY COMMISSION (AERC) TARIFF ORDER FY 2013-14 to FY 2015-16. Assam Power Generation Corporation Limited (APGCL)
ASSAM ELECTRICITY REGULATORY COMMISSION (AERC) TARIFF ORDER FY 2013-14 to FY 2015-16 Assam Power Generation Corporation Limited (APGCL) Petition No. 3/2013 ASSAM ELECTRICITY REGULATORY COMMISSION A.S.E.B.
More informationLOAN AGREEMENT FOR PACKING CREDIT/ POST SHIPMENT FINANCE IN FOREIGN CURRENCY (PCFC / PSCFC)
IBD 10 LOAN AGREEMENT FOR PACKING CREDIT/ POST SHIPMENT FINANCE IN FOREIGN CURRENCY (PCFC / PSCFC) This agreement is made at on in between M/s hereinafter called the Borrower for the sake of brevity (which
More informationSchedule 16 Significant Accounting Policies and Notes on Accounts
Schedule 16 A. Significant Accounting Policies : 1. Basis for preparation of Financial Statements The financial statements are prepared under the historical cost convention, in accordance with the Generally
More information11.437 Financing Community Economic Development Class 6: Fixed Asset Financing
11.437 Financing Community Economic Development Class 6: Fixed Asset Financing I. Purpose of asset financing Fixed asset financing refers to the financing for real estate and equipment needs of a business.
More informationPRESS NOTE REVISION OF ELECTRICITY TARIFF FOR 2016-17
KARNATAKA ELECTRICITY REGULATORY COMMISSION 6th & 7th Floor, Mahalakshmi Chambers, No. 9/2, M.G. Road, Bangalore-560001 PRESS NOTE REVISION OF ELECTRICITY TARIFF FOR 2016-17 The Karnataka Electricity Regulatory
More informationRev Re i v sed e Scheduled VI Dhinal Shah Charte Chart re r d Accoun Accoun a t nt
Revised Scheduled VI Dhinal Shah Chartered Accountant Structure of Presentation Setting the Context Structure of Revised Schedule VI Key Changes Key Points Setting the Context Setting the Context Towards
More informationMantas India Private Limited. Directors Report
Mantas India Private Limited Directors Report Dear Members, Your Directors take pleasure in bringing you the Annual Report of your Company along with the Audited Accounts for the financial year from April
More informationCOST OF CAPITAL, COST OF EQUITY, DEBT FINANCING AND DIVIDEND POLICY
Page of 4 5 6 7 8 9 0 COST OF CAPITAL, COST OF EQUITY, DEBT FINANCING AND DIVIDEND POLICY Overview PowerStream has followed the Report of the Board on Cost of Capital for Ontario s Regulated Utilities,
More informationINSTITUTE OF ACTUARIES OF INDIA
INSTITUTE OF ACTUARIES OF INDIA EXAMINATIONS 15 th November 2010 Subject CT1 Financial Mathematics Time allowed: Three Hours (15.00 18.00 Hrs) Total Marks: 100 INSTRUCTIONS TO THE CANDIDATES 1. Please
More informationWelcome&to&the&Credible&Refinancing&Guide!&
Welcome&to&the&Credible&Refinancing&Guide!& You re,interested,in,refinancing,you,student,loans,but,you,have,a,few, ques>ons? Great,,there,are,few,easier,and,beBer,ways,to,save,thousand,of,dollars! Having,said,that,,we,realize,that,the,refinancing,process,has,some,
More informationSub-national Debt Management
Sub-national Debt Management Indian Experience Alok Chandra Director, Ministry of Finance, India 27 June 2008 Structure Part A: Institutional Approaches to regulations of Sub-national Borrowings Part B:
More informationASSAM ELECTRICITY REGULATORY COMMISSION (AERC) Assam Power Distribution Company Limited (APDCL) TARIFF ORDER FY 2010-11 to 2012-13
ASSAM ELECTRICITY REGULATORY COMMISSION (AERC) Assam Power Distribution Company Limited (APDCL) TARIFF ORDER FY 2010-11 to 2012-13 Petition No. 6/2010 ASSAM ELECTRICITY REGULATORY COMMISSION A.S.E.B. Campus,
More informationTARIFF ORDER. For Electricity Department, State of Goa
TARIFF ORDER Business Plan for the M YT Control Period FY 2015-16 to FY 2017-1; And Annual Performance Review for FY 2014-15, And Determination of Aggregate Revenue Requirement And Retail Supply Tariff
More informationGovernment Accounting Standards Advisory Board
GASAB IGAS 10 Public Debt and Other Liabilities of Governments: Disclosure Requirements Government Accounting Standards Advisory Board CONTENTS Indian Government Accounting Standard (IGAS) 10 Public Debt
More information¼ããÀ ããè¾ã ¹ãÆãä ã¼ãîãä ã ããõà ãäìããä ã½ã¾ã ºããñ Ã
CIRCULAR CIR/MRD/DSA/33 /2013 October 24, 2013 To All Stock Exchanges Dear Sir/Madam, Sub: Listing of specified securities of small and medium enterprises on the Institutional Trading Platform in a SME
More informationSection 4-Tariff proposals and approved tariff
18. Tariff proposals Section 4-Tariff proposals and approved tariff As discussed in the foregoing paragraphs, even after taking the effect of improved Transmission & Distribution Losses, allowing of interest
More informationBrickwork Ratings assigns BWR BBB- & BWR A3 for the Bank Loan Facilities of 111.84Cr of Balasore Alloys Limited.
Rating Rationale Brickwork Ratings assigns BWR BBB- & BWR A3 for the Bank Loan Facilities of 111.84Cr of Balasore Alloys Limited. Brickwork Ratings (BWR) has assigned the following Ratings 1 for the Bank
More information: 1 : Time allowed : 3 hours Maximum marks : 100. Total number of questions : 6 Total number of printed pages : 7 PART A
Roll No : 1 : NEW SYLLABUS Time allowed : 3 hours Maximum marks : 100 Total number of questions : 6 Total number of printed pages : 7 NOTE : 1. Answer ALL Questions. 2. All references to sections relate
More informationASSOCIATION OF MUTUAL FUNDS IN INDIA LEVY OF SERVICE TAX VIS-À-VIS MUTUAL FUNDS A GUIDANCE NOTE
ASSOCIATION OF MUTUAL FUNDS IN INDIA LEVY OF SERVICE TAX VIS-À-VIS MUTUAL FUNDS A GUIDANCE NOTE A. BACKGROUND: Vide Finance Act, 2003, a new taxable service under the heading Business Auxiliary Service
More informationIGAS 3. Cash Flow Statements. Government Accounting Standards Advisory Board. Contents
Cash Flow Statements Government Accounting Standards Advisory Board Contents Description Page Number 1. Introduction 3 2. Objective 3 3. Scope 3 4. Benefits of Cash Flow Information 4 5. Definitions 4
More informationINDIAN INSTITUTE OF BANKING & FINANCE, MUMBAI
INDIAN INSTITUTE OF BANKING & FINANCE, MUMBAI EXAMINATION: CAIIB Question paper pattern for the December 2005 examination and onwards: The examination will be conducted purely on objective mode/multiple
More informationTechnical Accounting Alert
TA ALERT 2009-14 AUGUST 2009 Technical Accounting Alert Classification of loans with covenants as current or non-current Introduction Issue Loan agreements often include covenants that, if breached by
More informationG. No. 184 New Delhi, 3 December 2004 NOTIFICATION. Act, 1963 (38 of 1963), the Tariff Authority for Major Ports hereby disposes of the
(Published in Part - III Section 4 of the Gazette of India, Extraordinary) TARIFF AUTHORITY FOR MAJOR PORTS G. No. 184 New Delhi, 3 December 2004 NOTIFICATION In exercise of the powers conferred by Section
More informationRIIO-T1 business plan submission London Tuesday 6 September 2011
RIIO-T1 business plan submission London Tuesday 6 September 2011 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information.
More informationYear 2014 15. A perspective
Year 2014 15 Delhi Distribution Business What Determines Electricity Tariff What Determines Electricity Tariff A perspective Contents Electricity Value Chain What determines tariff Power Purchase & Transmission
More informationTime allowed : 3 hours Maximum marks : 100. Total number of questions : 7 Total number of printed pages : 7
Roll No : 1 : 373 Time allowed : 3 hours Maximum marks : 100 Total number of questions : 7 Total number of printed pages : 7 NOTE : 1. Answer FIVE Questions including Question No.1 which is compulsory.
More informationGovernment of Gujarat Science and Technology Department G.R. No: EHM/10/2011/276392/IT Sachivalaya, Gandhinagar RESOLUTION
Government of Gujarat Science and Technology Department G.R. No: EHM/10/2011/276392/IT Sachivalaya, Gandhinagar Date: 29 th February 2016. RESOLUTION Scheme of Assistance for Development of EMCs under
More informationChapter 3 Short Term Policies issued to Exporters
Chapter 3 Short Term Policies issued to Exporters 3.1 Short term policies Policies issued to the exporters covering goods exported on short term credit basis i.e. credit not exceeding 180 days are short
More informationIREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND
IREDA-NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY SUPPORTED BY THE NATIONAL CLEAN ENERGY FUND IREDA NCEF REFINANCE SCHEME REFINANCE SCHEME FOR PROMOTION OF RENEWABLE ENERGY
More informationWater Supply Authority. Regulatory Accounting Guidelines
Water Supply Authority Regulatory Accounting Guidelines Edition 2 February 2004 Regulatory Accounting Guidelines Edition 2 February 2004 Contents 1 General... 1 1.1 Background and introduction... 1 1.2
More informationBusiness Plan Planning Service Financial Analyses and Projections
Business Plan Planning Service Financial Analyses and Projections Financials Included With Every Ceo Resource Plan These are the financial analyses and projections that are included with all plans developed
More informationFinancial Statements and Ratios: Notes
Financial Statements and Ratios: Notes 1. Uses of the income statement for evaluation Investors use the income statement to help judge their return on investment and creditors (lenders) use it to help
More informationSubject: -Submission of Income Details & proof of savings for income tax financial year 13-14
Date CP No. To, The Incharge- F&A Division, Central Pollution Control Board, Parivesh Bhawan East Arjun Nagar, Shahadara, Delhi-110032 Sir, Subject -Submission of Income Details & proof of savings for
More informationGOVERNMENT DEBT STATUS AND ROAD AHEAD MINISTRY OF FINANCE DEPARTMENT OF ECONOMIC AFFAIRS NEW DELHI
GOVERNMENT DEBT STATUS AND ROAD AHEAD MINISTRY OF FINANCE DEPARTMENT OF ECONOMIC AFFAIRS NEW DELHI NOVEMBER 2010 Contents Chapter Particulars Page No. Executive Summary 1. Introduction 1 2. Public Debt
More informationLoan Application Form
Loan Application Form Part A 1. Name of the Scheduled Commercial Bank/ FI 2. Status of the Applicant Scheduled Commercial Bank / FI 3. Ownership Status Government / Private 4. Communication Address Address
More informationDIRECTORS REPORT TO THE MEMBERS
DIRECTORS REPORT TO THE MEMBERS Your Directors present their Fifth Report together with the audited accounts of the Company for the year ended 31 st March, 2013. FINANCIAL HIGHLIGHTS For the year ended
More informationElectricity Tariff Fixation Rules, 2050 (1994)
Electricity Tariff Fixation Rules, 2050 (1994) Date of publication in Nepal Gazette 2050.6.18 Amendments Publication Date 1. Electricity Tariff Fixation (First Amendment) Rules, 2050 2050.10.11 2. Electricity
More informationINDIAN BANKS: SENIOR CITIZEN BENEFITS & SCHEMES
INDIAN BANKS: SENIOR CITIZEN BENEFITS & SCHEMES Union Bank of India: Interest Rate Benefit in Term Deposits to Senior Citizens (Source of Information: www.unionbankofindia.co.in/personal_benifit_senior_citizen.aspx,
More informationApplication Form. (Document / Information / Data Requirement as per Appendix-II)
Application Form (Document / Information / Data Requirement as per Appendix-II) Facility Required (Corporate/Personal Loan) Amount (Rs. Crore) Purpose Tenor and Repayment Security Contact Person (Name,
More informationWelcome to workshop on revised schedule VI. K. Chandra Sekhar Company Secretary Ace Designers Limited, Bangalore
Welcome to workshop on revised schedule VI K. Chandra Sekhar Company Secretary Ace Designers Limited, Bangalore 1 Relevant provisions Indian Companies Act, 1956 Rules Notifications Circulars Accounting
More informationVUNTUT GWITCHIN FIRST NATION NOTES TO THE NON-CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED MARCH 31, 2005
1. Basis of presentation These financial statements have been prepared on a nonconsolidated basis and do not include the accounts of the First Nation's compensation fund or Vuntut Development Corporation,
More informationURBAN GAS SUPPLIERS LIMITED Regd. Office: 11B, Mittal Towers, Nariman Point, Mumbai 400 021 DIRECTORS REPORT
URBAN GAS SUPPLIERS LIMITED Regd. Office: 11B, Mittal Towers, Nariman Point, Mumbai 400 021 DIRECTORS REPORT The Directors of your Company are pleased to present the Fourth Annual Report together with
More informationT2S financials: status update
0 T2S financials: status update T2S Advisory Group Frankfurt am Main, 17-18 June 2014 T2S Programme Office European Central Bank Item 5.1 T2S financials: status update Eurosystem s reporting obligation
More informationCIRCULAR. Sub: Corporate Governance in listed entities - Amendments to Clause 49 of the Equity Listing Agreement
CIRCULAR CIR/CFD/POLICY CELL/7/2014 September 15, 2014 To All Recognised Stock Exchanges Dear Sir(s)/Madam(s), Sub: Corporate Governance in listed entities - Amendments to Clause 49 of the Equity Listing
More informationThe Institute of Chartered Accountants of India
CHAPTER 4 SIMPLE AND COMPOUND INTEREST INCLUDING ANNUITY APPLICATIONS SIMPLE AND COMPOUND INTEREST INCLUDING ANNUITY- APPLICATIONS LEARNING OBJECTIVES After studying this chapter students will be able
More informationDELHI TRANSCO LIMITED
DELHI TRANSCO LIMITED SCHEDULE-22: Notes forming part of Accounts. 1. Delhi Electricity Reform (Transfer Scheme) Notification No. 2869 dated 20-11-01. In exercise of the Power conferred by Section 60 read
More information