Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41

Size: px
Start display at page:

Download "Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41"

Transcription

1 Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41 ITEM #6 1) Scope of Work The scope of this proposal is: Hudson Street Well #1A and Hudson Street Well #2 - clean and rehabilitate, Foster Island Well #41 - remove and replace pump and motor. Motor and/or pump will be ordered after an inspection to determine what needs to be replaced. Foster Island Well #40 - repair /replace check valve in pitless adaptor Elmira Water Board (EWB) wants work done in the following sequence: (a) Pull pump and motor from Foster Island Well #41, inspect. (b) Repair/replace check valve on Foster Island #40 pitless. (c) EWB will order replacement pump and/or motor. (d) Contractor will then setup to re-develop Hudson Street Well #1A and #2. These may be completed before pump and/or motor arrives for Foster Island #41. (e) Install pump and motor on Foster Island #41. No unnecessary delays or work stoppages will be tolerated. The Contractor shall be held responsible, and payment may be withheld for damages done to the well due to any cause of negligence or faulty operation. For the project OVERTIME WORK, shall not apply. 2) Mobilization and Equipment The Contractor shall furnish and supply all necessary rigging and associated equipment to perform a thorough cleaning of the well screens and rehabilitation of the wells. This item includes moving material and equipment to and from the site. It also includes clean up of the well site at completion of the contract. (a) (b) The Contractor shall remove any debris from the bottom of the well using a bailing or air lifting method approved by the Owner s representative to the depth specified by the Well Design. The debris, if any, shall be collected at the surface and properly disposed of off site. The Contractor is responsible for the containment, removal, and disposal of all sludge and debris as part of this contract. Page 1 of 6

2 3) Preliminary Test Prior to pulling the pump & motor the EWB personnel shall conduct flow tests on Hudson #1A and #2 with a calibrated orifice, to measure the wells present capacity compared to its original performance and provide results to the successful contractor. 4) Pull Pump & Inspect The Contractor shall remove the pump and motor from all wells using all precautions to avoid any damage. For all pumps, the assembly shall be stored at the well site and dismantled for inspection by the Contractor. All bearing tolerances will be noted along with a complete inspection of the pump column and related parts. A written report will be submitted to the Owner. A cost estimate of necessary labor and material will be included if repair work is recommended. Foster Island #41 pump and motor needs to be inspected to determine required replacement/repair. 5) Video Inspection Of The Well Immediately after pulling the pumps the Contractor will perform an underwater inspection of the casing and the screen on Hudson 1A and #2. The camera must provide a clear color video image of the casing, the well screen and joints. After the final rehabilitation of the wells another video inspection will be made on all wells rehabilitated. The Owner will be provided a VHS videotape of each inspection. If final redevelopment indicates additional cleaning of the screen is necessary, a video log after this cleaning will be done at no cost to the Owner. 6) Well Rehabilitation The objective of this well rehabilitation project is to clean and rehabilitate all wells to improve their yield. The rehabilitation will be carried out in three phases: Phase 1 - Wire Brushing of the Well The contractor shall wire brush and scrape the well for a period of not less than 15 min per 20 foot interval. The wires should maintain a touch fit to the inside diameter and be capable of rotating while being raised and lowered. After brushing is complete the Contractor shall remove all debris from the well bottom by airlifting or bailing. The waste shall be neutralized by the Contractor to a ph greater than 6.5 and less than 8.5 and disposed of by the Contractor in accordance with current Environmental Regulations. Alternate - The Contractor may employ a percussion or air blast type energy system to clean the screen and the casing. Provide details on the type of air system being used. Phase 2-Acid Treatment - To address the biological fouling and loss of production capacity a strong chemical and mechanical agitation process will be used. Page 2 of 6

3 For Hudson #1A The chemical wash shall be: 80 gallons of phosphoric acid (75%Activity), 30 gallons of biodispersant (Johnson Screen NW-310/QC21), 2 gallon of NW-400 surfactant. For Hudson #2 The chemical wash shall be: 85 gallons of phosphoric acid (75%Activity), 30 gallons of biodispersant (Johnson Screen NW-310/QC21), 1 gallon of NW-400 surfactant, 2.5 gallons of NW220 (clay dispersant). The chemistry listed above is to be administered in two separate cleaning phases. The acid clean phase includes the phosphoric acid, the biodispersant and the surfactant. The mud and fine sediment removal phase will utilize the NW 220 (Hudson #2 only) to remove the mud and sediment. The Contractor shall furnish all labor, equipment, and material and services to acid clean the well. Material Safety Data Sheet (MSDS) for all additives must be submitted to the Owner's representative for approval prior to use of said additives. Care shall be taken throughout the entire well rehabilitation process to follow all the Federal, State, and local regulations pertaining to the handling and disposal of the acid and other chemicals. All chemicals must be NFS certified. The chemicals shall be batched in a polyethylene tank and the chemicals added to the water and mixed with a small circulating pump. The mixed solution should have a ph of 1.0 or less and is to be introduced into the casing with a small pipe starting at the standing water level to the bottom of the well. At the Owners discretion samples may be pumped or lifted to determine the ph. Acid must be added if necessary to keep the or less. After the chemicals are added an aggressive surging will be used to force the chemistry into the formation. The Contractor will swab the entire casing with a minimum 20' double surge block from the bottom of the well to the standing water level. Each 20' section of casing will be swabbed for 20 minutes and each 10' of screen shall be swabbed for 30 minutes. If the ph is above three, additional acid will be added and swabbed into place using the double surge block. After working the well the first day the solution shall stand overnight (12 hours). After 12 hours a ph sample will be taken by the Contractor and witnessed by the Owner s representative. If the ph is greater than 3.0 acid will be added to bring it below 3.0. Maintain the ph at 3.0 or below during the entire cleaning process. The EWB will pay for any additional cost of acid to maintain a PH less than 3.0. Page 3 of 6

4 The second day the well will be surged 6-8 hours before pump out following the same surging procedure as before except surging shall begin at the standing water level and work downward to the bottom of the well. At the discretion of the Owner's representative the well will be allowed to stand for an additional period of 48 to 72 hours following determination of the ph.the EWB will pay for one additional day of soak time. Any soak time beyond this time will be negotiated. The Contractor shall, by air lifting or pumping remove the acid in the well following a determination of the ph at the bottom. The pumping will be continuous at a minimum of 250gpm from each 20'section of screen for 15 minutes. Pumping shall begin at the bottom of the screen and work up to the top of the screen. The Contractor shall continue to pump or air lift from the well until the ph of the well water is between 6.8 and 7.4 and until the water remains clear for a minimum of five minutes. All of the acid treated water will be neutralized to 6.5 to 8.5 ph prior to disposal by the Contractor, according to the current Environmental Standards. The Owners representative will continue to monitor the well discharge to assure the Contractor is meeting the targeted ph range and all chemicals have been removed from the well. Phase 3 -Mud and Fine Sediment Removal (Hudson #2 only) - Following the acid wash a second phase of redevelopment should occur to remove mud and fines from the well and the gravel pack. The wells are to be surged with Johnson Screen NW-220 (clay dispersant) at a ratio of 1:250. The water and NW-220 shall be batched in a minimum 3000 gal tank and added to the casing with a small pipe from the standing water level to the depth of the well. Following injection of the chemicals the Contractor will swab the entire casing with a minimum 20' long snug fitting double surge block from the bottom of the well to the standing water level. Each 10' casing section will be swabbed for 30 minutes. The well will be allowed to stand for two hours. Immediately after the 2 hours the Contractor will then swab each 10' section for 15 minutes. Swabbing will begin at the top and work down. After the second swabbing the Contractor shall remove the chemistry and mud mixture by continuously pumping or air lifting at a minimum rate of 250gpm from each 10' section of screen for a minimum of 15 minutes, starting from the bottom of the screen up. The Contractor shall continue pumping or lifting until the water remains clear for a minimum of 5 minutes and it is apparent the sediment is no longer being removed from the well. Page 4 of 6

5 All redevelopment water shall be disposed of by the Contractor after it has been neutralized and settled in accordance with current Environmental Regulations. All discharge water shall be neutralized by the Contractor to ph greater than 6.5 and less than 8.5. The Contractor will be responsible for monitoring the ph level, treating, testing and disposing of the water. The Owner's representative will additionally monitor the ph of the water discharged to assure the Contractor is achieving the desired results. The Contractor will continue to pump from the well until the Owner's rep is satisfied all chemicals have been removed from the well. 7) Reinstallation of Pump & Final Pump Test for Hudson #1A A three hour final pump test will be conducted by the Contractor after reinstallation of the pump. The well will be pumped for one hour at the following rates; 450gpm, 650gpm, 850gpm. The final report will record water level, flow, drawdown, pressure and amps. 8) Reinstallation of Pump & Final Pump Test for Hudson #2 A three hour final pump test will be conducted by the Contractor after reinstallation of the pump. The well will be pumped for one hour at the following rates; 300gpm, 500gpm, 650gpm. The final report will record water level, flow, drawdown, pressure and amps. 9) Reinstallation of Pump & Motor & Final Pump Test for Foster Island #41 A three hour final pump test will be conducted by the Contractor after reinstallation of the pump. The well will be pumped for one hour at the following rates; 600gpm, 800gpm, 1,000gpm, 1,200gpm. The final report will record water level, flow, drawdown, pressure and amps. 10) Disinfection The Contractor shall furnish labor, equipment, material and services to "super chlorinate" Hudson 1A and 2. Mix a solution of 500 mg/l residual chlorine by mixing a solution of Hydroxyacetic Acid, Sodium Hypochlorite, NW-400. Add one gallon of NW400 for each 1,000 gallons of water. The Contractor shall use an appropriately sized polyethylene tank to mix the chemicals. Inject the mixed solution through a snug fitting double surge block. A quantity of 300 gallons of mixed solution shall be injected per 20'interval of well screen and swabbed into place. Swab from top of screen down to bottom. Samples shall be taken from the screened area to determine the chlorine residual. The total number of samples shall not exceed 6 to determine chlorine residual. The residual should be between 250ppm and500ppm. The residual shall not be lower than 200ppm and ph greater than 7.0 or increased dosage is required. After 24 hours the chlorine shall be air lifted continuously for 15 minutes for each 20 foot section of screen. Lifting shall begin at the base of the well and work upward to the top of the screen. The Contractor shall neutralize the chlorine discharge to a ph of 6.5 to 8.5 prior to allowing water to be discharged from the site. Disposal by the Contractor shall Page 5 of 6

6 meet current Environmental Specifications. After the above procedure the Contractor shall pump water from the well to allow the Owner's rep to collect water samples necessary for analysis. 11) Report Following the completion of all work the Contractor will prepare a report outlining in detail all the work done in the rehabilitation and results obtained for each well. 12) Bidding The Contractors bid, for all the individual items listed below, shall indicate : the quantity of time required or term lump sum calculation the hourly rate or lump sum price the total costs Bid Items: Mobilization Pull Pump Pump Inspection & Report Before & After Video Inspection Phase 1 -Air Clean or Wire Brush Phase 2-Acid Clean Chemicals (note amount calculated for each well) Phase 3-Mud & Fine Cleaning Chemicals (note amount calculated for each well) Disinfection Reinstallation of Pump & Final Test Any Rental Equipment Other Page 6 of 6

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK 10.01 SCOPE OF WORK The work covered by this section of the specifications consists in furnishing all labor, equipment and material necessary to perform the installation of a Type I water supply well per

More information

SECTION 15041 DISINFECTION OF PIPE AND WATER STORAGE FACILITIES

SECTION 15041 DISINFECTION OF PIPE AND WATER STORAGE FACILITIES SECTION 15041 DISINFECTION OF PIPE AND WATER STORAGE FACILITIES PART 1 GENERAL 1.01 DESCRIPTION This section describes requirements for disinfection by chlorination of potable water mains, services, pipe

More information

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

CHAPTER 4 WELL COMPLETION AND MAINTENANCE CHAPTER 4 WELL COMPLETION AND MAINTENANCE Section 1: Disinfection. (a) Each person who repairs, modifies, works on, or otherwise affects the physical components of a well shall clean and disinfect the

More information

Repair and Disinfection of Water Mains Water Protection Program fact sheet

Repair and Disinfection of Water Mains Water Protection Program fact sheet Repair and Disinfection of Water Mains Water Protection Program fact sheet 9/2012 Every year waterborne disease outbreaks occur in the United States as a result of public water distribution system defi

More information

Adjusting Chemical Levels in a Swimming Pool

Adjusting Chemical Levels in a Swimming Pool Adjusting Chemical Levels in a Swimming Pool When adding chemicals, there are three types of chemical adjustments that can be performed: product label chemical dosage, product label chemical adjustment,

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

SECTION 810 SEWER LINE CLEANING

SECTION 810 SEWER LINE CLEANING SECTION 810 SEWER LINE CLEANING I. GENERAL 1.1 DESCRIPTION OF WORK The work covered by this section consists of providing all labor, equipment, material and supplies and performing all operations required

More information

Sustainable Design, Operations & Maintenance of Water Wells

Sustainable Design, Operations & Maintenance of Water Wells Sustainable Design, Operations & Maintenance of Water Wells Extending the Life of Your Well August 2-4, 2011 Presented By: Seminar Overview Planning, Design & Construction Considerations Improving Water

More information

KODAK Developer System Cleaner and Neutralizer

KODAK Developer System Cleaner and Neutralizer KODAK Developer System Cleaner and Neutralizer TECHNICAL DATA / CHEMICAL March 2010 TI-2000 GENERAL INFORMATION KODAK Developer System Cleaner and Neutralizer is designed to remove the buildup of silver

More information

STANDARD SPECIFICATIONS SECTION 02959 SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT

STANDARD SPECIFICATIONS SECTION 02959 SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT STANDARD SPECIFICATIONS SECTION 02959 SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for rehabilitation of defective mainline

More information

Well Water Iron Removal Using Quantum DMI-65 Granular Filter Media

Well Water Iron Removal Using Quantum DMI-65 Granular Filter Media Well Water Iron Removal Using Quantum DMI-65 Granular Filter Media ASME Research Committee Power Plant and Environmental Chemistry Overland Park, Kansas April 2-4, 2007 Prepared by: W. H. Stroman Primary

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

Water System Disinfection

Water System Disinfection Water System Disinfection Document Number Revision 1 Approved By Ric Morris All 6/2/04 Active Divisions/Departments FEMC Raytheon Polar Services Company HARD COPY NOT CONTROLLED-CONTROLLED COPY AVAILABLE

More information

How To Water System

How To Water System Mid-Monroe Water System: Soluble Iron and Manganese Removal via Oxidation & Filtration Daniel Rickard, P.E. Engineering Project Manager Pennsylvania-American Water Company Who Is American Water We are

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

A Guide to Trouble-Free Cooling Towers

A Guide to Trouble-Free Cooling Towers A Guide to Trouble-Free Cooling Towers A basic understanding of cooling tower operation and maintenance will help keep a cooling water system running in top condition, year after year By David M. Suptic

More information

Fats, Oil and Grease. Best Management Practices Manual. Information, Pollution Prevention, and Compliance Information For Food Service Facilities

Fats, Oil and Grease. Best Management Practices Manual. Information, Pollution Prevention, and Compliance Information For Food Service Facilities Fats, Oil and Grease Best Management Practices Manual Information, Pollution Prevention, and Compliance Information For Food Service Facilities Pinellas County Utilities Water Quality Management Division

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components

More information

National Precast Concrete Association

National Precast Concrete Association National Precast Concrete Association NOTES 1. This manual does not claim or imply that it addresses any safety-related issues associated with its use. Operation and maintenance of precast concrete grease

More information

Technical Support Services Accelerated Learning Through the Visual Presentation of Technical Information

Technical Support Services Accelerated Learning Through the Visual Presentation of Technical Information TSS Module 11 Waste Neutralization pdf documents Text in pdf documents may appear fuzzy or blocky due to file compression. To change the appearence in Acrobat TM Reader TM 3.X, go to the menu item: File

More information

MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES

MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES John van Rijn INDEVELOPMENT MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES Any part of this publication may be

More information

GENERAL REQUIREMENTS:

GENERAL REQUIREMENTS: The City of Olean is seeking proposals for removal and service of a 14ENL-3 Flowserve pump. This will involve removal, servicing, testing, and reinstallation of the pump from the City of Olean Water Treatment

More information

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM OTCO Water Workshop March, 2011 Frank Woyma Plant Manager Nick Pizzi Vice-President EE&T ENVIRONMENTAL ENGINEERING & TECHNOLOGY, INC. Objectives Review the

More information

Cost Savings Gained through Rotary Impingement Tank Cleaning

Cost Savings Gained through Rotary Impingement Tank Cleaning Gamajet Cleaning Systems, Inc. Exton, Pennsylvania August 2012 Cost Savings Gained through Rotary Impingement Tank Cleaning Abstract: Specific case studies on the benefits of rotary impingement and CIP

More information

DRAFT July, 2006 Page 1 of 18

DRAFT July, 2006 Page 1 of 18 DRAFT July, 2006 Page 1 of 18 Swimming Pool Venue Environmental Health Outbreak Investigation Survey: An Environmental Health Systems Approach to Recreational Water Illness Prevention - Information Collection

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Ground Water Rule Request for 4-log Certification Chlorination

Ground Water Rule Request for 4-log Certification Chlorination Massachusetts Department of Environmental Protection - Drinking Water Program Ground Water Rule Request for 4-log Certification Chlorination Form: GWR D: 4-Log Certification - Chlorination Important Note:

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

What To Do When Your Well is Flooded. Common Sense Steps To Take If Your Well Is Covered by Flood Water

What To Do When Your Well is Flooded. Common Sense Steps To Take If Your Well Is Covered by Flood Water What To Do When Your Well is Flooded Common Sense Steps To Take If Your Well Is Covered by Flood Water Courtesy of CleanWaterStore.com 2016 Contents 1. What To Do If Your Well Is Covered by Flood Water...

More information

Rotary Tank Cleaning and Cost Savings

Rotary Tank Cleaning and Cost Savings Rotary Tank Cleaning and Cost Savings Gamajet Cleaning Systems, Inc. Exton, Pennsylvania June 2011 Abstract: Specific case studies on the benefits of rotary impingement and CIP optimization vs. the standard

More information

Treatment options for hydrogen sulfide. Testing for hydrogen sulfide

Treatment options for hydrogen sulfide. Testing for hydrogen sulfide Sometimes hot water will have a sour smell, similar to that of an old damp rag. This smell often develops when the thermostat has been lowered to save energy or reduce the potential for scalding. Odor-causing

More information

Increasing Productivity and Reducing Costs with CIP Optimization

Increasing Productivity and Reducing Costs with CIP Optimization Gamajet Cleaning Systems, Inc. Exton, Pennsylvania April 2012 Increasing Productivity and Reducing Costs with CIP Optimization Abstract: Case studies on the benefits of CIP optimization and rotary impingement

More information

E-Version SECTION 15318 - CHLORINATION SYSTEM PART 1 - GENERAL PART 2 - PRODUCT

E-Version SECTION 15318 - CHLORINATION SYSTEM PART 1 - GENERAL PART 2 - PRODUCT SECTION 15318 - CHLORINATION SYSTEM PART 1 - GENERAL 1.1. SCOPE OF WORK A. Under this item the Contractor shall furnish and install a sodium hypochlorite solution metering system complete with all accessories

More information

FY15 Gravity Sewer and Manhole Rehabilitation

FY15 Gravity Sewer and Manhole Rehabilitation Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE

More information

PAINT REMOVAL SYSTEM PAINT REMOVAL SPECIFICATION SAFE WORK METHOD STATEMENT FOR LEAD PAINT REMOVAL

PAINT REMOVAL SYSTEM PAINT REMOVAL SPECIFICATION SAFE WORK METHOD STATEMENT FOR LEAD PAINT REMOVAL PAINT REMOVAL SYSTEM PAINT REMOVAL SPECIFICATION SAFE WORK METHOD STATEMENT FOR LEAD PAINT REMOVAL CONTENTS: 1.0 AWARENESS AND PRECAUTION 2.0 TEST SAMPLING & REMOVAL EVALUATION 3.0 SITE EVALUATION 4.0

More information

Practice Tests Answer Keys

Practice Tests Answer Keys Practice Tests Answer Keys COURSE OUTLINE: Module # Name Practice Test included Module 1: Basic Math Refresher Module 2: Fractions, Decimals and Percents Module 3: Measurement Conversions Module 4: Linear,

More information

ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN

ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN The purpose of this plan is to provide detailed instructions for slug prevention and control. A complete copy of this plan is maintained

More information

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month , as published in July 2008 Opflow Question of the Month Thanks to: Mike Grahek, Los Angeles Department of Water, Los Angeles, California Ahmad Havivian, Black & Veatch, Gaithersburg, Maryland David Kroon,

More information

Indiana Department of Environmental Management. Well Disinfection

Indiana Department of Environmental Management. Well Disinfection Indiana Department of Environmental Management www.in.gov/idem Well Disinfection Why Disinfect? Well disinfection can eliminate or reduce many different kinds harmful bacteria and viruses as well as harmless

More information

Wastewater Collection Practice Test #3 Page 1 of 15

Wastewater Collection Practice Test #3 Page 1 of 15 Wastewater Collection Practice Test #3 Page 1 of 15 1) A 54 in. storm sewer flowing half full, at a velocity of 1.35 Ft./sec., will discharge how much flow into a creek in MGD? 13.85 MGD 10.73 MGD 1.85

More information

MATHEMATICS FOR WATER OPERATORS

MATHEMATICS FOR WATER OPERATORS MATHEMATICS FOR WATER OPERATORS Chapter 16: Mathematics The understanding of the mathematics of water hydraulics (flows, pressures, volumes, horsepower, velocities) and water treatment (detention time,

More information

Homeowner s Manual MIGHTY MAC. For: 500 Gallon-Per-Day. 600 Gallon-Per-Day. 750 Gallon-Per-Day

Homeowner s Manual MIGHTY MAC. For: 500 Gallon-Per-Day. 600 Gallon-Per-Day. 750 Gallon-Per-Day Homeowner s Manual For: MIGHTY MAC 500 Gallon-Per-Day 600 Gallon-Per-Day 750 Gallon-Per-Day Table of Contents I. Introduction II. About Your MIGHTY MAC System III. Homeowner (System Owner) Responsibilities

More information

How To Size A Stenner Pump

How To Size A Stenner Pump Metering Pumps Manufactured Since 1957 PCM Series Pump Control Module INSTALLATION AND MAINTENANCE MANUAL Table of Contents WarrantyandServicePolicy...3 Safety Information...............................................

More information

TEX-AIRE, INC. 1076 Pearl Drive Bossier City, LA 71111 318-752-3700

TEX-AIRE, INC. 1076 Pearl Drive Bossier City, LA 71111 318-752-3700 TEX-AIRE, INC. 1076 Pearl Drive Bossier City, LA 71111 318-752-3700 MIGHTY MAC Aerobic Wastewater Treatment Homeowner s Manual For MIGHTY MAC 500 Gallon-Per-Day MIGHTY MAC 600 Gallon-Per-Day MIGHTY MAC

More information

Spray Nozzles. Spray Control. Spray Fabrication. Spray Analysis. A Guide to Optimizing In-Tank Agitation and Mixing Using Eductors

Spray Nozzles. Spray Control. Spray Fabrication. Spray Analysis. A Guide to Optimizing In-Tank Agitation and Mixing Using Eductors s Control Analysis Fabrication A Guide to Optimizing In-Tank Agitation and Mixing Using Eductors Eductors Ensure Thorough Mixing to Improve Product Quality and Reduce Maintenance Time Tank mixing eductors

More information

TECHNICAL SPECIFICATIONS FOR LIQUID SODIUM HYPOCHLORITE

TECHNICAL SPECIFICATIONS FOR LIQUID SODIUM HYPOCHLORITE TECHNICAL SPECIFICATIONS FOR LIQUID SODIUM HYPOCHLORITE 1. GENERAL The intent and purpose of this specification document is for delivery of liquid sodium hypochlorite (12.5 Trade Percent Available Chlorine)

More information

Troubleshooting Your RO

Troubleshooting Your RO Troubleshooting Your RO Summary: There can be many reasons why a RO system suffers a loss in performance, and is unable to produce the proper quantity and/or quality of permeate water. Similar to a doctor

More information

Terms of Reference Air Handling Unit (HVAC System) Cleaning

Terms of Reference Air Handling Unit (HVAC System) Cleaning Terms of Reference Air Handling Unit (HVAC System) Cleaning Introduction General cleaning of the air handling units is currently undertaken by the Mechanical Division staff composing of 3 personnel. Cleaning

More information

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines: Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

CONTRACT DATA SHEET DRAIN CLEANING SERVICE CONTRACT #: 0510-08 (4700006459) CONTRACT DATES: 06/18/08 06/30/12

CONTRACT DATA SHEET DRAIN CLEANING SERVICE CONTRACT #: 0510-08 (4700006459) CONTRACT DATES: 06/18/08 06/30/12 CONTRACT DATA SHEET Monroe County Division of Purchasing 200 County Office Building, Rochester NY 14614 TITLE: DRAIN CLEANING SERVICE CONTRACT #: 0510-08 (4700006459) CONTRACT DATES: 06/18/08 06/30/12

More information

b. Alkalinity make your life easier and get the alkalinity between 80 and 120 PPM. c. ph from 7.2 and 7.8 so that the other chemicals work properly

b. Alkalinity make your life easier and get the alkalinity between 80 and 120 PPM. c. ph from 7.2 and 7.8 so that the other chemicals work properly 1. Adding Chemicals to your water: Chemicals should be added slowly over a period of time. Pool owner/operators need to remember that all chemicals added will have an effect beyond their intended purpose.

More information

Enhanced Hydrocarbon Recovery Via Proven & Safe Chemical Tank Cleaning

Enhanced Hydrocarbon Recovery Via Proven & Safe Chemical Tank Cleaning Enhanced Hydrocarbon Recovery Via Proven & Safe Chemical Tank Cleaning Contents Introduction Tank Storage and Cleaning - Main Issues Vision Petroleum s Solution Features Benefits of the V6 Sludge Breaker

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

WELL DEVELOPMENT COMPARING SEVERAL METHODS OF WELL

WELL DEVELOPMENT COMPARING SEVERAL METHODS OF WELL WELL DEVELOPMENT This continuing education course is primarily written for an audience of groundwater professionals who live in a water rich state, Florida. Because Florida is blessed with one of the most

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

WASTEWATER TREATMENT OBJECTIVES

WASTEWATER TREATMENT OBJECTIVES WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater

More information

Corrosivity of Water Supplies

Corrosivity of Water Supplies WD-DWGB-3-4 2009 Corrosivity of Water Supplies What is meant by Corrosivity? Corrosive water can be defined as a condition of water quality which will dissolve metals from metallic plumbing at an excessive

More information

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK PROCEDURE EMERGENCY (TEMPORARY) TREATED WATER SUPPLIES

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK PROCEDURE EMERGENCY (TEMPORARY) TREATED WATER SUPPLIES EMERGENCY (TEMPORARY) TREATED WATER SUPPLIES Document Title: Document Reference: Work Procedure - Emergency (Temporary) Treated Water Supplies Date: October 2013 Approved By: Public Health Team Title:

More information

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area. 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

Super Cascade Filtration Systems (CE)

Super Cascade Filtration Systems (CE) CE ONLY Super Cascade Filtration Systems (CE) Operation Manual Frymaster, a member of the Commercial Food Equipment Service Association, recommends using CFESA Certified Technicians. 24-Hour Service Hotline

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Sample Test Questions

Sample Test Questions Sample Test Questions The following questions are provided as examples of the types of questions that might be covered on your certification exam. These questions may help prepare you for certification

More information

Fusion Series Treatment Systems Small Scale Residential & Commercial Treatment Units

Fusion Series Treatment Systems Small Scale Residential & Commercial Treatment Units SECTION: C3.10.120 CL0052 0911 Supersedes New Fusion Series Treatment Systems Small Scale Residential & Commercial Treatment Units Clarus Environmental 3649 Cane Run Rd. Louisville, KY 40211 877-244-9340

More information

Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN

Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN I. PURPOSE The Municipality / Authority has structured this Sanitary Sewer Overflow Response Plan to satisfy

More information

Bio-Clean. for Septic Systems. Tips for Using Bio-Clean. Page Index METRIC CONVERSIONS

Bio-Clean. for Septic Systems. Tips for Using Bio-Clean. Page Index METRIC CONVERSIONS Bio-Clean for Septic Systems METRIC CONVERSIONS 1 tablespoon = 15ml 1/4 cup = 57 ml 1/3 cup = 76 ml 1/2 cup = 114 ml 1 pint = 1/2 litre 1 quart = 1 litre 1/2 gallon = 2 litres 1 gallon = 4 litres 1 pound

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System An application for the construction or alteration of an individual subsurface sewage disposal system shall

More information

Section C-1 Pipes and Fittings

Section C-1 Pipes and Fittings Section C-1 Pipes and Fittings C1.00 Work Included The work under this Division of the Specifications shall include all labor, materials, and equipment necessary to furnish and install all piping, pipelines,

More information

Water Storage Tanks. (Cisterns) Drinking water and your health. Water Hauling. Rainwater Collection. Construction Material

Water Storage Tanks. (Cisterns) Drinking water and your health. Water Hauling. Rainwater Collection. Construction Material Drinking water and your health Water Storage Tanks (Cisterns) This fact sheet is intended to be a general reference for cistern users. For detailed information on cistern construction and material standards,

More information

Applying Life Cycle Assessment to Drinking Water Treatment

Applying Life Cycle Assessment to Drinking Water Treatment Applying Life Cycle Assessment to Drinking Water Treatment W.Takashima*, S.Takizawa**and M. Fujiwara* *Japan Water Research Center, Minato-ku, Tokyo, 105-0001, Japan (takashima@jwrc-net.or.jp) ** University

More information

Routine Maintenance and Inspection

Routine Maintenance and Inspection THE CORPORATION OF THE VILLAGE OF WARFIELD POLICY TITLE: Sanitary Sewer Operations POLICY: #5435 PURPOSE: This policy is to provide the Village of Warfield s procedures for maintaining its sanitary sewer

More information

D. Open hydronic systems, including [condenser] [fluid-cooler spray] water, shall have the following water qualities:

D. Open hydronic systems, including [condenser] [fluid-cooler spray] water, shall have the following water qualities: SECTION 232500 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following HVAC water-treatment systems: 1. Open Loop Chemical Treatment Systems. 2. Closed Loop Chemical Treatment Systems. 3.

More information

Design & Construction Standards, Revised January 2013 5.21.30-1

Design & Construction Standards, Revised January 2013 5.21.30-1 PART 1 GENERAL 1.01 Scope of Standard A. This standard provides general requirements of The University of Texas at Austin for fire pumps. This document is not intended to serve as a guide specification.

More information

Inline Chlorinator Chlorine Chemical Feeder

Inline Chlorinator Chlorine Chemical Feeder Inline Chlorinator Chlorine Chemical Feeder Instructions Page 1 Chlorine setting in P.P.M. for center tube and cap Hole #1 = 2 P.P.M. Hole #2 = 8 P.P.M. Hole #3 = 30 P.P.M. Hole #A = 3.5 P.P.M. Hole #B

More information

Septic Tank Use & Maintenance Tips

Septic Tank Use & Maintenance Tips Yellowhead County Hamlet of Cadomin Septic Tank Use & Maintenance Tips This guide gives an overview of the responsibilities for property owners in Cadomin. For Seasonal, Permanent & Vacationing Cadomin

More information

DWSRF GREEN PROJECT RESERVE BUSINESS CASE EVALUATION STATE FISCAL YEAR 2015 INTENDED USE PLAN PROJECT NUMBER

DWSRF GREEN PROJECT RESERVE BUSINESS CASE EVALUATION STATE FISCAL YEAR 2015 INTENDED USE PLAN PROJECT NUMBER City of Gorman DWSRF GREEN PROJECT RESERVE BUSINESS CASE EVALUATION STATE FISCAL YEAR 2015 INTENDED USE PLAN PROJECT NUMBER 62660 COMMITMENT DATE: January 29, 2015 DATE OF LOAN CLOSING: May 21, 2015 GREEN

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

Keep the Water Moving Rehabilitation of a 1-million Gallon Water Storage Tank

Keep the Water Moving Rehabilitation of a 1-million Gallon Water Storage Tank AMERICAN WATER WORKS ASSOCIATION NEW JERSEY SECTION 2015 Annual Conference Keep the Water Moving Rehabilitation of a 1-million Gallon Water Storage Tank Jonathan T. Reed CDM Smith, Inc. Bill Mitchell,

More information

MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS

MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS The following information is designed to be used in conjunction with the Sewer Toolkit, located in the Wastewater section of the Florida Rural Water

More information

CITY OF GOLDEN DEPARTMENT OF PUBLIC WORKS, ENVIRONMENTAL SERVICES DIVISION

CITY OF GOLDEN DEPARTMENT OF PUBLIC WORKS, ENVIRONMENTAL SERVICES DIVISION CITY OF GOLDEN DEPARTMENT OF PUBLIC WORKS, ENVIRONMENTAL SERVICES DIVISION Grease, So What's the Problem? Does your facility produce grease? All commercial cooking facilities generate Fats, Oil, and Grease

More information

Replace the Pump Tube Classic

Replace the Pump Tube Classic Entire document: 7 pages THIS DOCUMENT CONTAINS GENERAL INSTRUCTION FOR SERVICING STENNER PRODUCTS. PLEASE BE SURE TO READ ALL SAFETY INFORMATION. NOTICE: Indicates special instructions or general mandatory

More information

Standard Hydraulic Piping Flushing Procedure

Standard Hydraulic Piping Flushing Procedure Page 1 of 6 1.0 Scope This procedure covers the minimum technical requirements for cleaning and flushing of Hydraulic and Piping, and related accessories. 2.0 Introduction In hydraulic fluid power systems,

More information

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment

More information

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the

More information

Aerated Wastewater T r eatment System

Aerated Wastewater T r eatment System GOVERNMENT Aerated Wastewater T r eatment System This Certificate of Accreditation is hereby issued by the Director-General of the NSW Ministry of Health pursuant to Clause 41(1) of the Local Government

More information

FAST Owner s Manual. MicroFAST NitriFAST HighStrengthFAST RetroFAST

FAST Owner s Manual. MicroFAST NitriFAST HighStrengthFAST RetroFAST FAST Owner s Manual FOR USE WITH (NSF Std 40 & 245) MicroFAST 0.5, 0.625, 0.75, 0.9, 1.5 (non NSF certified) MicroFAST 3.0, 4.5, 9.0 (ETV/EPA tested) RetroFAST 0.150, 0.250, 0.375 NitriFAST 0.5, 0.625,

More information

REPORT ON OPEN PURCHASE ORDERS FOR SUPPLIES, MATERIALS, EQUIPMENT AND SERVICES FOR FY 2005-2006 #2

REPORT ON OPEN PURCHASE ORDERS FOR SUPPLIES, MATERIALS, EQUIPMENT AND SERVICES FOR FY 2005-2006 #2 CITYOF ~ SAN]OSE CAPITAL OF SILICON VALLEY COUNCIL AGENDA: 06/28/05 REPLACEMENT ITEM:,(,1 q~) Memorandum TO: HONORABLE MAYOR AND CITY COUNCIL FROM: Scott P. Johnson SUBJECT: SEE BELOW DATE: June 27,2005

More information

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014)

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014) STEP 1 Immediately call EH&S at (510) 642-3073 with the following details of the incident: Name of First Responder Phone Number of First Responder Location of Spill Is the spill potentially greater than

More information

DEPARTMENT OF HEALTH COUN TY O F A LBA N Y 175 GREEN STREET ALBANY, NEW YORK 12202 INDIVIDUAL WATER SUPPLY AND SEWAGE DISPOSAL SYSTEM LAYOUT

DEPARTMENT OF HEALTH COUN TY O F A LBA N Y 175 GREEN STREET ALBANY, NEW YORK 12202 INDIVIDUAL WATER SUPPLY AND SEWAGE DISPOSAL SYSTEM LAYOUT DANIEL P. McCOY County Executive ELIZABETH F. WHALEN, MD, MPH Commissioner of Health DEPARTMENT OF HEALTH COUN TY O F A LBA N Y 175 GREEN STREET ALBANY, NEW YORK 12202 The Dr. John J.A. Lyons ALBA N Y

More information

Service Guide. Evaporator Coil Cleaning and Condensate Drain Maintenance Guidelines. ORDER No: UN-SVG001A-EN DATE: October 9, 2007

Service Guide. Evaporator Coil Cleaning and Condensate Drain Maintenance Guidelines. ORDER No: UN-SVG001A-EN DATE: October 9, 2007 Service Guide Evaporator Coil Cleaning and Condensate Drain Maintenance Guidelines ORDER No: UN-SVG001A-EN DATE: October 9, 2007 Introduction This document defines American Standard and Trane s recommendations

More information

How To Install A Mazzei Injector

How To Install A Mazzei Injector TECHNICAL BULLETIN No. 4 USE OF MAZZEI INJECTORS IN WATER-WELL / PRESSURE TANK APPLICATIONS The selection, installation and use of Mazzei Injectors in water-well/pressure tank systems is quite straightforward.

More information

Causes of Bacteria in Water Samples 1

Causes of Bacteria in Water Samples 1 The Center at Keene: 149 Emerald Street, Keene NH 03431 Phone: (603) 357-2577 / Toll Free: (800) 760-4246 Fax: (603) 352-3899 Email: chem@eai-labs.com Causes of Bacteria in Water Samples 1 The purpose

More information

FAST Owner s Manual. MicroFAST NitriFAST HighStrengthFAST RetroFAST

FAST Owner s Manual. MicroFAST NitriFAST HighStrengthFAST RetroFAST FAST Owner s Manual FOR USE WITH (NSF Std 40 & 245) MicroFAST 0.5, 0.75, 0.9, 1.5 (non-nsf certified) MicroFAST 3.0, 4.5, 9.0 (ETV/EPA tested) RetroFAST 0.150, 0.250, 0.375 NitriFAST 0.5, 0.75, 0.9, 1.5,

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information