Edge Hill University Carbon Management Programme. Carbon Management Plan (CMP) working with

Size: px
Start display at page:

Download "Edge Hill University Carbon Management Programme. Carbon Management Plan (CMP) 2010-2015. working with"

Transcription

1 Edge Hill University Carbon Management Programme Carbon Management Plan (CMP) working with

2

3 Edge Hill University Carbon Management Programme Carbon Management Plan (CMP) working with

4 Edge Hill University 2011 You may reproduce this material, free of charge, in any format or medium without specific permission, provided you are not reproducing it for financial or material gain. You must reproduce the material accurately and not use it in a misleading context. If you are republishing the material or issuing it to others, you must acknowledge its source, copyright status and date of publication. While great care has been taken to ensure that the information in this publication is accurate at the time of publication, we accept no responsibility for any errors or omissions. Where a specific product is referred to in this publication, no recommendation or endorsement of that product by Edge HIll University is intended, nor should it be inferred. First Published: March 2011 Further copies may be obtained from: Sustainability Durning Centre Edge Hill University St Helens Road, Ormskirk Lancashire, L39 4QP, UK

5 Contents Contents List of Figures 2 List of Tables 2 Foreword from Pro Vice-Chancellor Steve Igoe 4 Foreword from The Carbon Trust 5 Management Summary 7 1. Introduction Carbon Management Strategy Context and Drivers for Carbon Management Strategic Themes Targets and Objectives Emissions Baseline and Projections Scope Baseline Projections and Value at Stake Carbon Management Projects Existing Projects Planned / Funded Projects Near Term Projects Medium to Long Term Projects Non-Technical Initiatives Scope 3 Projects Projected Achievement Towards Target Carbon Management Plan Financing Assumptions Benefits / Savings Quantified and Un-Quantified Additional Resources Financial Costs and Sources of Funding Actions to Embed Carbon Management in Edge Hill University Policy Embedding CO 2 Saving Responsibility Data Management Communication and Training Procurement Engaging Suppliers Monitoring and Evaluation Keeping Track of Progress Programme Management of the CM Programme The Programme Board Strategic Ownership and Oversight The Carbon Management Team Delivering the Projects Continuity Planning for Key Roles Ongoing Stakeholder Management Annual Progress Review to Senior Management Team 34 Appendix A: Carbon Management Matrix Embedding 36 Appendix B: Definition Of Projects 37 Appendix C: Role Description Sustainability Champion (Graduwatt) 65 Appendix D: Summary of Environmental Management Strategy ( ) 67 Carbon Management Plan (CMP)

6 Edge Hill University List of Figures Figure 3.1 Summary of all 2008/09 Carbon Emissions 14 Figure 3.2 BAU vs. Target tonnes CO 2 16 Figure 3.3 BAU vs. Target Costs 16 Figure 3.4 Summary of Emissions and Targets from 2005 to Figure 4.1 Target and Identified Projects Set Against BAU 24 List of Tables Table 1.1 List of notable actions undertaken at Edge Hill 10 Table 3.1 Total emissions for all scopes in 2008/09 15 Table 3.2 Total emissions for scopes 1 and /09 15 Table 3.3 Total emissions for scopes 1 and /06 16 Table 4.1 Completed Projects 19 Table 4.2 Funded Projects 20 Table 4.3 Near Term Projects 20 Table 4.4 Medium to Long Term Projects 23 Table 4.5 Non-Technical Initiatives 23 Table 4.6 Scope 3 Projects 24 Table 5.1 Summary of Potential Cost and Carbon Savings Compared to 2008/09 Baseline 25 Table 5.2 Details of Capital Costs 26 Table 6.1 Awareness Calendar 29 Table 7.1 Composition of the Carbon Management Board 31 Table 7.2 Carbon Management Team Members 32 Table 7.3 Stakeholder Management Summary 33 2 Carbon Management Plan (CMP)

7 Carbon Management Plan (CMP)

8 Edge Hill University Foreword from Pro Vice-Chancellor, Steve Igoe In 2010, Edge Hill University celebrated 125 years as a high quality provider of Higher Education. From its inception, in St George s Hall, Liverpool in 1885, innovation and invention have been at the heart of what we do. More recently sustainability has taken an equally important role in the business we conduct and how we do so. As a significant provider of vocational graduates in the caring professions, our alumni are vital in creating and enhancing sustainable communities. Over recent years the success of the University has enabled it to enhance its leadership role in sustainable development, particularly in the way it addresses sustainability issues in the development of its campus infrastructure. Our Faculty of Health Building was adjudged the winner of the RICS North West Awards 2009 in the sustainability category. The University was also delighted to win the award recognising outstanding leadership through significant energy and CO 2 emissions savings from business operations at the inaugural Environment Agency Awards Steve Igoe Pro Vice-Chancellor (Resources) Edge Hill University All of this underlines the University s commitment, drive and enthusiasm, to take a leadership role both at regional and national level in developing a truly sustainable organisation for the next decade and beyond. We are delighted to be part of the current Carbon Management Programme and look forward to capturing and disseminating the undoubted benefits that will flow from our work in this area for many years to come. 4 Carbon Management Plan (CMP)

9 Foreword Foreword from Richard Rugg, of the Carbon Trust Cutting carbon emissions as part of the fight against climate change should be a key priority for Universities and Colleges - it's all about getting your own house in order and leading by example. The UK Government has identified the Higher Education sector as key to delivering carbon reduction across the UK in line with the Climate Change Act targets, and the HE Carbon Management Programme is designed in response to this. It assists Higher Education institutions in saving money on energy and putting it to better use elsewhere, whilst making a positive contribution to the environment by lowering carbon emissions. Edge Hill University partnered with the Carbon Trust on this ambitious programme in 2010 in order to realise substantial carbon and cost savings. This Carbon Management Plan commits the University to a target of reducing CO 2 by 6% by 2013/14 in absolute terms, and 27% over a business as usual scenario. It also underpins potential financial savings to the institution of around 235,000 per year by that date. Richard Rugg Head of Public Sector, Carbon Trust There are those that can and those that do. Universities can contribute significantly to reducing CO 2 emissions. The Carbon Trust is very proud to support Edge Hill University in their ongoing implementation of carbon management. Carbon Management Plan (CMP)

10 Edge Hill University 6 Carbon Management Plan (CMP)

11 Edge Hill University Summary Management Summary The objectives of the Higher Education Carbon Management (HECM) process are to: Change the current practices of the University, taking a whole-organisation approach so that, over the short to medium term, carbon reduction becomes embedded in management decision making across the full range of the University s operations; and To undertake a series of interventions and projects that will lead directly to measurable emissions reduction. This Carbon Management Plan (CMP) defines the steps that Edge Hill University will take to achieve these outcomes, by specifying and timetabling key actions that are credible and adequately resourced and have clear responsibilities allocated for implementation. These actions are not limited to specific technical interventions leading directly to emissions reduction but include the full range of management, policy and enabling actions that are required to embed carbon management in the strategic and operational policies and practices of the University. The CMP is intended to provide a practical and formal basis for implementing carbon emission reduction over the short to medium term. It is also intended to summarise the position Edge Hill University has reached at this stage in the carbon management process and set targets for the future. Strategic Drivers: Edge Hill University is committed to reducing its environmental impacts, and in recent years, has undertaken a number of sustainable initiatives from the implementation of an award winning Sustainable Travel Policy through to the development of the Faculty of Health building, which won the Royal Institute of Chartered Surveyors North West Award for Sustainability in The Carbon Management Board was established to evaluate the University s environmental impact and to coordinate solutions aimed at reducing it. The University has recently approved an Environmental Management Strategy ( ) that sets targets to reduce its environmental impact in ten different areas. In this plan, the University seeks to make the protection and enhancement of the environment integral in all that it does, continually improving its environmental performance wherever practicable. It is the Environmental Management Strategy that reinforces the primary goals of the Carbon Management Plan. University Growth: Edge Hill is one of the fastest growing Universities in the UK reflected in the 44% increase in student numbers (full time equivalents (FTE)) between 2005/06 and 2009/10. In order to accommodate the necessary growth in both student accommodation and teaching space, the University s building area has increased by 30% since 2005/06, of which 20% is since 2008/09. There are plans for this level of growth to continue until at least 2012 due to the development of the Student Hub and new sports facilities. Sustainability and carbon emission minimisation was a major consideration throughout the development process, resulting in a reduction from 550 to 501 kg CO 2 per FTE between 2005/6 and 2009/10. Baseline and Target Emissions: The carbon emissions baseline data for the University has been calculated using data from the 2008/09 academic year. The baseline data covers emissions from scope 1 and scope 2 activities that is emissions from combustion of gas and consumption of electricity on the main campus in Ormskirk, as well as from University-owned transport activities. Total carbon emissions from scopes 1 & 2 for the 2008/09 academic year were 6,566 tonnes CO 2 e. Efforts to reduce carbon are therefore regularly offset by the business need to increase space, equipment and campus residence. The target reductions attainable must reflect the 21% rise in emissions plus the anticipated 20% increase due to new development. Edge Hill University has therefore set challenging reduction targets against both the 2005/06 and 2008/09 baselines for scopes 1 & 2. Our contribution to the Higher Education Council for England (HECFE) reduction target is 5% to 2020 based on the 2005/06 baseline. The Carbon Management Plan target is set on the 2008/09 baseline and is 1,774 tonnes CO 2 e to 2013/14. This equates to a 27% reduction on the base year itself and 6% as an absolute target which includes the planned development. Carbon Management Plan (CMP)

12 Edge Hill University 2005/06 Baseline emissions (tonnes CO 2 ) 5, /09 Baseline emissions (tonnes CO 2 ) 6,566 BAU emissions (tonnes CO 2 ) to 2013/14 7,946 RES emissions (tonnes CO 2 ) to 2013/14 6,172 Cumulative saving on 2008/09 baseline (tonnes CO 2 ) 5,807 Value at Stake: Using the emissions baseline, two different consumption scenarios have been projected. The Business as Usual (BAU) scenario predicts the cost of emissions if no actions are taken to reduce carbon emissions. The Reduced CO 2 Emissions Scenario (RES) predicts the effect on cost and carbon emissions if emissions are reduced from the baseline. The total aggregated Value at Stake postulated from 2008/09 to 2013/14 in energy related costs is 910,000 and in carbon emissions is cumulative 5,807 tonnes of CO2e. Reduction Projects: In order to meet the target reduction in carbon emissions, a number of carbon saving projects and actions have been identified. Approximately thirty-eight potential projects for reducing scope 1 & 2 emissions have been identified. If all the projects are implemented, CO 2 emissions would be reduced by 1,428 tonnes by 2013/14 compared to the BAU scenario. Identified projects currently cover 80% of the Edge Hill reduction target. Edge Hill is confident in the fact that further projects will be identified and implemented over the next 5 years that will enable achievement of the 6% carbon reduction from the 2008/09 baseline. Sources of Funding: Approximately 275,000 of funding has been committed in 2010/11. This encompasses the sub-metering programme, awareness campaigns and PV installation. The total unsecured funding from 2012 to 2014 is 537,000 with savings predicted at 235,000. This funding includes the near and medium projects with paybacks less than 5 years, to long term projects with paybacks between five and ten years. The average payback period of the projects in the plan is 3.4 years. 8 Carbon Management Plan (CMP)

13 Carbon Management Plan (CMP)

14 Edge Hill University 1. Introduction Named after the district in Liverpool in which it was originally sited, Edge Hill College opened its doors on 24th January Initially offering teacher training to 41 students, Edge Hill has developed into one of the fastest growing Universities in the UK boasting a 44% increase in student numbers (full time equivalents (FTE)) between 2005/06 and 2009/10. The University has three faculties, Arts & Sciences, Education, and Health, which are situated on its main 160-acre site in Ormskirk, Lancashire. The campus now houses 1,046 residential students and 24 academic and support buildings. Sustainability has always been at the heart of the University s ethos, not only in the role of educator and community leader but also as a major employer and consumer of resources. The University has made great efforts to reduce its carbon footprint from the award winning Green Travel Plan in 2005 to designing and building new facilities of the highest quality, that incorporate a wide range of sustainable technologies whilst ensuring minimal operational and environmental impact. Table 1.1 identifies some of the major projects undertaken. Table 1.1 List of notable actions undertaken at Edge Hill 2004 Started Sustainable Urban Drainage System (SUDS) Green Travel Plan Faculty of Health incorporating Ground Source Heat Pumps, solar thermal and the innovative Green Wall to provide awareness New Business School incorporating solar thermal panels New residential accommodation incorporating mini CHP. Start of a rollout of Sun Ray 'Thin Client' Workstations commenced in Dec 2008 in the new Faculty of Health building Continued deployment of 'Thin Client' Workstations in new Business School Server consolidation and Vitalisation 2009/10 are ongoing 2010 New administration and IT building. Using heat reclaimed from the IT servers suite as a heat source for the underfloor heating system. Also includes solar photovoltaic and solar thermal panels. Working in partnership with the Carbon Trust has been instrumental in helping achieve these aims, not least in the development of the Faculty of Health, building which won the Royal Institute of Chartered Surveyors North West Award for Sustainability Carbon Management Plan (CMP)

15 Section 1. In order to minimise carbon emissions further, and to ensure Edge Hill plays its part in meeting the government s requirement to reduce carbon by 34% on 1990 baseline, the University has enrolled in the Carbon Trust 2010 Higher Education Carbon Management Programme (HECMP). The HECMP process consists of five stages: Step 1: Mobilise the organisation Step 2: Set baseline, forecast and targets Step 3: Identify and qualify options Step 4: Finalise Carbon Management Plan Step 5: Implement plan The first four steps are laid out within the HECMP programme and follow a pre-set timetable for attained objectives. Whilst the plan offers a system to identify technical projects on a holistic basis, Edge Hill has adopted a systematic approach to project identification by employing an Engineer with clearly defined role and responsibilities. This role has enabled projects to be identified on a building by building basis in order to ensure optimum project assessment. Stage five incorporates the implementation of the plan over the next five years. Carbon Management Plan (CMP)

16 Edge Hill University 2. Carbon Management Strategy The first formal interpretation of sustainable development was introduced in the Bruntland Report in This concept of providing for today whilst ensuring a positive legacy for future generations is fundamental to Edge Hill s culture and decision making. Using the three core elements of environmental, social and financial responsibility to direct its policies, the University strives to ensure its own legacy is positive for both the University and wider community. Carbon management is fundamental to these responsibilities. By limiting the use of fossil fuels it ensures fuel is available for future generations; reducing CO 2 emissions limits the potential impacts of climate change; and the savings achieved through reduced energy bills and reduced waste will be invested into the core business of education. 2.1 Context and Drivers for Carbon Management The UK Government is putting increasing pressure on the whole public sector to lead by example in cost saving and climate change mitigation through energy efficiency and emissions reduction. Action by the public sector will be critical to the achievement of the Government s climate change objectives. The Climate Change Act has a long term goal to reduce CO 2 emissions by 34% by 2020 and 80% by 2050 from a 1990 baseline to help the UK s transition to a low carbon economy. This has created a number of legislative drivers: Display Energy Certificates: From the 1st of October 2008 there is a legal requirement for all public sector buildings, with a total useful floor area of over 1,000m2, to show a Display Energy Certificate (DEC) in a prominent place, clearly visible to the public. Carbon Reduction Commitment: The Carbon Reduction Commitment (CRC) is a mandatory emission control scheme for organisations whose total electricity consumption is greater than 6,000MWh. If an organisation falls within the CRC scheme all electricity and fuel emissions are covered. The first phase of the plan charges 12/t CO 2, with all monies collected being retained for use to support public finances. If an organisation consumes between 3,000 and 6,000 MWh, an information disclosure will have to be made. Building Regulations, Part L: Building Regulations are increasingly steered toward reducing the requirement of lighting, heating and cooling for both domestic and non-domestic premises. The revised 2010 regulations require 25% less carbon emissions against Part L1A 2006 which is a 40% improvement over a dwelling build to the 2002 regulations. Capital funding for HEIs linked to carbon performance: HEFCE s 2008 and 2009 grant letters from the Secretary of State demand the establishment of a link between performance on carbon reduction and future capital allocations, leading to the requirement for Higher Education Institutions (HEIs) to set their own carbon reduction targets for 2020 and establish carbon reduction plans. Currently HEFCE are looking for reductions on scope 1 and scope 2 emissions only (related to site usage), set against a 2005 baseline. HEFCE also propose that HEIs commit to making reductions in scope 3 (indirect emissions) with plans to set targets against these emissions when more robust protocols are developed. Corporate branding: Students are becoming increasingly aware of environmental issues. The increasing engagement with carbon management and demonstrable results will provide an additional attraction to these students. Cost mitigation: measures to increase energy efficiency will reduce annual energy costs and manage the risk of volatile and rising energy prices. Energy and fuel costs have increased significantly since 2004 and this trend is not expected to change. 12 Carbon Management Plan (CMP)

17 Section Strategic Themes Health, Safety and Environmental Policy Statement (extract) To deliver and maximise performance improvements within safety and environmental management through creating the conditions for sustainable development Sustainability is woven into all policies and strategies adopted by Edge Hill. However it s the Environmental Management Strategy which reinforces the primary goals of the Carbon Management Plan. The Environmental Management Strategy ( ) sets objectives in nine different areas that will help Edge Hill reduce its environmental impact. In addition to each objective, measurable targets and time-bound actions are also defined. An annual report on progress against targets will be submitted as part of the Institutional Health, Safety & Environment Report. The Environmental Management Strategy ( ) sets out a requirement for: carbon reduction and conservation of natural resources through improved energy efficiency and the appropriate use of new technologies and practices. The strategy supports Carbon Management in the following areas. Appendix D provides a summary of objectives and targets. Environmental Management Systems Energy Management Transport Waste Management Water Community Involvement Procurement Construction and Refurbishment Emissions and Discharge 2.3 Targets and Objectives Edge Hill is one of the fastest growing Universities in the UK achieving a 44% increase in student numbers (full time equivalents (FTE)) between 2005/06 and 2009/10. Efforts to reduce carbon are therefore regularly offset by the consequential increase in space, equipment and campus residences. The campus building area has increased by 30% since 2005/06 of which 20% is since 2008/09. There are plans for this level of growth to continue until at least 2012 estimated at a further 21% rise in emissions. The target reductions attainable must reflect this growth. Therefore the 5% reduction to 2020 against the 2005 baseline for scopes 1 & 2 is challenging. Efforts to calculate scope 3 emissions have been made to be used as a guide and details of emissions are provided in section 3. Monitoring processes are currently being established but targets will not be set until robust monitoring practices have been embedded. Edge Hill will reduce the CO2 emissions from the 2005/06 baseline of 5601 tco 2 by 5%, by July 2020 for scope 1 & 2 activities. Interim milestone of 6% (1774 tco 2 ) reduction in emissions by July 2014 from the 2008/09 baseline of 6,566 tonnes. Scope 3 is being monitored from Carbon Management Plan (CMP)

18 Edge Hill University 3. Emissions Baseline and Projections 3.1 Scope In order to measure savings achieved, a baseline needs to be established. Information relating to the University s own buildings and fleet emissions is readily available (scope 1 and 2). Areas under scope 3 have not all been measured accurately in the past. In order to ensure these areas are addressed going forward estimations have been made for 2008/09. Due to the uncertainty of this data, scope 1 and 2 will be presented separately from scope 3. Targets for scope 3 will be set at a later date although projects to reduce emissions in this area will be identified within this plan. Definition of scopes: Scope 1: Scope 2: Scope 3: Direct emissions that occur from sources that are owned or controlled by the organisation, for example emissions from combustion in owned or controlled boilers, furnaces and vehicles. Emissions from the generation of purchased electricity consumed by the organisation. All other indirect emissions which are a consequence of the activities of the organisation but occur from sources not owned or controlled by the organisation for example, commuting, water and waste. Figure 3.1 Summary of all 2008/09 Carbon Emissions 3.2 Baseline The baseline 2008/09 was chosen as the base year as it represented the most current full year s data available. The year follows the financial year August 08 to July 09. Table 3.1 provides a full breakdown of emissions. All conversion factors are as provided by the HECMP. Total cost data cannot be provided due to lack of information in some scope 3 areas. 14 Carbon Management Plan (CMP)

19 Section 3. Table 3.1 Total emissions for all scopes in 2008/09 Tonnes of CO 2 for Base Year 2008/09 Building 6,520 Fleet 46 Commuting 1,996 Business Travel 438 Water 44 Waste 1,772 Total 10,816 A more detailed breakdown of scope 1 & 2 data can be found in Table 3.2. Table 3.2 Total emissions for scopes 1 and /09 Tonnes of CO 2 for Base Year 2008/09 Scope 1 Gas 3, ,123 Fleet 46 20,588 Scope 2 Electricity 3, ,352 Total 6, ,063 The University obtains most building emissions data through three main fiscal meters on campus, although there are a number of small external sites: Milton House, Silkhouse Court and Aintree Hospital, with adequate data, which are included within the figures. All other sites occupied by Edge Hill are charged on an unmetered basis and are therefore not included within the data. Insufficient sub metering prevents a breakdown of energy usage on an individual building basis. Sub metering is an identified project within the plan. The fleet is a mixture of six University Vehicles available for use by staff, a box van with tail lift, a truck and grounds vehicles. Most of the data is obtained from fuel cards, however for grounds vehicles using red diesel the information is taken from invoices. Scope 3 data is recorded in several ways: Water is measured via a fiscal meter; Waste information is derived from bin collection data; Business travel by car is calculated from expense claims and air travel is estimated based on travel insurance data; Consultants undertook a baseline assessment of the carbon emitted as a result of staff and student commuting by car (single-occupancy and car-sharing); Student commuting at the beginning and end of term is estimated using postcode analysis to derive driving distances; and International student commuting (air travel) is estimated using home country information provided by Academic Registry. Carbon Management Plan (CMP)

20 Edge Hill University In order to be monitored against HEFCE targets the baseline for 2005/06 is used. Both the electricity and gas data were recalculated in order to correct estimated consumption and to include the remote sites. Table 3.3 provides a breakdown of the 2005/06 baseline. Table 3.3 Total emissions for scopes 1 and /06 Tonnes of CO 2 for Base Year 2005/06 Scope 1 Gas ,408 Fleet 23 11,535 Scope 2 Electricity ,043 Total , Projections and Value at Stake In order to fully understand the impact of reductions it is necessary to understand what the reductions are being set against. As Edge Hill is a comparatively young University it has a programme of expansion including a new Student Hub and sports developments as well as increasing onsite student accommodation. The increased accommodation will be detrimental to onsite emissions but will help reduce emissions from student travel. From 2010/11 onwards the construction and operation of the student residences and new gym are predicted to contribute approximately 172 tonnes of CO 2 e annually. Likewise, the new Student Hub and Sports Development are predicted to generate approximately 745 tonnes of CO 2 e from 2011/12. Figures 3.2 & 3.3 identify the increase in emissions and costs in the Business as Usual (BAU) scenario (red line with squares). The assumptions incorporated into the BAU scenario are that electricity and gas prices remain unchanged until 2012/13 due to a fixed price contract but then rise by 5% per annum thereafter. Emissions are assumed to increase by 0.7% per annum, from the DTI (now DBERR) figures in EP68, and by 917 tonnes CO 2 e due to new building expansion. In Figure 3.2, the blue line (with triangles) shows the straight-line trajectory required to meet the 2014/15 emissions target (6% reduction from 2008/09). The gap between these lines is the Value at Stake, or the cost of no action, which means an additional 5,807t CO 2 e during the five year period. Figure 3.3 shows the financial Value at Stake, which indicates that no action could lead to an additional 910,000 of energy costs to the University. 16 Carbon Management Plan (CMP)

21 Figure 3.2 BAU vs. Target tonnes CO 2 Actual emissions, BAU increase, target predicted Figure 3.3 BAU vs. Target costs BAU increases and reduction target - financial Figure 3.4 indicates the growth in emissions and potential carbon savings that could be achieved through implementation of the projects identified within the plan. During the period from 2005/6 to 2008/9, any energy efficiency measures that were implemented were masked due to the extensive building programme. The buildings constructed during that time incorporated carbon reduction measures as part of their design and operation. However, emissions still rose by 17% over this period as these reduction measures could not completely mitigate the emissions from the usage of the buildings. The reduction of 5807 tco 2 shown in figure 3.5 relates to the accumulated saving from 2008/09 to 2013/14. There are further savings of 13,624 tco 2 between 2013/14 and 2020 assuming the BAU remains constant. The combined saving equates to 19,432 tco 2 between 2008/09 and Figure 3.4 Summary of emissions and targets from 2005 to 2020 Carbon Emission to Date Planned Reduction to 2015 (CMP) Planned Reduction from 2005 to 2020 Construction Lines Carbon Management Plan (CMP)

22 Edge Hill University 4. Carbon Management Projects The level of growth at the University has meant an increase in the buildings footprint of 32.5% since 2006 with further expansions planned over the next few years. This growth has been the result of record increases in student numbers and the associated demand for the Edge Hill University offering. All of the new buildings are designed to high carbon efficiency specifications and have won awards such as the RICS North West Award for Sustainability 2009 for the Faculty of Health building. The University has also won the Environment Agency Awards 2010 recognising outstanding leadership through significant energy and CO 2 emissions savings from business operations. Efforts to mitigate against the increasing requirement for ICT equipment have been made with the introduction of Sun Ray monitors, automated system shut down and a heat reclaim system using heat generated by the new server room as a base load for the buildings heating requirements. In order to address the increasing carbon footprint of the University a feasibility study was undertaken to assess the potential of large scale (2 * 3MW) wind turbines to cover the total campus energy footprint. The aim was to retain the Renewable Obligation Certificates in order to allow the campus to be classed as carbon neutral. The study identified the project was both technically and financially viable. However, the report also highlighted there are areas of issue such as the local council s planning policy and other environmental considerations. The report concluded the project was not likely to get planning approval at this time. As the holistic approach did not prove successful and in order to ensure all carbon reduction opportunities are identified, a Carbon Management Projects Manager has been appointed. Assessing each building individually, all appropriate projects have been identified and included within the plan. However the identified reductions are set against an extensive future expansion project. Identification of projects is a continuous process. Technical projects will be identified by the Carbon Management Projects Manager in consultation with representatives from other departments, and non-technical projects will be identified by the Sustainability Champions (Appendix C) and the Carbon Management Team. The quantities of energy/carbon and costs saved are the main drivers for the Finance Planning Team when considering approval of a project. Each project business case includes a section on the potential carbon and cost reduction benefits. 18 Carbon Management Plan (CMP)

23 Section Existing Projects Table 4.1 relates to projects that have been completed or are currently in progress. No project plan has been provided as the work is nearly complete. The associated project costs were part of a wider development programme and are therefore not available as independent costs. Table 4.1 Completed Projects Ref Project Lead Annual Savings (yr 1) Fin (Gross) tco 2 % of Planned CO 2 Savings Implement Year EHU001 to EHU004 Boiler de-centralisation for Venue and Old Gym D Oldham 14, % 2010 EHU007 Roll out of thin client terminals across campus M Allinson 4, % 2010 EHU011 Implementation of server virtualisation and consolidation M Allinson 3, % 2012 EHU027 Connection of solar thermal panels in Sporting Edge to provide hot water D Oldham 2, % 2010 EHU040 Installation of PV to generate electricity on Durning Centre D Oldham 2, % 2010 Totals 27, % Carbon Management Plan (CMP)

24 Edge Hill University 4.2 Planned / Funded Projects The University has already approved the projects listed in Table 4.2 for implementation. The awareness campaign started in December 2010 and the commencement of sub metering is due before the start of 2011/12. The awareness campaigns and associated behavioural change will be evaluated using the monitoring and targeting system. This system will also be utilised to quantify the delivered savings against scope 1 and 2 projects listed and as part of the business cases for future approved projects. On-going and long term maintenance of plant and equipment and of other items such as windows, seals etc has not been listed as a separate project as this is already included in the Facilities Management departmental budget. Table 4.2 Funded projects Ref Project Lead Cost Capital Operational Annual Savings (yr 1) Fin (Gross) tco 2 Pay back (yrs) % of Planned CO 2 Savings Implement Year EHU005 & EHU006 Staff and student awareness project P Brandwood 0 3,000 10, % 2011 EHU012 Sub-metering with Monitoring and targeting of consumption P Brandwood 121, , % 2011 Totals 121,000 3,000 52, % 4.3 Near Term Projects The projects listed in table 4.3 are short to medium term projects with less than a 5 year payback. Preliminary feasibility assessments have been done in anticipation that funding will be available once the projects have been approved. However, it is highly likely that some of the projects will require more detailed feasibility work such as small-scale trials and/or more accurate information relating to installation costs, prior to obtaining approval. Table 4.3 Near Term Projects Ref Project Lead Cost Capital Operational Annual Savings (yr 1) Fin (Gross) tco 2 Pay back (yrs) % of Planned CO 2 Savings Implement Year EHU008 Installation of ultra-low loss transformers across campus V Baichoo 125, , % 2012 EHU009 Replacement of part of the campus security and exterior lighting V Baichoo 24, , % Carbon Management Plan (CMP)

25 Ref Project Lead Cost Capital Operational Annual Savings (yr 1) Fin (Gross) tco 2 Pay back (yrs) % of Planned CO 2 Savings Implement Year EHU010 Implementation and enforcement of a Heating Policy across the campus estate V Baichoo , % 2012 EHU013 Replace main library and SIC lighting with new LED fittings V Baichoo 164, , % 2012 EHU015 Top-up roof insulation in Forest Court to 300mm V Baichoo 5, , % 2011 EHU016 De-lamping the Wilson Centre corridor and toilets lighting V Baichoo % 2011 EHU017 EHU018 EHU019 EHU020 EHU021 EHU022 EHU023 EHU024 Ground Floor T8 lighting replacement in LINC V Baichoo % Install solar film to minimise heat gain to ground floor computer rooms and middle floor offices on south-facing façade V Baichoo 2, , % Re-commission the controls, set-points, etc. for the LINC V Baichoo 1, , % Application of VSD controls to pump and AHU motors across selected campus buildings V Baichoo 12, , % Reduce power consumption of main chilled water circulating pump motors in LINC building V Baichoo % Replace MATEC classroom lighting in the MATEC building with like for like T5 in new fittings V Baichoo 10, , % MATEC Ground Floor Workshops lighting replacement & PIR Installation. V Baichoo % Replacement of main lighting in NGAS building with more efficient T5 equivalents V Baichoo 19, , % EHU025 Old gym main lighting replacement V Baichoo 1, , % 2011 Carbon Management Plan (CMP)

26 Edge Hill University Ref Project Lead Cost Capital Operational Annual Savings (yr 1) Fin (Gross) tco 2 Pay back (yrs) % of Planned CO 2 Savings Implement Year EHU026 Replace main lighting in Sporting Edge older gym V Baichoo 4, , % 2011 EHU028 EHU029 Replace 28 x 100W tungsten bulbs in Rose Theatre with 16 W GU24 CFLs V Baichoo 2, % 2011 Install dimming circuits to existing path and car park lighting V Baichoo 3, % 2011 EHU030 Replace fluorescent tube lighting in the Venue V Baichoo % 2011 EHU033 EHU034 EHU035 EHU037 EHU038 EHU039 Replace lighting in Main Building halls bathrooms V Baichoo % Installation of controls to boilers in campus plant rooms to minimise boiler dry cycling V Baichoo 35, , % Replace main lighting in Geography Building with T5 equivalents V Baichoo 1, % Replace lighting in Bio- Mechanics lab in the Wilson Centre with T5 equivalents V Baichoo % Insulation of hot water heating pipework in halls of Main Building V Baichoo 43, , % Replacing all air handling unit filters with energy efficient equivalents V Baichoo 5, , % EHU041 Insulate pipe flanges and valves in plant rooms V Baichoo 9, , % 2011 EHU043 Feasibility into MFD sleep mode reduction P Brandwood , % 2011 Totals 471,211 1, , % 22 Carbon Management Plan (CMP)

27 4.4 Medium to Long Term Projects The long term projects identified in Table 4.4 have paybacks between 5 and 10 years. They have been identified and formal quotes/proposals received from designated suppliers. No detailed feasibility has been undertaken yet, and funds have not been identified. However, project due diligence has been undertaken to assess the potential savings and costs involved. Indications of the potential carbon savings are provided. Table 4.4 Medium to Long Term Projects Ref Project Lead Cost Capital Operational Annual Savings (yr 1) Fin (Gross) tco 2 Pay back (yrs) % of Planned CO 2 Savings Implement Year EHU014 Replace combi boilers in Forest Court with condensing models V Baichoo 63,000-4,000 3, % 2012 EHU012 Replace lighting in Terrace Café V Baichoo 3, % 2012 Totals 66,081-4,000 4, % 4.5 Non-Technical Initiatives The projects in sections 4.1 to 4.4 have related to mainly technical projects. In addition to these there are a number of other initiatives being considered that are designed to endorse behavioural change outlined in Table 4.5. Table 4.5 Non-Technical Initiatives Ref Project EHU101 EHU102 Building closure - feasibility study. The merits to this will not be identified until the sub metering is installed. Paper reduction - feasibility study. Although the project will not reduce emissions significantly the culture of technology over paper reinforces the concepts of sustainability. EHU103 Inclusion of sustainability issues in staff handbook, induction and job descriptions. No direct carbon savings but reinforces a low carbon culture. Carbon Management Plan (CMP)

28 Edge Hill University 4.6 Scope 3 Projects In efforts to reduce the scope 3 emissions the following projects in Table 4.6 have been identified. A more detailed explanation can be found in Appendix B: Definition of Projects. Table 4.6 Scope 3 Projects Ref Project tco 2 EHU501 Priority parking for car sharers 31 EHU502 Cycle Lanes 53 EHU503 New Waste Management Contract EHU504 Composting food waste 90 EHU505 End-of-year reuse scheme in halls of residence Projected Achievement Towards Target Figure 4.1 highlights the anticipated increase in CO 2 emissions due to development identified in the BAU scenario. The development is to accommodate the major increase in student numbers. Set against this is the target reduction and the identified projects. The target represents a 6% saving in absolute terms but 21% against BAU. We have identified projects equating to 80% of the 1,774 tco 2 target reduction. The remaining 346 tco 2 of carbon savings will be identified and projects implemented over the course of the next five years. Figure 4.1 Target and identified projects set against BAU 24 Carbon Management Plan (CMP)

29 Section Carbon Management Plan Financing Edge Hill has not previously applied for monies from the HEFCE/Salix Finance Revolving Green Fund, preferring instead to fund projects independently. Finances are provided on a robust spend to save scenario but additional consideration is given to environmental and social wellbeing when related to energy efficiency and carbon reduction. This is due not only to a sound sense of corporate social responsibility but also forward thinking and the acknowledgment that cost associated to energy and carbon will continue to increase. The future capital outlay for all the projects will be approximately 833,000. Timescales for expenditure will be decided in a budgetary meeting in February Assumptions Electricity 7.54p/kWh Gas 3p/kWh Annual predicted cost increase electricity reduced to 7p/kWh by 2010/11 in line with current contract. All other cost calculations assume a 5% increase. BAU assumes an increase of 0.7% on the previous years consumption, that is the default value from the DTI (now DBERR) figures in EP68, and a contribution due to development works of approximately 1,200 tonnes CO2e 2008 to Benefits/Savings Quantified and Unquantified Table 5.1 shows the annual savings achieved on the 2008 baseline. The figures relate to the 2008 baseline and do not include the increases for BAU scenario. Table 5.1 Summary of Potential Cost and Carbon Savings Compared to 2008/09 Baseline Annual cost saving 0 87, , ,848 Annual CO 2 saving % of planned CO 2 savings 0% 30% 48% 81% Unquantified benefits: In addition to the financial benefits of carbon reduction there are a number of other benefits: Demonstration of community leadership in Corporate Social Responsibility University reputation Staff and student recruitment and retention Compliance with CIF2 Improved DEC ratings Mitigation against future energy price volatility Remaining below the CRC qualification threshold Carbon Management Plan (CMP)

30 Edge Hill University 5.3 Additional Resources A Carbon Management Projects Manager has been employed to undertake a carbon reduction audit on a building by building basis to identify potential carbon reduction projects. He will also project manage the funded technical projects. 5.4 Financial Costs and Sources of Funding All projects identified will be funded internally as there is currently no intention to take on any external loans. The capital cost for the projects currently underway are part of a larger development scheme and extraction of these costs is not available. The current status is: Table 5.2 Details of Capital Costs Figures in 1000 s 2008/ / / / / /14 Annual costs: Total annual capital cost Total annual revenue cost Total costs Committed funding: Committed annual capital Committed annual revenue Total funded Unallocated funding: Unallocated annual capital Unallocated annual revenue -4 0 Total unfunded To offset some of the financial expenditure there is an anticipated yearly receipt of 11,000 as payment from the feed-in-tariffs attached to Project EHU040. The 4,000 credit identified in 2012/13 unallocated annual revenue relates to the removal of a maintenance charge under Project EHU014. The financing of the projects will be presented for approval via our PVC of Resources, Steve Igoe, at the institutions Finance Committee in February. The Energy Manager and Carbon Management Project Manager will be responsible for project implementation. The Property Services Manager, Alan Wilson, will report on a monthly basis to Director of FM, Bill Hancox, who will take budgetary control and overall responsibility for project implementation. Financial updates will be provided to the Finance Director, Carl Gibson, on a monthly basis with an in-depth examination of projects four times a year. Project implementation will also be monitored through the Sustainability Group reporting to the PVC of Resources. 26 Carbon Management Plan (CMP)

31 6. Actions to Embed Carbon Management in Edge Hill University Section 6. Having previously worked with the Carbon Trust on building and technical projects many of the quick wins have been financed and addressed. There have been a number of ad hoc efficiency campaigns and a limited amount of training but there has been no holistic long term engagement, or information distribution, to provide leadership and guidance on carbon reduction to the University as a whole. For this reason, the scores are low for all areas of the Carbon Management Matrix, detailed in Appendix A. The appointment of an Environmental and Safety Co-ordinator and a new Energy Manager has allowed all aspects of sustainability to be highlighted and policies and strategies to be updated, implemented or planned. Their appointment has conciliated the efforts currently being taken by individuals and allowed knowledge transfer to take place and positive behaviour change across the University. The creation of a network of Sustainability Champions will ensure sustainability is addressed from the bottom up. Appendix C provides details of the role and responsibilities of the Sustainability Champions and their interactions with the Carbon Management Team, Heads of Department and Deans and Directors. Predominantly working with the Sustainability Team (Environmental and Safety Co-ordinator and Energy Manager), and their appropriate Carbon Management Team member, the Champions will ensure carbon reduction is addressed throughout the University on a day to day basis. In addition to this The Students Union play a significant role in addressing sustainability and has signed up to the Green Impact Awards which will provide measurable outcomes. 6.1 Policy Embedding CO 2 Saving As Edge Hill has expanded, using guidance from The Carbon Trust, it has ensured that all new buildings are thermally sound and have maximised the use of natural ventilation and renewable energy technologies. This, coupled with the diversion of over 95% of construction waste from landfill, has ensured a legacy of carbon efficiency in the capital projects environment. Carbon efficiency is also a significant driver behind the development of the new waste strategy and travel policy. The waste strategy is based on the waste hierarchy and looks to increase Edge Hill s recycling capabilities. It is overseen by the Housekeeping Manager. The Head of FM, in partnership with the Finance Department, will develop a travel policy over the course of 2011/12, which will encourage staff to consider cycling, public transport and car sharing over single-occupancy car travel when travelling for business purposes. There is no University sustainable procurement policy/procedure. The Environmental and Safety Co-ordinator is developing a draft sustainable procurement policy for the FM department of the University. This will be piloted within the department from 2011/12. The policy will be open for consultation and rolled out across the University as appropriate. The release of the Carbon Management Plan will be notified to all personnel via the Deans and Directors. There will be instructions that, as business plans and strategies are created or revised, they must adhere to the principles of energy efficiency and carbon reduction. Carbon Management Plan (CMP)

32 Edge Hill University 6.2 Responsibility During 2010 there were two full time members of staff dealing with carbon reduction. Outside of their specific remit there was no formal individual responsibility to sustainability. To enable shared responsibility of embedding this Carbon Management Plan, Human Resources will ensure that with effect from April 2011 all future job descriptions will include environmental awareness as a corporate responsibility. To ensure environmental corporate responsibility is disseminated amongst the existing staff profile, HR will bring this item to the Consultation and Negotiating Committees for both Support and Academic staff in the early spring of 2011 and follow this up with communication with all existing staff. Human Resources will also review how carbon reduction might be included in the performance review process. A network of Sustainability Champions is to be established by the start of the 2011/12 academic year to ensure sustainability is addressed from the bottom up. Appendix C provides a full description of the roles and responsibilities for all levels to ensure the Sustainability Champion is provided with the time and training necessary to fully perform their role. The Students Union signed up to the Green Impact Awards in Autumn 2010 and will demonstrate and promote environmental sustainability in accordance with the requirements of the programme. Through both the Sustainability Group and the Carbon Management Board the Sustainability Team lead the efforts of ensuring carbon reduction is addressed throughout the University reporting to PVC of Resources. These actions will improve the matrix score taking it into the Best category. 6.3 Data Management Energy meter readings have historically been collected manually, however we anticipate having a new automated monitoring and targeting system installed for the academic year 2011/12. This will provide the Energy Manager with half-hour electricity, gas and water data on a next day basis allowing greater control of individual buildings. The information will be reported by the Energy Manager to the Sustainability Group and updated on the sustainability web pages on a monthly basis. The University s waste management contract will be put out for tender during the first half of The tender will stipulate that all waste disposal data must be supplied. The exact format of the information is yet to be agreed but will be available from the start of the 2011/12 academic year. The waste data will be collected and reported to the Sustainability Group by the FM Housekeeping Manager. A new system for collecting and monitoring business travel information is being devised by the Finance Team. The information will be reported to the Sustainability Group and updated on the sustainability web pages on a monthly basis. The lack of external auditing of the data prevents the matrix score from becoming a Carbon Management Plan (CMP)

Queen s University Belfast Carbon Management Programme. Carbon Management Plan (CMP 2013)

Queen s University Belfast Carbon Management Programme. Carbon Management Plan (CMP 2013) Queen s University Belfast Carbon Management Programme Carbon Management Plan (CMP 2013) 5 June 2013 1 Contents Management Summary 1. Introduction 7 2. Carbon Management Strategy 2.1 Context and Drivers

More information

Working with. Carbon Management Board (CMP) 18 September 2009. William Stephens. Cranfield Executive

Working with. Carbon Management Board (CMP) 18 September 2009. William Stephens. Cranfield Executive Working with Carbon Management Plan (CMP) Date: Version: 18 September 2009 2.2 Owner: Approval route: Approval status: John Street William Stephens Carbon Management Board Cranfield Executive Approved

More information

Carbon Management Plan

Carbon Management Plan E-2015-02-02 Addendum Carbon Management Plan Date: 14 May 2014 Owners: Approval: K.W.Bullimore & M.Sackett A.Burrell Executive Summary This document sets out the Carbon Management Plan (CMP) for The Open

More information

Imperial College Carbon Management Programme

Imperial College Carbon Management Programme Imperial College Carbon Management Programme (CMP) Page 1 Contents Foreword from Rector 4 Foreword from the Carbon Trust 5 Management Summary 6 1 Introduction 10 1.1 Carbon Management Programme 10 1.2

More information

PEAK DISTRICT NATIONAL PARK AUTHORITY ENVIRONMENTAL MANAGEMENT ANNUAL PERFORMANCE REPORT 2013/2014

PEAK DISTRICT NATIONAL PARK AUTHORITY ENVIRONMENTAL MANAGEMENT ANNUAL PERFORMANCE REPORT 2013/2014 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 Carbon emissions (kgco2) Page 1 PEAK DISTRICT NATIONAL PARK AUTHORITY ENVIRONMENTAL MANAGEMENT ANNUAL PERFORMANCE REPORT 2013/2014 1. INTRODUCTION

More information

Charnwood Borough Council

Charnwood Borough Council Charnwood Borough Council 2015-2020 Version: 1.0 Owner: Strategic Director of Housing Planning Regeneration and Regulatory Services Approval Route: Carbon Management Board Approval Status: Draft Page 1

More information

Carbon Management Plan

Carbon Management Plan Carbon Management Plan June 2011 2 CONTENTS 1. Executive summary 5 2. Introduction 15 3. Background and context 16 4. Carbon management strategy 18 5. Carbon emissions baseline and projections 22 6. Past

More information

The School of Oriental and African Studies Carbon Management Plan

The School of Oriental and African Studies Carbon Management Plan Date: 4 th April 2011 Version number 11 Owner: McKinnell Approval route: Executive Board Approval status: Final Contents Foreword from the Director 3 Foreword from the Carbon Trust 4 Management Summary

More information

CABINET 26 MARCH 2009 THE LOCAL AUTHORITY CARBON MANAGEMENT PROGRAMME

CABINET 26 MARCH 2009 THE LOCAL AUTHORITY CARBON MANAGEMENT PROGRAMME THE LOCAL AUTHORITY CARBON MANAGEMENT PROGRAMME 1. Summary 1.1 This report sets out the work that has been undertaken in producing a Carbon Management Plan for Dartford Council. The Plan proposes a carbon

More information

PERTH AND KINROSS COUNCIL. Strategic Policy and Resources Committee 14 September 2011 CORPORATE ENERGY MANAGEMENT AND CONSERVATION POLICY

PERTH AND KINROSS COUNCIL. Strategic Policy and Resources Committee 14 September 2011 CORPORATE ENERGY MANAGEMENT AND CONSERVATION POLICY PERTH AND KINROSS COUNCIL 10 11/465 Strategic Policy and Resources Committee 14 September 2011 CORPORATE ENERGY MANAGEMENT AND CONSERVATION POLICY Report by Depute Director (Environment) This report seeks

More information

Hadlow College. Carbon Management Plan. Date: 25/01/2012. Version number: 1.1. Owner: Sue Brimlow

Hadlow College. Carbon Management Plan. Date: 25/01/2012. Version number: 1.1. Owner: Sue Brimlow Hadlow College Date: 25/01/2012 Version number: 1.1 Owner: Sue Brimlow Approval route: Sign off by Project Sponsor and Project Board Approval status: Final Signed off by the Carbon Trust Page 1 Contents

More information

London Borough of Waltham Forest Carbon Management Programme

London Borough of Waltham Forest Carbon Management Programme London Borough of Waltham Forest Carbon Management Programme (CMP) Date: April 2009 Owner: Approval Route: Approval Status: LACM Project Lead LACM Programme Board; Leadership Team and Cabinet Final Table

More information

Darlington Borough Council Carbon Management Programme

Darlington Borough Council Carbon Management Programme Darlington Borough Council Carbon Management Programme (CMP) Date: 31st March 2010 Version number: v1.0 Owner: Project Leader Approval route: CMB, CMT, Cabinet Approval status: Final draft, subject to

More information

glyndwr.ac.uk/sustainability environmental sustainability strategy

glyndwr.ac.uk/sustainability environmental sustainability strategy glyndwr.ac.uk/sustainability environmental sustainability strategy 2012-2014 overview of the environmental sustainability strategy 2012-2014 Glyndŵr University s Environmental Sustainability Strategy 2012-2014

More information

Introduction to the London Energy Efficiency Fund (LEEF)

Introduction to the London Energy Efficiency Fund (LEEF) Executive Summary Introduction to the London Energy Efficiency Fund (LEEF) 1. The London Green Fund (LGF) is a 100m Fund comprising of 50m from the London 2007-13 European Regional Development Fund (ERDF)

More information

CASE STUDY FOR NEWCASTLE UNITED ENERGY MANAGEMENT PROGRAM

CASE STUDY FOR NEWCASTLE UNITED ENERGY MANAGEMENT PROGRAM CASE STUDY FOR NEWCASTLE UNITED ENERGY MANAGEMENT PROGRAM WHAT THE CLUB HAS TO SAY With the introduction of the Carbon Reduction Commitment (CRC), rising energy prices and the corporate need to be more

More information

CARBON MANAGEMENT PLAN

CARBON MANAGEMENT PLAN Department Author Authorised By: Implementation By: Policy Reference: CARBON MANAGEMENT PLAN Estates Paul Wright & Fiona Williams - Carbon Management Team Lynda Powell Carbon Management Team PLEST1415008

More information

How To Be A Responsible Corporate Social Responsibility (Csr) Organisation

How To Be A Responsible Corporate Social Responsibility (Csr) Organisation CORPORATE SOCIAL RESPONSIBILITY STRATEGY 2013-2018 1 Contents Introduction...3 Our CSR Vision...5 Our CSR Objectives...7 Challenges and barriers...10 Implementation Framework...11 Communication Framework...13

More information

Sustainability and Environmental Review. Introduction

Sustainability and Environmental Review. Introduction Sustainability and Environmental Review Introduction Edmundson Electrical Ltd is a long established privately owned company with an unrivalled reputation in the marketplace and with a unique culture that

More information

Climate Local Hampshire County Council Our progress on November 2013

Climate Local Hampshire County Council Our progress on November 2013 Climate Local Hampshire County Council Our progress on November 2013 Since signing up to Climate Local on in July 2013 we have made the following progress towards achieving the commitments and actions

More information

CLEAN GREEN & SUSTAINABLE NS1439215

CLEAN GREEN & SUSTAINABLE NS1439215 CLEAN GREEN & SUSTAINABLE NS1439215 1 Contents 2 Introduction Strategic Alignment 1 - Energy Efficiency 2 - Water Management 3 - Fleet and Plant Management 4 - Carbon Offsets 5 - Waste Management Everything

More information

CARBON MANAGEMENT PLAN

CARBON MANAGEMENT PLAN CARBON MANAGEMENT PLAN Working with Version number: v1.0 Owner: Sustainable Development Manager Approved by University Court on 28 th March 2011 Contents Foreword from the Deputy Vice Chancellor, University

More information

working with Date: 12 April 2010 Version number: 6 Owner: Jan Hulme Approval route: Executive Board Approval status: Approved Page 1

working with Date: 12 April 2010 Version number: 6 Owner: Jan Hulme Approval route: Executive Board Approval status: Approved Page 1 Date: 12 April 2010 Version number: 6 Owner: Jan Hulme Approval route: Executive Board Approval status: Approved Page 1 Contents Foreword from Professor Pamela Gillies, Principal and Vice-Chancellor...

More information

Columbus State Community College. Climate Action Plan

Columbus State Community College. Climate Action Plan Columbus State Community College Climate Action Plan September 2009 Contents Introduction... 3 Commitment... 3 Community Education... 4 Carbon Footprint... 4 Accounting for Student and Employee Commuting...

More information

APPENDIX B - PL1 Homes that meet people s needs and aspirations

APPENDIX B - PL1 Homes that meet people s needs and aspirations APPENDIX B - PL1 Homes that meet people s needs and aspirations Decent and accessible homes are vital to all. Our focus on providing affordable homes is being progressed primarily through the Affordable

More information

Renewable and Low Carbon Energy Study for Central Lincolnshire

Renewable and Low Carbon Energy Study for Central Lincolnshire Design + Planning Building Engineering Renewable and Low Carbon Energy Study for Central Lincolnshire November 2011 Executive Summary STUDY OBJECTIVES The Central Lincolnshire Joint Strategic Planning

More information

James Watt College Carbon Management Programme

James Watt College Carbon Management Programme James Watt College Carbon Management Programme (CMP) Date: 22072010 Version number: 1 Owner: Health, Safety and Environment Service Approval route: Climate Change Action Plan Group Leadership Team BoM

More information

Thames Water is pleased to comment on the proposed changes to the London Plan 2014.

Thames Water is pleased to comment on the proposed changes to the London Plan 2014. Boris Johnson Mayor of London (London Plan) Greater London Authority City Hall More London The Queen s Walk London SE1 2AA Thames Water Property Services Your ref Our ref Name Phone Email London Plan Review

More information

Energy Management Strategy

Energy Management Strategy Energy Management Strategy Gloucester s Energy Management Strategy sets out the way for the organisation to measure and manage all the energy and water resources it uses. The main areas it looks at are

More information

Asset Management Strategy

Asset Management Strategy Greater Manchester Fire and Rescue Service Asset Management Strategy 2013-2015 Appendix 1 Document Version Control Document Version Date Written by 0.1 June 2012 Andrea Heffernan 0.2 December 2012 Andrea

More information

Waste Management Action Plan 2011-2015

Waste Management Action Plan 2011-2015 Waste Management Action Plan 2011-2015 Approved on: 7 June 2011 Owner: Program Manager, 8203 7723 Trim Reference: ACC2011/77875 Next Review Date: June 2014 Executive Summary This Waste Management Action

More information

BESPOKE EMX 08043. Guidance for SME s

BESPOKE EMX 08043. Guidance for SME s Guidance for SME s What is BESPOKE? Who can apply? 1. Business size & location 2. Eligible business sectors 3. State Aid requirements 4. Eligible improvement works 5. Conditions of Funding What do I need

More information

The London Waste and Recycling Board business plan 2015-2020. November 2014. London Waste and Recycling Board 169 Union Street London SE1 0LL

The London Waste and Recycling Board business plan 2015-2020. November 2014. London Waste and Recycling Board 169 Union Street London SE1 0LL The London Waste and Recycling Board business plan 2015 2020 November 2014 London Waste and Recycling Board 169 Union Street London SE1 0LL info@lwarb.gov.uk www.lwarb.gov.uk 2015 2020 Business Plan Contents

More information

Energy Strategy and Carbon Management Programme

Energy Strategy and Carbon Management Programme 2014 Energy Strategy and Carbon Management Programme East Ayrshire Council is committed to reducing its Carbon emissions and will put CO2 emissions reduction at the core of its business activities Contents

More information

University of Glasgow Strategic Travel Plan 2010 2015

University of Glasgow Strategic Travel Plan 2010 2015 University of Glasgow Strategic Travel Plan 2010 2015 Jess Bailey Travel Plan Specialist Viola Retzlaff University of Glasgow Document Control Date Reviewed: March 2010 Version Number: 1 Author/Revised

More information

NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013

NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 APPENDIX 1 NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 Page 1 of 10 1. INTRODUCTION It is widely recognised that asset management is a core component of effective

More information

Case Study: Low carbon refurbishment of Westborough Primary School

Case Study: Low carbon refurbishment of Westborough Primary School Case Study: Low carbon refurbishment of Westborough Primary School Summary The buildings at Westborough Primary had evolved through a fragmented and piecemeal series of building additions and adaptations

More information

Highland Council Carbon Management Plan 2009-2012. The Highland Council. Draft Carbon Management Plan 2009-2012. Page 1

Highland Council Carbon Management Plan 2009-2012. The Highland Council. Draft Carbon Management Plan 2009-2012. Page 1 The Highland Council Draft Carbon Management Plan 2009-2012 Page 1 Page 2 Contents Foreword from the Chief Executive, The Highland Council 4 Foreword from the Carbon Trust 5 Introduction 6 1. Context and

More information

Best Practice Guide BPGCS007

Best Practice Guide BPGCS007 Best Practice Guide BPGCS007 ENERGY MANAGEMENT Introduction: With rising fuel costs, opening of electricity and gas markets to alternate suppliers and climate change, the requirement to monitor and reduce

More information

SAP 2012 IN A NUTSHELL

SAP 2012 IN A NUTSHELL SAP 2012 IN A NUTSHELL The consultation version of the SAP 2012 methodology was published by the Department of Energy and Climate Change (DECC) on January 4th 2012. This article from Dyfrig Hughes of National

More information

Higher Education Carbon Management Programme University of Central Lancashire. Carbon Management Strategy & Implementation Plan 2010 Update

Higher Education Carbon Management Programme University of Central Lancashire. Carbon Management Strategy & Implementation Plan 2010 Update Higher Education Carbon Management Programme Carbon Management Strategy & Implementation Plan 2010 Update Date: September 2010 Version: 1.0 Approval Status: Approved by University Board, Nov 2010 Project

More information

Glenorchy City Council Asset Management Strategy for Infrastructure Assets

Glenorchy City Council Asset Management Strategy for Infrastructure Assets Glenorchy City Council Asset Strategy for Infrastructure Assets 2014/15 to 2017/18 Version 1.3 June 2014 Glenorchy City Council Asset Strategy for Infrastructure Assets Document Control Document Control

More information

Big Yellow Group PLC Basis of Reporting 1st April 2012 31st March 2014 Corporate Social Responsibility

Big Yellow Group PLC Basis of Reporting 1st April 2012 31st March 2014 Corporate Social Responsibility Big Yellow Group PLC Basis of Reporting 1st April 2012 31st March 2014 Corporate Social Responsibility Deloitte LLP provides independent and limited assurance of selected subject matters in our annual

More information

ENERGY SAVINGS ACTION PLAN 2014 2018

ENERGY SAVINGS ACTION PLAN 2014 2018 Environment Unit ENERGY SAVINGS ACTION PLAN 2014 2018 LISA MILLER ENVIRONMENT MANAGER JOHN HAZELTON ENERGY & WATER SUSTAINABILITY PROJECTS ENGINEER FACILITIES MANAGEMENT DIVISION MAY 2014 APPROVED BY:

More information

Queen Margaret Hospital Steam Boiler Replacement

Queen Margaret Hospital Steam Boiler Replacement NHS Fife Estates, Facilities and Capital Services Queen Margaret Hospital Steam Boiler Replacement July 2014 1. Introduction In 2011, NHS Fife submitted an application for funding to the Health Facilities

More information

Capita Symonds Real Estate Sustainability Report 2012 Royal London Asset Management Portfolio

Capita Symonds Real Estate Sustainability Report 2012 Royal London Asset Management Portfolio Capita Symonds Real Estate Sustainability Report 2012 Royal London Asset Management Portfolio Highlights Over 10,000 tonnes CO2 equivalent saved from entering the atmosphere Carbon Saver Gold Standard

More information

Policy No. (EF11) Sustainable Development Management Policy

Policy No. (EF11) Sustainable Development Management Policy Policy No. (EF11) Sustainable Development Management Policy The following personnel have direct roles and responsibilities in the implementation of this policy: All Trust Staff Version: 2 Ratified By:

More information

How To Fund A School

How To Fund A School Schools Energy Efficiency Loans Application Notes 1. The Schools Energy Efficiency Loans Scheme (the Scheme ) The Scheme allows maintained and grant aided schools ( Schools ) to apply for an interest free

More information

Asset Management. Enabling effective estates strategies >

Asset Management. Enabling effective estates strategies > Asset Management Enabling effective estates strategies Enabling effective estates strategies In these challenging times, we help our clients deliver strategies that contribute to the overall performance

More information

Certification Report. Harrow College. All UK Operations including all sites and subsidiaries

Certification Report. Harrow College. All UK Operations including all sites and subsidiaries Certification Report Harrow College All UK Operations including all sites and subsidiaries 20 February 2015 Contents 1. Introduction 2. Assessment Parameters 3. Footprint Measurement and Reduction 4. Carbon

More information

Further Education (FE) Colleges Energy Efficiency Loans Application Notes

Further Education (FE) Colleges Energy Efficiency Loans Application Notes Further Education (FE) Colleges Energy Efficiency Loans Application Notes 1. The Salix Energy Efficiency Loans Scheme (the Scheme ) The Scheme allows FE Colleges to apply for an interest free loan to finance

More information

Environmental sustainability BBC Environment Targets: Performance 2014/15

Environmental sustainability BBC Environment Targets: Performance 2014/15 Environmental sustainability BBC Environment s: Performance 2014/15 BBC Environmental targets The data over the following pages reflects the BBC s continued commitment to reducing environmental impacts

More information

Thames Valley Police Carbon Management Plan 2015-2020

Thames Valley Police Carbon Management Plan 2015-2020 Thames Valley Police Carbon Management Plan 2015-2020 Date: 20 th February 2015 Version number: Owner: Approval route: Approval status: V5 Francis Habgood (Deputy Chief Constable) Business Support Programme

More information

Environmental Performance Report April 2011 March 2012

Environmental Performance Report April 2011 March 2012 Essex County Fire & Rescue Service Our Values: Respect, Accountability, Openness and Involvement Environmental Performance Report April 2011 March 2012 Contents Executive summary...3 Introduction...4 Environmental

More information

Warmer Healthier Homes: A Consultation Paper on a new Fuel Poverty Strategy for Northern Ireland

Warmer Healthier Homes: A Consultation Paper on a new Fuel Poverty Strategy for Northern Ireland Warmer Healthier Homes: A Consultation Paper on a new Fuel Poverty Strategy for Northern Ireland A Response by the Chartered Institute of Housing in Northern Ireland September 2010 The Chartered Institute

More information

Sustainable Supply Chain Policy

Sustainable Supply Chain Policy Sustainable Supply Chain Policy 1. Contents Page 2. Introduction & Purpose 1 3. Definitions 1 4. Benefits of a Sustainable approach to the Supply Chain 2 5. Operational Context 2 6. Elements & Principles

More information

Domestic energy consumption in Barnet has reduced but remains higher than the British average:

Domestic energy consumption in Barnet has reduced but remains higher than the British average: HOME ENERGY EFFICIENCY ACT (HECA) RETURN LB BARNET 31ST MARCH 2013 The following report sets out the energy conservation actions being or proposed to be taken by London Borough of Barnet that it considers

More information

SAINSBURY S GREEN LOAN FRAMEWORK

SAINSBURY S GREEN LOAN FRAMEWORK Under embargo until 00.01 BST on Sunday 20 July 2014 SAINSBURY S GREEN LOAN FRAMEWORK July 2014 Highlights: Innovative Green Loan aligned with the Green Bond Principles Strong alignment of Sainsbury s

More information

Corporate Carbon Neutral Plan

Corporate Carbon Neutral Plan This Carbon Neutral Plan will guide the District of 100 Mile House decision making process in terms of reducing corporate energy consumption and greenhouse gas emissions and in achieving carbon neutrality.

More information

Building a Low-Carbon Economy The UK's Contribution to Tackling Climate Change. www.theccc.org.uk

Building a Low-Carbon Economy The UK's Contribution to Tackling Climate Change. www.theccc.org.uk Building a Low-Carbon Economy The UK's Contribution to Tackling Climate Change www.theccc.org.uk Structure of the presentation 1. The 2050 target 2. The first three budgets 3. Wider social and economic

More information

FIRST ANNOUNCEMENT AND CALL FOR ABSTRACTS. 7th International Conference on Energy Efficiency in Domestic Appliances and Lighting (EEDAL 13)

FIRST ANNOUNCEMENT AND CALL FOR ABSTRACTS. 7th International Conference on Energy Efficiency in Domestic Appliances and Lighting (EEDAL 13) FIRST ANNOUNCEMENT AND CALL FOR ABSTRACTS 7th International Conference on Energy Efficiency in Domestic Appliances and Lighting (EEDAL 13) 11-13 September 2013 Coimbra, Portugal Introduction Citizens and

More information

Combined Heat and Power Central Area

Combined Heat and Power Central Area The University of Edinburgh SEAG Operations Group SEAG Operations Paper 6 4 th May 2011 4th May 2011 Combined Heat and Power Central Area Brief description of the paper This paper describes the current

More information

Cabinet Sub Group - Performance Board

Cabinet Sub Group - Performance Board Cabinet Sub Group - Performance Board Part 1 1 November 2012 Item No 4 Subject Purpose Author Ward Summary Fuel Poverty To provide Performance Board with an outline of what constitutes Fuel Poverty and

More information

Prudential plc. Basis of Reporting: GHG emissions data and other environmental metrics.

Prudential plc. Basis of Reporting: GHG emissions data and other environmental metrics. Prudential plc. Basis of Reporting: GHG emissions data and other environmental metrics. This Basis of Reporting document supports the preparation and reporting of GHG emissions data and other environmental

More information

Proposal for a Demonstration Exemplar at British Sugar, York

Proposal for a Demonstration Exemplar at British Sugar, York Executive 21 July 2009 Report of the Director of City Strategy URBAN ECO SETTLEMENT Proposal for a Demonstration Exemplar at British Sugar, York Summary 1. This paper outlines a proposal for funding a

More information

Energy saving technology to deliver the fastest returns. Top 10 energy saving options

Energy saving technology to deliver the fastest returns. Top 10 energy saving options Energy saving technology to deliver the fastest returns Top 10 energy saving options How can you increase efficiency, reduce costs and cut your carbon emissions? Unstable energy prices, increased costs,

More information

Reporting criteria for selected key performance indicators in the 2014 Responsible Business Report

Reporting criteria for selected key performance indicators in the 2014 Responsible Business Report Reporting criteria for selected key performance indicators in the 2014 Responsible Business Report Introduction This Reporting Criteria document details the approach and scope applied to key environmental

More information

COFELY DISTRICT ENERGY DELIVERING LOW CARBON SUSTAINABLE ENERGY SOLUTIONS

COFELY DISTRICT ENERGY DELIVERING LOW CARBON SUSTAINABLE ENERGY SOLUTIONS COFELY DISTRICT ENERGY DELIVERING LOW CARBON SUSTAINABLE ENERGY SOLUTIONS UK s largest provider of Direct Energy schemes COFELY District Energy is the UK s largest district energy company serving users

More information

SUSTAINABILITY CHARTER. May 2012. 1 R&CA Sustainability Charter V1

SUSTAINABILITY CHARTER. May 2012. 1 R&CA Sustainability Charter V1 SUSTAINABILITY CHARTER May 2012 1 R&CA Sustainability Charter V1 Introduction By their very nature, restaurant and catering businesses are significant users of energy, water and raw materials. Cooking

More information

The economic scale of community and locally owned renewable energy in Scotland and projections to 2020

The economic scale of community and locally owned renewable energy in Scotland and projections to 2020 The economic scale of community and locally owned renewable energy in Scotland and projections to 2020 1. Key Points Grant Allan, Fraser of Allander Institute, University of Strathclyde and ClimateXChange

More information

Drives and motors. A guide to using variable speed drives and motors in data centres Meeting your Carbon Reduction Commitment (CRC)

Drives and motors. A guide to using variable speed drives and motors in data centres Meeting your Carbon Reduction Commitment (CRC) Drives and motors A guide to using variable speed drives and motors in data centres Meeting your Carbon Reduction Commitment (CRC) The power behind the data Private and public businesses, from banks to

More information

Water Efficiency Self-Assessment Guide from

Water Efficiency Self-Assessment Guide from Water Efficiency Self-Assessment Guide from 1 Water Efficiency Self-Assessment Guide from Anglian Water Introduction More than 97% of the water in the world is too salty to drink, 2% is locked in glaciers

More information

carbon neutral update April 2008

carbon neutral update April 2008 carbon neutral update April 2008 With almost 25,000 employees and around 1,000 buildings within Australia, NAB s carbon footprint is substantial. Most of our direct environmental impacts result from the

More information

ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement

ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement ECO Stars Fleet Recognition Scheme Improving Local Air Quality Through Operator Engagement Mark Cavers, Transport & Travel Research Ltd and Ann Beddoes, Barnsley Metropolitan Borough Council mark.cavers@ttr-ltd.com

More information

1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the draft 2015/16 2019/20 Revenue Financial Plan.

1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the draft 2015/16 2019/20 Revenue Financial Plan. ITEM NO. 11(a) 2015/1 201/20 REVENUE FINANCIAL PLAN Report by the Chief Financial Officer SCOTTISH BORDERS COUNCIL 18 December 2014 1 PURPOSE AND SUMMARY 1.1 This report seeks approval to consult on the

More information

Towards a Schools Carbon Management Plan Evidence and assumptions informing consultation on a schools carbon management plan June 2009

Towards a Schools Carbon Management Plan Evidence and assumptions informing consultation on a schools carbon management plan June 2009 Towards a Schools Carbon Management Plan Evidence and assumptions informing consultation on a schools carbon management plan June 2009 Contents Introduction... 3 Section A: Carbon emissions from schools

More information

Table of Contents. January 2013

Table of Contents. January 2013 Champlain College Green Revolving Fund January 2013 Table of Contents Champlain College Green Revolving Fund Charter...2 Mission...2 Goals...2 Management...2 Green Community Fund Provision...3 Loan Disbursement

More information

Formulating an energy management action plan

Formulating an energy management action plan Formulating an energy management action plan Eskom Energy Management Information Pack: Brochure 1 Index Formulating an energy management action plan 1 Structuring an energy management action plan Sample:

More information

Energy Efficiency and Renewable Energy For Schools

Energy Efficiency and Renewable Energy For Schools Energy Efficiency and Renewable Energy For Schools Jesse Putzel & David Pitcher (energy conservation and solar centre) ecsc - who we are Environmental Charity involved in both energy efficiency and renewable

More information

NECAQ Sustainability Program The Business Case

NECAQ Sustainability Program The Business Case NECAQ Sustainability Program The Business Case Key messages Energy efficiency is a fundamental element in the progression towards a future low-carbon economy. Actions to increase energy efficiency can

More information

PRUPIM. Interim Sustainability Report 2007

PRUPIM. Interim Sustainability Report 2007 Executive summary PRUPIM Interim Sustainability Report 2007 Welcome to the Executive Summary of our 2007 Interim Sustainability Report, which provides an overview of PRUPIM s sustainability performance

More information

We help businesses utilise the benefits of solar energy to reduce electricity costs. For Free.

We help businesses utilise the benefits of solar energy to reduce electricity costs. For Free. HARNESS Helping businesses benefit from solar energy to reduce electricity costs. For Free. We help businesses utilise the benefits of solar energy to reduce electricity costs. For Free. REI funds, develops,

More information

Corporate Energy Conservation and Demand Management Plan 2014. Engineering Department. Public Works Division

Corporate Energy Conservation and Demand Management Plan 2014. Engineering Department. Public Works Division Engineering Department Public Works Division August 14 th, 2014 Table of Contents 1.0 Current State of Corporate Energy Management... 3 1.1 Energy Data Management... 3 1.2 Energy Supply Management... 3

More information

TOWN OF CARRBORO NORTH CAROLINA

TOWN OF CARRBORO NORTH CAROLINA TOWN OF CARRBORO NORTH CAROLINA TRANSMITTAL PLANNING DEPARTMENT DELIVERED VIA: HAND MAIL FAX EMAIL To: From: Board of Aldermen David Andrews, Town Manager Department Directors Chris Lazinski, Consultant

More information

COUNTY OF PETERBOROUGH - ENERGY MANAGEMENT PLAN TEMPLATE

COUNTY OF PETERBOROUGH - ENERGY MANAGEMENT PLAN TEMPLATE COUNTY OF PETERBOROUGH - ENERGY MANAGEMENT PLAN TEMPLATE Energy management plans can be extremely large, complicated, and expensive. But they don t need to be. In its simplest form, an energy management

More information

Bloomsbury Colleges Environmental Policy Statement

Bloomsbury Colleges Environmental Policy Statement 15 December 2011 P a g e 1 Bloomsbury Colleges Environmental Policy Statement The Bloomsbury Colleges are committed to the responsible use of energy, water and other resources with the aim of minimising

More information

4 Adoption of Asset Management Policy and Strategy

4 Adoption of Asset Management Policy and Strategy 4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are

More information

University of Melbourne Symposium on ICT Sustainability Dan Pointon 25 November 2008

University of Melbourne Symposium on ICT Sustainability Dan Pointon 25 November 2008 University of Melbourne Symposium on ICT Sustainability Dan Pointon 25 November 2008 Contents Welcome and Introduction Chapter 1: Data centre energy recap Chapter 2: Co-generation Chapter 3: CTC case study

More information

Land East of Clitheroe Road Renewable Energy Statement

Land East of Clitheroe Road Renewable Energy Statement Land East of Clitheroe Road Renewable Energy Statement Commercial Estates Group 6th December 2010 WSP Document Reference Renewable Energy Assessment QM Issue/revision Issue 1 Revision 1 Revision 2 Revision

More information

Sustainable Development Strategy

Sustainable Development Strategy Sustainable Development Strategy Our vision and strategy: A railway fit for the future 2013 2024 Document Ref: SBPT204 Version 0.71 Executive summary Network Rail exists to generate outstanding value for

More information

Our Customer Charter.

Our Customer Charter. Our Customer Charter. www.lokaenergy.com Introduction Our commitment to provide the highest standards of customer service and understand the diverse needs of all our customers. Welcome to Loka We provide

More information

Carbon Management Programme Review. Summary

Carbon Management Programme Review. Summary Carbon Management Programme Review Summary London Borough of Hammersmith & Fulham Dated: 20-12-2013 Page 1 of 7 Prepared for: Dr. Vassia Paloumbi Job Title: Carbon Reduction Manager Telephone#: (0) 20

More information

Sustainable Schools 2009. Renewable Energy Technologies. Andrew Lyle RD Energy Solutions

Sustainable Schools 2009. Renewable Energy Technologies. Andrew Lyle RD Energy Solutions Sustainable Schools 2009 Renewable Energy Technologies Andrew Lyle RD Energy Solutions RD Energy Solutions Energy efficiency and renewable energy consultancy Project management of installations Maintenance

More information

University of the Arts London. Carbon Management Plan

University of the Arts London. Carbon Management Plan University of the Arts London Carbon Management Plan Date: February2014 Version number: 5 Owner: Ian Lane Approver: Steve Howe Contents Foreword 3 Management Summary 4 1. Introduction 9 2. Carbon Management

More information

The University of Manchester. Environmental Sustainability Plan to 2015. January 2013

The University of Manchester. Environmental Sustainability Plan to 2015. January 2013 The University of Manchester Environmental Sustainability Plan to 2015 January 2013 Document control box Title: Environmental Sustainable Plan 2012 2015 Date approved: 9 th April 2013 Approving body: Implementation

More information

People Strategy 2013/17

People Strategy 2013/17 D a t a L a b e l : P U B L I C West Lothian Council People Strategy 2013/17 Contents 1 Overview 2 2 Council Priorities 8 3 Strategy Outcomes 10 1 Engaging and motivating our employees 13 2 Recognised

More information

ANNUAL ENVIRONMENTAL REPORT 2009

ANNUAL ENVIRONMENTAL REPORT 2009 ANNUAL ENVIRONMENTAL REPORT 2009 Index Executive summary 3 Our approach 5 Energy 7 Travel 8 Waste 9 Water 11 Governance 12 Appendix 13 2 Executive summary St. James s Place has reduced its normalised carbon

More information

University of Brighton Sustainable Procurement Strategy 2011-2015

University of Brighton Sustainable Procurement Strategy 2011-2015 University of Brighton Sustainable Procurement Strategy 2011-2015 Sustainable procurement in a challenging environment Introduction There is widespread recognition that climate change and the use of dwindling

More information

Electricity Market Reform:

Electricity Market Reform: Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001

More information