Review of Shared Services Canada s Collaborative Procurement Process
|
|
|
- Prosper McLaughlin
- 10 years ago
- Views:
Transcription
1 Review of Shared Services Canada s Collaborative Procurement Process Presentation to the Information Technology Infrastructure Roundtable May 2015 Yves Genest, Chief Audit and Evaluation Executive Office of Audit and Evaluation
2 Agenda Overview of the Review Overview of the Collaborative Procurement Process (CPP) Summary of Findings: Interviews with Information Technology Infrastructure Roundtable (ITIR) members CPP file review CPP vendor feedback Literature review Conclusions Appendix 2
3 Overview of the Review Objective of the review: To identify opportunities for improvement Examination phase: December 2014 to March 2015 Methodologies employed: Interviews with ITIR members File review of CPP projects Analysis of vendor feedback Literature review [Additional details on these methodologies, as well as the review limitations and mitigation strategies, are provided in the Appendix.] Not an audit or evaluation 3
4 Overview of the Collaborative Procurement Process Developed at Shared Services Canada (SSC), building on Public Works and Government Services Canada s (PWGSC) National Shipbuilding Procurement Strategy and used for SSC s complex procurement projects. Refined by initial consultations with the information and communications technologies (ICT) sector (2011 to 2012). Aligned with SSC s vision to support value for money by closer collaboration and ongoing discussion with the ICT sector. Characterized by: engagement with industry early in the procurement process (pre- Requests for Proposal, or RFP) to co-develop requirements; generally shorter timeframes for the procurement process (from launch to contract award). 4
5 Overview of the Collaborative Procurement Process (Continued) The chronology of the typical CPP: 5
6 Summary: Interviews with Information Technology Infrastructure Roundtable members Key Themes: Engagement with Vendors SSC Capacity Innovation Small- and Medium-sized Enterprises Suggested Best Practices 6
7 Summary: Interviews with Information Technology Infrastructure Roundtable members (Continued) Engagement with Vendors: Overall, the CPP is viewed positively and as an improvement in engagement with vendors, compared to the traditional procurement approach. One-on-one meetings are viewed as the CPP s most helpful vendor engagement mechanism. Industry Days and Requests for Information are perceived more as platforms for SSC announcements. ITIR members indicated that there is no feedback on vendors input provided throughout CPP phases. A few ITIR members noted that the vendor community could better align with SSC s needs by having greater access to relevant SSC planning documents. 7
8 Summary: Interviews with Information Technology Infrastructure Roundtable members (Continued) SSC Capacity: ITIR members recommended that SSC increase its participation at innovation and trade events. Some members recommended keeping and developing leadingedge expertise in-house to drive procurements. ITIR members would like to see SSC explore opportunities to leverage the existing procurement capacity of other governments / departments and vendors (possibly through partnerships with them). SSC s procurement model is viewed as conservative, rigid and risk averse (as is the case with government procurement generally). 8
9 Summary: Interviews with Information Technology Infrastructure Roundtable members (Continued) Innovation: Innovation procurement was recognized as a challenge for SSC and the CPP. There are programs that test innovative technologies within government (PWGSC s Build in Canada Innovation Program). However, none are available to procure innovative services and products. As a way to support innovation, SSC could incorporate requirements for innovation in RFPs. Other opportunities could involve an innovation testing program within SSC, which could: serve as a test bed for potential CPPs prior to their launch; and focus on end-state business requirements. 9
10 Summary: Interviews with Information Technology Infrastructure Roundtable members (Continued) Small- and Medium-sized Enterprises (SME): SMEs make up an important part of the ICT sector in Canada. SMEs in Canada have demonstrated the capacity to innovate in various areas related to IT. SSC would benefit: by fostering more integration of SMEs in its procurements; and through a wider distribution of risk across project components. This could be achieved by: parcelling large procurements into integrated and layered components; and including clauses encouraging vendors to identify how SMEs will be leveraged. 10
11 Summary: Interviews with Information Technology Infrastructure Roundtable members (Continued) Suggested Best Practices: Increasing clarity about the end-state requirements for large IT procurements and possibly breaking down procurement into manageable pieces. Focusing on the overall value and merit as opposed to lowest cost. Favouring low bids does not always result in lower costs, as low bids may be a reflection of the amount of risk a vendor is willing to take. Vendors may recoup funds through other means, such as managing change orders. Incorporating proven innovative procurement solutions in other jurisdictions (provincial, U.S. government), including: set-asides for innovation pilots and SMEs; the provision of seed money to vendors for bid preparation; and the inclusion of a proof-of-solution stage prior to contract award. Measuring and reporting on procurement results. 11
12 Summary: File Review The Office of Audit and Evaluation (OAE) obtained files from SSC Procurement. Selected six CPP projects that had advanced the furthest through CPP phases. Reviewed files against Gartner s best practices. Results validated with procurement officers. CPP Project Transformation Initiative Data Centre Consolidation Services GCNet Wide Area Network (WAN) Services High-performance Computing Renewal Services Data Centre Server Storage Infrastructure Hosted Contact Centre Services Status Awarded / Implementation Awarded / Implementation Awarded RFP RFP RFP 12
13 Summary: File Review (Continued) The CPP has evolved and adapted across projects. There is variability in how CPPs are designed and managed, which reflects the flexibility and adaptability of the procurement process in relation to vendor feedback and project requirements over time. There is also variability in bid assessment/evaluation approaches (e.g. 80/20 versus 10/90 split between financial and technical criteria across CPP projects). Evaluation criteria and their weighting methodology in CPP projects are very complex. 13
14 Summary: Vendor Feedback on File Overall, vendors felt that CPP projects followed procurement steps. Some vendors noted that one-on-one meetings were effective. SSC can make improvements in notifying vendors of changes made to documents, as well as in making announcements to vendors in a timely manner. Most vendors expressed concerns about the heavy weighting on the financial components of the evaluation criteria, versus the technical components. They also had concerns about the financial evaluation methodology itself. Some vendors noted that the process was long and costly. However, they also commented on the insufficient time allocated, at certain stages in the process, to provide feedback to SSC and prepare proposals. 14
15 Summary: Literature Review Early engagement with vendors provides significant opportunities for collaboration and supports value-for-money procurements. Complex and unique solution procurements benefit from weighting technical components over financial components and an initial test to proof solution and cost. A fixed-price or price-cap approach tends to favour value for money and provides vendors with opportunities for innovation. Parcelling of large procurements into integrated components allows for more effective risk management. In this approach, the use of a contract manager has demonstrated positive outcomes. Open and flexible procurement solutions are required to support innovation and SMEs. Clear governance, ownership and accountability of procurement processes and reporting on value achieved ensure a fair, open and transparent procurement. 15
16 Conclusions: Do you agree? Overall, the CPP is viewed as a step in the right direction to promote effective collaboration with industry. The process is seen as open and inclusive. Enhancing reciprocity and communication in the relationship was identified by ITIR members and vendors as an area for improvement. The CPP s potential was perceived as not being fully realized in past CPP projects because the collaborative aspect in defining RFP requirements with the prospective vendors was, ultimately, secondary to the role played by the financial assessments of the bids. Among the suggestions for strengthening procurement capacity were: participation in industry and innovation forums, leveraging external capacity, supporting innovation, including a proof-of-solution stage in the procurement process, and focusing on best value. 16
17 Appendix: Review Methodology Methodologies employed by the OAE: Interviews with past and current, internal and external ITIR members (n=11); File review of SSC projects that have used CPP* (n=6); Analysis of vendor feedback provided in post-award debriefs and post-rrr surveys that were available on file (n=7); Literature review to identify best practices in procurement. The OAE did not conduct interviews with the CPP projects technical and procurement authorities. Meetings with procurement staff were held to validate file-review observations. *Projects that had advanced the furthest through CPP phases were selected. 17
18 Review Limitations and Mitigation Strategies Limitation CPP is a new and continually evolving process. The small number of CPP projects and the uniqueness of each CPP made comparison and generalization across projects difficult. Each ITIR member represents a different group of the ICT sector and has a different experience with CPP, bringing a unique perspective. Some ITIR members shared not only personal opinions, but also feedback received from vendors or industry associations. Some vendors chose not to provide feedback to SSC. Some vendor feedback available on file was consolidated by SSC Procurement rather than documented verbatim. Mitigation Strategy Results were analyzed for highlevel themes, which were corroborated across all methodologies for consistency. Comments were grouped into broad themes (e.g. vendor engagement, innovation) and were reported as summaries. Secondary references (i.e. vendor opinion) were identified. All vendor feedback available on file was incorporated into analysis. The OAE may conduct a vendor survey to update the findings of this review in the future. 18
Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change
Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change For Decision Member Champion(s): Cllr A Alford, Corporate - Director:
Vendor Performance Evaluation
Vendor Performance Evaluation Canadian Public Procurement Council Oct. 27-29, 2014 Agenda 1) Objectives and 2) Evaluation 3) Evaluation Templates and 4) Use of Vendor Score 2 13:00 14:00 1 Objectives and
Public Sector Chief Information Officer Council
Report to Public Sector Chief Information Officer Council White Paper on a Pan Canadian Opportunities for Collaboration Project Goal Two Report: Outline and Approach Draft v1.0 Submitted by: Stuart Culbertson
Corporate Procurement Strategy 2014-2017
Strategy 2014-2017 Strategy 2014-2017 Introduction The Brighton & Hove community is distinctive for its strong international flavour and vibrant diversity of cultures. The make-up of the local population,
Office of the Chief Information Officer
Office of the Chief Information Officer Business Plan: 2012 2015 Department / Ministère: Executive Council Date: November 15, 2012 1 P a g e This Page Left Intentionally Blank 2 P a g e Contents The Business
Transformation Initiatives: Status Update
Transformation Initiatives: Status Update Presentation to the Information Technology Infrastructure Roundtable June 11, 2014 Grant Westcott, Chief Operating Officer and Vice-Chair, Information Technology
The Open Group Perspective on Public Sector Cloud
The Open Group Perspective on Public Sector Cloud Public Sector Cloud Conference Reston VA, March 19-20 2012 Andras Szakal Chief Architect, IBM Federal Software Group, Distinguished Engineer and Senior
Speaking Notes for. Liseanne Forand. President, Shared Services Canada. At GTEC
Speaking Notes for Liseanne Forand President, Shared Services Canada At GTEC October 20, 2011 1 I d like to start by thanking the GTEC board for giving me the opportunity to talk to you today about the
Delivering Government Services through the Cloud. Ian Osborne, Intellect Director Cloud & Government IT ICT KTN
Delivering Government Services through the Cloud Ian Osborne, Intellect Director Cloud & Government IT ICT KTN Where are we heading? Old World Static Silo Physical Manual Application New World Dynamic
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
Digital government toolkit
Digital Government Strategies: Good Practices Canada: Enterprise IT Governance, Planning, Reporting and Oversight The OECD Council adopted on 15 July 2014 the Recommendation on Digital Government Strategies.
IT Standards & Contract Management
Appendix F IT Standards & Table of Contents Vision of Action... 2 Background... 3 Goals and Objectives... 4 Projects... 5 Metrics and Measures... 6 F IT Standards & Carol Steffanni Director, MDIT Bureau
Integrated Risk Management:
Integrated Risk Management: A Framework for Fraser Health For further information contact: Integrated Risk Management Fraser Health Corporate Office 300, 10334 152A Street Surrey, BC V3R 8T4 Phone: (604)
Colorado Department of Health Care Policy and Financing
Colorado Department of Health Care Policy and Financing Colorado MMIS and Fiscal Agent Operations Services Draft RFP Release Response and Pre-RFP Bidder s Conference Announcement Details Colorado Medicaid
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF FEBRUARY 17, 2015
EXTRACT FROM COUNCIL MEETING MINUTES OF FEBRUARY 17, 2015 Item 3, Report No. 5, of the Finance, Administration and Audit Committee, which was adopted without amendment by the Council of the City of Vaughan
2003 Patricia Ensworth Page 1
1 1 Sample software development project 2 1.1 Start project 3 1.2 Initiation phase 4 1.2.1 Develop project charter 5 1.2.2 Project charter approved 6 1.3 Planning phase 7 1.3.1 Product activities 8 1.3.1.1
Report on Hong Kong SME Cloud Adoption and Security Readiness Survey
Report on Hong Kong SME Cloud Adoption and Security Readiness Survey Collaborated by Internet Society Hong Kong and Cloud Security Alliance (HK & Macau Chapter) Sponsored by Microsoft Hong Kong Jointly
AER reference: 52454; D14/54321 ACCC_09/14_865
Commonwealth of Australia 2014 This work is copyright. In addition to any use permitted under the Copyright Act 1968, all material contained within this work is provided under a Creative Commons Attribution
APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report
Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...
Length of Contract: 2 months (with an option to extend for a further 5 months).
1. Introduction The Joint Workplace Solution (JWS) team will shortly complete the migration of some 2000 users from SharePoint 2007 to 20 and alongside this a programme of developing a series of line-of-business
GOVERNANCE AND MANAGEMENT OF CITY COMPUTER SOFTWARE NEEDS IMPROVEMENT. January 7, 2011
APPENDIX 1 GOVERNANCE AND MANAGEMENT OF CITY COMPUTER SOFTWARE NEEDS IMPROVEMENT January 7, 2011 Auditor General s Office Jeffrey Griffiths, C.A., C.F.E. Auditor General City of Toronto TABLE OF CONTENTS
Critical Steps to Help Small and Mid-Sized Businesses Ensure CRM Success
Critical Steps to Help Small and Mid-Sized Businesses Ensure CRM Success Table of Contents Abstract............................................ 3 CRM Drivers and Benefits............................. 4
Company size matters: Perspectives on IT Governance
www.pwc.com/ca/technology-consulting Company size matters: Perspectives on IT Governance versus large Canadian organizations and IT Governance PwC conducted research for the 4th edition of the IT Governance
Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN
Pendleton Solar Energy Centre COMMUNITY ENGAGEMENT PLAN Large Renewable Procurement (LRP) I PENDLETON SOLAR ENERGY CENTRE 844.553-3336 [email protected] www.pendletonsolar.ca Table of Contents 1.
Data Centre Networks Overview
TELECOMMUNICATIONS TRANSFORMATION PROGRAM Data Centre Networks (DCN) Industry Day Data Centre Networks Overview Michel Fortin Director General, Telecommunications Transformation Program Transformation,
BUSINESS SECTOR STRATEGY:
BUSINESS SECTOR STRATEGY: MEDICAL TECHNOLOGY Created with: MEDEC - CANADA S MEDICAL TECHNOLOGY COMPANIES February 2011 Open for Business is Ontario s initiative to create faster, smarter and streamlined
Division of Human Resources. Strategic Plan For a Culture of Excellence
Division of Human Resources Strategic Plan For a Culture of Excellence TABLE OF CONTENTS INTRODUCTION... 2 DEPARTMENTAL MISSION STATEMENT ALIGNMENT... 4 HUMAN RESOURCES STRATEGIC DIRECTIONS... 5 HR STRATEGIC
GOVERNMENT RESPONSE TO THE CHILD INTERVENTION SYSTEM REVIEW
GOVERNMENT RESPONSE TO THE CHILD INTERVENTION SYSTEM REVIEW October 2010 Closing the Gap Between Vision and Reality: Strengthening Accountability, Adaptability and Continuous Improvement in Alberta s Child
Payment Card Industry Data Security Standard (PCI DSS) v1.2
Payment Card Industry Data Security Standard (PCI DSS) v1.2 Joint LA-ISACA and SFV-IIA Meeting February 19, 2009 Presented by Mike O. Villegas, CISA, CISSP 2009-1- Agenda Introduction to PCI DSS Overview
Audit of Project Management Governance. Audit Report
Audit of Project Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 3 What we examined... 3 Why it is important... 3 What we found... 3 Background... 5 Objective... 6
LONDON BOROUGH OF SOUTHWARK
APPENDIX 1 LONDON BOROUGH OF SOUTHWARK The annual report to the Audit & Governance Committee on Risk and Insurance for 2011/12, and the key corporate risks Presented to the Audit & Governance Committee
Negotiating Vendor Contracts. Key Initiative Overview
Christopher Ambrose Research Vice President This overview provides a high-level description of the Negotiating Vendor Contracts Key Initiative. IT leaders can use this overview to understand how to improve
Cloud Sourcing G-Cloud 5 Framework
Cloud Sourcing G-Cloud 5 Framework Cloud Sourcing Service Definition Document April 2014 Warnford Court, 29 Throgmorton Street, London, EC2N 2AT T: +44 20 7947 4176 Table of contents 1 Cloud Sourcing 3
How To Vote Online And Telephone With An Ipod Or Ipod
P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 11.1.2 Halifax Regional Council November 10, 2015 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Richard Butts, Chief
Confident in our Future, Risk Management Policy Statement and Strategy
Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents
Information Technology Control Framework in the Federal Government Considerations for an Audit Strategy
Information Technology Control Framework in the Federal Government Considerations for an Audit Strategy Presentation to The Institute of Internal Auditors Breakfast Session February 6, 2014 Outline of
integrate 2: Business Process Redesign
Nevada System of Higher Education integrate 2: Business Process Redesign Executive Summary TABLE OF CONTENTS I. BACKGROUND AND OBJECTIVES 2 II. METHODOLOGY AND APPROACH 3 III. PROJECT OUTCOMES 5 IV. MAJOR
Audit of Financial Management Governance. Audit Report
Audit of Financial Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 2 What we examined... 2 Why it is important... 2 What we found... 2 Background... 4 Objective...
Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007
Appendix G: Organizational Change Management Plan DRAFT (Pending approval) April 2007 Table of Contents TABLE OF CONTENTS... 1 INTRODUCTION:... 2 ABT ORGANIZATIONAL CHANGE MANAGEMENT SCOPE... 2 PEOPLESOFT
Corporate Procurement and Supply Services
Corporate Procurement and Supply Services CORPORATE SERVICES Branch Manager: Dan Lajeunesse 16 CORPORATE PROCUREMENT AND SUPPLY SERVICES 2016 2018 BUSINESS PLAN Table of Contents INTRODUCTION Our Branch
Service Alberta BUSINESS PLAN 2010 13
Service Alberta BUSINESS PLAN 2010 13 Service Alberta BUSINESS PLAN 2010-13 ACCOUNTABILITY STATEMENT The business plan for the three years commencing April 1, 2010 was prepared under my direction in accordance
A Privacy Officer s Guide to Providing Enterprise De-Identification Services. Phase I
IT Management Advisory A Privacy Officer s Guide to Providing Enterprise De-Identification Services Ki Consulting has helped several large healthcare organizations to establish de-identification services
NSW Government ICT Governance Framework for Whole of Government Investments
NSW Government ICT Governance Framework for Whole of Government Investments November 2014 CONTENTS 1. Introduction 1 2. Scope and application 2 3. Purpose 2 4. Outcomes 2 5. Governance framework 3 6. Governance
Shared Services Canada and Cloud Computing Architecture Framework Advisory Committee
Shared Services Canada and Cloud Computing Architecture Framework Advisory Committee Transformation, Service Strategy and Design December 17, 2012 Agenda TOPICS PRESENTER(S) 9:00 9:15 Opening Remarks and
Canada School of Public Service 2012-13. Departmental Performance Report
Canada School of Public Service Departmental Performance Report Original version signed by: The Honourable Tony Clement President of the Treasury Board and Minister for the Federal Economic Development
University of Brighton Sustainable Procurement Strategy 2011-2015
University of Brighton Sustainable Procurement Strategy 2011-2015 Sustainable procurement in a challenging environment Introduction There is widespread recognition that climate change and the use of dwindling
Developing Excellence in Leadership, Training and Science
DELTAS Africa Initiative Outline Developing Excellence in Leadership, Training and Science August 2014 Improving School Governance 1 The Wellcome Trust and its partners have launched an initiative with
Auditor General s Office. Governance and Management of City Computer Software Needs Improvement
Auditor General s Office Governance and Management of City Computer Software Needs Improvement Transmittal Report Audit Report Management s Response Jeffrey Griffiths, C.A., C.F.E Auditor General, City
Industry Engagement: Canada s Military Procurement System Canadian Association of Defence and Security Industries (CADSI)
Industry Engagement: Canada s Military Procurement System Canadian Association of Defence and Security Industries (CADSI) On behalf of: Industry Canada, National Defence, and Public Works and Government
Request for Consulting Services For the Preparation of an International Marketing Strategy EXECUTIVE SUMMARY
Request for Consulting Services For the Preparation of an International Marketing Strategy EXECUTIVE SUMMARY The City of Abbotsford, Economic Development Department, is seeking a consultant to develop
OPTIMUS SBR. Optimizing Results with Business Intelligence Governance CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE.
OPTIMUS SBR CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE. Optimizing Results with Business Intelligence Governance This paper investigates the importance of establishing a robust Business Intelligence (BI)
How are companies currently changing their facilities management delivery model...?
Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy
Management of Business Support Service Contracts
The Auditor-General Audit Report No.37 2004 05 Business Support Process Audit Management of Business Support Service Contracts Australian National Audit Office Commonwealth of Australia 2005 ISSN 1036
CLOUD COMPUTING FOR SMALL- AND MEDIUM-SIZED ENTERPRISES:
CLOUD COMPUTING FOR SMALL- AND MEDIUM-SIZED ENTERPRISES: Privacy Responsibilities and Considerations Cloud computing is the delivery of computing services over the Internet, and it offers many potential
Digital Continuity in ICT Services Procurement and Contract Management
Digital Continuity in ICT Services Procurement and Contract Management This guidance relates to: Stage 1: Plan for action Stage 2: Define your digital continuity requirements Stage 3: Assess and manage
The Australian Public Service Big Data Strategy
The Australian Public Service Big Data Strategy Improved understanding through enhanced data-analytics capability AIIA response March 2014 Contact for this submission: Suzanne Roche 39 Torrens St Braddon
Guidance on Framework Agreements
1. Introduction Guidance on Framework Agreements The purpose of this document is to provide guidance to public purchasers on the operation of framework agreements as provided for under current public procurement
CYBER AND IT SECURITY: CLOUD SECURITY FINAL SESSION. Architecture Framework Advisory Committee November 4, 2014
CYBER AND IT SECURITY: CLOUD SECURITY FINAL SESSION Architecture Framework Advisory Committee November 4, 2014 1 Agenda TIME TOPICS PRESENTERS 9:00 9:15 Opening Remarks and Introductions Shirley Ivan,
Project Team Roles Adapted for PAAMCO
Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,
Key Considerations for MANAGING EVALUATIONS
Key Considerations for MANAGING EVALUATIONS Authors: (Brief Reference Guide) Dr. Rita Sonko, Addis Berhanu and Rodwell Shamu Pact South Africa June 2011 1 P age This publication is made possible by the
Fairfax County Listening Project: Strengthening Nonprofits. Community Meeting March 7, 2011
Fairfax County Listening Project: Strengthening Nonprofits Community Meeting March 7, 2011 Discussion Timeline Welcome Presentation of Listening Project Findings Discussion of Project Findings Dialogue
153rd SESSION OF THE EXECUTIVE COMMITTEE
PAN AMERICAN HEALTH ORGANIZATION WORLD HEALTH ORGANIZATION 153rd SESSION OF THE EXECUTIVE COMMITTEE Washington, D.C., USA, 4 October 2013 Provisional Agenda Item 5.2 CE153/5 (Eng.) 30 September 2013 ORIGINAL:
Accountability Report. Department of Internal Services
Accountability Report 2014 2015 Department of Internal Services Table of Contents Accountability Statement... 3 Message from the Minister and Deputy Minister... 4 Financial Results... 5 Measuring Our Performance...
How Cisco IT Improved Strategic Vendor Management
How Cisco IT Improved Strategic Strategic sourcing for vendor management results in flexibility, simplicity, and reduced costs. Cisco IT Case Study / Business Management / : This case study describes the
Cloud Computing. Key Initiative Overview
David W. Cearley Research Vice President and Gartner Fellow This overview provides a high-level description of the Cloud Computing Key Initiative. IT leaders can use this guide to understand what they
2014 Business Plan & Budget
2014 Business Plan & Budget Finance Department Mission Statement To support our internal and external stakeholders in bringing together people, partnerships and possibilities to be financially strong and
Shared Services Defined
Shared Services 101 Shared Services Defined The objective of Shared Services is to optimize the delivery of costeffective, flexible, quality services to all clients. Combines the Best of Both Models: Scale
3.05. Infrastructure Ontario Alternative Financing and Procurement. Chapter 3 Section. Background. Alternative Financing and Procurement
Chapter 3 Section 3.05 Infrastructure Ontario Alternative Financing and Procurement Background Alternative Financing and Procurement Alternative Financing and Procurement (AFP) is the name given to the
EMERGENCY COMMUNICATIONS SERVICE DELIVERY IN BRITISH COLUMBIA
EMERGENCY COMMUNICATIONS SERVICE DELIVERY IN BRITISH COLUMBIA Police Communication Centres and 911 Public Safety Answering Points STRATEGIC VISION SUMMARY OF CONSULTATION COMMENTS JULY 2015 Copyright 2015,
The Eduventures Market Guide to Online Program Management (OPM) Executive Summary
The Eduventures Market Guide to Online Program Management (OPM) Executive Summary TABLE OF CONTENTS Executive Summary...1 About This Report...2 Definition of Online Program Management (OPM)...3 Industry
Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN. CR_2215 Attachment 1
CR_2215 Attachment 1 Financial Services FINANCIAL SERVICES & UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN Acting Branch Manager: Stacey Padbury Table of Contents INTRODUCTION Our
QA Engagement Models. Managed / Integrated Test Center A Case Study
1 QA Engagement Models Managed / Integrated Test Center A Case Study 2 Today s Agenda» Background» Overview of QA Engagement Models MTC & ITC» The Journey to Steady State» Transition Approach» Challenges
Memorandum to the Public Administration Select Committee
Memorandum to the Public Administration Select Committee Government Response to the Public Administration Select Committee s report: Government and IT a recipe for rip-offs : time for a new approach: Further
Reshaping the enterprise for the future of work. Are you ready?
Reshaping the enterprise for the future of work. Are you ready? Reshaping the enterprise for Why Pomeroy? the future of work. Pomeroy is a leading independent provider of comprehensive IT infrastructure
MedIT Strategic Plan. Mission: To support excellence in health education, research, and service with innovative and sustainable technology solutions.
MedIT Strategic Plan 2010 2013 Mission: To support excellence in health education, research, and service with innovative and sustainable technology solutions. The UBC Faculty of Medicine and MedIT work
Payroll Operations and Information Management and Payroll Services Alliance Management Office Annual Report. November 2007
Payroll Operations and Information Management and Payroll Services Alliance Management Office Annual Report November 2007 1. Initiative Overview 2. Status Update 3. Appendix A: Contract Objectives 4. Appendix
ISO20000: What it is and how it relates to ITIL v3
ISO20000: What it is and how it relates to ITIL v3 John DiMaria; Certified Six Sigma BB, HISP BSI Product Manager; ICT (ISMS,ITSM,BCM) Objectives and Agenda To raise awareness, to inform and to enthuse
Office of the Chief Information Officer. Annual Report 2012 13
[Type text] Office of the Chief Information Officer Annual Report 2012 13 This page is intentionally blank Message from the Minister As the Minister Responsible for the Office of the Chief Information
Request for Proposals for Software Development Services. Questions and Answers
Request for Proposals for Software Development Services Questions and Answers Question: What is the open-source license that the NIEM profile will be distributed under and how will the NIEM profile source