ID: Lessons learned in engineering development for Major Projects. CERTIFICATION PAPER FOR CCE/CCC exam.

Size: px
Start display at page:

Download "ID: 58095. Lessons learned in engineering development for Major Projects. CERTIFICATION PAPER FOR CCE/CCC exam."

Transcription

1 ID: Lessons learned in engineering development for Major Projects CERTIFICATION PAPER FOR CCE/CCC exam. May 07,

2 Table of Contents ABSTRACT... 4 INTRODUCTION AND PROBLEM STATEMENT... 5 CRITICALITY OF DETAILED ENGINEERING... 6 HOW MAJOR PROJECTS DIFFER FROM SMALLER PROJECTS?... 6 SCOPE OF THE STUDY... 7 LESSONS LEARNED MAP... 9 FEL (FEED) DEVELOPMENT:... 9 PROJECT EXECUTION: ORGANIZATION CAPABILITY: PROJECT CONTROLS AND ESTIMATING: CONCLUSION

3 List of Tables Table 1: Scope of study... 7 Table 2: PEP content findings Table 3: Phased vs. all at once approach - Pros and Cons Table 4: Procurement and contracting strategy - lessons learned Table 5: Engineering norms sample for estimate validation List of Figures Figure 1: Stage gate process... 5 Figure 2: Factors impacted by detailed engineering... 6 Figure 3: Study: project cost growth... 8 Figure 4: Study - home office cost growth... 8 Figure 5: Lessons learned map... 9 Figure 6: Permitting timeline sample Figure 7: Pending change orders at end of FEED Figure 8: Impact of open scope at the end of FEED Figure 9: FEED - Detail engineering overlap Figure 10: Health and process safety studies road map Figure 11: Phased vs. all at once execution Figure 13: Quality management lessons learned Figure 14: Sample KPI report Figure 15: Engineering / Construction overlap Figure 16: Sample engineering budget development Figure 17: Schedule assurance lessons learned Figure 18: Sample engineering discipline progress report

4 Abstract Over the last ten years, the market has witnessed an increased number of major refinery projects that were executed to meet the market demand and reap the benefits of commercial opportunities. These projects often intended to reposition and expand existing refineries through building new process units and revamping existing ones. This resulted in complex engineering scope requirements and hence execution challenges and significant performance issues. From experience, projects that fail in engineering often end up with construction and field problems, operability issues, start up delays and significant budget and schedule overrun. This paper examines the challenges faced by five major projects during the front-end engineering and design (FEED) phase that led to significant performance issues and deliver a lessons learned map of key areas of interest to best develop and execute the detailed engineering phase. 4

5 Introduction and problem statement The decisions to execute major projects are typically based on the competitive analysis, scope definition and execution planning performed during the FEED stage. The FEED is the most critical stage where its easy to influence the design at a relatively low cost [7]. Unfortunately, projects that are under time constraints often shorten the timing of the FEED stage to meet their respective schedule. The perception is that any open scope and planning deliverables can be finalized after project sanction. However, without the appropriate scope definition, the sanction estimates will not carry the level of confidence needed at this stage. This exposes the project to the risk of major issues in detailed engineering, field construction and eventually start up and commissioning. Most of the owner companies now adopt a stage gate process for the execution of their projects as shown in figure 1. The process emphasize on completing the deliverables at each stage and going through a stringent decision making process before proceeding forward. The process reaches a major decision point at the end of the FEED phase where project sanction (full authorization and funding) is sought. Figure 1: Stage gate process The FEED phase typically focuses on preliminary design and execution planning deliverables that helps the stakeholders understand the process systems capabilities, execution difficulties, schedules and most importantly the economics of the projects. At the end of this stage, the project team will request full authorization to commit to procurement activities and detailed engineering work. The authorization request is typically supported by +/- 20% estimate and appropriate schedule to depict the execution path of the project. It s fair to say then that if the FEED phase is not complete, yet the project is authorized to move forward to detailed engineering, authorization estimates and schedules may have been based on incomplete scope definition. The incomplete scope and poor planning will creep to the detailed engineering phase and cause rework in engineering deliverables produced during the FEED. This will eventually lengthen the detailed engineering and construction phase. This paper examines the challenges faced by five major projects during the FEED that led to significant projects performance issues. Lessons learned map detailing key areas of interest is also presented to help direct the manager s attention to some of the common occurrences during the life the project that often leads to poor performances. The paper is structured as follows: 5

6 I will first address the criticality of the detailed engineering phase. Since the study focuses on the detailed engineering aspect of major projects, I will discuss what characterize major projects and add to their complexity. Using data from the five major projects, I will then construct a lessons learned map and discuss the respective areas of interest. Criticality of detailed engineering Engineering performance will likely affect the parameters listed in Figure 2. To declare a failure in detailed engineering in a specific project will be dependent on cost and schedule overruns, process safety issues and if the unit is not performing according to design specs (operability). The magnitude of cost and schedule overrun and how acceptable they are, is mainly dependent on the stakeholder requirements and analysis of the overall project. It s important to note that a 10% engineering overrun will increase the project cost by 2% (impact of engineering only). Additionally, the greater impact will be due to the extension of the engineering schedule, field rework, delay in construction and start up and operability problems. One must consider the impact this has on the project economics and project feasibility. Is the project still economical with this overrun? These overruns can definitely be avoided! Figure 2: Factors impacted by detailed engineering How major projects differ from smaller projects? The Project s cost is 200MM 1BB - This is however is not a standard May trigger complex environmental and regulatory requirements - The environmental and regulatory requirements may dictate the availability of permit before authorization. In some projects, this may trigger changes in scope. For example, building a new process unit to handle sulfur levels or firing limits. Will stir the labor market (engineering and construction) - Due to their size, these projects will require huge labor pool to execute engineering and constructions. This becomes extremely challenging if different projects are competing for these 6

7 Scope of the study resources which will impact cost and schedule (projects will pay more to acquire these resources). Have longer schedules > 40 months, from alternative selection through start up. Process engineering and OSBL (outside boundary limit) complexity the complexity in the ISBL (inside boundary limit) will drive complexity in the OSBL. Since OSBL engineering often lags ISBL, OSBL estimates are often understated. May require the use of several contractors - This also poses a challenge and requires stringent plan to manage the interface among the various parties. Requires significant owner s organization and financial profile It is extremely important for the projects to have dedicated owner s team to oversee and review the work being executed by the contractors. May be part of a program Major projects are often part of major modernization programs. The execution requires an integrated project management team to manage the changes and scope evolution and assess the impact on other projects within the same program. Lessons learned were based on a study performed on five major projects as outlined in the table below: Project Execution Schedules Project Sanctioned Cost Project Type All Process Units Owner s Companies represented 3 EPCm represented 2 280MM 850MM 3 Greenfield (projects C, D & E) 2 Mix of Revamp, Brownfield & Greenfield (projects A&B) Table 1: Scope of study A series of interviews were conducted by the project team with people on each project. Upon analysis of the project data, it was found that the average cost overrun for these five projects was about 6% and ranged from 4% to 9% as seen in figure 3. This increase is above the project contingency plus management reserves. Projects that consisted of revamp and brownfield scope have typically experienced more cost growth than those of a greenfield type projects. This is not uncommon considering the amount of discovery that could be encountered on site, specifically for 7

8 older process units. This would result in engineering design rework and field delays which can extend the turnaround (TAR) window. 10% 9% 8% 7% 6% 5% 4% 3% 2% 1% 0% Total Project - Cost Growth Mix of Revamp, Brow nfield & Greenfield Greenfield Project A Project B Project C Project D Project E Figure 3: Study: project cost growth Furthermore, the average home office cost growth for these five projects was about 14% and ranged from 11% to 19% as shown in figure 4. It s important to note that projects with highest engineering growth contributed to the highest overall cost growth. 30% 25% 20% 15% 10% 5% 0% Project Definition & Detailed Engineering Cost Growth Project Definition Detailed Engineering Project A Project B Project C Project D Project E Mix Greenfield Figure 4: Study - home office cost growth One may perceive the results as typical cost growth (9% isn t that bad). I believe an acceptable level of overrun, is dependent on the stakeholder requirements, market strategy and conditions. However, when considering the impact of the overrun on the IRR and the economic feasibility of the project, this may present a serious issue. Additionally, if the project was built as part of a program, the impact of the scope change and cost overrun will drive changes downstream on other projects being executed. The 9% overrun becomes multiplied for the overall program. 8

9 Regardless of the magnitude of the overrun and the perception of its adequacy or not, these challenges can be minimized and even avoided by simply following best and recommended practices around project execution and understanding business priorities. I intend to present some of the shortcomings that major projects always experience and how they can be converted into lessons learned to help deliver projects with best in class safety, cost, schedule and operability performance. Lessons learned map The lessons learned on these projects were generated using workshops at close out, a series of questionnaires to the project team and personal interviews. The results were then analyzed and categorized into four different main categories and six sub categories as shown in figure 5. Figure 5: Lessons learned map FEL (FEED) Development: Research in the construction industry has always identified good scope definition as a critical factor in executing a successful project [3,4] Without the appropriate definition, any work that is estimated and planned may not reflect a true picture of what the project is intending to build. The lessons learned generated around this area were focused on the team s understanding of the business priorities, the level of scope definition and the impact of the environmental regulations on 9

10 the scope and schedule. This area also tested the importance of applying the value improvement practices and the outcome they generated. Clear business objectives: it was found that projects personnel didn t believe they had a clear understanding of the business objectives and even when decision criteria s and boundary conditions were set on the project, they were changed multiple times causing the development of more project alternatives. When the business objectives remained unclear after sanction, they triggered major late scope changes which are costly. It was also noted during one of the interviews that economical evaluations of the alternatives didn t consider any inherent specific risks or opportunities within each alternative. A SWOT (strength-weakness-opportunities-threat) workshop would have generated risks or opportunities list to support the financial analysis. This would have also supported minimizing the number of alternatives going into the next stage and hence shorten the FEED duration. Environmental regulations and requirements: During the feed development, some projects didn t identify accurately the impact of permitting and potential environmental regulations on the cost and schedule for each alternative. For example, the change in sulfur specifications would have increased the estimated cost for one project by more than 50 million but was not incorporated until late FEED. This caused not just an increase in the project cost but delayed the schedule as well. Additionally, the early project schedules didn t allow sufficient time for the receipt of permit (sample high level schedule in figure 6). If the permit application from submittal to receipt required two years, this might have rendered some alternatives infeasible. This might also require the team to commit funding before sanction which increases the risks of regret spend in the case the permit was not approved. Project Selection Review Permit Strategy Prepare Permit Application Application Submittal Permit Review & Issuance Project Sanction Year Quarter Figure 6: Permitting timeline sample Soil data and site information: The workshop conducted revealed that soil data and hydrology were not definitive by the end of the FEED stage. As such the test for 10

11 Pending Changes Count % Cost Growth contamination was not done and triggered the involvement of the remediation contractors which extended the project schedule. Furthermore, some of the assumptions around site plan could have been narrowed if several walkthroughs were conducted with the engineering and construction contractor and led by the site operations team. Value improvement practices (VIP): All project team personnel reported pressure from senior management to apply as much VIPs as possible. This would have helped the project in increasing their FEED score when external and internal reviews are conducted. The teams felt however that some VIPs workshops were compressed to the point they lost their true value and noted more benefits could have been attained if only critical and relevant VIPs were conducted. Scope definition and offsite utility requirements: The analysis of the data set as shown in figure 7 depicts that all projects in this study had pending design changes that rolled over to detailed engineering. This might have been a reflection of unclear business objectives but the correlation with the cost overrun was expected Pending Changes End of FEL Det. Eng Cost Grow th Pending Changes Project A Project B Project C Project D Project E 30% 25% 20% 15% 10% 5% 0% Mix Greenfield Figure 7: Pending change orders at end of FEED Projects were allowed to go through to detail engineering knowing too many scope items were still open. This would typically happen because the business would like to maintain some flexibility as the project go through the stage gate process. This need for flexibility resulted in significant project cost and schedule overrun. Figure 8 below supports this argument. The first Gantt chart depicts high level project schedule with a common overlap between engineering and schedule. Typically, 70-80% engineering complete will support the start of construction effort, specifically in site and civil work. 11

12 Figure 8: Impact of open scope at the end of FEED The second Gantt chart depicts a project with open scope items at the end of FEED. Because there is a perception that these open items can be finalized in execute without any impact to the schedule, the project is allowed to go through the stage gate. Once in the execute stage; the project team finds themselves doing the actual FEED work in execute. This typically results in delays in the engineering schedule and eventually delays in the construction schedule and start up. In the third Gantt chart, the team realizes that the engineering schedule is slipping but decides to maintain the construction schedule as is, to finish the project on time. However, maintaining the construction schedule would mean that construction work would start early. This results in major rework when engineering deliverables and issue for construction (IFC) are issued. Some projects overlaps the FEED with detail engineering. While this is typically done to accelerate the schedule, the results are weak engineering products and cost overrun. Figure 8 shows how the overlap undermines the importance of the FEED stage and increases the project s minimum exposure / cancelation costs. Other engineering schedule slippage revolved around underestimating the OSBL scope of the project. Most projects in this set didn t perform any comprehensive OSBL scope studies in the FEED and allowed for a percentage in their estimate. Unfortunately, changes in ISBL costs and schedule drove changes in the OSBL scope, cost and schedule. 12

13 Figure 9: FEED - Detail engineering overlap For health, environmental and process safety studies, the questionnaires identified the criticality of conducting process safety studies early in FEED. This would help ensure that the alternative selection process account for the process safety risks that would be incorporated into the preliminary design for that selected option. Furthermore, hazop (hazard and operability study should be performed on IFD (Issue for design) drawings at the end of FEED to assess any risks/ causes of loss of containment and the existing safe guards and whether they are sufficient. These studies would be eventually be followed by a detailed review on mature and vendor packages P&IDs (Process and instrumentation diagrams) before IFC are issued. The road map outlined below depicts the team s perception of what process safety and health studies need to be completed over the project life cycle. Figure 10: Health and process safety studies road map Project Execution: The success of major projects largely depends on how well the team plan the work and work the plan to achieve the project objectives, while maintaining good cohesion between all aspects of the project [6,10]. The questionnaires and interviews focused next on the project execution plan (PEP) 13

14 developed for each project during the FEED stage. The critical performance indicator here was to ensure that the final PEP addressed all project functions to close out. Additionally, topics such as procurement and contracting, quality management, cashflow constraints and the interface with the plant projects and turnaround process were assessed. Project execution plan: Table 2 finalizes the findings from the different projects in this study regarding the content of the project execution plan. PEP document length Roles and Responsibilities Stage gate review timeline Permitting timeline Interface with the turnaround / shutdown Delegation of authority / Financial authority PEP should be concise and simple and reference the what in the project. The PEP should reference detail plans to address the hows This was an area that caused issues and scope shifts in three of the five projects. The PEP should clearly state the scope areas and responsibility division between the owner and contractor. This should also be part of the estimate assurance review to ensure that the estimate covers all costs. The PEP should include key dates for any reviews needed in the schedule. This will allow internal and external stakeholder to account for these reviews in their schedule. If the project is being done under a joint venture (JV) umbrella, some stakeholders may require thirty to sixty days to make a decision on specific gate. If this is not planned from the outset, schedule delays is expected. As addressed in the previous section, key permitting dates and assumptions should be stated in the PEP. The TAR process in most of the companies may include constraints regarding the review of IFCs, material on site and any other plant reviews. Projects should incorporate these specific milestones in their schedule and state the assumptions clearly in the PEP. Some projects faced serious schedule issues due to change order approval delay. The PEP should include the first line approval authorities and their delegates in the instant critical approvals are sought. Table 2: PEP content findings 14

15 Program / project interface: The survey questioned the considerations that were assessed for each project that was executed within a program. It was realized that in this study set, multiple major projects were executed concurrently within the program which posed various execution challenges. To understand the consequences of this approach, a comparison was made between programs that utilized a phased approach for their execution against projects that were executed concurrently (figure 11). PROJ A PROGRAM A Phased approach PROJ B PROJ C PROJ D PROJ A PROGRAM B all at once PROJ B PROJ C Figure 11: Phased vs. all at once execution PROJ D While the impact affected procurement and construction, the emphasis here was on the FEED and detailed engineering work. Table 3 depicts the advantages and disadvantages of the two approaches. Program B Program A Engineering design Team & knowledge transfer OSBL Labor shortage Team interface Cash flows Risk that changes in design in one project are not incorporated into other projects Possibility of Rework Significant need for large and skilled pool of labor Larger Owner s organization to manage the interface. Heavy annual cash flow is needed. If program becomes cash flow constrained, problem is magnified. Potential Project team continuity/learning curve benefits Can be negatively impacted by inefficient construction of infrastructure to support the phased investment. Table 3: Phased vs. all at once approach - Pros and Cons 15

16 Procurement and Contracting Strategy: The lessons learned identified in the survey are summarized in table 4 for procurement and contracting: Procurement Contracting Projects must invest some time in FEED (through a contract strategy workshop) investigating an effective form of performance or hybrid contracts (mixed strategy contracts) Project controls must participate in shaping the contracting and procurement strategy. This will help set the standard for effective execution and a contract that can be easily controlled Consideration a competitive bid process for FEED and detail engineering if the schedule allows. This would prevent the existing contractor from becoming complacent. Allow sufficient time in the schedule for a contractor change out. If there is a shift in contractors, consider the time and cost it takes for a smooth handover. Ordering equipment during FEED will help set the pace for a faster execution and provide an understanding of the project scope which will drive minimum scope changes. Since minimum exposure is increased now for the project (if cancelled), consider negotiating cancellation terms or pay only for preliminary vendor engineering data to support the preliminary design at the end of FEED Vendor and fabrication shops limited capabilities may add significant time to the schedule. Hence the importance of historical experiences and prequalification assessments in understanding the vendor s performance and impact on schedule. Allow the risk analysis workshop conducted early FEED to reflect the risks of major equipment fabrication and delivery cycle time. Develop a licensor-epc interface plan / clarify roles and responsibilities regarding design package delivery. Table 4: Procurement and contracting strategy - lessons learned Cashflow constraints /Schedule driven projects: Multiple projects in this set had experienced cashflow constraints several times during their life cycle. The cashflow constraints triggered major changes to project execution planning, staffing and caused the loss of key team members. This impact was even multiplied when the project was schedule driven. Team members reported that a thorough analysis of the impact of the cashflow constraint was never conducted by the respective personnel. Surprisingly, the message to senior management was the ability of the project to conform to the cashflow constraints and still meet the project schedule. This was demonstrated by the team going through the FEL 2 and FEL 3 stages with incomplete deliverables because the funds were not available. The incomplete FEED 16

17 work was thought to be non-critical because deliverables would be finalized in execute. The results were deliverables rework, inconclusive scope and major execute stage delays. Quality management: A quality management system (QMS) provides the basis to develop and deliver quality requirements by integrating quality management processes into the design, procurement, construction and handover activities. The study conducted on the five projects revealed areas that were not incorporated as part of the PEP, or didn t work according to plan. The areas are highlighted in figure 12 in the context of the standard quality management processes; 1) quality planning, 2) quality assurance, 3) quality controls and 4) quality improvements. Figure 12: Quality management lessons learned Main findings as noted by the core teams in these projects were around having ambiguous roles and responsibilities, the lack of a clear interface plan with the contractors and suppliers and lack of standard tools to measure key performance indicators on the projects. Furthermore, the team noted that contractors in three of the projects didn t provide any details on how they would go about self assessing their quality levels, specifically around the design. Typically every discipline would have an activity plan that determines all procedures to be followed. This also would serve as a 17

18 checklist for future quality audits. One contractor did have an activity plan for each discipline but upon review, it was found out that the discipline lead didn t need to comply with all checklist requirements in some areas. This for example should have checked by the owner s lead during the FEED for compliance versus their policy and procedures. The commitment to improvement as viewed by these projects should have been apparent by the team dedication to record all issues and disseminate the information internally and externally as part of a bigger knowledge management effort. Root cause analysis should have been done also to understand reoccurring quality issues. A sample KPI report is shown in figure 13. The KPI report could assesses the number of non conformance reports generated on design versus or number of audits performed versus planned. Figure 13: Sample KPI report Engineering / Construction interface: Engineering typically should not overlap construction by more than 30-40% [1]. This is mainly because if the overlap is larger, 18

19 engineering is still not matured enough to start construction. The early construction efforts will likely trigger rework in the field as engineering deliverables are finalized. Figure 14: Engineering / Construction overlap Organization capability: The criticality of the availability and dedication of resources to the project success are often understated. Project teams often reports that they don t have the resources to provide the necessary oversight on the project. This in turn affects cost and schedule. This area is also overlooked when assessing the capability of the contractors, suppliers and fabricators. The lessons learned recorded from the five projects emphasized the same message. Market conditions and labor shortage: With the execution of more major and mega projects, the market ability to respond to the demand is often constrained by the availability of the resources in both the owner and contractor organization. The project schedule must allow time for the ramp up of the resources. Additionally, the project team must assess carefully the quality of the resources brought on the project during peak time. In three of the projects in this study, project managers responded to schedule delays by bringing in more labor, only to realize the additional labor was not as efficient as they expected. Owner s organization: The owner s team is the backbone to the success of any project. Any deliverables produced on the project will require the owner s team approval before proceeding forward. Projects often underestimate the size of the owner s team and in many cases resources are brought in at partial capacity (resources not fully dedicated to the project). This contributed to the schedule delays in two projects in this study. 19

20 Stakeholder management: The lessons learned recorded in this study suggested that stakeholders might not have been involved enough in the stage gate review and decision making process. Their late involvement caused rework issues and had greater impact on the schedule. Peer review: Peer reviews are always planned on the project for assurance purposes and to capture the peer s experience in executing similar projects. However, due to the wide range of resources needed in the peer review, early planning is needed to secure their attendance at the meeting. Team alignment / retaining: Managers always agree that people is the number one contributor to the project success. Hence, retaining key team resources must be a priority in all projects. This task not only fosters a homogeneous environment within the team, but is critical for knowledge management transfer internally within the project and externally with the business. Project controls and estimating: A successful project controls system will serve as an early alarm system to depict deviation from the project plan and recommend the appropriate actions. A successful system will start with the development of processes and procedures for effective budget and schedule development and the respective monitoring and reporting effort. Key lessons learned identified in this area are shown below. Project controls requirements: Effective project controls starts with strict project controls requirements. The effective planning for project controls should start early in FEED and involve owners and contractor team members. One of the early activities would be in finalizing the project controls calendar for cost and schedule reporting timeline. Additionally: o For projects executed by multiple contractors, standard reporting template would support and accelerate the reporting process. o The contractors physically progressing procedures should be evaluated, understood and audited consistently. o Detailed engineering estimates should be based on discipline hours by drawings and should directly link to the engineering schedule. o A rigorous change management program should be implemented early in the process. Potential changes should be identified regardless of the team s conception of their relevance and size. o A cost risk analysis must also reflect the changes and risks identified in the schedule. Schedules and estimates can t be divorced. Budget development: An effective way to develop engineering budgets is to prepare a deliverable based cost estimate by determining at the discipline level, the amount of hours needed by drawings, allowing for supervision hours, recycling and revisions. The hours generated by discipline are then reflected in the detailed engineering schedule and resource leveling occurs to ensure a feasible schedule. The resource loaded schedule generates the resource histograms and man-hours curves. A sample engineering budget template for mechanical engineering is shown in figure

21 Figure 15: Sample engineering budget development Schedule assurance: There are many papers that identified excellent techniques for evaluating and assessing the quality of the schedules [1,2]. Schedule assurance activities may depict areas of concerns in the native file, the basis of schedule or quantitatively through benchmarking with industry projects. This is shown in figure 16. SCHEDULE ASSURANCE SCHEDULE SYSTEM VALIDATION QUALITATIVE QUANTITIAVE Review of the native files Constraints Average activity float Resource loading Schedule logic review Excessive lag check Project schedule Progress stated Alignment of the schedule with the business objectives Permitting timeline Contracting strategy Procurement long lead items Cashflow assumptions Critical path Risk analysis Design model reviews timeline High level project duration comparisons against similar industry projects Other metrics check Drawings IFCs to installation Figure 16: Schedule assurance lessons learned 21

22 Estimate validation: Current trends in cost estimation of major projects are driving owners to emphasize on the importance of producing reliable and accurate estimates to avoid any potential overruns [5,8,11].The estimate validation process in general should assess alignment of the estimate with the schedule and execution plans. Additionally, quantitative analysis could address engineering norms such as: Engineering norms Detailed engineering costs as a % of Total costs, field or equipment costs. Engineering hours per drawing type. Engineering hours per construction quantities. Engineering labor rate / use of international offices. Isometric drawings per piece of equipment. Construction quantities per piece of equipment. Staffing plan analysis in comparison to the schedule. Table 5: Engineering norms sample for estimate validation Productivity measurements: This area is concerned by having a detailed physical progressing plan that has been reviewed and agreed on among all parties. One of the key issues that projects experienced in this study was the inconsistent and out of order reporting of physical progress (for example: piping leading process engineering). Figure 17 depicts a sample progress report that could be utilized to verify the contractor s progress: Figure 17: Sample engineering discipline progress report 22

23 Change management: The following are essential for implementing an effective change management program: Changes in scope that impacted the estimates from FEL1 and FEL 2 must be recorded because the trend in estimates from the early feed phases to sanction often catches the stakeholders by surprise [9]. A clear process to accept/ reject a change should be documented and agreed. The team should be encouraged to freeze the design and execution strategy by the end of FEED stage. Methodologies for scope deletion / scope addition change order estimates should be agreed. Project controls audits: The owner s team must always be involved in auditing the contractors processes and procedures, cost and schedule reporting. The audits should be planned per the quality control audit schedules and should be as periodic as needed to assure continuous compliance and improvements. Conclusion This paper presented metrics and analysis on detailed engineering from five major refinery projects. The analysis was married with a study on the lessons learned captured from these projects to demonstrate how certain aspects of the planning and scoping during FEED may have contributed to the cost growth. This study concludes in general that projects that are pushed through a concise FEED stage often end with significant cost overruns and delays. This does not mean that projects should take their time during the FEED, but it means that the scope and planning basis should be complete to enable the projects to move forward with minimal changes. The study revealed that successful projects will have clear business objectives; ambiguous business objectives will often result in major late changes. Additionally, a scope and design basis that is frozen at the end of the FEED stage will help accelerate the schedule and minimize changes in the detailed engineering phase and eventually rework in construction. Projects must spend sufficient time developing a project execution plan that emphasizes a good contracting and procurement strategy and understands the impact of the interface with other projects being executed concurrently. Projects must define the quality control requirements and set the process to periodically evaluate and measure improvements in all aspects of the project. This study also reviewed the impact of the organization capability on the performance of the project. It was concluded that projects must have sufficient and dedicated resources to execute the work and provide adequate oversight. The impact of market conditions on the availability and quality of resources must be taken into consideration during the planning phase of the project. An efficient project controls system will allow for detailed estimate and schedule reviews before a baseline is finalized. The project controls organization must also participate in shaping the contracting strategy in order to support the controlling of the cost and schedule. One area that is found to be typically weak is the assurance about the physical progress reporting system. Owner must review, understand and periodically audit this system for inconsistency or overstatement. 23

24 Bibliography No. Description 1 Amanda M. Madl Downstream Schedule Analysis for NON-Schedulers 2010 AACE INTERNATIONAL TRANSACTIONS 2 Andrew Avalon, PE PSP, and Curtis W. Foster Schedule Quality Assurance Procedures 2010 AACE INTERNATIONAL TRANSACTIONS 3 Construction Industry Institute, Pre-Project Planning Handbook, Special Publication 39-2 Austin, USA Construction Industry Institute, Project Definition Rating Index (PDRI) Implementation Resources, Austin, USA Gregory C. Shirley and Jeremy L. Banks Best Practices for an Independent Review Process for High-Dollar, High-Risk Cost Estimates 2007 AACE INTERNATIONAL TRANSACTIONS 6 Hammad Ud Din Tahir, CCE Effective Planning Techniques for the Execution of an EPC Project Cost Engineering Vol. 46/No. 4 APRIL James D. Whiteside, II PE, and Tyler Humes, Front-End Engineering and Design: Influence over a Project s Outcome Page AACE INTERNATIONAL TRANSACTIONS 8 Larry Dysert et all 2002 The estimate review and validation process AACE Cost Journal 9 Mr. Vijay S. Jambhekar and Mr. Stephen D. Weeks Change Management During FEED an Owner's Case Study 2008 AACE INTERNATIONAL TRANSACTIONS 10 Richard A. Selg, CCE and David Richard Rihel Successfully Managing One-Of-A-Kind Projects 2007 AACE INTERNATIONAL TRANSACTIONS 24

25 11 W. Doug Creech 2003 Owner s Validation of Contractor s prepared estimates AACE Cost Journal 25

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Acompany that consistently selects the right projects and

Acompany that consistently selects the right projects and PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

Cash flow is the life line of a business. Many start-up

Cash flow is the life line of a business. Many start-up PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

IAG EFFECTIVE SCOPE MANAGEMENT THROUGH MULTI-LEVEL CLIENT ENGAGEMENT

IAG EFFECTIVE SCOPE MANAGEMENT THROUGH MULTI-LEVEL CLIENT ENGAGEMENT Your Trusted Partner for Technology Driven Energy Projects IAG EFFECTIVE SCOPE MANAGEMENT THROUGH MULTI-LEVEL CLIENT ENGAGEMENT International Alliance Group IAG is an international program management organization

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE

Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.

More information

NFSA Project Management Guidelines

NFSA Project Management Guidelines NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

AACE International Recommended Practice No. 18R 97

AACE International Recommended Practice No. 18R 97 AACE International Recommended Practice No. 18R 97 COST ESTIMATE CLASSIFICATION SYSTEM AS APPLIED IN ENGINEERING, PROCUREMENT, AND CONSTRUCTION FOR THE PROCESS INDUSTRIES TCM Framework: 7.3 Cost Estimating

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002 DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009

More information

How to successfully manage your mega-project

How to successfully manage your mega-project BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

Saving Troubled Projects

Saving Troubled Projects Saving Troubled Projects 2012 Instructor and Developer Mark Waldof Mark Waldof Consulting Retired Lockheed Martin University of Minnesota Instructor CCE Business Improvements Consultant Project Management

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Project Time Management an essential element to project success

Project Time Management an essential element to project success Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects

More information

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500 Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: office@sts.ch Phone:

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information

AACE International Recommended Practices

AACE International Recommended Practices AACE International Recommended Practice No. 18R-97 COST ESTIMATE CLASSIFICATION SYSTEM AS APPLIED IN ENGINEERING, PROCUREMENT, AND CONSTRUCTION FOR THE PROCESS INDUSTRIES TCM Framework: 7.3 Cost Estimating

More information

PMP Project Management Professional Study Guide, Third Edition

PMP Project Management Professional Study Guide, Third Edition PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management

More information

Plug IT In 5 Project management

Plug IT In 5 Project management Plug IT In 5 Project management PLUG IT IN OUTLINE PI5.1 Project management for information systems projects PI5.2 The project management process PI5.3 The project management body of knowledge LEARNING

More information

IMPROVING CONTRACT MANAGEMENT BY END USERS

IMPROVING CONTRACT MANAGEMENT BY END USERS IMPROVING CONTRACT MANAGEMENT BY END USERS Claudia Mara Dias Wilson, Ph.D. Carlos A. Ulibarri, Ph.D. New Mexico Institute of Mining and Technology A Research Project Sponsored by New Mexico Department

More information

ICT Project Management

ICT Project Management THE UNITED REPUBLIC OF TANZANIA PRESIDENT S OFFICE PUBLIC SERVICE MANAGEMENT ICT Project Management A Step-by-step Guidebook for Managing ICT Projects and Risks Version 1.0 Date Release 04 Jan 2010 Contact

More information

How to successfully manage your mega-project

How to successfully manage your mega-project How to successfully manage your mega-project Part I Early planning and organizing for success kpmg.com 2 Building, Construction & Real Estate How to successfully manage your mega-project A three-part series

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

SOFTWARE PROJECT MANAGEMENT

SOFTWARE PROJECT MANAGEMENT SOFTWARE PROJECT MANAGEMENT http://www.tutorialspoint.com/software_engineering/software_project_management.htm Copyright tutorialspoint.com The job pattern of an IT company engaged in software development

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

Frequently Asked Questions in Project Management

Frequently Asked Questions in Project Management Frequently Asked Questions in Project Management 1. Question: What is Project Management? Answer: Project Management is the collection and application of skills, knowledge, processes, and activities to

More information

Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects)

Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects) Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects) Process and Tools that Enable Project Teams to Achieve World-Class Performance and thereby Improve

More information

Project Delivery Process Overview

Project Delivery Process Overview New Jersey Department of Transportation Project Delivery Process Overview Presented by the Program Management Office January, 2012 Project Delivery Process Overview The New Jersey Department of Transportation

More information

Managing Successful Software Development Projects Mike Thibado 12/28/05

Managing Successful Software Development Projects Mike Thibado 12/28/05 Managing Successful Software Development Projects Mike Thibado 12/28/05 Copyright 2006, Ambient Consulting Table of Contents EXECUTIVE OVERVIEW...3 STATEMENT OF WORK DOCUMENT...4 REQUIREMENTS CHANGE PROCEDURE...5

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

Fundamentals of Measurements

Fundamentals of Measurements Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

(Refer Slide Time: 01:52)

(Refer Slide Time: 01:52) Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This

More information

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry

Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry By: Arash Shahi Senior Product Manager, Coreworx 519-772-3181 Contents Executive Summary 3 Background 4

More information

connected excellence in all we do Turnaround Management

connected excellence in all we do Turnaround Management connected excellence in all we do Turnaround Management Turnaround Delivery Team Function and Responsibility Purpose of the function is to facilitate effective turnarounds by maximising work done during

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

This alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed by the IIBA.

This alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed by the IIBA. Red River College Course Learning Outcome Alignment with BABOK Version 2 This alignment chart was designed specifically for the use of Red River College. These alignments have not been verified or endorsed

More information

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.

More information

Certificate In Project Management (CIPM)

Certificate In Project Management (CIPM) Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Certificate In Project Management (CIPM) Course Overview The Certificate

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY 1. Preamble: Rail Vikas Nigam Ltd (RVNL) is a Public Sector Undertaking specializing in development and execution of railway projects. In the course of its operations, it is prone

More information

PROJECT AUDIT METHODOLOGY

PROJECT AUDIT METHODOLOGY PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 This three-day, instructor-led course is intended for individuals who are interested in expanding their knowledge base and technical skills about Microsoft Project. The course begins with the basic concepts

More information

Risk Review Process Basics

Risk Review Process Basics 2011 PMOC Annual Meeting FEDERAL TRANSIT ADMINISTRATION Risk Review Process Basics Michael P. Wetherell, PE - Urban Engineers David N. Sillars, PE Sillars Consulting FEDERAL TRANSIT ADMINISTRATION 2011

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

A COMPARISON OF PRINCE2 AGAINST PMBOK

A COMPARISON OF PRINCE2 AGAINST PMBOK Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the

More information

PMO Metrics Recommendations

PMO Metrics Recommendations Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

Module 1 Diploma of Project Management

Module 1 Diploma of Project Management Module 1 Diploma of Project Management Project Management Fundamentals in association with This two day course takes participants through all aspects of Project Management and provides in depth examination

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Project Management Office (PMO)

Project Management Office (PMO) Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project

More information

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software. DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

Guidelines for a PROJECT EXECUTION PLAN

Guidelines for a PROJECT EXECUTION PLAN Guidelines for a PROJECT EXECUTION PLAN 1. OBJECTIVES The objectives of this guideline are: To provide a standard template for Project Execution Plans (PEP); To identify the critical items which need to

More information

The Four Planes of Capital Projects

The Four Planes of Capital Projects The Four Planes of Capital Projects An Integrated Approach to Capital Project Due Diligence August 2009 Westney Consulting Group, Inc. www.westney.com Management by objectives work - if you know the objectives.

More information

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities

More information

Capital Efficiency Keys to Success Dan Morlang

Capital Efficiency Keys to Success Dan Morlang Capital Efficiency Keys to Success Dan Morlang Vice President Capital Projects AP-Networks Agenda 1 Capital Efficiency Background 2 Current State of Projects 3 Addressing Three Industry Themes 4 Wrap-Up

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Dynamic Change Management for Fast-tracking Construction Projects

Dynamic Change Management for Fast-tracking Construction Projects Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations

More information

2014 STAMP Conference MIT Partnership for a Systems Approach to Safety Using STAMP Principles in Risk Management of Large Scale Pipeline Projects

2014 STAMP Conference MIT Partnership for a Systems Approach to Safety Using STAMP Principles in Risk Management of Large Scale Pipeline Projects 2014 STAMP Conference MIT Partnership for a Systems Approach to Safety Using STAMP Principles in Risk Management of Large Scale Pipeline Projects Lorena Pelegrín 27/03/2014 Table of Contents Background

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

Operational Risk Management - The Next Frontier The Risk Management Association (RMA)

Operational Risk Management - The Next Frontier The Risk Management Association (RMA) Operational Risk Management - The Next Frontier The Risk Management Association (RMA) Operational risk is not new. In fact, it is the first risk that banks must manage, even before they make their first

More information

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?... CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Philip R. Moncrief, P.E. Table of Contents 1. INTRODUCTION...

More information

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community

More information

WHITE PAPER APRIL 2012. Leading an Implementation Campaign to Address the Convergence of Healthcare Reform Initiatives

WHITE PAPER APRIL 2012. Leading an Implementation Campaign to Address the Convergence of Healthcare Reform Initiatives WHITE PAPER APRIL 2012 Leading an Implementation Campaign to Address the Convergence of Healthcare Reform Initiatives New healthcare reforms have created an unprecedented impact on hospital systems operations.

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

Project Management Standards: A Review of Certifications/Certificates

Project Management Standards: A Review of Certifications/Certificates Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

How To Develop A Mobile Application Development Cycle

How To Develop A Mobile Application Development Cycle Enterprise Mobile Application Development Lifecycle by Introduction Everyday newer mobile technologies are introduced. Mobile application developers have to keep ahead with the myriad of different mobile

More information

pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage

More information

Assessment of NCTD Program Management Framework for Positive Train Control Program

Assessment of NCTD Program Management Framework for Positive Train Control Program Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation

More information