BRG Look Back Study. November 30, 2015



Similar documents
Project Delivery Methods & Contract Types CSTM 102 Spring 2013

School Construction Projects

The programming, design

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

1.040 Project Management

Operational Parameters. for the. Review and Evaluation of. Construction Management Projects

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS

Owner s project control review Baker Tilly Virchow Krause, LLP

How to get value for money from service providers on major projects

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES

Contract Administration

CONSIDERING GC/CM There are some benefits and risks to using GC/CM. Departments should consider these carefully.

Oregon Public Contracting Coalition Guide to CM/GC Contracting

Puget Sound Emergency Radio Network: Project Schedule and Cost Risks

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS

Project Procurement Management

OVERALL RATING: PARTIALLY SATISFACTORY

Construction Management/ General Contractor Alternative Contracting Process

PROJECT PROCUREMENT MANAGEMENT

AN OWNER'S GUIDE TO CONSTRUCTION AND PROGRAM MANAGEMENT. Enabling Project Success Under Any Delivery Method

REPORT 2014/078 INTERNAL AUDIT DIVISION

6.0 Procurement procedure 1 Infrastructure

Bodily Injury Thematic Review

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

STATE OF NEW HAMPSHIRE 2013-EG-03 REQUEST FOR PROPOSALS PLAN MANAGEMENT CONSULTANTS

Construction Delivery Methods for Texas school districts

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Seattle Public Schools The Office of Internal Audit

Procurement Strategy and Contract Selection

Job Description. Supply Chain Development Manager

City of Portland Job Code: CLASS SPECIFICATION Senior Labor Relations Analyst

INSE 6230 Total Quality Project Management

PMO Director. PMO Director

C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods

Appendix 18 NEC3 Options

Project Risk Identification. IH 635 Managed Lanes Project Exhibit A to Project Development Plan 1

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES)

OVERSIGHT OF CAPITAL PROJECT PLANNING & PROCUREMENT

Analysis Item 65: Department of Revenue Property Valuation System

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

REQUEST FOR STATEMENT OF INTEREST AND QUALIFICATIONS (SOIQ) FOR ARCHITECTURAL SERVICES Provo City School District

Risk Management in the Development of a Penta-P Project

UNECE PPP Healthcare Standard

Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011)

REQUEST FOR PROPOSAL

RELOCATION ASSISTANCE SERVICES SPECIFICATIONS (LUMP SUM)

Request for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School

PHASE 3: PLANNING PHASE

IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011

Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,

Contract No. E22PS02. PROJECT CONFIGURATION MANAGEMENT PLAN (CMP) for PRELIMINARY ENGINEERING AND DESIGN/BUILD PROCUREMENT

REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT

RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT. Cincinnati Streetcar Project June 2015

Town of Montreat Buncombe County, North Carolina

Infrastructure Procurement Options Guide

PHASE 3: PLANNING PHASE

Advantages and Disadvantages of Staffing Models

Any business relationship between a bank and another entity, by contract or otherwise

REQUEST FOR PROPOSAL SPECTATOR FACILITY FEASIBILITY STUDY ADDENDUM NO. 1

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES

BLUEPRINT PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS CONSTRUCTION PRACTICE

Part E: Contract management

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects

September 2005 Report No

Project Procurement Management

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

PRO-NET A Publication of Building Professional Development Partnerships for Adult Educators Project. April 2002

WHITE PAPER DEVELOPING A SUCCESSFUL WEBSITE RFP. Find the Right Web Development Partner through an Engaging and Informative RFP.

STATE OF MAINE DEPARTMENT OF EDUCATION RFP # PAYROLL SERVICES FOR TEMPORARY RESOURCES

Tel: (617) Fax: (617) OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2

OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.

Final Audit Report. Audit of the Human Resources Management Information System. December Canada

Request for Qualifications & Proposal. Architectural Team. Lake County School District R-1. On-Call Services. For

P a g e 1. Review of the Transfer of Box Office Operations from the Halifax Metro Centre to Trade Centre Limited

REQUEST FOR PROPOSALS ( RFP ) FOR FINANCIAL ADVISOR TO IMPLEMENT USE AGREEMENT(S) PROCESS AS DESCRIBED IN STRATEGIC AND CAPITAL NEEDS STUDY

Principles for CCP Recovery

Transcription:

BRG Look Back Study November 30, 2015 1

BRG Look Back Study 2

BRG Look Back Study Fully Independent, No Prior GLX History, No Conflicts Document Review and Analysis Interviews and Site Visit MassDOT/MBTA HDR/Gilbane (PM/CM) Hatch Mott MacDonald/Patrick Engineering (OR) Stanton (ICE) AECOM/HNTB (Designer) WSK (CM/GC) ARUP Nossaman FTA/PMOC CIM & ACE/MA 3

Look Back Study Objectives: Independent Assessment of Management Effectiveness & Clarity of Professional Services Providers and MassDOT/MBTA Staff, Including Staffing and Training Decisions Independent Assessment of the Determination to use the CM/GC Methodology Independent Analysis of Project Cost Estimating and Risk Analysis Independent Analysis of Cost Drivers that Contributed to Project Budget Overruns 4

Look Back Study Findings: What have we learned? No silver bullets Multiple problems Inter-connected Longstanding 5

GLX Project Story Absence of a Reliable Project Budget Flawed Structure & Application of CM/GC Project Delivery Model Project Management Excessively Schedule Driven 6

Excessively Schedule Driven 7

Look Back Study Findings: Schedule-Driven Project Schedule - The Driving Force Behind Selection of CM/GC Delivery Method GLX Project is a Legal Requirement Under State Implementation Plan with Mandated Deadlines Schedule Minimization (Overlap of Design and Construction) Federal Funding Considerations Related to Schedule Minimization Flexibility to Address Project Uncertainties 8

Look Back Study Findings: Schedule-Driven Project Schedule Pressure Impacted the Ability to Successfully Implement CM/GC Schedule Pressure to Develop and Complete the Full Funding Grant Agreement by the End of CY 2014 9

Absence of a Reliable Project Budget 10

BRG Look Back Study Analysis of Cost Estimating and Risk Analysis 11

Look Back Study Findings: Analysis of Cost Estimating and Risk Analysis A Reliable Project Budget is Defined as being within +10% and -5% of what it would Cost to Design and Construct the Project 12

Look Back Study Findings: Analysis of Cost Estimating and Risk Analysis A Reliable Project Budget was Achievable as Early as October 2012 when the Project s Design was 30% Complete 13

Look Back Study Findings: Analysis of Cost Estimating and Risk Analysis A Reliable Project Budget has not been Produced to Date 14

Flawed Structure & Application of CM/GC Project Delivery Model 15

What is CM/GC Procurement? Phases 2 through 4 of the project use a contract delivery method called Construction Manager/General Contractor (CM/GC). In this procurement method A CM/GC contractor is procured through a qualifications- and feebased selection process A design team is procured under a separate contract The MBTA, CM/GC and design team work together to develop designs which the CM/GC prices at a Guaranteed Maximum Price (GMP) The use of CM/GC on the GLX Project was approved as a pilot program by legislation signed on June 19, 2012 The MBTA Board of Directors approved use of this approach on July 11, 2012 16

What is CM/GC Procurement? Another key piece of the CM/GC methodology is the Independent Cost Estimator (ICE). The ICE provides cost estimating services on individual GLX construction packages, which are used for comparison with the bids received from the CM/GC team on those packages Potential advantages of the CM/GC model are that it overlaps design and construction, thereby shortening overall program delivery time and providing a single point of responsibility A potential disadvantage of the CM/GC model is that CM/GC faces no competition 17

GLX Procurement Timeline The work associated with Phases 2-4 of the GLX Project was broken down into a series of guaranteed maximum price (GMP) contracts with the CM/GC July 2013 October 2013 Fall 2014 May - Aug 2015 WSK chosen as the CM/GC 1 st three GMP contracts were awarded to WSK Stanton hired by the MBTA as the ICE MBTA received bids from WSK for GMP 4 (contract which covers the remaining work on Phase 2 of the GLX project) 18

CM/GC Methodology Questions Is CM/GC a Reasonable Delivery Model? Yes Was CM/GC the Right Model for the GLX Project? Insufficient Information to Judge Was CM/GC Developed and Administered Effectively for GLX Project? No Should the MBTA use CM/GC in the future? Only with Open Book Cost Accounting and Current Best Practices 19

Look Back Study Findings: Assess the Determination to Use CM/GC Justifications for Using CM/GC Schedule - The Driving Force Behind Selection Other Justifications - Not Realized Then or Not Important Now Design Refinement with WSK Preconstruction Involvement Cost Certainty with Construction Guaranteed Maximum Pricing MBTA Maintained Control of the Design Single Point of Responsibility for Construction 20

BRG Look Back Study Assessment of the Determination to use the CM/GC Methodology Flaws in the Structure and Application of the CM/GC Model Flawed CM/GC Proposal Evaluation Fee-Based Criteria Failure to Use Open Book Cost Accounting No Visibility into Construction Costs Incurred and Contractually - Specified 4.25% Fee Markup Disconnect Between the ICE IGMP Estimating and HDR/Gilbane s IGMP Budgets WSK was Allowed to Qualify its IGMP Proposals Effectively Shifting Project Risk back to the MBTA Negating Intended Cost Certainty Considered in the CM/GC Model 21

BRG Look Back Study Assessment of the Determination to use the CM/GC Methodology Flaws in the Structure and Application of the CM/GC Model Excessive IGMP Negotiations Between HDR/Gilbane, the ICE, the MBTA and WSK - Occurred over Several Months and Allowed WSK to Secure Highest Price for its Work While Remaining within 110% of the ICE Estimate Insufficient CM/GC Training for HDR/Gilbane and the MBTA BRG Recommends that CM/GC Model not be Considered for Future Projects unless Open Book Cost Accounting can be used and the Project Team Receives Further CM/GC Training 22

CM/GC Item Best Practice GLX Experience Pricing Pricing & contract provisions and administration should be consistent Qualifications & assumptions made regarding means & methods should be included in the contract Budgeting Establish strict budgeting protocols Cost Accounting If a GMP contract, open book cost accounting should be used Manual & contract contemplate GMP, but lump sum used CM/GC qualifications were included in the IGMP Agreements Unclear whether assumptions were included that would protect the MBTA No reliable budgeting process adopted Not adopted 11/16/2015 23

CM/GC Item Best Practice GLX Experience Cost Estimating Open book Cost reconciliations at 60%, 90%, & 100% design No pre-defined ranges of acceptability Multipliers and Other Mark-ups Clearly identify cost items included in multipliers and other mark-ups Cap mark-ups Subcontracting CM/GC is required to follow owner s bidding practices Open book cost estimation not adopted Cost reconciliations did not consistently occur at set design stages 110% range of acceptability defined in the Manual & the contract Multiplier is limited to profit & HOH Indirect costs are not capped CM/GC was required to obtain three bids Three bids not always obtained 11/16/2015 24

CM/GC Item Best Practice GLX Experience Preconstruction Services Should be a highly collaborative & open process End goal of identifying high-risk items & mitigations Value Engineering Be open to VE suggestions Incentivize parties to suggest VE solutions Design Management Design should be managed in order to minimize scope creep and budget busts Unclear how collaborative the relationships really were Many VE solutions were rejected No design to budget requirements 11/16/2015 25

CM/GC Item Best Practice GLX Experience Minimize Construction Packages Minimum number of construction packages An early works package may be used General Provisions Based on design-bid-build contract documents Appropriate risk shifts based on risk items & mitigations identified during preconstruction services 7 IGMP packages Unclear whether risk items and mitigations were identified Some risks were shifted back to the MBTA inappropriately 11/16/2015 26

Management Clarity and Effectiveness 27

Management Clarity & Effectiveness: Adequacy of MBTA Staffing MBTA Staffing Model 4 FTEs from MBTA to Manage PM/CM, CM/GC, Designer and ICE HDR/Gilbane Used as Additional MBTA Staff QA/Audits New Starts Final Design Management CM/GC Pre-Construction and Construction Oversight Integration of HDR/Gilbane with MBTA Staff Co-Location and Shared Understanding Flexibility with Staffing Levels 28

Management Clarity & Effectiveness: Adequacy of MBTA Staffing Long Term Consequences Missed Opportunity for Institutional Knowledge at MBTA Increased Professional Service Costs on Projects Reduced Staffing Decision Flexibility Inability to Facilitate Greater Internal Focus on Progress, Performance and Risk 29

Management Clarity & Effectiveness: Areas for Improvement Review the Emphasis of Schedule on Decision-Making Develop Staff s Core Competencies through Training Create Stronger Accountability for Project Cost Certainty Build Resilience Through Robust Mitigation Strategies 30

Appendix BRG Background 31

Berkeley Research Group, LLC BRG: Global Consulting Firm 878 Professionals Programmatic and Project-Specific Project Risk Management Consulting Services Claims Analysis and Expert Witness Testimony Experience Including Professionals with Extensive Cost Analysis and Infrastructure Construction Expertise 32

Berkeley Research Group, LLC Terry L. Yeager Civil Engineer/MBA Over 20 Year s Experience as a Heavy and Highway Contractor Including Mega Projects, Design Build Projects and PPP Projects Over 12 Year s Experience as a Dispute Resolution and Project Risk Management Consultant Claims Analyst with Significant Expert Witness Testimony Experience 33

Berkeley Research Group, LLC Terry Rodgers Finance/Ph.D. Management Over 30 Year s Consulting with Public & Private Organizations and State & Federal Agencies Construction Industry Experience with Cost Analyses & Claims, Compliance Reviews, Management Oversight and Operational & Strategic Management Services 34