NEC3 Engineering & Construction Contract An Overview



Similar documents
NEC3: The Engineering and Construction Contract An overview

Appendix 18 NEC3 Options

How To Write A Contract

Guidance Notes for the NEC Engineering and Construction Contract

Introduction to NEC3. Course agenda. Course objectives. Session 1 Background and underlying principles the concept

JCT Standard Building Contract SBC/Q

GETTING STARTED WITH THE NEC3

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

NEC3: Early Warning and Compensation Events

C1.2 CONTRACT DATA PROVIDED BY EMPLOYER (ECC3)

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Letters, Instructions, etc.

Managing programme change on an NEC3 form of contract

NEC ECC Option F ERF 2066 Duynefontein building refurbishment

DIRECTORATE OF ESTATES & FACILITIES

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard

ANNEX 8 Contract Management Strategy

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

CLIENT / PROJECT MANAGER AGREEMENT

Contract Management. Brief 22. Public Procurement. September 2011

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

EXPERIENCE SHARING ON THE ADMISITRATION OF THE DSD PILOT CONTRACT (NEC

Producing a programme under the NEC form of contract

Gilbert Kwok LLB (English Law), LLB (PRC Law), FHKIS, FRICS Partner, Construction & Engineering Group, Li & Partners

Outsourcing Factsheet

NEC Users Group Workshop Defined Cost

Standard forms: JCT 2005, NEC3 and the Virtual Contract

PPC2000 Contracts RICS East of England and CIOB - Framework and Partnering Agreements CPD 21 June 2010 Richard Cooke. Contents.

Guide to Procuring Construction Projects

Measured development Construction and Engineering Training Supplement Guide

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Thames Water Utilities Limited. Settlement deed

The FIDIC Suite of Contracts

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

The New Standard Construction Contracts: NZS3910, 3916 and 3917

both the Employer and Contractor teams access and administer contracts in a common environment available 24hrs per day, 365 days per year

A JCT 2011 Minor Works Building Contract

THE NEW ENGINEERING CONTRACT: IMPROVED PROCUREMENT AND CONTRACTING WITH ITS SIMPLICITY, CLARITY AND GOOD PROJECT MANAGEMENT PROVISIONS

LUONNOS. Client s representatives In contract matters In matters related to project execution

A Contract for Just Digging a Hole

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

Smart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version)

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance

NZIA Standard Construction Contract

PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

QSS 0: Products and Services without Bespoke Contracts.

INTERNSHIP TRAINING SCHEME

Consumer Code. for Home Builders

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

EXHIBIT "B" CRITERIA AND BILLING FOR EXTRA SERVICES

Activity Schedules in the NEC3 Engineering and Construction Contract

CALIFORNIA CONSTRUCTION CONTRACTS, DEFECTS, AND LITIGATION (1st Edition) November 2015 TABLE OF CONTENTS

Australian Standard. General conditions of contract for design and construct. AS (Incorporating Amendment No. 1)

GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES

HONG KONG HOUSING AUTHORITY GUIDELINES FOR THE GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS 2013 EDITION

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

GUIDANCE NOTE Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development

The International Operating and Client Servicing Procedures are divided into the following sections:

Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods

GREENFIELD MIDDLE SCHOOL ROOF PROJECT

CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014

NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING

7.4.1 Be required to make exhaustive or continuous on-site reviews;

REACTIVE REPAIRS, CYCLICAL & PLANNED MAINTENANCE POLICY

Performance Measurement on the London Construction Programme

North London Plumbing & Heating Terms and Conditions

Health and safety policy

LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS

ACT on Payment Services 1 ) 2 ) of 19 August Part 1 General Provisions

LIABILITIES FOR DESIGN DEFECTS IN A COLLABORATIVE, INTEGRATED DIGITAL AGE. A presentation on the UK experience By Karen Gough, Barrister

PRACTICE NOTES FOR QUANTITY SURVEYORS

This is Document Schedule 5 Part 1 referred to in this Contract SCOTTISH MINISTERS REQUIREMENTS SCHEDULE 5 PART 1 QUALITY MANAGEMENT SYSTEM

SUMMER WORKS SCHEME (SWS) 2014

Conditions of Contract

Schedule 11. The Transfer of Undertakings (Protection of Employment) Regulations 2006

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

WRITTEN STATEMENT OF SERVICE /TERMS AND CONDITIONS OF SERVICE

Government Construction. A Guide to the implementation of Project Bank Accounts (PBAs) in construction for government clients

Contract Certainty Principles and Guidance Notes

Chase Surety Bond Facility Application Form

Chartered Architectural Technologists: Client information for domestic projects

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

Bonds. Brian E. Rawling, Brian E. Rawling & Associates

MR GREGORY YAU-MING TUNG. (Bachelor of Science in Quantity Surveying with Honours) (Date of Qualification 1987)

6.0 Procurement procedure 1 Infrastructure

Appendix A. Call-off Terms and Conditions for the Provision of Services

September Claims Guideline

Risks in International Consultancy Appointments: The FIDIC White Book

To be used in conjunction with the Invitation to Tender for Consultancy template.

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES

Transcription:

NEC3 Engineering & Construction Contract An Overview Delivering Professional Solutions to the Property Industry Michael Dunn FRICS FCIArb LLB LLM Director of Contract Services T: 01274 693 622 E: m.dunn@rpp.co.uk www.rpp.co.uk The New Engineering Contract (NEC) The NEC is a division of Thomas Telford Ltd which is a wholly owned subsidiary of the Institution of Civil Engineers the owner and developer of the NEC Development/publication of NEC Consultative edition 1991 First Edition 1993 Second Edition 1995 (ie NEC 2) name change Third edition June 2005 (ie NEC 3) 2

NEC 3 : Suite of Contracts NEC 3 documents The Engineering and Construction Contract The Engineering and Construction Subcontract The Engineering and Construction Short Contract The Engineering and Construction Short Sub-Contract The Professional Services Contract The Adjudicator s Contract Term Services Contract Framework Contract Supply contract Detailed guidance notes and flow charts 3 NEC3 : Characteristics Its use stimulates good management of relationships between the two parties to the contract and hence of the work included in the contract It can be used in a wide variety of commercial situations for a wide variety of types of work and in any location engineering/building/contractor design/international projects Clear and simple document using language and a structure which are straight forward and easily understood present tense/lack of mandatory language/short sentences 4

Approach to drafting defined terms capitalised e.g. Works Information (cl.11.2.19) specified Terms are in italics (e.g. works) and identified within the Contract Data clause 10.1 The Employer, the Contractor, the Project Manager and the Supervisor shallact as stated in the contract and in a spirit of mutual trust and cooperation 5 NEC3 : Endorsements & Use Latham (1994) The approach of the New Engineering Contract is extremely attractive. The NEC is capable of being a common contract for the whole industry Office of Government Commence In December 2008, the Public Sector Construction Clients Forum made a unanimous decision to move towards standardising procurement approaches through member organisations use of the NEC3 forms Position of ICE 6

Pick& mix approach to creating a project specific contract core clauses main options clauses secondary option clauses general UK specific dispute resolution option clauses Contract Data Part 1 and Part 2 7 Core clauses (structure of contract) Core clause 1 -General Core clause 2 - The Contractor s main responsibilities Core clause 3 -Time Core clause 4 -Testing and Defects Core clause 5 -Payment Core clause 6 - Compensation events Core clause 7 -Title Core clause 8 -Risks and insurance Core clause 9 - Termination 8

Main options Option A : Priced contract with activity schedule Option B : Priced contract with bill of quantities Option C : Target contract with activity schedule Option D : Target contract with bill of quantities Option E : Cost reimbursable contract Option F : Management contract A main option must be selected 9 Secondary Options (17 Nr) Option X1 : Price adjustment for inflation Option X2 : Changes in the law Option X3 : Multiple currencies Option X4 : Parent company guarantee Option X5 : Sectional Completion Option X6 : Bonus for early Completion Option X7 : Delay damages Option X12 : Partnering 10

Secondary Options (17 Nr) (cont d) Option X13 : Performance bond Option X14 : Advanced payment to Contractor Option X15 : Limitation of Contractor s liability for his design to reasonable skill and care Option X16 : Retention Option X17 : Low performance damages Option X18 : Limitation of liability Option X20 : Key Performance Indicators 11 Secondary Options (17 Nr) (cont d) Option Y (UK)2: Housing Grants Construction and Regeneration Act 1996 Option Y (UK)3: Contracts (Rights of Third Parties) Act 1999 Option Z : Additional conditions of contact Dispute Resolution Option W1 : Dispute Resolution Procedure (Non HGCR Act 96) Option W2 : Dispute Resolution Procedure (HGCR Act 96 applies) Note: references X8 to X11, X19 and Y(UK)1 are not used X8 to X11 in PSC / X19 in TSC / Y(UK) 1? 12

Contract Documents? Form of agreement (see Guidance Notes Appendix 3) Letter of acceptance (?) Contact data : part one provided by the Employer Main option stated Secondary options etc Contract data : part two provided by the Contractor The Contractor s pricing document Works Information Site Information Form of tender (see Guidance Notes Appendix 2)(?) 13 Administration Project Manager Supervisor (e.g. clause 4 Testing & Defects and clause 7 Title) no quantity surveyor or architect mentioned Certificates e.g. Completion certificate (cl 30.20) / Defects Certificate (cl 43) / Payment certificates (cl 51) Contractor and PM to act within timescales set out in contract (cl.13.3) might be a specific period set out in the clause (e.g. cl 31.3) or reply within the period for reply 14

Early warning by Contractor or PM (cl.16) as soon as become aware that a matter could cause an increase in the total of Prices / cause a delay in Completion / cause a delay in meeting a Key Date / impair performance of worksin use Contractor gives an early warning of any matter which could increase his total cost Risk Register is a register of risks listed in the Contract Data(cl 11 (14)) PM to enter early warning matters on Risk Register (cl 16.1) Risk reduction meeting (cl.16.3) / PM to review Risk Register following decisions at meeting / issue to Contarctor 15 Programme programme identified in Contract Data part one Contractor submits a programme to PM for acceptance (cl.31.1) Accepted Programme (cl.11.2.1) PM has 2 weeks to accept or notify of reason for not accepting (cl.31.3) Cl.31.2 sets out what the Contractor is to show on each programme revised programme (cl.32) content /submission procedure assessment of compensation events 16

Defects terminology Defect -a defined term (cl. 11.2(5)) defects date defect correction period (weeks one period) Defects Certificate (cl. 11.2.(6)) until defects date the Supervisor can instruct the Contractor to search for Defects (cl.42.1) Contractor to correct Defects whether notified or not (cl. 43.1) the Supervisor may notify a Defect at any time before defects date (cl.42.2) 17 Defects (cl. 40/41/42) prior to Completion Contractor to correct notified defects if it would prevent Employer/others doing their works (cl.11.2(2)) after Completion Contractor to correct notified defects before end of defects correction period (cl. 43.2) Supervisor issues Defects Certificate at the later of the defects date or last defects correction period (cl. 43.3) for the last notified defect accepting defects / uncorrected defects(45) PM assessment 18

Completion Certificate Notified defect Defects correction period Defects date Defects certificat e Defects prior to completion Notified defects Defects correction period 19 Payment (cl.50) PM assesses amount due at each assessment date and certifies amount within 1 week of assessment date first assessment date decided by PM thereafter assessment interval as stated in Contract Data until 4 weeks after issue of the Defects Certificate and at Completion of thewhole of the works Y (UK)2 HGCR Act 96 Different terminology e.g. Price for Work Done to Date / Defined Costs difference between Option A and Option C 20

Compensation events no separate extension of time or loss and/or expense provisions both time and money addressed under compensation events cl 60 there are 19 compensation events (listed at cl.60.1) which if occur not the fault of the Contractor e.g. change in Works Information weather Employer could add to the list at tender stage set out in Contract Data 21 Compensation events notification of event by PM or Contractor (cl 61) event changes Prices/Completion Date/Key Dates procedure premised upon submission of Contractor s quotations process prospective not retrospective quotations (cl 62) includes changes to Prices/Completion Date(s)/Key Dates details to be included alterations to Accepted Programme 22

Compensation events valuation based on Defined Costs (cl 63) provision for alternative quotations procedural timescales placed upon Contractor to submit quotations PM to respond PM can undertake his own assessment (cl.64) if Contractor fails to submit a quotation Contractor s assessment is not correct 23 Compensation Events : Timetable notification of CP PM s decision C submits quotation PM replies < 1 wk > < 3 wks > < 2 wks > failure to respond? notice 2 wks failure to reply? notice 2 wks 24

Questions Delivering Professional Solutions to the Property Industry 25