technical tips and tricks



Similar documents
technical tips and tricks

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

technical tips and tricks

Microsoft Project 2010

5. Creating a Gantt Chart

OVERVIEW. Microsoft Project terms and definitions

technical tips and tricks

Microsoft Office Project Tips and Tricks

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

technical tips and tricks

technical tips and tricks

Introduction to Microsoft Project 2010

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project Exam Study Guide

Project Management: Intermediate Microsoft Project 2010

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Mastering Microsoft Project 2013

Planning and Scheduling Your Project Using Microsoft Project 2003

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Tracking Project Progress

Mastering Microsoft Project 2010

PERCEPTION PERT-PAC Using Microsoft Project 2000

ELECTRO-MECHANICAL PROJECT MANAGEMENT

Microsoft Project 2013 Guide to Task and Resource Planning

Using MS Project in Translation Projects Management

MICROSOFT OFFICE PROJECT - SYLLABUS

1 Start a new project

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Project Management Quick Reference Guide for MS Project 2010

MANAGING MULTIPLE PROJECTS

ECDL / ICDL Project Planning Syllabus Version 1.0

Microsoft Project 2007 Level 1: Creating Project Tasks

Project Management by Using MS PROJECT 2013

Project Management Courses

Microsoft Project 2010 Advanced

NE-50413B Mastering Microsoft Project 2010

Collaborative Scheduling using the CPM Method

WORK PROGRAM GUIDELINES

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

Computer Training Centre University College Cork

Contents. iii. ix xi xi xi xiii xiii xiii xiv xv xvi xvii xix

MSP How to guide session 2 (Resources & Cost)

Creating a New Project

MS Project Tips and Tricks

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Open Workbench Warrior. Beginner's Guide to Open Workbench

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

1. INTRODUCTION PRODUCT Installation Documentation Website workbench features...2

Applied Project Management ( APM )

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

Mastering Microsoft Project B; 3 days, Instructor-led

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Project Management: Tracking Progress and Earned Value with MS Project 2003

ECDL / ICDL Project Planning Project Management Software Level 2. Syllabus Version 1.0 (UK)

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

University of Sunderland. Microsoft Project. Basic Guide

Chapter 2: Project Time Management

Planning and Managing Projects with Microsoft Project Professional 2013

Scheduling Glossary Activity. A component of work performed during the course of a project.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

Introduction to Project Management ECE 480. Erik Goodman

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Set up projects quickly Key: =Feature Included =Improved in Office Project Standard 2007 =New in Office Project Standard Project Standard 2003

Applied Software Project Management

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Lesson 6 - Managing Resources in a Project Plan

Project Management Courses

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

Microsoft Project Activity

Planning and Managing Projects with Microsoft Project Professional 2013

MS Project 2000 Tutorial: Introduction

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

ESKIPM2(SQA Unit Code- F9CX 04) Project management software

Session 6. Microsoft Project. Emanuele Della Valle. Lecturer: Dario Cerizza

Chapter 3 Managing the Information Systems (IS) Project

Mastering Microsoft Project 2013

ESKIPM3 Project management software

A Short Introduction to Project Management

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Project Planning and Scheduling

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

Introduction to Project Management

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

Project Quick Reference. The Assignment Equation. EPM Architects

Systems Analysis and Design

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

Dashboards and Reporting for Program Management

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Microsoft Project Microsoft Project The smart way to learn. Microsoft Project one step at a time!

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Transcription:

technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart way to learn Microsoft Project. For further information, please go to: /project_mentor.htm More useful tips and tricks can be found on the Project Learning blog: www.projectknowledge.net Related Document(s) Filtering & grouping by schedule status /pdf/i1.2.pdf

Introduction Planning a project is one thing; managing a project effectively is often something completely different, and with its own set of challenges. Of the Microsoft Project users that track actual progress against project tasks, disappointingly few understand how to compare a planned schedule with what actually happened. These users are probably unaware of the wealth of information available to them, and the value they can get from correctly interpreting that information. These tips and tricks illustrate a number of ways that schedule comparisons can be made, together with how the information available can be interpreted. Background Before replanning a project, a comparison should be made between the project's current schedule and baseline information. A simple comparison can determine: If any slippage has occurred; the tasks that exhibit the slippage or the amount of slippage that exists. The project's schedule is normally compared to the overall baseline for the plan (which is usually agreed between the Project Manager and the Project Sponsor). The schedule can also be compared with interim baselines to determine any changes since a previous project update. These comparisons can be invaluable, as they can highlight trends occurring within the project that may be missed by simply looking at a project's critical path.

Making baseline comparisons Looking for schedule variances When a project has been updated with progress, there will invariably be differences between the current schedule and its baseline. This can be seen most clearly within the Tracking Gantt view. In the example below, the nonworking time from Tim Brown's resource calendar has been added for clarity. The view above is indicating: o Design structure started and finished on time. The baseline bar and the actual bar for this task are scheduled identically. o Write body text started on time and is split. It is scheduled to finish very late due to a resource calendar affecting when work upon the task can resume. o Set page layouts is delayed because of its late-running predecessor. o Create exercises started early and it finished early. o Test exercises started and finished early, well before its deadline date. o Create contents & index has a delayed predecessor, so it too is delayed. o The milestone Manual completed has not been rescheduled because of its delayed predecessor. Hints If tasks were delayed beyond deadline dates, an indicator could show a warning message. If milestones (or indeed any tasks) appear earlier than the finish of their predecessor(s), they probably have an inflexible constraint against them. If so, a scheduling conflict probably exists.

Quantifying schedule variances Whilst a simple visual comparison is useful, there are ways to make a more meaningful comparison between the current schedule and the baseline. Fields within the Variance table provide this information: From the View menu, select Table and then select Variance: o If a task has a positive start variance: Its scheduled start is later than its baseline start. o If a task's start variance is a negative value: It started earlier than its baseline. o If a task has a positive finish variance: Its scheduled finish is later than its baseline finish. o If a task's finish variance is a negative value: It finished earlier than its baseline. Hints Start variances and finish variances for summary tasks reflect their baseline performance. In the example above the Content summary task above started on time, but is expected to finish six days late. The Exercises summary task started three days early, but is expected to finish three days late. When tasks have a finish variance greater than their start variance, they are overrunning; they are expected to take longer to complete than originally planned. These tasks may well have cost variances associated with them as well.

Quantifying changes to slack values Schedule comparisons can also be made with slack values that tasks possess. These fields can be found within the Schedule table: From the View menu, select Table and then select Schedule: o If tasks are completed or are critical: Their total slack value will be 0. o If any tasks can be delayed without affecting the project finish date or a task with an inflexible constraint: Their total slack value will be positive. o If a scheduling conflict exists: Tasks will have a negative total slack value. Hints Where negative slack values are displayed against tasks, the sequence of tasks needs to be performed quicker in order to meet the project finish date or an inflexible constraint. In the example above, a saving of one day on EITHER Set page layouts OR Create contents & index would be enough to bring the project back on schedule and reduce the total slack to be 0 days.

Making comparisons to interim baselines Schedule comparisons can also be made against interim baselines (plans). This can provide a comparison with the project's schedule prior to the latest update. In order for this to be possible, some simple procedures should be adopted: Before updating the project with progress, create an interim baseline (plan). This will copy the current schedule into the interim baseline value: a. From the Tools Menu, select Tracking and then select Save Baseline. b. Set to copy the scheduled start into Start1 and the scheduled finish into Finish1 for all tasks, confirmed with OK. Repeat the process before each update to the project.

Once interim plans have been created, comparisons can be made against them: Use the Table Definition dialog box to create custom tables that display appropriate fields: Create new views that contain custom bar styles to display the latest interim baseline status compared to the current schedule:

o The bar style for baseline bars has been replaced with a bar style for the third interim baseline (Start3 / Finish3): o Where there is a variance between the 'Interim 3' bars and the normal task bars, a slippage will have taken place as a result of the 'Interim3' update to the project (for example, Write body text, Set page layouts and Create contents & index have all slipped). Before updating a project with ANY actual progress, consider the update frequency. This will determine when each change of status date should take place. Ensure that the project team is aware of every status date and hence when the updates will be performed. Create calculated fields to compare interim baseline values with current schedule values; for example to determine a variance between a scheduled finish date and the 'Finish 4' field. This would allow comparison with the project at its fourth change of status date. Up to 4 rows of bar styles can be displayed. This can provide a very detailed schedule comparison (if required): Hints

Adding progress lines to a Gantt chart Another way that progress can be measured is by the addition of progress lines to a Gantt chart. These progress lines can be used for a graphical representation of task slippage. To apply progress lines: a. From the Tools menu, select Tracking and then select Progress Lines. b. Select to show a progress line based upon the project's status date: c. Confirm with OK to display: o The progress line for Write body text has been drawn back behind the status date. This indicates that the task is behind schedule. o The progress against the two summary tasks is rolled up from their subtasks. The summary tasks are described as being ahead of schedule.

Hints Multiple progress lines can be added, for example at each change of status date. The style of progress lines can be defined within the 'Line Styles' tab of the Progress Lines dialog. Progress line display can be selected as well as cleared within the Progress Lines dialog.