The Implementation of the RIIO Framework



Similar documents
RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd

Interaction between business context and an appropriate WACC for ESBN

RIIO-T1 business plan submission London Tuesday 6 September 2011

RIIO-T1 & RIIO-GD1: UNCERTAINTY ISSUES

Glossary of terms: RIIO-T1 and GD1 review

NETWORK OUTPUT MEASURES CONSULTATION

RII0-GD1. Business Plan

Thames Tideway Tunnel Cost of capital

UK Power Networks Business plan (2015 to 2023) Executive summary

Transmission Price Control Review: Updated Proposals and Smithers & Co. Ltd.: Report on the Cost of Capital. Response to consultation

The form of the price control for monopoly water and sewerage services in England and Wales a discussion paper

We hope all the questions are understandable, If you have any difficulties please

Delivering Power: The Future of Electricity Regulation in London s Central Business District

London: capital of debt. Reducing the health consequences of personal debt

QUALITY OF SERVICE DISCRETIONARY REWARD SCHEME GAS DISTRIBUTION NETWORK OPERATORS ENTRY FORM

Statement from the CEOs of Scotia Gas Networks and Mutual Energy

National Grid Gas plc Annual Report and Accounts 2015/16. Company number

Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE

Gas and Electricity Connections Industry Review

UTILITY REGULATOR WATER. Water & Sewerage Services Price Control

4 th August Review of NIW's Business Plan: Cost of Debt and WACC Assumptions

SP Energy Networks Business Plan

National Grid Gas Transmission s RIIO-T1 business plan overview

ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX

Water Charges Plan Decision Paper (Executive Summary)

Best Practice in Economic Regulation: Lessons from the UK

National Grid Electricity Transmission s RIIO-T1 business plan overview

RULE DETERMINATION Rule Proponents

Peer Comparison: U.K. Water Corporate Securitizations

UK Power Networks. Investor Presentation. Basil Scarsella Director of Strategy, Regulation & CFO. September

RIIO T1 Business Plan Update January 2012

DTI Consultation on Proposals for a Special Administrator Regime for Energy Network Companies Ofgem s Response

CBI Scotland welcomes the opportunity to respond to the Scottish Government s paper Corporation Tax: Discussion Paper Options for Reform.

AUDITORS LIABILITY AND ITS IMPACT ON THE EUROPEAN CAPITAL MARKETS ABI RESPONSE TO EUROPEAN COMMISSION DG INTERNAL MARKET CONSULTATION PAPER

Business plans. for our three electricity networks. Draft for consultation business plan for 2015 to November ukpowernetworks.co.

SP Transmission RIIO-T1 Business Plan

Framework for assessing capex and opex forecasts as part of a building blocks approach to revenue/price determinations

Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and

Appendix 5D Ernst & Young Accounting Treatment

NIGERIAN ELECTRICITY REGULATORY COMMISSION. Presentation at the ELECTRIC POWER INVESTORS FORUM

Inputs, outputs and outcomes what should price limits deliver? A discussion paper

ADVICE ON ESTIMATING NETWORK RAIL S COST OF CAPITAL

ENA Submission to the Parliamentary Renewable and Sustainable Energy Group Inquiry into the access and management of renewables and the Grid

Monitoring and Treatment of Network Rail s Underspend and Efficiency: Policy Statement

Innovative Regulation for Intelligent Networks

Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our annual performance reporting

How To Decide If There Is A Need For Regulatory Intervention In Relation To End To End-To-End Competition In The Postal Sector

Value for money and the valuation of public sector assets

Regulatory Accounting Guidelines for Network Rail Infrastructure Limited. March 2013

Network Capability Proposal

CANEGROWERS submission to the 30-year electricity strategy

Full year 2014 results. Analyst meeting Brussels, 27 February 2015

Principles and key features of required reform

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

Capital Maintenance Planning From a historical and future perspective

The Future of London s Power Supply

December Reviews of Public Electricity Suppliers 1998 to Distribution Price Control Review. Final Proposals

Financeability and financing the asset base a discussion paper

15 April 2011 Re: Expansion of the Victorian Energy Efficiency Target

Asset Management Practices, Investments and Challenges

Gas transport tariffs calculation

High Yield Bonds in a Rising Rate Environment August 2014

ITSPA response to Ofcom s strategic review of consumer switching

Aligning Rate Making and Grid Modernization

Transcription:

The Implementation of the RIIO Framework EPRG Winter Conference James Grayburn December 2014 Cambridge

This presentation assesses Ofgem s implementation of RIIO framework following introduction of new controls across all sectors RIIO (revenue, incentives, innovation and outputs) framework established by Ofgem as part of RPI-X@20 review Ofgem has recently published final determination for electricity distribution (RIIO-ED1) and now all sectors subject to RIIO price controls (RIIO-T1, which applies to transmission companies, and GD1, which applies to gas distribution, both implemented in 2013) Assess key elements of new framework drawing on Ofgems own approach to assessing companies plans Process Incentivising companies plans through fast-tracking A lighter touch Outputs and incentives Defining outputs instead of inputs Addressing capital bias through totex mechanism Efficient expenditure Ofgem s approach to benchmarking Efficient financing Setting allowed equity Cost of debt index mechanism 1

Companies business plans have improved under the RIIO process, a clear success of the new framework Companies have taken greater ownership of plans; engaged with network users; clearly defined outputs; and, developed asset management plans Fast-tracking whereby Ofgem agrees to a company s plan early and in-full where plan is well-justified has been important component of incentivising better plans: Ofgem fast-tracked Scottish TOs (at RIIO-T1), and WPD (at RIIO-ED1); no GDN qualified (RIIO-GD1) Q: Is the cost of incentivising improved plans through fast-tracking too high and/or unfair? We estimate WPD allowances ca. 770m higher (or >10% of totex), a cost borne by WPD customers, an increase of ca. 10 on average annual customer bill. (Ofgem calculates benefit at 250m.) The costs and benefits of fast-tracking WPD Costs borne by WPD customers 1 2.5% totex= c. 160m Improved companies plans Benefits accrue to others (1) WPD s submission is 6,469.4 million in totex and 458.0 million in RPEs, totalling to 6,927.4 million. Ofgem s hypothetical slow-track view is 6,091.6 million in totex and 16.8 million in RPEs, totalling to 6,108.4 million. Source: Ofgem FD. 2

An objective was to make price controls simpler, but they have become more complex (but not unnecessarily so?) Simplifying framework was an initial objective the current approach to price controls struggles to meet the call for simplicity from the Better Regulation Commission.. While undoubtedly very clever, some schemes in our price controls, such as the IQI.. are virtually unfathomable to those outside the cognoscenti. Alistair Buchanan, Ofgem s RPI-X@20 project, 2010 Ofgem points to targeted, proportionate, riskbased approach.. but in practice new framework is more complex But in practice price control has become more complex, eg: Price control reviews now run to almost three years (before less than two) to allow for process changes, namely fast-tracking Annual adjustments and regulatory mechanisms more complex, eg. cost-of-debt, indicated by more than doubling of price control licence conditions Reporting requirements more extensive (notably around outputs monitoring) Conclusion: More complex but not unnecessarily so? 3

Defining outputs instead of inputs should promote least cost solutions to delivering safe and reliable networks Key part of new framework is to set contract in terms of outputs (eg reduction in risk) as opposed to inputs (eg, length of mains replaced) which provides incentives to realise outputs (eg, safety, reliability, customer service etc.) at least cost Some success at defining outputs, and associated incentive mechanisms, eg. in relation to iron mains replacement where reduction in mains risk has replaced mains length decommissioned in regulatory contract But in general, difficult to define outputs for key expenditure areas which are measurable/controllable/auditable, e.g. asset risk metrics (which combine risk of asset failure based on condition, with consequence of failure) Risk that companies default to inputs based approach to ensure that they can demonstrate compliance at ex post review But problems with outputs based approach reflect inherent difficulties rather than Ofgem s approach per se 4

The totex approach should address capex bias, by equalising incentives and promoting whole-life cost approach Many GDNS underspent on capex pre RIIO Nearly all DNOs underspent on capex pre RIIO The GDNs spent less than capex allowances at GDPCR1 The DNOs spent less than capex allowances at DPCR4 Pre-RIIO, apparent incentives to seek capex solutions as companies retained greater share of opex outperformance (resulted in capex bias or RCV growth strategy ) Totex approach based on unified incentive rate which makes companies indifferent to opexcapex solutions, and should promote whole-life cost approach Q1: Is capex bias more perceived than real? Evidence from energy distribution companies shows that networks outperformed on capex historically, and thus no clear capex bias Q2: Is capex bias in part consequence of setting allowed return > financing cost (which has now been addressed)? 5

RIIO framework has not addressed underlying concerns with interpretation of benchmarking results EPN efficiency gap declines from 450m to 300m under alternative model Plausible alternative model forms produce different efficiency scores Ofgem recognises that there is no single correct model: it develops three; identifies benchmark as UQ Even so, plausible alternative model specifications produce very different efficiency scores, eg. NERA models based on alternative cost drivers produce very different results to Ofgem although both equally statistically valid (or invalid) RIIO-GD1 IQI Efficiency Score: NG (in red) is Ranked 2, 5,6 and last despite common management High-level observations from RIIO raise questions about validity of use of benchmarking: Networks within same group have very different efficiency scores despite common management, e.g. NG, SP, WPD London networks tend to perform poorly (last at GD1, 11/14 at ED1; 7/14 at DPCR5) Efficiency rankings demonstrate persistency over time. Explained by persistent good management or persistent omitted variables that favour one set of companies over another? 6

Imperfect models favour one set of companies over another set, and create winners and losers Evidence from gas distribution (and other sectors with comparative regime, notably water) shows that companies that are well-ranked by models at price review subsequently outperform price controls the most (and those ranked poorly underperform). Comparative efficiency analysis creates arbitrary winners and losers according to chosen model Well-ranked companies tend to show greatest outperform at subsequent review Water service: 2010-2015 Wastewater: 2005-2015 Gas Distribution: Forecast Performance Over RIIO-GD1 7

RIIO marked by lower allowed returns to equity*; cost of debt mechanism does not allow cost recovery (*with the exception of fast-tracked TOs) Diminishing (allowed) returns to equity under RIIO price controls Diminishing (allowed) returns to equity holders under RIIO, in common with other UK and European regulators Lower allowed return for RIIO-ED1 in response to NIE CC decision High return to equity for Scottish TOs runs against trend But higher realised returns? GDNs expect outperformance of around 10% on average over RIIO-GD1 (compared to 5% pre-riiio) Simplified approach to CoD mechanism creates winners and losers In theory, well-designed cost of debt indexation should ensure that debt allowances track costs No allowance for debt issuance costs (in absence of supposed halo effect ), and on average industry will under-recover by ca. 20bps Ofgem s simplified approach to weighting index has created winners and losers depending on companies historical issuance profile Industry expects underperformance of c.20 bps, with a range of -100bps to +25 bps 8

Using Ofgem s traffic light scorecard used at fasttracking, it scores well on process and outputs, but less well on expenditure and financing Ofgem s assessment of companies mirrors our assessment of Ofgem: good on process, but poorer on cost efficiency and financing Process Demonstrable improvement in plans More complex (but necessarily so?) Outputs and incentives Efficient expenditure Efficient financing Outputs framework should promote cost efficiency Unified incentive rate addresses capital bias (although more perceived than real?) Ofgem assesses efficiency based on three different model forms Even so, alternative model specifications produce very different results Diminishing (allowed) returns but higher realised Concerns over design of CoD mechanism, creating winners and losers 9

Contact Us James Grayburn Senior Consultant NERA London +44 20 7659 8572 James.grayburn@nera.com Copyright 2014 NERA UK Limited All rights reserved.