ServiceNow Phase I: Service Desk Consolidation Project Charter



Similar documents
Information Technology Services ServiceNow: Change Management Phase I Project Charter

OE PROJECT CHARTER TEMPLATE

ENTERPRISE CHANGE MANAGEMENT PROCESS

Crosswalk Between Current and New PMP Task Classifications

Project Lifecycle Management (PLM)

OE PROJECT CHARTER TEMPLATE

Appendix A-2 Generic Job Titles for respective categories

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

IT Project Management Methodology. Project Scope Management Support Guide

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview

How To Write A Project Management Plan

Test Plan (a Real Sample) SoftwareTestingHelp.com Live Project Training - OrangeHRM

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

Procurement Reporting - OBIEE

SAP ERP Upgrade Checklist Project Preparation

Wilhelmenia Ravenell IT Manager Eli Lilly and Company

Project Charter Updated

OE PROJECT CHARTER Business Process Management System Implementation

The position reports directly to the Diversification Program Manager and indirectly to the Program Management Office (PMO)

Integrating Project Management and Service Management

INFORMATION TECHNOLOGY. SERVICE ASSET AND CONFIGURATION MANAGEMENT PROCESS Version 3, Rev. May 5, 2015

Organization. Project Name. Project Overview Plan Version # Date

Develop Project Charter. Develop Project Management Plan

Software Test Plan (STP) Template

ABC COMPANY Extended Accounting System (EAS) Project Charter Sample

Final. North Carolina Procurement Transformation. Governance Model March 11, 2011

Department of Administration Portfolio Management System 1.3 June 30, 2010

SLCM Framework (Version ) Roles and Responsibilities As of January 21, 2005

Program Lifecycle Methodology Version 1.7

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing

44-76 mix 2. Exam Code:MB Exam Name: Managing Microsoft Dynamics Implementations Exam

Project Management and Scrum A Side by Side Comparison by Anne Loeser, October 2006

Agile Master Data Management TM : Data Governance in Action. A whitepaper by First San Francisco Partners

IT Service Provider and Consumer Support Engineer Position Description

PMO Starter Kit. White Paper

Project Governance Plan Next Generation Project Oregon Military Department, Office of Emergency Management, Program (The OEM 9-1-1)

Business Systems Analyst Job Family

PMP Examination Tasks Puzzle game

Project Management Office (PMO) Charter

How To Implement An Enterprise Resource Planning Program

Draft Requirements Management Plan

Project Charter. Online Expense Claims Final Version

EMA Service Catalog Assessment Service

IT Project: System Implementation Project Template Description

BAL2-1 Professional Skills for the Business Analyst

The George Washington University

Cisco IT Technology Tutorial Overview of ITIL at Cisco

STAGEnet Help Desk Task Force Project Charter

ITRM Guideline CPM Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

Project Scorecard Template

Facilities Portfolio Management Tool

<name of project> Software Project Management Plan

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

PROJECT SCOPE STATEMENT

Business Relationship Manager Position Description

Project Charter EMI Outreach July 25, OE Project Charter. 1.0 July 25, 2011 Draft w/ VC Denton comments included /02/2011 Proofed/edited

AGILE SOFTWARE TESTING

Infasme Support. Incident Management Process. [Version 1.0]

Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases

Why are PMO s are Needed on Large Projects?

Process Validation Workshops. Overview Session

Project Charter. 1. Project Stakeholders: Position Title/Name/Organization Phone

Project Charter Client: IPS

Cisco Unified Contact Center Planning and Design Service

SA Tool Kit release life cycle

KMS Implementation Roadmap

ITS Project Management Methodology

Fermilab Computing Division Service Level Management Process & Procedures Document

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B

UCPath Project Status Report

Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes

RFP Attachment C Classifications

Release Management: Effective practices for IT delivery

Strategic Planning & Change Management 3 DAYS

Project Management Office (PMO)

State of Tennessee Sourcing Event #9160 ServiceNow Preliminary Statement of Work (SOW)

BIG DATA KICK START. Troy Christensen December 2013

Why Data Governance - 1 -

ISO JTC 1 SGBD Mtg and ACM Workshop

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions

ID Task Name Time Pred

Camber Quality Assurance (QA) Approach

HKITPC Competency Definition

IT Field Services. Comprehensive computer support and service for UCSF. Nothing should come between you and the great work you do!!

Business Analyst Position Description

Project Management Change Management Procedure

Risk management and the transition of projects to business as usual

Subject Area 1 Project Initiation and Management

ITSM Application Implementation

The purpose of this course is to provide practical assistance for defining and managing project scope.

Colorado Department of Health Care Policy and Financing

Allstate Getting Much More from Its IT Services with ServiceNow Cloud-Based IT Service Management Solution

Domain 1 The Process of Auditing Information Systems

Training Programs for Enterprise-Wide Change

2003 Patricia Ensworth Page 1

Project Scope Management in PMBOK made easy

Transcription:

Prepared By: Jodi Muller and Rebecca Nguyen Date of Publication: 06/6/2011 Version 1.6

Table of Contents PROJECT OVERVIEW... 3 PROJECT SCOPE... 3 OUT OF SCOPE... 3 PROJECT APPROACH... 4 ESTIMATED COST... 5 MILESTONES AND TIMELINE... 5 PROJECT ASSUMPTIONS... 5 PROJECT RISKS... 6 PROJECT CONSTRAINTS... 6 PROJECT DEPENDENCIES... 6 ROLES AND RESPONSIBILITIES... 7 PROJECT ORGANIZATIONAL CHART... 12 1

Revision History Version Date Author(s) Revision Notes 1.0 4/28/11 Jodi Muller Initial Draft 1.1 5/11/11 Rebecca Nguyen Updated Roles and Responsibilities section 1.2 5/16/11 Jodi Muller 1.3 5/17/11 Rebecca Nguyen 1.4 5/19/11 Rebecca Updated Project Scope and Roles 1.5 5/23/11 Jodi Updates based on initial review w/key group. 1.6 6/6/11 Jodi Updated Key Stakeholder to Julie, added Stakeholders, updated Project Organizational Chart. 2

Project Overview The project is the first phase of a larger ServiceNow Product Roadmap Project. The Roadmap supports the overall UCSF Operational Excellence (OE) initiative, and focuses on replacing Remedy and implementing an enterprisewide Service Management tool for UCSF. A project charter will be developed separately for each phase of the roadmap. This first phase of the ServiceNow Roadmap project specifically supports the Service Desk Consolidation portion of the OE initiative. The Service Desk Consolidation includes ITS, Medical Center, School of Medicine ISU and SFGH. The consolidated Service Desk will use the same IT Service Management solution, ServiceNow. ServiceNow offers a suite of on-demand IT Service Management solutions offered via the internet and modern software as a service (SaaS). School of Medicine and Medical Center IT are currently using ServiceNow for Incident Management, Employee Self Service, Asset Management and Service Catalog (Medical Center - telephone only). Project Scope ServiceNow Phase I will focus on implementing the following ServiceNow modules for UCSF Service Desk groups of ITS, Medical Center, School of Medicine ISU and SFGH: o o o Out of Scope Incident Management Fine-tune existing Incident Management build for Medical Center and SOM ISU to support the consolidated Service Desk Incident Management process. Implement Incident for ITS and SFGH according to the consolidated Service Desk Incident Management process. Service Level Agreement Service Catalog Implement Service Level targets for ITS, Medical Center and SFGH (currently in place for SOM ISU) Build out existing Service Catalog to include current/existing online requests from ITS, SOM ISU, SFGH, and Medical Center. (All current online services will be evaluated.) Employee Self Service (ESS) Build out/modify existing ESS page to integrate News and Announcements, Quick Links, Service Catalog items, Help items, knowledge search, etc. The goal is to develop a single landing page for customers. Other IT groups, including ones using Remedy Non-IT groups New Service Catalog items 3

Project Approach UCSF Information Technology Services The project approach is a waterfall project which is a sequential software development process where we have project phases in a cascading affect. Below is the Waterfall model project management approach for this particular project: Phase Activities Define business problem and project goals Define usability needs Create project proposal with ballpark estimate Note: Estimate is only for budget allocation planning Define initial project scope, risks, constraints and assumptions Define resources needed to gather requirements and develop plan Gather high level requirements Create and review Proof of Concept in parallel with gathering requirements Create project estimate Design, develop and test functionality with client Adjust functionality and project scope according to client priorities Provide user training Implement solution Provide bug fixes Review lessons learned Approach Initiate Discover Execute Train Go Live Key Deliverables Creative Brief (for user interface Situation/ Target/ Proposal Document (STP) Project Overview with Discovery Estimate High Level Requirements (HLR) Proof of Concept Project Estimate Solution Design Document Revised Requirements Revised Estimate/ Burn Charts Sprint Deliverables Tricks and Tips Training Collateral Implement solution Closing Statement Maintenance Agreement 4

Estimated Cost This project will be funded by the OE Service Desk Consolidation project. Milestones and Timeline Milestone Deliverable(s) Completed Approach and Initiate Define scope for Phase 1 Discover Execute Train and Go Live Define Risks, Constraints and Assumptions Define ServiceNow Project Team roles and responsibilities Develop initial project plan/schedule Gather and Document current processes for Incident and Service Catalog for ITS, Medical Center, SOM ISU and SFGH Identify and document gaps between Incident and Service Catalog for ITS, Medical Center, SOM-ISU and SFGH Propose consolidated process Obtain sign-off/approval of proposed consolidated process Review current ServiceNow build and document fixes and enhancements required to support the consolidated process. Gather and Document detailed requirements. Develop ServiceNow according to requirements Test functionality Document Training materials Train staff Go Live Project Assumptions Certain assumptions and premises need to be made to identify and estimate the required tasks and timing for the project. The project assumptions listed below are based on current knowledge today. If an assumption is invalidated at a later date, then the activities and estimates in the project plan should be adjusted accordingly. Only the following groups will be converted to ServiceNow during Phase 1: ITS, Medical Center IT, SOM ISU and SFGH. All remaining Remedy users (IT and Non-IT groups) will be converted at a later date to be determined. Remedy will be used in parallel with Service-Now. 5

Project Risks UCSF Information Technology Services Project risks are characteristics, circumstances, or features of the project environment that may have an adverse effect on the project or the quality of its deliverables. Known risks identified with this project have been included below. A plan will be put into place to minimize or eliminate the negative impact of each risk to the project. Risk Area 1. Resources There are competing projects that are potentially utilizing same resources. Level (H/M/L) M Risk Plan Mitigation To be determined in future Risk Mitigation Workshop session. 2. Staff Resistance to change by system users. 3. Parallel processing Until Remedy is retired, some users/groups may be required to do parallel processing on Remedy and ServiceNow. M M Mitigation Strategy - Focus needs to be placed on the system user to be involved in the implementation process. Provide information regarding the project in advance and request input during planning process. Provide regular progress communication to ensure users get adequate training and support on ServiceNow. Mitigation To be determined in future Risk Mitigation Workshop session. Project Constraints 1. Some processes/integrations will remain on Remedy until all modules are built out in ServiceNow. 2. Consolidated Service Desk must be in place by December 2011. 3. Vacant positions within ServiceNow team. Project Dependencies Project Date Due Deliverable Dependency 6

Roles and Responsibilities Name Role Responsibilities Opinder Bawa Project Sponsor Meet regularly with Product Manager and Project Manager (bi-weekly) to review project timeline, key milestones and outstanding issues. - Work with the Product Manager in identifying objectives, key deliverables, and communicating changes to all impacted areas. - Share accountability for the project. Be readily available and accessible for consultation with Product Manager or Project Manager. Act as an umbrella when roadblocks occur for Product Manager, Project Manager and team - prevent scope and schedule creep. Confirm project direction and advocate for the project. Rebecca Nguyen Product Manager Meet regularly with Project Manager (weekly) to review project timeline, key milestones and outstanding issues. Be readily available and accessible for consultation with Project Manager. Act as an umbrella when roadblocks occur for Project Manager and project team. - Prevent scope and schedule creep Aid the Project Manager in lining up, getting commitment from, and managing crossfunctional support of resource needs: - Protect resources from getting pulled into other projects - Lead project budget creation and validation - Lead efforts to secure external funding Ensure project stays in line with budget. Review & approve project status reports: - Provide official backing of the project - Communicate project closure and results to organization - Act as an escalation route for the Project Manager Attend team meetings as needed to keep project on track Contribute in post-evaluation of project: key lessons learned 7

Name Role Responsibilities Jodi Muller Project Manager Identify, track, manage and resolve project issues. Proactively disseminate project information to Product Manager and all stakeholders. Identify, communicate and mitigate project risk. Ensure that the solution is of acceptable quality. Proactively manage scope to ensure that only what was agreed to is delivered, unless changes are approved through change management. Define and collect metrics to give a sense for how the project is progressing and whether the deliverables produced are acceptable. Manage the overall schedule to ensure work is assigned and completed on time and within budget. Prepare and distribute project status report on regular basis (weekly or bi-weekly) to Product Manager Julie Cox Key Stakeholder Review/validate/concur on project charter. Validates and communicates project objectives and goals that are aligned with the strategic goals of the stakeholders. Maintain ongoing communication with the Product Manager and Project Manager. Review/concur with project plan, costs, and overall risks. Provide guidance in cost and schedule development. Ensure project staff availability. Review, concur and participate in milestone review briefings. Prioritize any changes to project scope. Review whether stated improvements or benefits were realized from the project 8

Name Role Responsibilities IT Directors - Kevin Barney - Jane Wong - Jose Claudio - David Rusting - Michelle Fanner Stakeholders Work with Product and Project Managers in providing Department domain knowledge Review, concur and participate in milestone review briefings Work with the Product Manager, Project Manager and Key Stakeholders in voicing concerns or issues impacting the success of the project to ensure any risks are mitigated and issues are resolved in a timely manner. HelpDesk Oversight Committee - Russ Cucina - Erik Wieland - Cathy Garzio - Rob Cotterman - Doug Carlson - Ann Dobson - Frank Farm - Mounira Kenanani - Lynda Jacobsen - Deborah Reiter - Phaedra Bell - Chris Orsine - Julie Cox - Zachary Martin - Jane Meier - Pete Kearney Terrie Coleman Shawn Hall Peter Stampfer Quinn Hearne Kurt Glowienke Dan Pucillo John Gingrich Maintain ongoing communication with the project manager. Business Analyst Conduct interviews subject matter experts to gather business processes and requirements. Document business processes, gaps and requirements. Identify and communicate any risks to Project Manager. Work closely with developer by answering/clarifying any processes or requirements. Subject Matter Work with Product and Project Managers in Experts (SMEs) providing Department domain knowledge Assist Business Analyst in providing requirements. Work with the Product Manager, Project Manager and Key Stakeholder in voicing concerns or issues impacting the success of the project to ensure any risks are mitigated and issues are resolved in a timely manner. Participate in identifying potential resources in their division/unit that could assist with requirement gathering, gap analysis, user acceptance testing and training. Assist the Project Manager in identifying total number of users, divisions/units impacted by the conversion to ServiceNow. 9

Name Role Responsibilities Ed Martin Development Manager Review Functional Requirements and assign work to Developers. Insure thorough testing of all functionality and features that are outlined to be delivered. Work with the Product and Project Manager to ensure deliverables are achieved as identified. Vacant ServiceNow Developers Review, analyze and understand existing ServiceNow build and additional functionality/modules to be implemented Review business requirements to provide effective solutions. Document Functional Specifications and Technical Design on ServiceNow development. Perform analysis, code writing, debugging, testing and documenting the development of all requirements identified for this project. Perform thorough unit testing of all functionality and features that are outlined to be delivered. Create and identify development project deliverables to be added to the overall project schedule Work with the designated Project Manager to ensure deliverables are achieved as identified. Peter Stampfer Shawn Hall Administrators Perform fundamental administration and configuration tasks in ServiceNow TBD QA Engineer Verify that the ServiceNow project has undergone the appropriate level of complete testing cycles to ensure successful implementation. Create and provide test plans and other test documentation as required Track/resolve both staging and production bugs. Design and prioritize test cases/scripts, along with running and verifying test scripts and report findings Work with individuals that have been identified as User Acceptance Testers to provide guidance and mentorship Create and identify testing project deliverables to be added to the overall project schedule Create and maintain bug tracking systems and test environments Sign-off on all test cases and provide go/no go recommendation to Product Manager, Project Manager and project team. 10

Name Role Responsibilities TBD User Acceptance Tester(s) Peter Kearney Process Engineer for Service Desk Consolidation Execute the test cases using sample source documents as inputs and ensure that the final outcomes of the tests are satisfactory Validate that all test case input sources and test case output results are documented and can be audited Document any problems, and work with the project team to resolve problems identified during testing Sign-off on all test cases and provide go/no go recommendation to Project Manager and project team. Work with Product and Project Managers in providing OE Service Desk Consolidation process knowledge Maintain ongoing communication with the Product Manager and Project Manager. Reviews/validates and communicates project objectives and goals that are aligned with the strategic goals of the OE Service Desk Consolidation 11

Project Organizational Chart ServiceNow Phase 1 Project Team Opinder Bawa Project Sponsor Key Stakeholder Rebecca Nguyen Product Manager Julie Cox Stakeholders Jodi Muller Project Manager IT Directors HelpDesk Oversight Committee Ed Martin Development Manager Peter Kearney Process Engineer SD Consolidation Development Team QA Engineer Terrie Coleman Shawn Hall Business Analyst Business Analyst Dan Pucillo Subject Matter Expert (SME) Peter Stampfer Subject Matter Expert (SME) Kurt Glowienke Subject Matter Expert (SME) John Gingrich Subject Matter Expert (SME) Quinne Hearne Subject Matter Expert (SME) User Acceptance Tester User Acceptance Tester User Acceptance Tester User Acceptance Tester NOTE: This is an Organizational Project Chart. The purpose of this chart is not to represent a hierarchical organizational chart or reflect a direct reporting structure. 12

Project Approvals Project Sponsor Opinder Bawa Date Product Manager Rebecca Nguyen Date Project Manager Jodi Muller Date Director Julie Cox Date Customer Services and UCSF Consolidated Help Desk 13