Seattle Public Utilities Green Stormwater Infrastructure: O&M Program



Similar documents
Operations and Maintenance

Seattle Public Utilities. Natural Drainage Systems (NDS) Maintenance Manual

PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS

Operation & Maintenance Document Templates

Stanford Graduate School of Business Knight Management Center Campus

PICP Construction. Why PICPs The Big Picture. Key things to know about PICPs

Post-Construction Stormwater Management Checklist* (5,000 SF or Greater)

CASFM Stormwater Quality Field Trip June 23rd, 2011

Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury

57 th Annual Transportation Conference Montgomery, AL February 12, 2014

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

Permeable Pavement Operation & Maintanence Guide

Residential Turf Removal Program Application Package

Solutions Library Solution 4: Permeable Pavement

Low Impact Development Permeable Paving

GREEN ROOFS. Location. Design SMALL COMMERCIAL GUIDE CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT

Design, Construction and Maintenance of Permeable Pavements Case Studies and Technical Resources Robert Bowers, P. Eng.

Low Impact Development Checklist

APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS

Residential Turf Removal Program Application Package

Guidelines for. Permeable Pavement

Permeable Interlocking Concrete Pavements

Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices

GENESEE COUNTY DRAIN COMMISSIONER S OFFICE

DPD Director s Rule

Landscape Maintenance

Pervious Concrete Pavement Maintenance and Operations Guide

Landscape Maintenance

Lessons Learned from the Expert BMP Panel Process That May Apply to MTDs. Tom Schueler Chesapeake Stormwater Network

Storm Water Management Requirements for Construction Projects Less than One Acre

Sustainable/LEED Landscaping

Structural/Hydrologic Design & Maintenance of Permeable Interlocking Concrete Pavement

4.3 Cisterns and Rain Barrels

Green Infrastructure for Single Family Residences

Retention/Irrigation. Design Considerations. Soil for Infiltration Area Required Slope Environmental Side-effects

Use of Green Roofs to Meet New Development Runoff Requirements. Greg Davis Nov. 8, 2007

City of Atlanta. Department of Watershed Management. Post-Development Stormwater Management Ordinance Summary of Revisions

Permeable Interlocking Concrete Pavement A Low Impact Development Tool Training for Municipal Officials

Guidelines for Control of Water Runoff on Small Lots. Revised 6/09

Post-Construction Storm Water Management Program: Planning, Design, Construction, and Operation. Presenters:

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations

GUIDANCE DOCUMENT. Prepared for Washington State Department of Ecology Water Quality Program

BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ

Pervious Pavement. An Infiltration BMP A LID Technique. Dan Huffman Vice President, National Resources National Ready Mixed Concrete Association

WSUD maintenance guidelines. A guide for asset managers

How To Amend A Stormwater Ordinance

Pervious Pavement SYSTEMS THINKING. THE NEW DESIGN PROBLEM and the Role of the Civil Engineer. LOW IMPACT DEVELOPMENT Introduction

A Developer s Guide: Watershed-Wise Development

(Source: Center for Neighborhood Technology)

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

RainWise Frequently Asked Questions

GROUNDS MAINTENANCE-WATER USE DFC Environmental Management System

Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program Checklist for Stormwater Report

P-23 - DEVELOPMENT OF DELAWARE DEPARTMENT OF TRANSPORTATION STORMWATER BEST MANAGEMENT PRACTICE INSPECTION PROGRAM

Building Your Interlocking Concrete Pavement to Last a Lifetime

APWA Green Pavement Alternatives

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

City of Camas. Storm Sewer Systems. Operation & Maintenance Manual. Public & Private Systems

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

AquaPaver & SF-Rima Permeable Interlocking Concrete Pavers

CONSTRUCTION PERMIT SUBMITTAL CHECKLIST

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

Vehicle Tracking Pad

Pervious Concrete Pavements: How to Reduce Demand on Your Stormwater System

MODULE 2 RULES RELATING RULES RELA

Fairlington Community Center

GreenPlanIT LID Site Suitability Tool. Patty Frontiera, Pete Kauhanen, Marshall Kunze,

Writing a Successful Exterior Landscape Maintenance RFP

Estimating Stormwater System Annual Maintenance and Repair Costs - A GIS Approach

Post Construction and Redevelopment Inspection Manual

Porous Pavement Alternatives Cost Analysis

2013 Trevi Gardens Annual Meeting. Presented By:

Maintaining water sensitive urban design elements

How To Plan A Buffer Zone

City of Des Moines Stormwater Structural Control Maintenance Guidelines

Pervious Pavers: Where is the Perviousness?

SUSTAINABLE URBAN DRAINAGE SYSTEMS

Clarendon CISD. Integrated Pest Management Program (IPM) Manual Updated & Board Acknowledgement 11/10/11

1800 Washington Boulevard, Baltimore, MD TTY Users Larry Hogan, Governor Boyd

Appendix C. Municipal Planning and Site Restoration Considerations

Achieving Consensus on Sustainability Tucson s Water Harvesting and Graywater Ordinances

ELMER AVENUE. Water Augmentation Study NEIGHBORHOOD RETROFIT DEMONSTRATION PROJECT

Stormwater Management Facilities. Operation and Maintenance for Private Property Owners

Sustainable Site Pavement Systems

Installing Porous Pavement Waukesha County Dept. of Parks & Land Use Storm Water BMP Design and Installation Workshop March 11, 2009

Underground Injection Control Storm Water Information

How to Build a Rain Garden at Your Home

Permeable Interlocking Concrete Pavements

Follow the Drop. Activity Overview Students observe and collect information about water runoff on their school property. Objective Students will:

Caltrans non-standard Special Provisions Pervious Concrete. David Akers Feb 28, 2012

Operations and Maintenance Plan

Stormwater Credit Open House Q&A

Green Stormwater Infrastructure in the Sustainable Site. Outline: 2/19/2014. The Stormwater Problem: Impacts of turning spongy forests into cities

SCOPE OF WORK Specifications for Landscaping, Lawn Maintenance & Pest Control

Self-Certification Checklist

Community Greenscapes & Trails

Updates on Pervious Pavement Design and Construction. Jason T. Peterein, P.E. June 19, 2012

Permeable Interlocking Concrete Pavements

Standards Oversight Council (SOC) Supporting Technical Standards for Urban and Rural Soil and Water Conservation

Activity Yes No N/A Notes

Transcription:

Seattle Public Utilities Green Stormwater Infrastructure: O&M Program

O&M Maintenance Package O&M Maintenance Package 1. Landscape Maintenance Manual 2. NDS/LID Maintenance Manual for ROW 3. Identifiable and detailed levels of service 4. Porous Pavement 5. O&M Facility Checklists 6. Key Performance Indicators 7. O&M Estimating Database Tool Life Cycle Costs Risks

Homeowners Landscape Manual Encourage and educate residence Landscape Maintenance Manual Maintenance personnel Homeowners living adjacent to systems

NDS Manual Sections Inspection/Checklist and Recommended Maintenance Activities 1. Vegetation and Landscaping 2. System Functionality 3. Hardscape and Infra-Structure 4. Infiltration Failure Swale Ponding 5. Recommended Maintenance for Other Elements 6. Safety, Mobility, and Accessibility

Maintenance Manual Summary Routine maintenance activities Non-routine maintenance activities Inspection/checklist Scheduling and performing maintenance activities in the ROW Images and descriptions

Levels of Service (LOS) LOS A Excellent effort LOS B Good effort LOS C Moderate effort LOS D Poor effort

Layout and How To Select the desired Service Level for maintenance

1-Vegetation and Landscape Maintenance Inspection/checklist Vegetation is mostly healthy Good appearance Small quantities of weeds Edges are loosely defined Grass encroaching on the swale (or vice versa) Insert photo Levels of Service B - Good

Noxious and Nuisance Weeds Special considerations need to be identified Provide link to jurisdiction s s web site Photos Identification key Reporting requirements if applicable Spotted Knapweed

Level of Service D - Poor effort Inspection/checklist Sediment is significant Infrastructure is mostly inaccessible Trash is present Significant competition between roots and any pipes Viewlands Cascade

All Levels of Service Stormwater sedimentation structures are less than ½ full or in accordance with NPDES requirements

4-Infiltration Failure Evidence of a cell holding water for more than 24 hours needs to be reported One Call Center for Seattle Operations and Maintenance Asset Manager Monitor swale for ponding water Retrofit swale

5-Recommended Maintenance for Other Elements Pest control Spill prevention and response Safety Mobility Accessibility Permeable pavements Irrigation systems

Manual is a Working Document Work, work, and continue to work with field crews Update photos to continue refining document Document lessons learned Include BMP s

Porous Pavement Cleaning Evaluation Sidewalk and street cleaned and tested Single and combination treatments Pressure washing breaks up top layer and allows for material to be remove Monitoring every six months

January 2009 Before Infiltration rate 0 in/hr After Infiltration rate 208 in/hr

Restoration Infiltration Rates Leaf blower - 0 in/hr Industrial pressure washer @ 3000psi 4.5 in/hr to 21 in/hr Regenerative air sweeper truck - 0 in/hr Walk behind leaf vacuum 0 in/hr Combination treatment 0.75 in/hr to 209 in/hr

Testing Results Combinations Treatments Leaf Blower/Pressure Washer/Street Sweeper Leaf Blower/Pressure Washer Pressure Washer/Vacuum SPU Vactor Truck Pressure Washer/SDOT Pressure Washer Pre Cleaning Infiltration Rate (in/hr) Post Cleaning Infiltratio n Rate (in/hr) Improved Infiltratio n % 0.75 5.3 85.8 2.25 41.5 94.6 0.75 208.9 99.6 0 16.5 100.0

Porous Pavement Seattle porous pavement spec. Inspector and installer checklists BMP s Levels of services Frequency/schedule Standardized infiltration testing Recommended maintenance activities

Checklists Condensed version of manual Developed for each section of the manual Reduce maintenance activities to a summary Eliminate photos Identify key performance indicators monitoring and reporting

Checklist Form - Example photo

Key Performance Indicators (KPI s) Determine LOS achieved for swales Provides an overall reporting score for high level management Indicators help identify successes areas of improvement failures for each system

Key Performance Indicators (KPI s) Data includes Project location Drainage area Maintenance target Reporting of maintenance LOS achieved Provides Accountability Reporting method Excellent asset management tool for management

O&M Estimating Database Tool- Vegetation Inputs: Level of Service Square footage Discount rate Establishment time Life of project Replacement frequency

O&M Estimating Database Tool- Vegetation Summary of Line Item Cost Output Mowing for grass lined swales Plant maintenance inspection including litter and minor weed removal Inspection Watering Mulching above ordinary high water mark Replacement cost (15yr)

Vegetation Estimated O&M Costs LOS B 47,290 SQ FT Initial 3 year Landscape Establishment Total Present Value Annual Value assuming 0% community participation $177,614 $65,221 Established (starting year 4) 0% community participation $562,228 $28,615 25% community participation $421,671 $21,461 50% community participation $281,114 $14,308 75% community participation $140,557 $7,154 90% community participation $56,223 $2,862 Soil Replacement (every 15yrs) $466,952 $23,527

Life Cycle Costs - Pinehurst Present value of O&M + construction costs LCC for Pinehurst (47,290 ft 2 ) $1.2M+ $5.2M = $6.4M Initial estimates $4.8 million construction cost Comparable project to retrofit $8.9 million Total project cost 453K for 660 ft blk Includes all design, project management, const. cost Present value of O&M costs compared to traditional systems is significantly less

Lessons Learn and Risks

Questions? www.seattle.gov/util/naturalsystems