Project Development & Delivery Supporting Document



Similar documents
Asset Management Policy March 2014

Asset Management Services

Sustainable Development Strategy

Our Group strategic framework

Central Cardiff Enterprise Zone. Strategic Plan 2015

Project and Programme Management Capability Improvement Study

Passenger Rail Service Satisfaction Quarter 2 Statistical Release. 18 December Responsible Statistician: Dr Fazilat Dar

Demand for Long Distance Travel

3. Output framework. Key messages in this chapter

TfL and Network Rail s consultation on Crossrail 2 Response from London First

ata ports & harbours airports railways roads & highways info@ata-recruitment.co.uk

Procurement requirements for reducing waste and using resources efficiently

PEOPLE AND ORGANISATION DEVELOPMENT STRATEGIC FRAMEWORK FOR LOCAL GOVERNMENT IN NORTHERN IRELAND

Business Plan. Executive Summary UK Shared Business Services Ltd

BS Collaborative Business Relationships Product Guide

Asset Management. Enabling effective estates strategies >

Midlands Connect. Economic Impacts Study

Consultation on possible location of main site

JOB AND PERSON SPECIFICATION

Network Rail Monitor. Quarters 3-4 of Year 1 of CP5 12 October 2014 to 31 March June 2015

Asset Management Strategy ( ) Doing things Differently A New Approach for a sustainable future

Construction Management

Network Rail Infrastructure Projects Joint Relationship Management Plan

APPENDIX B - PL1 Homes that meet people s needs and aspirations

People & Organisational Development Strategy

Asset management capability

Director Global IT Service Delivery Information Services

Network Rail October 2007 Strategic Business Plan. Supporting Document. Demand Forecasting in the SBP

Senior Project Manager A14 Cambridge to Huntingdon, Complex Infrastructure Programme Grade 6. Candidate Pack

Review of the Assurance and Approval Processes applicable to Investment Projects Progress Update

Managing Extreme Weather at Transport for London. ARCC Assembly - 12 June 2014 Helen Woolston, Transport for London Sustainability Coordinator

The ScotRail Alliance a new approach to our customers and our railway. Phil Verster, Managing Director, ScotRail Alliance

A future driven by innovation

Certification in Humanitarian Supply Chain Management (CHSCM) Competence Model. Final Version 2007

Project Management Manual

Around 33 million journeys are currently made on Metrolink every year. This is forecast to increase to 44 million journeys by 2019.

Long Term Planning Process: London and South East Market Study. October 2013

School of Business and Economics. The Loughborough MBA.

Business Plan. Building Scotland s International Competitiveness

JOB AND PERSON SPECIFICATION

National Passenger Survey Autumn 2012 Main Report

INFORMATION TECHNOLOGY & MEDIA SERVICES

The City of Edinburgh Council Business plan A thriving, sustainable capital city

SOUTH EAST EUROPE TRANSNATIONAL CO-OPERATION PROGRAMME. Terms of reference

The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy

Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change

Project, Programme and Portfolio Management Delivery Plan 6

TOTAL CAPABILITY IN SCAFFOLDING & ACCESS SYSTEMS REACHING NEW HEIGHTS OF INNOVATION & SAFETY

The Loughborough MBA. Inspiring Winners.

How are companies currently changing their facilities management delivery model...?

LONDON GROWTH DEAL. Building London s skills base and supporting businesses; Helping Londoners into sustainable employment; and

Procurement Strategy Delivering Social Value for our Community

Monitoring Highways England The monitoring framework

IMPERIAL WEST TRANSLATION HUB

Stirling s Economic Strategy A Strategy for Jobs

CENTRAL MANCHESTER UNIVERSITY HOSPITALS NHS FOUNDATION TRUST

Commercial Property Features List 2016

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations

place-based asset management

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy

Head of CIO Office Information Services

E: Business support and access to finance

D-G4-L4-126 Police contact management and demand reduction review Deloitte LLP Service for G-Cloud IV

Crossrail Property Impact Study

Lessons learned from creating a change management framework

Trust Board Meeting: Wednesday 11 March 2015 TB Oxford University Hospitals Trust Nursing and Midwifery Strategy

DTZ Insight Public administration employment Major office markets weather the storm

Technical & Engineering: AEROSPACE & DEFENCE

Unleashing your growth potential Product Innovation and Development

Integrated Fares and Ticketing Programme - update

Ubertas Cloud Services: Service Definition

Different approaches and models for sustainability Beej Kaczmarczyk, Learning Curve Group, and Alasdair Redmond, CIO, City of Liverpool College

Sustainable Supply Chain Policy

BBC Technology Strategy

I AM DELIGHTED TO INTRODUCE OUR FIRST COMMUNITY CHARTER, WHICH SETS OUT

Transport for London. Projects and Planning Panel

Transcription:

Project Development & Delivery Supporting Document Our ambition is to be the best rail infrastructure project delivery organisation in the UK Document Ref: SBPT207 Version 0.3

Introduction To achieve the vision of delivering more capacity, moving more passengers faster, more reliably and more safely than ever will require a major capital investment programme. This programme will need to be delivered whilst demonstrating increased levels of value for money, and minimizing the impact on the running of the operational railway. We will build on the successful completion in CP4 of a significant portfolio of works, including Thameslink KO1, Kings Cross Station, FTN/GSMR, and major track renewals and signaling upgrades. However this programme will require us to further improve our capability to effectively and efficiently design, develop, integrate and deliver major projects, programmes and renewals. It will require an innovative approach to delivery, and earlier and stronger collaboration with our supply chain, and to change our approach to the specification and packaging of projects. What we have done so far? Last year we embarked on an ambitious change programme to create an organisation that can provide an effective and efficient customer focused delivery capability and provide outstanding value. We revised our capital project organisation by establishing customer-focused internal project delivery business units in the form of regional organisations matched to routes. We have retained national delivery teams and programmes where there was value in keeping specialist skills and a pan route focus: Regions Western & Wales (including Crossrail) Southern Central Scotland and the North East National Programmes Track renewals Signalling Thameslink FTN/GSMR We introduced a client structure as the first step in creating a full client capability A client capability enabling the effective development and definition of requirements and work aggregation to support efficient delivery. A simplified but robust operating model that delivers: Effective governance and assurance Improved project delivery Improved Efficiency Improved People Capability Key Initiatives Track Delivery Efficiency programme Introduction of a new Quality Management framework Simplification of systems and processes A comprehensive programme of supplier engagement events 10 point people capability workstream Review Areas We created a Network Rail International Consultancy business to enable the sale of consultancy services covering the full range of Network Rail s capabilities. We launched a series of pilot project alliances which will help inform and test or our revised customer and supply chain engagement. We are working to create A further devolved organisation with clear interfaces both with the Network Rail client organisation and the central Network Rail business. Transparency over costs and value adding services will have been achieved. Network Rail 2

Change the Business DIME Programme The DIME Programme was commenced in 2011 with its prime objective being to demonstrate and deliver Value for Money across the rail capital programme, seeking operational cost reductions within the delivery organisations to support the efficient delivery within CP5. The objectives of DIME are to: Create an internal client who defines what they want Re-structure the internal projects delivery business in order to become more market competitive Enable the internal projects delivery business to compete for non-nr work The strategy to achieve this will be to: Create a client capability in each Route who produce clear output requirements Commercialise the relationship between client and deliverer Align deliverer with the Routes Achieve earlier market engagement and greater supply chain collaboration Enable a simple, lean and agile deliverer structure The DIME Programme is split into four phases: Phase 1 Strategic Approval [completed] Phase 2 Programme Validation and Development [completed] Phase 3 Programme Delivery [completed] Phase 4 Programme Implementation and further changes [In Progress] By April 2012, DIME Phase 3 delivered the following: A revised capital project delivery framework which recognises devolution through the establishment of customer-focused internal project delivery organisations in the form of Regional organisations matched to routes. A client organisation structure ready to support the next stage of development in phase 4. An International Network Rail Consultancy business to enable the sale of consultancy services covering the full range of Network Rail s capabilities including Strategic Planning, Asset Management, Operations and Maintenance as well as infrastructure Projects.. A series of Pilot projects which will help inform and test or our revised customer and supply chain engagement approaches, assuring capability improvements. DIME Phase 4 will deliver by the start of CP5: A further devolved organisation with clear interfaces both with the Network Rail client organisation and the central Network Rail business, achieving transparency over costs and value adding services A client capability within the Route organisations, enabling the effective development and definition of requirements and work aggregation to support efficient delivery. A simplified but robust operating model that delivers: Effective governance & assurance Improved Project Delivery Improved Efficiency Capability Network Rail 3

DIME Phase 4 Approach & Outcomes DIME Phase 4 is formed and builds on the Phase 3 deliverables achieved in April 2012 and seeks to deliver the following outcomes: Services: Engage with our clients earlier in the lifecycle enabling greater innovation opportunity Leverage the IP Unique Selling Points (USPs) as well as develop a portfolio of services to be available to the marketplace Deliver and demonstrate whole life cost design solutions Engage with our supply chain earlier in the lifecycle encouraging integrated partnerships and goals Enable vertical alignment across our supply chain with more focus on the 2nd tier Reduce cost of, and improve the value for money from services provided by NRIL to IP Generate flexible business models enabling IP to enter and exit varying markets smoothly Demonstrate we are upper quartile performers compared to our peers Processes: Create an integrated simplified management system across IP Seek ISO 9001, 14001, 18001 and BS11000 accreditation A clear focus on creating simplified, flexible and fit for purpose processes/systems with clear ownership and which effectively interface with our clients Embed knowledge management within IP enabling information re-use and best practice across IP Effective governance and compliance enabling staff greater ability to make timely decisions Improve and simplify performance management information and reporting A focus on work delivered forecasting to enable accurate in-year cost and profit projections Transparent arms length engagement with NRIL People: A customer focussed business encouraging listening, flexibility, responsiveness and demonstrable VFM Live the NR values of honesty, openness, courage and service as well as being a partnering orientated business A strong focus on developing our staff so they have broader skills base whilst maintaining specialist USP skills Staff more receptive and adaptable to change Improved staff performance management Highly engaged and motivated staff Organisation: Be a P&L Business that is geographically structured with national and major programmes A flexible but leaner structure enabling staff to move easily between businesses and simple integration of partners into the business Seek industry awards and be proactive in maximising positive press coverage of IP A mature Business Development /Client Engagement discipline Network Rail 4

Track Delivery Efficiency Programme The Track efficiency programme has two areas of primary focus, these being Safety and Deliverability. The safety focus is on evaluation and development of the new modes of working primarily aimed at supporting an effective reduction in access requirements, whilst deliverability concentrates on technologies and approaches for Plain Line, Switches and Crossings and High Output activities. Network Rail 5

Deliver the Outcomes Regional Performance Current delivery performance can be used as a barometer of future success for CP5. To that end the following sections outline the key achievements to date of the new Regional & Programme organisations established in April 2012. Key Achievements Scotland & NE Region c 55m Finsbury Park to Alexandra Palace re-modelling project The introduction of Alliance contracting on the upgrading of the GN/GE diversionary Route around the ECML. We are also completing the significant civil works as part of the new c 45m Hitchin Grade separation project on the ECML. In Scotland, we are continuing to make good progress on the Edinburgh Waverley station renewals programme including c 12m re-roofing, completion of c 16m Steps project providing access to the lower levels by the Balmoral Hotel. We have recently been awarded the Borders Rail project to create a new Railway between Edinburgh and Tweedbank. At the same time we are working closely with the Scotland Route and Transport Scotland to provide an efficient solution to the 650m Edinburgh to Glasgow Improvements Programme (EGIP) Key Achievements Western & Wales Reading Station bridge slide over live railway, moving 12 months ahead of baseline schedule Commissioning Nuneaton North Chord freight link Award of 2.17bn third party work with Crossrail Limited Early works at Acton and Stockley completed High Output OLE system under construction and operator appointed under ECI Major Early Contractor projects underway for Gowerton, Swindon to Kemble, Energlyn Station, North/South Wales journey time and Freight train lengthening using third party funding Major bridge slide completed across river Loughor in Wales Hitchin Grade Separation installation of beams across the ECML Reading Station Development Works Network Rail 6

Regional Performance Key Achievements Southern Region Waterloo Balcony - A new retail balcony at Waterloo was delivered on time and under budget. Officially opened in July, this scheme has provided eighteen new shops and restaurants, eased overcrowding, and improved access to Waterloo East station. Olympics Infrastructure - Eight Access for All projects were delivered in advance of the Games and platform extensions at Boxhill, Leatherhead and Ashstead were finished ahead of schedule for the men s Olympic cycle road race. In addition, a total of forty-three bridges and associated structures were repainted across the region. East London Line extension Phase 2 - A new 1.3km link was completed as part of the London Overground orbital network. NSIP Projects - Numerous station improvement projects have been delivered including Southampton Central, Network Rail s 250th NSIP project which was opened by the Transport Secretary. The station was completely refurbished including a new art deco style frontage, an enlarged booking hall and waiting room, state-of-the-art information screens and an improved drop-off area. Route Support Many projects have been undertaken at short notice or in an accelerated time frame to support route priorities. Examples include junction lighting between London Bridge & Cannon St and major embankment stabilisation works at Stonegate and Salfords following landslides. Key Achievements Central Region Completion of Liverpool Central Station. Key programme milestones completed on the electrification of Manchester to Liverpool. Commencement of Manchester Victoria Roof. Introduction of novel Alliance approach on the Stafford/Norton Bridge project. Commencement of Evergreen 3 (Bicester to Oxford) in alliance with Chiltern Railways. Birmingham Gateway Project Construction of Moor Street Link Network Rail 7

Programme Performance Key Achievements Track More mechanised delivery of PL track than in previous years with 5 high output systems (40% of PL). Enabled adjacent line opening for both freight and passenger trains, higher speed hand back (80mph+) and improved track quality on West Coast, East Coast and East Midland Routes. More modular S&C delivery (60%+) using state of the art Tilting Wagons and cranes. Delivered our first 2 mid-week S&C sites in mid-week 8hr possessions. A number of technology and innovation trials under way to increase efficiency following Benchmarking visits to Europe and InnoTrans. e.g. highly automated, mechanised and safer S&C refurbishment, signalling plug & commission & high output on 3rd rail routes. Key Achievements Thames Link Programme Commissioned KO1 Signalling in the core (final phase) Final KO1 protocol milestone achieved Easter 2012 KO1 new timetable commenced on schedule May 2012 Achieved full operational functionality at Farringdon & Blackfriars prior to Olympics London Bridge: commencement of train shed roof works Completion of KO2 GRIP4 with estimate in line with budget. Authority paper for 1.9bn incremental authority endorsed by NRIP to November NR Board Blackfriars roof at 9th July 12 Network Rail 8

Programme Performance Key Achievements FTN / GSMR Programme Integrated Network Rail and Industry team to deliver the programme. 4910 train cab units fitted to accommodate GSM-R radios out of a total of 7,800 Installation of 15,000km of optical fibre, 3,200 communication nodes and 2,500 radio masts. Current active operation of the GSM-R network by 16 TOC s/foc s on 31% of the operational railway with a target to bring live south of the Severn/Wash by the end of December 2012 Agreements with TOCS and FOCs on G1 Network Change (NCN5) and commercial compensation terms. Key Achievements Signalling Programme Delivering 12/13 to date the following commissionings Stourbridge to Hartlebury East Suffolk Water Orton Harrogate NASR II Stalybridge. 1300 Signalling Equivalent Units, SEU s delivered 12/13 to date. TM demonstrator delivered. Delivery of Framework contracts and the drive to collaboratively deliver. Network Rail 9

Manage the Business Central Support Organisation Performance The central functions provide the governance, assurance and process consistency across Infrastructure Projects organisation. Key Achievements Finance & Commercial: Improved IPSOS survey results with proportion of dissatisfied suppliers now below the 15% benchmark Commercial Directors Forum Implementation of the Fair Payment Charter BS11000 Certification and the expansion of the collaborative working programme Developed and implemented capital projects alliances including the development of new alliance procurement processes Delivered collaborative awareness workshops for Band 1&2 managers in IP in order to support cultural & behavioural change Development of the Rail Method of Measurement cost planning tool Procurement of a new suite of Professional Services Framework Agreements to support project delivery Key Achievements Programme & Technical Services Efficiency savings of 1.1m Created the Quality Management team, framework and plan for the IP business Mapped and identified the key business systems and begun a programme of significant rationalisation Developed and commenced delivery of the Total Value systems engineering training programme. Delivered the Project Automated reporting suite to the IP business. Created an IP business plan to complement the SBP Supported the DIME change programme Delivered effective governance over the bank holiday working activity Network Rail 10

Central Support Organisation Performance Key Achievements Safety & Sustainability Effective delivery of the Life saving Rules to the IP teams and throughout the supply chain Delivery of the revised Close Call Reporting System Delivery of highly respected CDM and Behavioural Safety training courses, including external service provision Support to the Green Construction Board on carbon reduction in infrastructure Delivery of pan industry environmental forums Delivery of several high profile safety communication campaigns through the safety trucks including occupational health and linkage with Cancer Research Key Achievements Human Resources Launched a pilot Inclusive Leadership Programme; Supported 220 individuals who have left IP through the DIME process; Completed the first comprehensive Talent assessment across the business using the Korn Ferry nine-box grid process; Recruited 420 new staff into the business ; Completed the transfer of Track business into IP; Supported the launch of the new NR Consultancy business; Consulted unions and staff on upcoming relocation of central staff to MK:Quadrant; Provided ongoing support to employees and Managers through the devolution process, as we separated into Regions and programmes. Network Rail 11