Section JACK AND BORE. This specification provides the requirements for using the jack-bore for the project.

Similar documents
CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Special Specification 7021 Water Main and Sewer Line Replacements

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION SHEETING, SHORING AND BRACING

SECTION 2 POTABLE WATER SYSTEMS 2.1 GENERAL 2.2 SYSTEM DESIGN

FY08 SEWER POINT REPAIRS BID TABULATION

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION GRAVITY SANITARY SEWERS

SECTION DUCTILE IRON PIPE AND FITTINGS

Section 2100-Trenching and Tunneling

SECTION POLYVINYL CHLORIDE (PVC) PIPE

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Wastewater Capital Projects Management Standard Construction Specification

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION 3 SANITARY SEWER DESIGN

SECTION 603 SANITARY SEWER FORCE MAINS

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION PRECAST CONCRETE UTILITY STRUCTURES

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

SECTION DUCTILE IRON PIPE AND FITTINGS

SECTION SANITARY SEWER PIPE

Section 402. STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

CONSTRUCTION PERMIT REQUIREMENTS

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

SANITARY SEWER SPECIFICATIONS

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

SECTION STORM DRAINAGE SYSTEM

MDWASD 8/1999 SECTION TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

DIVISION 4300 STORM DRAINAGE

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

Construction Standards for the City of Bristol, Tennessee. Adopted: January 8, 2002

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SECTION SUPPORT OF EXCAVATION

SECTION 15 AIR RELEASE VALVE ASSEMBLIES General

SECTION STORM DRAIN SYSTEM

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

SECTION ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL

SECTION EARTH MOVING

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

SECTION ABANDONMENT OF SEWER MAINS

SECTION GROUND WATER STORAGE TANKS

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

SECTION POLYVINYL CHLORIDE (PVC) PIPE

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

LS 2540 SEWER LATERALS AND INSPECTION TEES

Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING

City of Lubbock Public Works Engineering Design Standards and Specifications

High Strain Dynamic Load Testing of Drilled Shafts

C. Section TESTING LABORATORY SERVICE.

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

SECTION REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:

DESCRIPTION OF WORK:

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

INSTALLATION OF INSITUFORM LINER

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION 802 GRAVITY SEWER PIPE

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

ASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.

CITY ENGINEERS ASSOCIATION OF MINNESOTA

Let Us Give Utilities the Respect that they Deserve.

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

SECTION 5: SANITARY SEWER SYSTEM DESIGN

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

SECTION PRECAST CONCRETE STRUCTURES

CHAPTER 8 CIVIL DESIGN

SECTION SELECTIVE DEMOLITION

Transcription:

CCU STANDARD SPECIFICATIONS Section 002445 JACK AND BORE Effective Date: Nov. 1st, 2011 Page 1 of 6 PART 1 - GENERAL 1.1 SCOPE It is the intent of this specification to provide the requirements for any jacking-boring for the project. All jack-bore installations shall meet the requirements of the Florida Department of Transportation (FDOT) permit, if applicable 1.1.1 General: This specification provides the requirements for using the jack-bore for the project. 1.1.1 Work Included The Contractor shall, unless specified otherwise, furnish all labor, materials, equipment, tools, and all other associated appurtenances necessary to do the work required under the contract to include but not limited installing the steel casing, installing the carrier pipe and the placement of spacers, between the carrier pipe and the steel casing, and sealing the ends of the casing pipe. 1.1.2 Location of the Work The location of this work is as shown on the Contract Documents 1.1.3 Coordination of the Work The Contractor shall be responsible for the satisfactory coordination of the jack-bore with other construction and activities in the project area. Delays in work resulting from lack of such harmony shall not in any way be a cause for extra compensation by any of the parties. 1.1.4 Working Hours The work shall be carried out in accordance with local ordinance and so as not to cause any unreasonable nuisance to affected residents. Under emergency conditions, this limitation may be waived by the consent of Charlotte county Utilities (CCU).

1.2 METHOD OF MEASUREMENT & PAYMENT The work shall be measured and the compensation determined in the following manner: 1.2.1 Jacking-Boring Jacking-Boring of the casing pipe shall be paid for at the contract bid price per lineal foot installed for each size specified which shall included the cost of furnishing all casing pipe, casing end seals, casing pipe jointing material and all other appurtenances and the cost of the jacking pits, grouting, dewatering, trenching, sheeting, backfilling, restoring the surface (unless separate bid item is provided), necessary permits and all other labor, equipment, and materials, necessary to install the casing pipe complete in place at the depth specified and in accordance with the plans and these specifications. Carrier pipe shall be paid as per the applicable type of pipe specifications. Restraints and carrier pipe spacers shall be considered incidental to the carrier pipe and no direct compensation will be made therefore. 1.3 REFERENCED STANDARDS (Latest Revision) ASTM Designation A252, ASTM Designation A139 AASHTO Code NSF: Standard 61 Florida Administrative Code FDEP: Wastewater Collection/Transmission System Requirements Ten States Recommended Standards for Wastewater Florida DOT Standard Specifications for Road and Bridge Construction FDOT Utility Accommodation Guide Specifications for Pipelines Conveying Nonflammable Substances (American Railway Engineering Association) 1.4 PARTIAL LISTING OF RELATED SECTIONS 001570 - Erosion and Sediment Control 001760 - Surveying and Record Drawings 002240 - Dewatering 002320 - Gravity Sewer Systems 002325 - Force Mains 002330 - Low Pressure Sewer Systems 002335 - Potable Water and Reclaimed Water Mains 002340 - Valves 002345 - Fire Hydrants 002530 - Submersible Sewage Pump Lift Station-Package Design 002540 - Submersible Sewage Pump Lift Station- Standard Design 002930 - Grassing Page 2 of 6

Note: This is only a partial listing of related sections. The Contractor shall be responsible to review the entire contract documents. 1.5 SUBMITTALS 1.5.1 For only those materials that the Contractor is requesting deviations from these specifications, the Contractor shall submit in writing documentation to justify approval of these materials by Charlotte County Utilities (CCU) prior to the start of the project. The Contractor shall submit four (4) signed copies of the material submittals. 1.5.2 The contractor submittals shall include the statement that the submittals have been reviewed and the materials meet the contract specifications and/or standard details. 1.5.3 Final approval is at the discretion of CCU. PART 2 - PRODUCTS 2.1 MATERIALS 2.1.1 General The materials used in this work shall be all new and conform to the requirements for class, kind, size and material as specified below. Proper implements, tools, and facilities shall be provided and used by the Contractor for the safe and convenient execution of the work. The Contractor shall meet the jointing and cutting pipe direct bury force main, low pressure sewer systems, potable water and reclaimed water mains requirements as they apply to the jack-bore. 2.1.2 Steel Casing Pipe for Jacking-Boring Steel casing pipe for jacking-boring shall conform to ASTM Designation A252, Grade 2 or ASTM Designation A139, Grade B. Recycled steel casing pipe conforming to the requirements of this section as approved by CCU may be used. Proper documentation shall be provided. The minimum casing pipe size and wall thickness shall be as shown in the following table. For sizes not included, or for special design considerations and/or in the case of known aggressive soils, approval shall be obtained from CCU. The casing pipe nominal diameter shall be 10 inches larger than the carrier pipe outside diameter. Page 3 of 6

Casing Pipe Nominal diameter (Inches) 2.1.3 Carrier Pipe for Jacking-Boring: Casing Pipe Minimum Shell Thickness (Inches) 12 0.250 14 0.282 16 0.282 18 0.312 20 0.343 22 0.375 24 0.403 26 0.438 28 0.469 30 0.469 32 0.500 34 0.532 36 0.532 38 0.563 40 0.563 42 0.563 The carrier pipe shall be PVC, ductile iron or HDPE in accordance with CCU technical specifications. 2.1.4 Casing End Seals for Jacking-Boring: Casing end seals shall be Plico or approved equal 2.1.5 Joints for Jacking-Boring: All carrier pipe joints shall be restrained to include the first joint outside of the casing. 2.1.6 Casing spacer: Casing spacer by Cascade Waterworks Manufacturing Co., or approved equal, shall be used. Stainless steel nuts and bolts shall be used. PART 3 - EXECUTION 3.1 GENERAL REQUIREMENTS The Contractor shall comply with all appropriate regulatory agency requirements respectively as per the permits issued for this project. Page 4 of 6

3.2 CONSTRUCTION REQUIREMENTS Steel casing pipe shall be jacked-bored in place to provide a casing for the carrier pipe. Jack-bore pits or shafts shall be excavated and maintained to the minimum dimension necessary to perform the operation. Said excavations shall be adequately barricaded, sheeted, braced and dewatered, as required, in accordance with CCU Specifications and OSHA requirements. Jack-bore pits will normally be no closer than four feet from the edge of pavement, with the permitting agency having final determination of the required setback distance. The jack-bore operations shall be done simultaneously, with continuous installation, until the casing pipe is in final position. Correct line and grade shall be carefully maintained. Add on sections of casing pipe shall be full-ring welded to the preceding length, developing watertight total pipe strength joints. The casing installation shall produce no upheaval, settlement, cracking, movement, or distortion of the existing roadbed or other facilities. Casing pipes crossing under roadways/railroads shall be located at suitable approved alignments in order to eliminate possible conflicts with existing or future utilities and structures, with a minimum 36-inch depth of cover between the top of the casing pipe and the surface of the roadway. For casing pipe crossings under roadways/railroads, the Contractor shall comply with the regulations of said authority in regard to design, specifications, and construction. State highway casing installations shall be as specified in the FDOT, "Utility Accommodation Manual," and for railroads the American Railway Engineering Association, "Specifications for Pipelines Conveying Nonflammable Substances," shall be applicable. Casing pipe holes shall be mechanically bored through the soil by a cutting head on a continuous auger mounted inside the pipe. The auger shall extend a minimum distance beyond the end of the casing pipe to preclude formation of voids outside of the pipe shell. The casing pipe shall be adequately protected to prevent crushing or other damage under jacking pressures. Backstops shall be provided for adequately distributing the jack thrust without causing deformation of the soil or other damage. Should the casing pipe be damaged, such damaged portion, if not in the hole, shall be replaced; however, if inserted, the encasement pipe shall be abandoned in place, grouted full, and suitably plugged, and an alternate installation made. The ends of the casing pipe shall extend on both sides a minimum distance of four feet beyond the edge of pavement or as specified in the permit requirements or designated on the engineering drawings, whichever is greater. The casing pipe shall be cut and trimmed. Once cut and trimmed the ends of the casing pipe shall be sealed to the carrier pipe using casing end seals, mechanically fastened to both pipes. Once the casing pipe is in place, the actual carrier pipe shall be installed inside the casing. All carrier pipes shall be installed with restrained joints as shown on CCU Standard Details. The carrier pipe shall be installed within the casing pipe using stainless steel casing spacers to center the carrier pipe within the casing pipe. The casing runner height shall be large enough so that it does not interfere with the pipe-restrained joints. The spacers shall be equally spaced Page 5 of 6

along the length of the casing pipe. All carrier pipe joints in the casing shall be restrained to include the first joints outside of the casing and the carrier pipe shall be restrained to the adjoining mains. END OF SECTION Page 6 of 6