Strategic Plan for Mercury Remediation at Y-12

Similar documents
Proposed Plan for Outfall 200 (OF200) Mercury Treatment Facility (MTF)

Strategic Plan for Mercury Remediation at the Y-12 National Security Complex Oak Ridge, Tennessee

FINAL PLAN OF REMEDIAL ACTION

External Technical Review of the Mitigation and Remediation of Mercury Contamination at the Y-12 Plant, Oak Ridge, TN

Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Even collection systems with high-performing operation and maintenance programs will eventually

8.30 PBS SR-0030 Soil and Water Remediation

Performance Management for Environmental Remediation Projects. William C. Lattin, PMP US Department of Energy Idaho Operations Office

Risk-Based Decision Making for Site Cleanup

5. Environmental Analysis

11.0 WORK SCHEDULE, WORK PLANS, AND ASSOCIATED REPORTS

Proposed General Plan Update Goals, Policies, and Implementation Actions

Section 4 General Strategies and Tools

2006 Standard Application Processing Time. 10 months. 14 months

DRAFT. GROUNDWATER REMEDY COMPLETION STRATEGY: Moving Forward with Completion in Mind

ENVIRONMENTAL QUALITY

Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination

Part B Integrated Monitoring Design for Comprehensive Assessment and Identification of Impaired Waters Contents

Installation Environmental Restoration Defense Logistics Agency, Defense Supply Center Richmond Narrative

ENVIRONMENTAL PROTECTION AGENCY

REQUEST FOR PROPOSALS

April 30, 2013 E M. Environmental Management. safety performance cleanup closure

Site Description and History

7.0 Stream Restoration

TRAINING SPCC/SWPP Training UGA. Automotive Center. Campus Transit

Baltimore City Phase II Watershed Implementation Plan (WIP) July 2, 2012

Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN

Unauthorized Discharges and Sanitary Sewer Overflows

Region 8 Conference Amalgam Separators What s New? 101 Review May 11 14, 2009

GENERAL OBLIGATION BONDS

11 September 2002, 0930 Hours

Site Description and History

INTRODUCTION TO GREEN & SUSTAINABLE REMEDIATION: THREE APPROACHES

DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF WATER QUALITY PROTECTION. Policy for Permitting Surface Water Diversions

The Buffalo River Restoration Project Frequently Asked Questions

UNDERGROUND STORAGE TANK SYSTEM CLOSURE REPORT FORM

CITY CLERK MEMORANDUM 15-70

A sediment monitoring program for North America

DOE/ORO Cleanup. Progress. Annual Report to the Oak Ridge Community

Development of A Risk Informed Approach to D&D Priority Setting Forensic Evaluation of D&D at Oak Ridge with a Focus on K 25 and K 27

Floodplain Connectivity in Restoration Design

Proposed Terms of Reference for EIA studies

Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting

DOCUMENTATION OF ENVIRONMENTAL INDICATOR DETERMINATION Interim Final 2/5/99 RCRA Corrective Action Environmental Indicator (EI) RCRIS code (CA725)

NASA Stennis Space Center Environmental Resources Document

Environmental Cleanup Update Briefing on the Portsmouth Gaseous Diffusion Plant Joel Bradburne DOE Site Lead Portsmouth/Paducah Project Office

BJC/OR-271 Guidance for Conducting Risk Assessments and Related Risk Activities for the DOE-ORO Environmental Management Program

How To Manage Waste In The Northwest Tokson

Preventing Storm Water Pollution: What We Can Do

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

Natural Resource Damage Assessment. Emphasis on Groundwater May 4, 2004

SPCC for Food Services

Greater Los Angeles County Region

WASTEWATER TREATMENT OBJECTIVES

March 21, Environmental Management Program Strategies: A National Responsibility

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.

CHAPTER 103. FINANCIAL ASSISTANCE

Capital Construction and Debt Service

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

Save Our Heritage Organisation v. San Diego Unified Port District

Wyckoff/Eagle Harbor Site Bainbridge Island, Washington

Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan

Chapter 22: Overview of Ecological Risk Assessment

DOCKET NO. D CP-2 DELAWARE RIVER BASIN COMMISSION

COST AND PERFORMANCE REPORT

Sediment Management Standards Cleanup Action Decision: Duwamish/Diagonal CSO/SD

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

1.7.0 Floodplain Modification Criteria

Combined Sewer Overflow Control

Street Address (number and street): City: County: ZIP Code: B. CURRENT SITE PRIORITY INFORMATION Was free product present this quarter?

Georgia Department of Public Health. Georgia Onsite Sewage Management Systems. Background and Use of Onsite Wastewater Treatment Systems in Georgia

SECTION 3.2 CLIMATE AND PRECIPITATION

REMEDIAL ACTION PERMITS FOR GROUND WATER GUIDANCE

Kansas City s Overflow Control Program

Agua Hedionda Creek Flood Plain Information; Department of Army, Los Angeles District,

Introduction to Lockheed West Seattle. Working Together. Site Background. Lockheed West Seattle Superfund Site

Title 27A. Environment and Natural Resources Chapter 1 - Oklahoma Environmental Quality Act Article III - Jurisdiction of Environmental Agencies

FACT SHEET STATEMENT OF BASIS HARLEY DOME 1 PRODUCED WATER TREATMENT FACILITY UPDES PERMIT NUMBER: UT NEW PERMIT MINOR INDUSTRIAL

DOCUMENTATION OF ENVIRONMENTAL INDICATOR DETERMINATION Interim Final 2/5/99 RCRA Corrective Action Environmental Indicator (EI) RCRIS code (CA750)

Rouge River Watershed, MI Region 5. Community Case Study ROU-1. Number of CSO Outfalls. Combined Sewer Service Area. Wastewater Treatment Capacity

City and County of San Francisco 2030 Sewer System Master Plan TASK 400 TECHNICAL MEMORANDUM NO. 405

Wastewater Regulation and Designing Changes in South East Asia

WQBELs Part II: Characterizing the Effluent and Receiving Water. David Hair Environmental Engineer US Environmental Protection Agency Washington, DC

Swamp Area Passive Treatment System Kettle Creek Watershed, Clinton County, PA

Environmental Protection Agency

Pamela Birak, Jordan Lake State Park, Chatham County, NC

City of Charlottetown Wastewater Treatment Expansion & Upgrading

Addendum. Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek. February 23, 2009

PERMITTEE/FACILITY NAME: City of Detroit Water and Sewerage Department / Detroit Wastewater Treatment Plant

SAMPLE CHAPTERS UNESCO EOLSS SURFACE WATER MONITORING. Masanori Ando Musashino University, Japan

RDCO Area East Liquid Waste Management Plan Options. Public Information Meetings Sep 30 and Oct 1, 2008

Clean Water Services. Ecosystems Services Case Study: Tualatin River, Washington

County Watersheds. Total Project Cost - $11.1 M. Project Description. Funding Sources. Project Milestones. Service Impact

5.14 Floodplains and Drainage/Hydrology

INTRODUCTION AND BACKGROUND

NEVADA CITY WASTEWATER TREATMENT INQUIRY

Spill Prevention, Control and Countermeasure (SPCC) Training

NPDES Permit No. IL Notice No. JAR: jar. Public Notice Beginning Date: February 21, Public Notice Ending Date: March 25, 2013

New Cumberland Army Depot Formerly Used Defense Site (FUDS) Marsh Run Park Site Restoration Community Meeting

Transcription:

Strategic Plan for Mercury Remediation at Y-12 Laura Wilkerson Portfolio Federal Project Director for Y-12 Projects ORSSAB Meeting April 9, 2014 1

Y-12 National Security Complex (Y-12) City of Oak Ridge ETTP Y-12 ORNL 2

Mercury Contamination Resulted from Historical Operations Beta-4 Hg Recovery Furnace Alpha-5 Alpha-4 Alpha 2 3-4 -

Historical Mercury Releases From 1950s 1963 more than 20 million pounds of mercury were used at Y-12 in a process that separated lithium isotopes for weapons production Approximately 2 million pounds of mercury were unaccounted for Of the 2 M pounds, over 700,000 pounds suspected to have been released to the environment (air, surface water, soils/sediments) Y-12 workers unload and dump mercury flasks circa 1955 4

Mercury Cleanup Objectives at Y-12 Reduce mercury flux leaving site and entering public waters Remove or stabilize mercury sources (buildings and soil/sediment) Remove and dispose of excess, deteriorating facilities Remediate land and make available for future needs and missions 5

Mercury Strategic Plan Background Draft Strategic Plan submitted March 2013, followed by Mercury Workshop in August 2013; Strategic Plan updated and final issued January 2014 Mercury contamination is a complex problem that requires a phased deliberate, and multi-pronged approach that is responsive and adaptive Strategy includes near term and long term actions to complete mercury remediation at Y-12 Building, Equipment Demolition Augmentation relocation and/or reduction Clean water diversion Future contact water management Flow Augmentation Secondary Pathway Mercury Project Beta-4 Partial LMR Alpha-5 LMR & Bldg Characterization S&M mercury removal UEFPC Bank Stabilization Water Management Possible need to line stream bed and/or bank Research, develop, demo, apply In Situ remediation Source Isolation Completed & Ongoing Scope Source Removal Capture and Treat Technology Development and Planning Future Scope Construct and operate new Outfall 200 MTF Assess operations and need for further actions BSWTS CMTS OF200 MTF Conceptual Design Free Mercury Removal 5 Tanks D&D 81-10 Characterization WEMA Sewer Cleanout SPSS Treatability Studies for Soils Soils Feasibility Study Soil Vapor Analysis Site Conceptual Model Hg water/fish/sediment studies Technology Development Plan Debris treatability study Fate and transport modeling Soil, Sediment, Subsurface Remedial Actions 6

Near-Term Goal: Reduce Mercury Discharges to Surface Water Hg, Mercury, (µg/g (fish), (ppm µg/l [fish], (water)) µg/l [water]) 2.0 1.8 1.6 1.4 1.2 1.0 0.8 0.6 Water Fish 175 175 150 150 125 100 125 75 100 5075 2550 025 Average Daily Hg Flux (g/d) leaving UEFPC Average Daily Hg Flux (g/d) leaving UEFPC Water Redbreast Rockbass 1983 0 1987 1991 1995 1999 2003 2007 2011 1983 1987 1991 1995 1999 2003 2007 2011 Mercury Flux (kg/yr) 2009 3.90 2010 7.00 2011* 12.20 2012 11.10 2013 5.20 *WEMA Storm Sewer Cleanout 0.4 FDA Fish Consumption Advisory Surface Water ROD Limit 0.2 NPDES Permit Level Surface Water 0.0 BSWTS start AWQC/Surface Water 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 7

Regulatory Standards for Mercury in Water 2000 1500 Mercury Concentration (ng/l, ppt) 1000 Federal Drinking Water Standard (2,000 ppt) State AWQC Continuous Discharge Aquatic Life (770 ppt) Average Mercury Concentration at Station 17 500 0 Interim ROD Goal (200 ppt) State AWQC Recreational Use (51 ppt) 8

Near-Term Plan Proposed Mercury Treatment Facility Revised conceptual design to be submitted for regulatory review in April Conceptual Design To treat flow at OF 200 Capacity 3,000 gallons per minute Allows for further expansion modular and scalable design FY 2014/15: Studies to refine treatment parameters, examine storm and process flows for possible diversion, characterize site Mercury remediation goals Reduce mercury flux leaving creek and entering public waters Provide future mercury reduction capabilities for wastewater projected to be generated during large-scale demolition Line Item Capital Project Preliminary design planned to begin in FY 2015 Operational by FY 2020 9

Mercury Treatment Facility Schedule CERCLA Documents *D2 RDWP FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 FY 2021 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 *Focused FS/Proposed Plan 9/30/2014 *UEFPC Ph I ROD Amendment 9/30/2015 *Remedial Design Report 9/30/2016 *Remedial Action Work Plan 9/30/2017 Pre-Design Studies *Multiple studies (e.g., storm flow) Design *Prepare Design Plan & Criteria *Preliminary Design *Final Design Site Development/Construction *Construction *Facility Startup DOE HQ Approval *Prepare/Submit Critical Decisions CD-1 CD-2/3 CD-4 *HQ Review/Approval Review and approvals under CERCLA. = FFA Appendix E Milestones. 10

Ongoing Studies/Actions UEFPC flow augmentation to be eliminated Began in 1996, 4.5 M gal per day flow added per NPDES permit requirement Increases mercury flux due to re-suspension of sediment Ongoing field studies in EFPC and related laboratory studies Fish mercury/population studies and trends Methylation studies Mercury sources in LEFPC (bank erosion studies, sediment characterizations) Floodplain mercury bioaccumulation studies (spiders) in the FIELD...in the Laboratory 11

Additional Near-Term Studies Proposed Proposed studies outlined in Mercury Strategic Plan planned to begin this FY, based on sufficiency of funding and priorities Field Research Station Eco-Enhancement Water Chemistry Manipulations LEFPC Sediment/Bank Stabilization UEFPC Sediment Stabilization/Removal Reclassification of UEFPC (OF200 to St. 17) Eco-Enhancement Field Research Station 12

Near-Term Approach FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 FY 2024 Diversion Studies WEMA Process flows Watershed diversion Storm Flow/Modeling Implement Feasible Diversions OF200 Mercury Treatment Facility Design and Construction OF200 MTF Operation Evaluation of: Hg removal efficiency Effluent discharge 1200 ft downstream Flow Augmentation (reduce, relocate, eliminate) EFPC Field Studies Fish mercury/populations/other Methylation studies Mercury sources; sediment/bank studies (Action Plan 1) Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 (proposed studies will float within this 6-year time frame) CERCLA Alternatives Evaluation Alternative Action(s); duration TBD Field Research Station [2 years] Eco-Enhancement [2 ½ + years] Water Chemistry Manipulations [2 years] LEFPC Sediment/Bank Stabilization [3 years] UEFPC Sediment Stabilization/Removal [1 year] Reclassification of UEFPC (OF200 to Station 17) [1 + year] Planned Actions/studies currently in budget Proposed Actions/studies not currently in budget 13

Long-Term Goal: Mercury Source Remediation Four large former mercury use buildings to be demolished Local soil remediation to follow each building demolition Cleanup to occur along side ongoing missions and within high security footprint Remediation to include UEFPC sediments and Lake Reality 14

Y-12 Mercury Clean-up Schedule Oak Ridge Environmental Management Planning Baseline Y-12 Outfall 200 Mercury Treatment Facility Planning, Construction ( ) and Operation ( ) Ongoing/Proposed Field/Laboratory Studies ( ) Possible Follow-on Actions (, duration?) Mercury-Use Facility D&D and RA Other Mercury-Related RA and RODs = CERCLA Alternatives Evaluation Fiscal Years (2014 2046) 14-17 18 22 23-27 28-32 33-37 38-46 Mercury-Related D&D and RA Scope 15

Summary of Strategic Plan Plan presents phased approach to reaching goals, including in-stream AWQC for mercury, 51 ppt Near-Term Plans (Interim Actions) Outfall 200 Mercury Treatment Facility design, construction, operation Ongoing fish-mercury studies, bank studies, flow augmentation modification Proposed eco-enhancement, water chemistry, stabilization studies Long-term plans for source removal Building demolition Soil remediation UEFPC sediment and Lake Reality remediation 16