VII. Monitoring and reporting



Similar documents
U N I T E D N A T I O N S E N V I R O N M E N T P R O G R A M M E. Evaluation Manual EVALUATION AND OVERSIGHT UNIT

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT

Identification. Preparation and formulation. Evaluation. Review and approval. Implementation. A. Phase 1: Project identification

Northern Delaware Intergroup Bylaws January 2010

UNDP Programming Manual December Chapter 7: MONITORING, REPORTING AND EVALUATION Page 1

PARTICIPATORY SELF-EVALUATION REPORTS: GUIDELINES FOR PROJECT MANAGERS

REPORT 2016/066 INTERNAL AUDIT DIVISION. Audit of management of technical cooperation projects in the Economic Commission for Africa

Declaration to be submitted by directors in the Applicant Company 1

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism

Regulation on the implementation of the Norwegian Financial Mechanism

Implementation Plan: Development of an asset and financial planning management. Australian Capital Territory

LORD CHANCELLOR S CODE OF PRACTICE ON THE MANAGEMENT OF RECORDS UNDER

ACCOUNTING POLICIES AND PROCEDURES SAMPLE MANUAL

PAPER-6 PART-5 OF 5 CA A.RAFEQ, FCA

SAMPLE FINANCIAL PROCEDURES MANUAL

Risk Management Strategy EEA & Norway Grants Adopted by the Financial Mechanism Committee on 27 February 2013.

Project Management Guidelines

H:\Cost\OMB\OMB completed templates\subpart F-Audit Requirements\Subpart F Audit Req Word Docs\Uniform-Guidance-Section_200.

(2) They shall come into force on the date of their publication in the Official Gazette.

International environmental governance. Bali Strategic Plan for Technology Support and Capacity-building

CARRIAGE MUSEUM OF AMERICA ACCOUNTING POLICIES AND PROCEDURES MANUAL. February 2014

Internal Audit of the Georgia Country Office

AGENCY MANAGEMENT FRAMEWORK FOR INSURANCE AGENT

Changes introduced in this new edition of the UNEP project manual are listed below: 1. A. Conceptual foundations of UNEP programmes and projects

The size and composition of the Board is to be determined from time to time by the Board itself in an effort to balance the following goals:

INSPECTION MANUAL FOR CREDIT RATING AGENCIES

EVALUATION OF THE CORPORATE PERFORMANCE MANAGEMENT FRAMEWORK

STATUTORY INSTRUMENTS SUPPLEMENT No. 1 11th May, 2012.

ANNEXURE 1 Policy for Managing the Performance of Section 57 Employees of the City of Johannesburg

REPORT 2014/078 INTERNAL AUDIT DIVISION

GODADDY INC. CORPORATE GOVERNANCE GUIDELINES. Adopted as of February 3, 2015

Agenda item number: 5 FINANCE AND PERFORMANCE MANAGEMENT OVERVIEW AND SCRUTINY COMMITTEE FUTURE WORK PROGRAMME

FROM: «Contract_Start_Date» VENDOR ID NUMBER: TO: «Contract_End_Date» «Federal_Tax_ID_» FUNDING AMOUNT FOR INITIAL PERIOD: «Contract_Amount»

Schedule of Charges. 1st January 2015 to 30th June Consumer Finance

APPENDIX 3B Financial Criteria for Retention on the Specialist List and Requirements for Acceptance of a Tender

Charter of the Audit Committee of the Board of Directors

HALOGEN SOFTWARE INC. AUDIT COMMITTEE CHARTER. oversee the qualifications and independence of the independent auditor;

Livelihoods and Food Security Trust Fund (LIFT) Skills and Vocational Training in Rakhine State

The ASCA National Model: A Framework for School Counseling Programs. Program Audit

Decisions of the Board Eighth Meeting of the Board, October 2014

Using the logical framework matrix

TERMINAL EVALUATION TERMS OF REFERENCE

Department of Defense Information Assurance Scholarship Program. Sponsored by the. DoD Chief Information Officer

COVERAGE: All Employees

How To Monitor A Project

website: BYE-LAWS & REGULATIONS

FERRARI N.V. AUDIT COMMITTEE CHARTER (Effective as of January 3, 2016)

Rolls Royce s Corporate Governance ADOPTED BY RESOLUTION OF THE BOARD OF ROLLS ROYCE HOLDINGS PLC ON 16 JANUARY 2015

Guidance Note on Developing Terms of Reference (ToR) for Evaluations

Children s Council of the International Technology and Engineering Educators Association

CORPORATE BUSINESS CONDITIONS

South Puget Sound Community College Emergency Operations Plan Annex H RECOVERY

ITS Project Management

BOTTOMLINE TECHNOLOGIES (DE), INC. AUDIT COMMITTEE CHARTER

Municipal Accounting ULB Level Reform

AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT HUMAN RESOURCE AUDIT PROGRAM

F I N A N C I A L R E G U L A T I O N S

HEWLETT-PACKARD COMPANY CORPORATE GOVERNANCE GUIDELINES

TERMS OF REFERENCE FOR PROJECT MANAGEMENT AND SUPERVISION CONSULTANTS REHABILITATION AND UPGRADE OF SCADA SYSTEM AND EMS

Guidance on the Governance and Management of Evaluations of Horizontal Initiatives

Introduction. Acknowledgments Support & Feedback Preparing for the Exam. Chapter 1 Plan and deploy a server infrastructure 1

Timor- Leste. United Nations Development Programme. Vacancy Announcement

C ONTENTS. Acknowledgments

MEMORANDUM OF UNDERSTANDING BETWEEN THE CITY OF WALNUT CREEK AND DIABLO REGIONAL ARTS ASSOCIATION

College Governance Statement of Principles, Scheme of Delegation and Terms of Reference

Part 1. MfDR Concepts, Tools and Principles

3 BUSINESS ACCOUNTING STANDARD,,INCOME STATEMENT I. GENERAL PROVISIONS

How To Write Project Management Guidelines

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management

U.S. DEPARTMENT OF THE INTERIOR SENIOR LEVEL AND SCIENTIFIC AND PROFESSIONAL PERFORMANCE AGREEMENT AND APPRAISAL SYSTEM.

1 of 7 31/10/ :34

NATIONAL UNIVERSITY OF SCIENCE AND TECHNOLOGY

Center for Medicare and Medicaid Innovation

CORPORATE GOVERNANCE GUIDELINES

UNICEF FINANCIAL REGULATIONS AND RULES LEGACY FRRs vs AMENDED FRRs MATRIX

Environmental and Material Flow Cost Accounting

Tweet. Share. Applications to vacancies must be received before midnight Copenhagen time (CET) on the closing date of the announcement.

DATA QUALITY STRATEGY

INDEX OF TABLES. II 8 Import Components of Final Uses, III 1 The Balance of Payments, by Main Category,

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management

THE GAZETTE OF PAKISTAN EXTRAORDINARY PUBLISHED BY AUTHORITY SECURITIES AND EXCHANGE COMMISSION OF PAKISTAN NOTIFICATION

NATIONAL ENVIRONMENT MANAGEMENT AUTHORITY (NEMA)

15 Organisation/ICT/02/01/15 Back- up

COMMON FUND FOR COMMODITIES

I. The Role of the Board of Directors II. Director Qualifications III. Director Independence IV. Director Service on Other Public Company Boards

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP

Guidelines for Narrative and Financial Reporting

HR Services. Employee Handbook Conditions Of Service (Research Staff) Duties and Hours of Work. Off-Site Activities

FINAL AUDIT REPORT. Audit of Arrangements for Global Banking and Investment Management in OPPBA

Introduction to the ITS Project Management Methodology

CHARTER TIO Board of Directors

* The official list of textbooks and materials for this course are found on Inside NC.

Ninth Round PROJECT MONITORING, REPORTING, REVISION AND EXTENSION GUIDELINES

Walchandnagar Industries Limited. Policy on Preservation of the Document. (Effective from December 01, 2015)

Transcription:

VII. Monitoring and ing Project monitoring and ing are essential com ponents of project management. The project coordinator and the project coordinator s supervisor are the principal beneficiaries of the monitoring information and should use it to ensure that projects are implemented as efficiently and effectively as possible. A. Project monitoring There is a growing emphasis on demonstrating performance rather than simply producing outputs, which changes the emphasis in monitoring and ing requirements. Monitoring is the continuous process of assessing the status of project implementation in relation to the approved work plan and budget. Monitoring helps to improve performance and achieve results. The overall purpose of monitoring is to ensure effectively managed results and outputs through measurement and assessment of performance. If a project is poorly designed or based on faulty assumptions, however, even the best monitoring is unlikely to ensure its success. Particularly important is the design of a realistic chain of results, outcomes, outputs and activities. Monitoring is the responsibility of the project coordinator and may be carried out informally (through weekly meetings) or formally (through written s). Regular monitoring enables the project coordinator to identify actual or potential problems as early as possible in order to facilitate timely adjustments in project implementation. Project coordinators should track the outputs and measure their contributions to results by assessing changes from baseline conditions. Project coordinators need to keep an ey e on key results because they can indicate whether a strategy is relevant and efficient or not. Relevance in a results-based context refers to whether or not a UNEP project intervention contributes to the achievement of key results and objectives. Good monitoring consists of the following: 25 (f) Focus on results and follow -ups: It looks for what is going well and what is not progressing in terms of progress toward the intended results; Regular communication by the project coordinator or : The project coordinator or should be dedicated to assessing progress, looking at the big picture and analyzing problem areas. They should ensure continuous documentation of the achievements and challenges as they occur and avoid having to try to remember the events some time later; Regular analysis of s : The project coordinator or should review project -related s, including financial s, by the implementing partners to serve as a basis for their analysis; Use of participatory monitoring mechanisms to ensure commitment, ownership, follow -up, and feedback on performance: These include outcome groups, stakeholder meetings, steering committees, and focus group interviews; Ways to objectively assess progress and performance based on clear criteria and indicators stated in the logical framework matrix of the project document: The project team should agree on a performance measurement system by developing indicators and baselines; Active generation of lessons learned, ensuring learning through monitoring tools, adapting strategies accordingly and avoiding repeating mistakes from the past. 25 UNDP (2002), Handbook on monitoring and evaluating for results. Monitoring and ing 50

B. Project ing 26 Project ing is the formal presentation of monitoring information. The main reasons for ing are the following: C. Reporting responsibility To formally inform management : Reporting ensures that management, particularly the project coordinator s supervisor or project, is formally appraised of the progress made in project implementation and the supervisor or project is aware at an early stage of actual and potential problems and any remedial action taken; To validate requests for further funding: Reporting ensures that the is kept informed of all aspects of project implementation., together with project coordinators or s, can then ensure that disbursed funds have been properly used before authorizing any further release of funds; To serve as an audit and evaluation trail: Reporting maintains a record of all actions taken during project implementation. It therefore constitutes a vital resource for auditors and evaluators in assessing whether a project has been implemented in accordance with the rules and regulations and as efficiently and effectively as possible; To serve as a reference for future projects: Reporting serves as a vital resource for ensuring that lessons learned (project successes, failures, best practices) through project implementation are available for consideration when formulating and implementing future projects; To to the donors on the project s progress: Often, ing is requested by donors as they have shared interests with UNEP in the success of projects. Donors sometimes fund projects contingent upon satisfactory progress. They increasingly ask for progress and final s at the results and objectives level rather than at the level of output or activity delivery. The project coordinators, under the overall responsibility of their respective division s, must ensure that all project s are submitted on time. Projects can only be closed once all the ing requirements have been met. Reporting on projects is part of the coordinator s tasks included in the performance appraisal system work plans, and forms part of the staff performance appraisals. Project coordinators who have been reassigned within the organization, have to formally hand over their project responsibilities to the project taking over from them. Division s have the responsibility to ensure that proper handing-over of projects takes place. Submission of all outstanding s for projects under their responsibility is part of the signing-off requirements that have to be fulfilled before staff who are leaving the organization can be given formal clearance from the Human Resource Management Service (see annex XVI on signing-off requirements related to projects). D. Reporting requirements Reports need to be sent to the, PCMU and Evaluation and Oversight Unit, under cover of a memorandum signed by the responsible division. Reporting requirements differ depending on whether a project is external (table 1) or internal (table 2). The following tables contain summaries of the ing requirements. 26 See also section IX on evaluation. 51 Monitoring and ing

Table 1: Reporting requirements for external projects Report type Prepared by Responsibility Preparation frequency/period Submission Format 27 Activity Annually for Jan June/ Due by 31 July (or as per ing cycle agreed with the donor) To Project cc: & PCMU Annex X Progress coordinator s Annually for Jan Dec/ Due by 31 Jan. (or as per ing cycle agreed with the donor) Annex XI Final coordinator's End of the project/ Due within 60 days of completion Annex XII Self-evaluation fact sheet (EFS) Project s Annually on each current or completed project/ by the end of January To EOU cc: Project http://www.unon.org/e ou Quarterly financial and cash advance statement Quarterly Due by 30 April, 31 July, 31 Oct, and 31 Jan. cc: Annexes XIII and XV Audited financial Biannually by 30 June/ Within 180 days of the completion of the project cc: Final statement of account Cooperating agencies Annually by 15 February/ Within 60 days of the completion of the project To Project cc: Inventory of nonexpendable equipment (items over $1,500) Annually by 31 January and within 60 days of the completion of the project/ to be attached to the progress cc: 27 An electronic form for each is available in the http://www.unep.org/project_manual. Standard paragraphs related to each ing requirements are available in annex V. Monitoring and ing 52

Table 2: Reporting requirements for internal projects and internally implemented activities Report type Prepared by Responsibility Preparation Frequency/period Submission Format Progress Project coordinator Project coordinator s Annually for Jan Dec/ Due by 31 Jan. Annex IX Final Project coordinator Project coordinator's End of the project/ Due within 60 days of the completion Annex X Self-evaluation fact sheet (EFS) Project s Project Annually on each current or completed project/ by the end of January To EOU cc: Project http://www. unon.org/eo u Activity For externally implemented projects, project coordinators or the implementing agencies should submit an annual activity for the first half of the calendar year (from January to June). The activity for the second half of the year is not necessary as the annual progress (from January to December) is inclusive of the activities implemented for the entire year, including the second half of the year. The activity is intended to reduce the ing requirement on activities for the second half of the year and look at the progress for the entire year together with the matching activities for the same period. Information on the activities implemented in the second half of the year, therefore, needs to be extracted from the progress. Annual activity s are due by 31 July. Due to varying ing cycles of different donors, however, the ing dates may differ. For the projects with donor-determined progress ing cycle, the activity ing date will usually fall at the mid-point of the progress ing date. Progress The progress is required for all projects and internally implemented activities with earmarked funding. 28 The provides a framework for assessing status and a record of project implementation at any given time. Its primary purpose is to ensure that the project coordinator s supervisor or project is formally appraised of the status of project implementation and that the decisions or actions necessary for successful implementation of the project have been or are being taken and documented in a timely manner. The should provide information on the status of delivery of project activities, outputs, results and impacts (if possible); as well as information on any actual or potential problems and deviations from the approved work plan and budget. The should also indicate any agreed upon changes to the approved work plan and any decisions or actions regarding the future direction of the project. Usually, progress s are due by 31 January, especially for United Nations Fund and Development Account funded projects. For projects with donor -specific progress ing cycles progress s should be submitted on donor-determined ing dates. Although progress s are required to be produced on a yearly basis, more frequent s can be produced as the project coordinator s supervisor deems necessary. 28 See B. costed work plan, projects and memorandums of understanding and letters of agreement in section I for the definitions of project and internally implemented activities. 53 Monitoring and ing

Final The final is required on completion of all projects and internally implemented activities with earmarked funding. The final should be prepared by the project coordinator and should contain information on the achievement of objectives, results and outputs. It should clearly explain any variances from the originally approved project in terms of duration, cost, results and outputs or services. The final is similar in content to the progress, except that it has added information on lessons learned and project sustainability and replicability. Attention should be given to the requirements for project closure (see annex XVII). Thes e may include the requirement for an audit certificate. It should also be noted that for projects implemented by supporting organizations, the absence of a final, inventory of non-expendable equipment or the audit certificate, will result in the final payment to the supporting organization being withheld. The final should be submitted within 60 days of completion of the project. Self-evaluation Self -evaluations should be submitted by project s annually to the Evaluation and O versight Unit on all projects and internally implemented activities with earmarked and trust fund contributions. These evaluations determine the extent of achievement of results, status and challenges of project implementation, budget management issues, gender issues, sustainability arrangements, impacts and risks. Financial s Cooperating agencies: Project expenditure statements: Cooperating agencies should submit to the Chief,, UNON, quarterly project expenditure statements and final account statements for each project, showing the amount budgeted for the year, amount expended since the beginning of the year and, separately, the unliquidated obligations (see the standard text in annex V and formats in annexes XIII and XIV). Cash advance statements : A statement of advances of cash provided by UNEP should be submitted to the Chief of, UNON, quarterly (in the format shown in annex XV) together with the project expenditure statement. : Project expenditure statements : should submit to the Chief,, UNON, quarterly project expenditure statements and final account statements for each project, showing the amount budgeted for the year, amount expended since the beginning of the year (see the standard text in annex V and formats in annex XIII). The expenditure statements as at 31 December for projects with annual budgets of $50,000 and above, certified by a duly authorized official, should be dispatched to the Chief of, UNON within 15 days (see the standard text in annex V and format in annex XIII). Cash advance statements : A statement of cash advances provided by UNEP should be submitted to the Chief of, UNON quarterly (in the format shown in annex XV) together with the project expendit ure statement. Monitoring and ing 54