HLV - Pile. High level displacement pile. Consulting Design Execution



Similar documents
BUTE Department of Construction Management and Technology

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

METHOD OF STATEMENT FOR STATIC LOADING TEST

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Boden und Wasser Büro für Hydrogeologie, angewandte Geologie und Wasserwirtschaft

PILE FOUNDATIONS FM 5-134

Module 1 : Site Exploration and Geotechnical Investigation. Lecture 4 : In-situ tests [ Section 4.1: Penetrometer Tests ] Objectives

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

CEEN Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

Behaviour of Prefabricated Timber Wall Elements Under Static and Cyclic Loading

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

The advantages and disadvantages of dynamic load testing and statnamic load testing

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

GLOSSARY OF TERMINOLOGY

Design and Construction of Auger Cast Piles

Dynamic Load Testing of Helical Piles

Determination of Thermal Conductivity of Coarse and Fine Sand Soils

KWANG SING ENGINEERING PTE LTD

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

PROVA DINAMICA SU PALI IN ALTERNATIVA ALLA PROVA STATICA. Pile Dynamic Load test as alternative to Static Load test

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by

Stabilenka HUESKER. and Separation. Engineering with Geosynthetics SKER HUESKER HUESKER HUESKER HUESKERHUES

Improvement in physical properties for ground treated with rapid impact compaction

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Step 11 Static Load Testing

An Automatic Kunzelstab Penetration Test

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

ENCE 4610 Foundation Analysis and Design

DEVELOPMENT AND APPLICATIONS OF TUNED/HYBRID MASS DAMPERS USING MULTI-STAGE RUBBER BEARINGS FOR VIBRATION CONTROL OF STRUCTURES

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Vibration Isolation in Data Centers

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

How To Design A Foundation

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

CHAPTER: 6 FLOW OF WATER THROUGH SOILS

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

DYNAMIC TESTING OF MICROPILES. COMPARISON OF STATIC AND DYNAMIC TEST RESULTS

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Soils, Foundations & Moisture Control

Site Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions

DESIGN SPECIFICATIONS FOR HIGHWAY BRIDGES PART V SEISMIC DESIGN

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

PILE TESTING SPECIFICATION

Designed and Engineered to Perform

SECTION SHEETING, SHORING AND BRACING

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Geotechnical Investigation Test Report

ALLOWABLE LOADS ON A SINGLE PILE

Geotechnical Testing Methods II

PDCA Driven-Pile Terms and Definitions

Methods for Seismic Retrofitting of Structures

PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.

COSMOS 2012: Earthquakes in Action COSMOS 2012

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

Building Pit Roche Building 1 Basel, Switzerland

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Chapter 3 Pre-Installation, Foundations and Piers

PP MASTERTM S T I F F N E S S S N 1 2 R I N G THE NEW POLYPROPYLENE SEWER PIPE SYSTEM

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

FLOORS REINFORCEMENT Shear Stud Connector for steel- concrete composite structures cold applied by pins

MANUFACTURED HOUSING USED AS DWELLINGS

SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

ON THE INTERPRETATION OF SEISMIC CONE PENETRATION TEST (SCPT) RESULTS

STATNAMIC : Pile Load Testing Equipment

Lighthouse Engineering, L.L.C.

Forensic engineering of a bored pile wall

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

Seismic Risk Prioritization of RC Public Buildings

LABORATORY DETERMINATION OF CALIFORNIA BEARING RATIO

Federation of Piling Specialists Testing Datasheet No 1

High Capacity Helical Piles Limited Access Projects

MODEL-SIZED AND FULL-SCALE DYNAMIC PENETRATION TESTS ON DAMPING CONCRETE

Table of Contents 16.1 GENERAL Overview Responsibilities

CARLOS FERNANDEZ TADEO & ASOCIADOS, S.L. Range of Services

USE OF CONE PENETRATION TEST IN PILE DESIGN

c. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.

Washington ,

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

DEM modelling of the dynamic penetration process on Mars as a part of the NASA InSight Mission

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

Instrumentations, Pile Group Load Testing, and Data Analysis Part II: Design & Analysis of Lateral Load Test. Murad Abu-Farsakh, Ph.D., P.E.

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

EVALUATION OF SEISMIC RESPONSE - FACULTY OF LAND RECLAMATION AND ENVIRONMENTAL ENGINEERING -BUCHAREST

Transcription:

HLV - Pile High level displacement pile Consulting Design Execution

The - Pile High level displacement pile HLV - piles are an ideal system to transfer loads for any type of foundations, e.g. for building structures, halls, bridges, sewage plants, dams, pipelines, etc.

Dornbirn/Austria Ideally a universally applicable, prefabricated driven pile system should fulfill the following requirements: The material should be resistant and not be damaged by driving with extremely high impact. Once driven into the soil, the material should secure a safe foundation without problems for many decades. It should be possible to produce piles of almost any length on site during construction. The final pile length should be determined exclusively on the basis of local soil conditions determined by the penetration resistance measured. This allows the foundation to be flexible and economically adaptable to prevailing soil conditions. Gmunden/Austria

On site, the individual pile sections should be quickly, simply and safely connectable to form a secure and force-bearing connection. Pile construction should require only light and few pieces of equipment, allowing small constructions even in narrow spaces. The frequency and power of impact of the pile driver should be adjusted so as to cause only minimal vibrations. The individual pile sections should be rather short to allow easy transport and construction of piles under limited working height. Altaussee/Austria Our HLV - piles completely fulfill all these requirements. Since 1985, more than 2.0 million meters (more than 6.5 million feet) of HLV - piles have been constructed and have proven reliable. Currently, about 200 000 m (more than 550 000 feet) of piles are installed every year. Bruck a. d. Leitha/Austria

Driving - Piles Process of driving After some preliminary excavation, the initial section of the pile, fitted with a driving shoe, is positioned in the hole and driven in. The subsequent section is taken up and driven into the conical collar of the previously driven section, thus producing a stable, force-bearing connection. This driving process is repeated until the desired final depth is reached as determined on the basis of penetration resistance. The pile is then cut at the desired height according to plan design using a cutting wheel. This cut-off is fitted with a driving shoe and used as the initial section of the subsequent pile. This avoids waste. Depending on the load to be transferred, the pile head is equipped with a pressure load distribution plate and/or additional tensile reinforcements. As the sections to be driven have only little mass, piles may be constructed using light, easy to move hydraulic excavators equipped with hydraulic blow hammers. Therefore, piled foundations may also be constructed in narrow and difficult locations. Driving the piles into the soil causes only little vibration even in close vicinity of existing buildings. The pile axis may be as close as 40 cm to the adjacent building or structure. As the piles require only little equipment, even inclined piles may be constructed at almost any angle and in almost any direction. Krems/Austria St. Veit a. d. Glan/Austria

Technical data Internal load-bearing capacity ductile cast iron Diameter Cast iron pipes Wall thickness working load (according to ONR 22567 and ETA 07/169) 118 mm 7.5 mm 678 kn 118 mm 9.0 mm 764 kn 170 mm 9.0 mm 1,253 kn 170 mm 10.6 mm 1,391 kn Internal load-bearing capacity steel ST52 Diameter Steel piles Wall thickness working load 114.3 mm 6.3 mm 538 kn 152.4 mm 8.0 mm 956 kn 177.8 mm 10.0 mm 1,403 kn External load-bearing capacity of HLV - piles in soil 1) Piles without grouting Piles are driven without grouting when they will be embedded in a sufficiently load-bearing layer of soil or reach rock. This allows the usage of the maximum internal bearing capacity. 2) Shaft grouting with concrete mortar Particularly in loose soils, shaft grouting is necessary to increase external load-bearing capacity. Concrete mortar is grouted through the pile tube during driving, this mortar filling the circumferential space created by the driving shoe which has a larger diameter. This provides higher soil density and closer connection to the soil. Particularly in sandy and gravelly soils, this system reaches allowed shaft friction values of up to 200 kn/m2. External load-bearing capacity in non-coherent soil Empirical values for load-bearing parameters: Soil compactness Blow number SRS 15 Driving time (sec/m) Shaft friction value Very loose 0-2 Pressed 0 Loose 3-5 Approx. 5-10 40 kn/m 2 Medium dense 6-15 Approx. 10-20 80 kn/m 2 Dense 16-30 Approx. 20-30 120 kn/m 2 Very dense > 30 > 30 150 kn/m 2 shaft grouting

External load-bearing capacity in coherent soil Empirical values for load-bearing parameters: Soil consistency Blow number SRS 15 Driving time (sec/m) Shaft friction value Slurry 0-1 Pressed 0 Soft 1-2 Pressed 0 Soft - stiff 3-4 Approx. 5-10 20 kn/m 2 Stiff 5-7 Approx. 10-15 40 kn/m 2 Medium hard 8-15 Approx. 15-30 70 kn/m 2 Hard >15 > 30 100 kn/m 2 Immissions Noise levels during driving Example: BVH Druckzentrum Strohal construction site Values in db(a) L 1 * L 50 * L 95 * Basic noise level of construction site 76.0 71.1 68.8 Nose level during driving 79.0 74.1 69.7 L 1, 50, 95 * = Level reached or exceeded in 1, 50, or 95% of the time of measurement Noise levels did not rise more than 3 db(a) The driver noise level is in the same range as the basic noise level. If the blow hammer is about 50 m away from the measuring device, it is about as loud as a car driving close by. Vibrations during driving Druckzentrum Strohal: Pile construction using 2 drivers Maximum: 0.22-0.77 mm/s Average: 0.04-0.13 mm/s Admissible driving velocity according to Austrian standard ÖNORM S 9020 I Industrial buildings 30.0 mm/s II Residential buildings 20.0 mm/s III Buildings having less frame strength than I and II above 10.0 mm/s IV Historical monuments and buildings which may collapse 5.0 mm/s

Components - Pile concrete pump tensile reinforcement according to static requirements plate: ST52 or higher quality 160/160/20 to 280/280/40 excavation prior to driving pile shoe for piles without grouting collar connection pile shoe for grouted piles Concrete mortar grouting is carried out during driving.

building constructions industrial constructions foundations for pipelines bridges Examples for the use of - Piles Building constructions Requiring easily movable equipment and only short construction times, the pile system is particularly useful for building foundations between existing buildings in urban areas. The construction of capping beams on the piles saves considerable amounts of concrete, thus increasing the economy of this pile system. Industrial constructions The pile system is very useful for supporting prefabricated halls, which nowadays are usually lightweight constructions that are highly sensitive to settling, particularly different degrees of settling. The piles may be directly inserted into small tubular foundations, thus forming building supports which reliably divert wind and earthquake energies into the ground. Bridges When casting the foundation of bridge abutments, it is very important to be able to move equipment quickly and easily. Load transfer must be clearly divided according to load components. Moments are transferred to the pile block, while horizontal forces are transferred to inclined piles. Foundations for pipelines In soft soils, foundations for water or sewage pipelines are necessary to avoid excessive settling.

Proof of load-bearing capacity by means of driving criteria HLV - Piles: Ø 170 mm, concrete grouted Ø 250 mm Service load: 1000 kn Soil composition in Selzthal, Austria 0.00 = ground level - 5.00 peat silt, sandy, clayey, - 13.00 organic particles - 15.50 gravel - 24.00 groundwater level silt, sandy with peat ground moraine rocky - 36.20 silty depth (m) pressed pressed pressed Test driving Selzthal, Austria HLV - Pile: 170 mm, shaft grouted driving time (sec./m) driving time > 200 sec. Load test in Selzthal, Austria driving time (sec./m) settling mm HLV - Pile = 170 mm, shaft grouted

Determining driving criteria by means of pile load bearing tests Static load test Test arrangement reaction pile, ductile, Ø 170/250, Gewi Ø 50 mm test pile, ductile, Ø 170/250 Selected piles are subjected to static load bearing tests to determine the settling behavior under load and to adjust estimated driving criteria. After constructing, the HLV - Pile is pressed down gradually, using a hydraulic press, while exactly maintaining loading and time increments, until the test load defined by a structural engineer is reached. The loading steps (test cycles) are determined in cooperation with a geologist or soil expert and have to be individually adapted to the prevailing soil conditions, particularly in waterlogged, cohesive soils. Heb 1000, L = 10.50 m 3.75 m 3.75 m force measuring device 7.50 m pressure cylinder test pile, ductile, Ø 170/250 mm The test results are implemented in further project planning to optimize the economy and applicability of the HLV - pile system, if possible. Laibach/Slovenia Rottenmann/Austria

Dynamic driving monitoring General As static load tests are very expensive and time-consuming, Grund- Pfahl- und Sonderbau GmbH has decided to develop a test method allowing measurement of both the kinetic energy involved and the soil resistance against driving. The new method, referred to as»dynamic driving monitoring«, allows fast and cost-efficient verification of driving criteria for the load-bearing capacity of piles that have been found by trial and error before. Initial parameters Future outlook Results The sensors on the sample detect the acceleration. Simple mathematical integration over time yields the velocity, and further mathematical integration yields the displacement. In addition, strain gauges measure sample deformation. Taking into account the geometry (diameter and wall thickness) and the E-module of the sample material, the forces existing during driving may be calculated. In a further step, the kinetic energy may be determined. When preparing the sample, the greatest challenge is to fasten the acceleration sensors and the strain gauges. The measurements show that when driving HLV - piles the acceleration may be as high as 1,800 g. As a consequence, the main focus has to be on the quality of the driving hammer. This development should lead to firm interpretation of measured data with respect to pile service loads, making no distinction between the base pressure and the combined base pressure and shaft friction piles. Moreover, the driving formula according to Prof. Fröhlich, Austria, now allows the checking of estimated service loads of cast in situ concrete piles of the Zeissl- GPS system conventionally used in Austria. First results show that when using the test load formula according to Prof. Fröhlich, we are well on the safe side. Grund- Pfahl- und Sonderbau GmbH is now able to quickly check the capacity, i.e. the kinetic energy of our driving hammers any time and to adapt it to prevailing soil conditions. Therefore, measurement data can now prove that the piles we produce have the necessary load capacities. As a»by-product«of this development, we are now also able to carry out dynamic load tests on slim piles up to a service load of approx. 500 kn quickly and costefficiently. As quality management is highly important for us at Grund- Pfahlund Sonderbau GmbH, we regularly re-check the data using static load tests.

The - energy pile A combination of two sophisticated products Pile foundation as energy producer The basic idea of the energy pile technology is to extract (geothermal) heat from the soil via the foundation and to provide suitable systems to use it to heat the building. On the other hand, this system may also be used for cooling by dissipating excessive heat into the soil. In this system, the soil and groundwater may function as seasonal accumulators of energy for cooling and heating. solar energy heating energy The combination of two sophisticated products Pile foundations may be used for energy transfer by laying absorber lines into the piles. The company Nägele Energie- und Haustechnik has used this system for decades under the trade name enercret. Well proven and universally applicable, the HLV - piles of Grund- Pfahl und Sonderbau GmbH are ideal for such installations. The use of HLV - piles and enercret together combines the advantages of two high quality products. geothermal energy The HLV - energy pile provides a safe and highly economical foundation system for cost-efficient and eco-friendly production of heating and cooling energy. It is ideal to be used in a wide variety of applications. 12 14 C Heating and cooling buildings via their foundations temperature ( C) breadth (m) length (m) Simulation of temperature distribution in four energy piles operated in series

Grund- Pfahl- und Sonderbau GmbH Industriestraße 27a A-2325 Himberg bei Wien Tel.: +43(0)2235/87777-0 Fax: +43(0)2235/86561 E-Mail: office@gps-bau.com Branches Lustenauerstraße 56 A-6850 Dornbirn Tel.: +43(0)5572/398855 Fax: +43(0)5572/386279 E-Mail: gps-dornbirn@gps-bau.com www.gps-bau.com Connected and subsidiary companies Grund- und Sonderbau GmbH Niederlassung Berlin Kurfürstendamm 38/39 D-10719 Berlin Tel.: +49(0)30/53006-0 Fax: +49(0)30/53546-37 E-Mail: gps.berlin@gps-bau.com Stump Spezialtiefbau GmbH Zentrale Am Lenzenfleck 1-3 D-85737 Ismaning Telefon: +49(0)89/960701-0 Telefax: +49(0)89/963151 E-Mail: info@stump.de www.stump.de Mitglied der Vereinigung industrieller Bauunternehmungen Österreichs Mitglied der Vereinigung österreichischer Bohr- und Spezialtiefbauunternehmungen Messerschmittweg 13 A-6175 Kematen in Tirol Tel.: +43(0)5232/3333-200 Fax: +43(0)5232/2617 E-Mail: gps-kematen@gps-bau.com Josef-Sablatnig-Straße 251 A-9020 Klagenfurt Tel.: +43(0)463/33533-700 Fax: +43(0)463/33533-709 E-Mail: gps-klagenfurt@gps-bau.com Stump-Hydrobudowa Sp. z o.o. ul. Delfina 4 b PL-03-196 Warszawa Tel.: +48/22/6142498 Fax: +48/22/6142498 Stump Spezialtiefbau spol. s.r.o CZ-Úvalská 28 100 00 Praha 10 Strasnice Tel.: +420/2/747815 37/0 Fax: +420/2/74781516 Qualitätsmanagement Zertifiziert nach ÖNORM ISO 9001 Registrier Nr.: 97010-02 Sicherheitsmanagement Zertifiziert nach Kriterien der SCC** Registrier Nr.: 97010-51 by Grund- Pfahl- und Sonderbau GmbH, Himberg - Layout: Graphic-Design Mario Oberhofer, Villach - Photos: Grund- Pfahl- und Sonderbau - Print: Wulfenia Druck, Feldkirchen/Kärnten 09/2008