METHOD STATEMENT for INSTALLATION OF MICROPILE

Similar documents
ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

Design and Construction of Auger Cast Piles

Embedded Parts Introduction - Anchors

METHOD OF STATEMENT FOR STATIC LOADING TEST

The International Workshop on Micropiles, 2007

High Strain Dynamic Load Testing of Drilled Shafts

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

SECTION CAST-IN-PLACE CONCRETE

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

BUTE Department of Construction Management and Technology

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS

1. Lay out 2 pieces of 7/8" tubing and mark for bending as shown. Remember that the bend is in the shaded area as shown below in Figure 1.

Chapter. Restoration of Damaged Structures

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

In-Track Repair of Concrete Ties. Deland Humpherys, Director Track Mtce

Detailing of Reinforcment in Concrete Structures

Installation PowerPoint for Grasscrete Formers

KWANG SING ENGINEERING PTE LTD

Wastewater Capital Projects Management Standard Construction Specification

DO NOT attempt to repair hub and wheel bearing assembly.

Guidelines For Sealing Groundwater Wells

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Awning Instructions. Standard Manual 1.5m to 4.5m

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

COMPARISON OF DRILLING TECHNOLOGIES BETWEEN TOP DRIVE AND ROTARY TABLE IN GEOTHERMAL FIELDS: A CASE STUDY OF OLKARIA GEOTHERMAL FIELDS.

Quadrant Shower Enclosure. Telephone Cleaning. All chrome surfaces should be cleaned using a clean damp cloth.

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Introduction to JIGS AND FIXTURES

High Capacity Helical Piles Limited Access Projects

SECTION 10 WATER WELL SUPPLY SCOPE OF WORK

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

SECTION 411 DRILLED PIERS

Lab 1 Concrete Proportioning, Mixing, and Testing

Pro-Lift Steel Pile Foundation Repair

TRUCK MOUNTED KNUCKLE BOOM HYDRAULIC CRANE PROPOSAL

PILE TESTING SPECIFICATION

Safe & Sound Bridge Terminology

Geotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

TopSky DLG Installation Manual

Sample Career Ladder/Lattice for Energy (Petroleum Sector)

Shower and Floor Gullies Channel Drain and Tile Drain SECTION

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Power Cube Open Source Ecology Page 1. Power Cube. Version 4

GENERAL RUBBER LINING PRINCIPLES

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Concrete Specification for Cooling Tower and Basin

Moving Small Mountains Vesuvius Dam Rehab

B Dinesh Prabhu, Asst. Professor, P E S College Engg., Mandya, KARNATAKA 1

For a Coastal Site. A Pier-and-Beam Foundation. Our company specializes in oceanfront

Fabrication of Reinforcement

System. Stability. Security. Integrity. 150 Helical Anchor

TARIFF CODE and updates standard

Hilti HIT-HY 200 with rebar

HUS-V Screw anchor. HUS-V Screw anchor. Basic loading data (for a single anchor) Mean ultimate resistance

Oil and Gas Pipeline Design, Maintenance and Repair

Atlas Copco Surface drill rigs. SmartROC T35/ T40. Hole diameter: SmartROC T35: mm (2 1 /2 4 1 /2 ) SmartROC T40: mm (3 5 )

Site sampling and testing of concrete

DIRECT PUSH DRILLING.

TRUCK MOUNTED KNUCKLE BOOM HYDRAULIC CRANE PROPOSAL

Rotary Vertical Drilling System (RVDS)

PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.

SECTION DRILLED CONCRETE PIERS (CAISSONS)

CIVL451. Soil Exploration and Characterization

How To Design A Foundation

300 SERIES 331, 332, 333, 344, 356 AND 367 MODELS

Highly flexible couplings

GEOTHERMAL DRILLING ABSTRACT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SECTION STORM DRAINAGE SYSTEM

Range Road RR Series Semi-Automatic Firewood Processor. Crated Unit Assembly Manual

Drive shaft, servicing

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

Operating Instructions Hand pallet trucks HU Profi. Issue

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

DESIGNING STRUCTURES IN EXPANSIVE CLAY

DTU Animal Cart Programme

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Lay blocks with mortar

Tool And Material Checklist

(T indicates a Tropicalised version with extended workability. No change has been made to the formulation)

Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014

RAUFOSS EXPLOSIVE COMPRESSION FITTINGS

ATLAS RESISTANCE Pier Foundation Systems

PART 1 GENERAL 1.1 SECTION INCLUDES

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

Transcription:

METHOD STATEMENT for INSTALLATION OF MICROPILE A. MATERIAL TO BE USED 1. Grout Grout shall be mixed from Ordinary Portland Cement and clean water free from harmful substances. Usage of other cement which has a higher strength and/or workability shall also be allowed. 2. Grout Mix The proportions of grout and the minimum strength of work cubes shall comply with the following requirements : Range of water/cement ratio Target Resistance to crushing 0.42-0.50 (cube strength) 7 days 28 days (Typically 0.45) 21 N/mm 2 30 N/mm 2 The quantities of cement in the mix shall be measured by weight. The grout shall be free from segregation, slumping and bleeding. Grout shall be mixed on site and shall be pumped into its final position as soon as possible. Non-shrink admixture (SIKA Intraplast-Z TM, also an expansion admixture) shall be added at approximately 1% by weight. 3. Grout Test Two sets of three test cubes shall be taken per one grouting operation for testing purpose. Three test cubes shall be tested at 7 days and the remaining cubes at 28 days after casting. The characteristic strength of the grout shall be 21 N/mm 2 and 30 N/mm 2 at 7 days and 28 days. (Note that expansion admixtures may cause a slight decrease in cube strength)

4. Main Load Bearing Component Reinforcing Steel The main steel component and the grout shaft of the micropile shall be designed to support the external loads and bending to be transmitted to/from the load bearing stratum for end-bearing/tension piles, which shall consist of a top anchorage or pilecap (provided by the structural/pilecap contractor) and an axial steel component. Typical axial steel component consisting of hot rolled deformed high tensile bar with minimum yield stress of 460 N/mm 2 or API Pipe. B. FABRICATION OF MICROPILE API Pipes 1. If API Pipes are used, they shall be joint by either a pipe sleeve (screw-type) or fully butt-welded all around (see installation procedure). 2. Spacers consist of a small piece of steel plate tag-welded onto the pipe at 3m intervals, each interval in 2 direction or using PVC spacers adhered using epoxy or tie wire. Reinforcement Bars 1. The reinforcement of the piles are typically prefabricated on-site or elsewhere and brought to site. The bars and links are tied together with tie wire to form prefabricated cages. 2. To join the lengths of the cages, the reinforcement bars shall be lapped 40 times the diameter or 40D. The joining of the bars (if necessary) shall be done by tie wire or welding. 3. Spacers used shall be PVC pipes cut into small lengths and tied to the reinforcement bars. Alternatively, ready-made PVC round spacers can be clipped to the links. A second alternative consist of PVC lantern which is clipped to the main-bars.

C. METHOD FOR DRILLING / MICROPILE INSTALLATION STEP 1 : The pile point is determined by a surveyor and position the drill rig on top of the point. The first drill rod with a drill bit is placed above the drill point. Ensure verticality is achieved before starting drilling works. This is done by checking the verticality of both the first drill rod and the mast using a spirit level.

STEP 2 : Wash Boring Drilling Technique For drilling in both soft and/or hard soils (typically SPT N>50), the hole can be drilled with the wash boring method using either a drag bit or roller (tricone) bit. Wash boring, also known as the reverse circulation system is an assembly of a the drill bit - drag bit or roller bit being assembled to the end of a string of drill rods onto a drill rig or drill frame. The drill bit is advanced by adding drill rods when drilling. Water is pumped through the string of drill rods and the outflow water emerging from the borehole is channelled to a holding pit and recycled through a slurry pump back into the drill rig s swivel head hence the term reverse circulation.

STEP 3 (if required) : If collapsible soil layers is encountered from step 2, or anticipated from the soil investigation record, drilling using temporary casing shall be employed. Advance a casing into by either drilling using a casing shoe (by wash boring method) without the aid of a drill rod OR using a drill rod with drag/roller bit together with a casing up to the suspected collapsible layer felt by the driller or SI report. The latter method can be done without a casing shoe. Upon reaching the end of the collapsible area (usually sand), cease the advancing of the casing. Continue drilling using drag/roller bit until the depth of the pile is reached.

STEP 4 : Upon completion of the drilling, the borehole is cleaned by flushing out any soil particles from the inside of the casing with recirculation water or air. API pipes / Reinforcement Bars (Cage) installation : - If a mobile crane is to be used for, move the drilling rig back. The pipe / rebar cage shall be lowered segment-by-segment using a mobile crane. Cordon the area for safety reasons. If the drilling rig winch is to be used, lift the pipes/rebar cage up segment-by-segment using the winch. Cordon the area for safety reasons. The joints of the API Pipe shall be properly screwed together with grease to assist tightening If welding is used, clean the edge of the pipe and conduct a full butt weld on the outside of the pipe. If Reinforcement Bars are used, lap the bar for 40D and join by tie wire or welding.

STEP 5 : If in Step 4, the mobile crane is used to install the API Pipes/Rebar Cage, the same mobile crane can be used to pull/withdraw the temporary casing. Shall this cannot be done due to safety reasons (crane parked too far away), move the drill rig back. Withdraw the casing using the winch tied around the casing. Shall this be unsuccessful, reattach the adaptor and using the reverse circulation method (wash boring), flush water into the casing to loosen it while withdrawing the casing using the rotary unit.

STEP 6 : Mix the cement bag with water in a mixer according to the design mix measurement. The mixed grout shall be filtered and poured into a holding tank. Grouting of the micropile is then carried out by Tremie Method using a hose installed right up to the end tip of the pile Rebar assembly cage or API Pipe with flow holes cut at the tip of the API pipe. Pump the grout into the pile using a piston or diaphragm pump. Grouting is done until neat grout appears at the top of the borehole. Upon completion, the grout hose is extracted. Shall any leftover temporary casing is extracted, or at any time after grouting, the grout level drops below the cut-off level, top-up the hole with grout.