City of West Palm Beach makes Water Treatment Plant Improvements by Implementing Priority Projects



Similar documents
Water Water Treatment Plant Tour

NEW GENERATION PROGRAMMABLE AUTOMATION CONTROLLER

How To Water System

Iron and Manganese BACTERIA AND IRON AND MANGANESE

White Paper. Chemical dosing and blending - the role of precision actuators

Highly Colored Water Removal Using Nanofiltration Membranes at the Colored Water Treatment Facility. Adam Zacheis, Project Manager Carollo Engineers

CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM

2. AUDIT OBSERVATIONS

Basic Chemistry of Chlorination

Ion Exchange Softening

Chemical Feed System Operation and Design Considerations

Town of New Castle Utility Department Introduction

Indiana s Newest Filtration Facility; East Chicago

Site Attendance Guidelines for Automated/Unattended Monitoring and Process Controlled Facilities

Description of the Water Conserv II Facility

WATER TREATMENT IN AUCKLAND

Advanced_O&M_Task_List_Example_Tool_06_02_16: O&M Example

PLCs and SCADA Systems

8 Chemicals from water treatment and distribution

Chemistry at Work. How Chemistry is used in the Water Service

Nitrification TCEQ. Public Drinking Water Conference Austin, Texas August 16, A System s Perspective after 20 years of Chloramination

AutoLog ControlMan. Remote Monitoring & Controlling Service

Intelligent Device Management with DCS, PLC, and RTU

Tumbarumba 3ML/d DAFF Water Treatment Plant

Offshore oil platform power and control system

Applying Life Cycle Assessment to Drinking Water Treatment

Cambridge Wastewater Treatment Facility

Residuals Management Somersworth Drinking Water Treatment Facility. Ian Rohrbacher, Treatment Operator IV

Removing Heavy Metals from Wastewater

City of Kenora Water Treatment and Distribution System. Drinking Water Quality Management System. Operational Plan Version 11

Paralleling Switchgear

Wireless Communications for SCADA Systems Utilizing Mobile Nodes

Amiad s AMF² pre-treatment technology ensures efficient and reliable nanofiltration of Scottish Highland loch water

Pennie huck Corporation and Subsidiaries Capital Expenditure Budget ($000) Project

FAQ s & Product & Troubleshooting Guide 37

CREATING A GREEN FUTURE THROUGH WATER REMEDIATION

Introduction To SCADA and Telemetry

Problems with Hypo: Best Design Practices for Smooth and Efficient Sodium Hypochlorite Feed Systems Chad Hantelman, City of Bremerton Jeff Zahller,

City of Cape Coral, Florida FY Proposed Operating Budgets

E-Version SECTION CHLORINATION SYSTEM PART 1 - GENERAL PART 2 - PRODUCT

Genesee Advanced Water Treatment Facility

Complete SCADA solution for Remote Monitoring and Control

PERFORMANCE TESTING OF A 380 ML/D RETROFITTED MEMBRANE/UV OXIDATION WTP. Introduction

Facility Classification Standards

Intelligent Decision Support System (DSS) Software for System Operation and Multiple Water Resources Blending in Water Treatment Facilities

How To Ensure Safety At A Swimming Pool Or Spa

Winnipeg Sewage Treatment Program Integrated Management System

EXISTING WASTEWATER TREATMENT FACILITIES

William E. Dunn Water Reclamation Facility. Facility Overview & Information

HC900 for Boiler Control Applications

Microfiltration for Removal of Manganese from Surface Water

Wireless Field Data Backhaul

EASTERN IRRIGATION SCHEME, VICTORIA: OPERATION OF AN ULTRA-FILTRATION PLANT FOR A CLASS A RECYCLED WATER SCHEME. David Aitken. Earth Tech Engineering

Water Treatment and Reverse Osmosis Systems

Partner for automation Water technology


Products, systems and services for water and wastewater treatment plants Enhanced plant performance, efficiency and reliability

SCADA and Security Are they Mutually Exclusive? Terry M. Draper, PE, PMP

Presented By: David J. Musto, Principal Thermo Systems L.L.C. East Windsor, NJ USA

Genesee Advanced Water Treatment Facility

A Proposed Integration of Hierarchical Mobile IP based Networks in SCADA Systems

SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist

The 3rd Busan Global Water Forum Multi-Parameter Water Quality Monitoring System. Aqua of Sep 2015 Kyung-Yup Hwang

DRAFT July, 2006 Page 1 of 18

Holistic Aeration and Chemical Optimization Saves Big Money from 1 MGD to 600 MGD. Trevor Ghylin, PE PhD

QUEENSLAND HEALTH POPULATION HEALTH QUEENSLAND INVESTIGATORS REPORT

December 2003 EPB 241B. Some sections are completed, some are partially complete and some are left blank.

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015

DOW Ultrafiltration. Case History. High Turbidity and Temperature Fluctuation No Obstacle for DOW Ultrafiltration

MOBILE WATER TREATMENT FACILITY UMUV 01

Communication Interface Units. CIU Prime & CIU Plus

HMS Industrial Networks. Putting industrial applications on the cloud

SECTION 13XXX CONTROL DESCRIPTION (DICP Models NC, 412, 622, 826, 1030)

Water System Disinfection

Dynamic Modeling Of An Ozone Disinfection Facility

Water Softening for Hardness Removal. Hardness in Water. Methods of Removing Hardness 5/1/15. WTRG18 Water Softening and Hardness

FOXBORO. I/A Series SOFTWARE Product Specifications. I/A Series Intelligent SCADA SCADA Platform PSS 21S-2M1 B3 OVERVIEW

SCADA System Fundamentals

The Control of ph and Oxidation Reduction Potential (ORP) in Cooling Tower Applications By Charles T. Johnson, Walchem Corporation

DENVER, CO. WHAT S ON TAP? Grading Drinking Water in U.S. Cities June 2003 KEY CONTAMINANTS IN DENVER S WATER DENVER

Pump Controller Type ABS PC 441 Monitoring and/or Control of Pumps and Pumping Stations

GE Intelligent Platforms. PACSystems High Availability Solutions

Does my drinking water contain Fluoride?

CERTIFICATION TO OPERATE WATER AND WASTEWATER TREATMENT SYSTEMS APPLICATION INSTRUCTIONS

Water Services Corporation SCADA A Tool for Efficient Resource Management

Monitoring Underground Power Networks

EXISTING WASTEWATER TREATMENT FACILITIES

WHAT DOES A SWIMMING POOL OPERATOR NEED TO KNOW?

MC4-50 Feeding System

Recently Completed Projects - Storage Projects

Upper Occoquan Service Authority Centreville, Virginia A Case Study

Drinking-Water System Inspection Program Inspection Report The Deep River Drinking Water System Inspection Number 1-8CZR5

Chemical Feed Systems Best Practices

Transcription:

October 13, 2014 Tulsa, OK City of West Palm Beach makes Water Treatment Plant Improvements by Implementing Priority Projects Ron Cass Gert-Jan Schers

Location West Palm Beach 2

Consent Order - 2008 Source Water Protection Staffing and operator certification Disinfection TTHM excursion WQ monitoring plan 10 years to implement a membrane-based treatment system 3

Consent Order 4

Source Waters 5

Conventional Surface Water Treatment Built 1894 Surface water, 47 mgd Conventional treatment Lime addition Enhanced coagulation Media filtration Chloramine residual 6

History Built 1894 Surface water, 47 mgd Late 2007 Operational issues Mid 2008 Operations Improve Mid 2009 Filter upgrades Nov 2011 Chemical mixing & metering Feb 2012 SCADA 2014 Generator building and primary power redundancy 7

Technology Evaluation 8

Condition Assessment Methods 9

Project Priority Five immediate projects year 0-2 Five projects year 3 6 Two projects year 7-10 10

Condition Assessment Funding 11

Facility Access Diverted traffic from Banyan Blvd Valued assets, underground INJ pts Provides Turn lane truck Access Fiber optic connectivity security checkpoint, cameras 12

Watershed Management 13

Training Chlorine Concentration Chloramine Formation NH 2 Cl Chloramine Decomposition NH 2 Cl + NHCl 2 Free Chlorine, HOCl, OCL Applied Chlorine Dose, mg/l Theoretical Breakpoint Chlorination

Filter Upgrades Filter Valves and actuators GAC over sand media replacement SCADA controlled (complete) Laterals and blower rehab 15

Finished Water Turbidity 16

Gaseous Chemical Replacement 2008 Vulnerability Study Significant risk in major metro area Gaseous Chlorine Anhydrous ammonia 2010 Switched to liquid forms Ready for automation 17

Replacement of Chemical Systems Sodium Hypochlorite Aqueous Ammonia Fluoride Corrosion Inhibitor Polymer Sodium Hydroxide 18

Finished Water Chemical Dosing Venturi - flow metering Provides 1 signal for flow pacing Static mixer Accessible injection 19

Finished Water ph 20

Total Chlorine 21

Finished Water Color 22

New 4160V transformers Gear: Double-ended electrical feeds Redundant fed switchboards Closed transition between utility and standby power Electrical FPL Feed 23

Electrical - Generator Building Existing generator problems Too large, façade, enclosures Fan driven rain Loss of power: potential flooding New dedicated generator bldg Gensets, switchgear, ATS, 24 2014

SCADA Process Monitoring - Historic 1990 Transition from manual to automatic Analog signals for process monitoring 1996 Facility upgrade MOVs for process control, S5 PLCs 2007 Filter upgrade Actuators, PakScan, S7 PLCs 2008 Booster pump station Radio Network AB ControlLogix PLCs 25

SCADA Issues Patchwork quilt of SCADA systems No City standards for hardware or software HMI differed for 3 different systems Increased risk of operator error 26

SCADA Challenges Very limited facility shutdowns Avoiding blind spots Old to new software Parallel programming Run simultaneously DOH required continuous monitoring Cutting ties to old RTUs 27

SCADA Improvements System redesigned from ground-up Standardized communication protocols Modbus, DeviceNet, Profibus and TCP/IP Transparency for troubleshooting Phased approach 1. Fiber optic backbone 2. PLC & RIO 3. Process control refinement 28

SCADA Network Architecture SLUDGE PRESS BACKWASH PUMPS ELEC/ GENERATOR BLDG SLUDGE PS RAPID MIX OPS BUILDING OPS LAB EAST HSP NORTH FILTERS CHEM GRAVITY THICK MID FILTERS WEST FILTERS EAST FILTERS AMMONIA WEST HS CHLORINE NORTH RAW 29

Chemical Dosing HMI 30

Plant Finished Water HMI 31

Remote Pump Station HMI 32

Improvements 2008 through 2015 Security upgrades Operational Improvements Staff training and certification Improved control Filter Upgrades Chemical Mixing & Metering SCADA System Primary power and distribution redundancy 33

Improvements through 2018 74 projects 60 of which are completed Source of supply Watershed protection Supply redundancy Operational Improvements Staff training and certification Security upgrades Treatment infrastructure improvements Process improvements Reliability projects Primary power redundancy Distribution safeguards and monitoring SCADA System 34

Summary WTP is now a safer facility though still not complete New electrical gear uninterrupted operation Delayed monitoring & manual operation replaced Process automatically monitored & controlled Met all WQ & Ops standards for the last 4 years 35

Questions? Architectural Rendering of Future Operations Building 36