Rooftop Solar and Net Metering in India - A Detailed Analysis

Similar documents
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF

Rooftop Solar PV Power : Potential,Growth and Issues related to

Financial Analysis of Solar Photovoltaic Power plant in India

G.O.MS.No. 8 Dated Read the following:-

Renewable Energy Certificate Mechanism

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO , SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.

Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation

Grid Connected Solar Power in India. Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India

Solar Power Plants FAQs

CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008

Analysis of state-wise RPO Regulation across India

THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE

Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014

Wind Power Programme in India

Initiatives by TEDA and

Analysis of Solar Energy Industry in India & Its Future Prospects

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com

Government of India Ministry of New and Renewable Energy MNRE

POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI

Tamil Nadu WiNd ENErgy ProfilE

TWO NEW MUST-HAVE RESEARCH REPORTS ON THE RENEWABLE ENERGY SECTOR

Existing Wind Power Policies and Incentives

SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems

Delhi Solar Energy Policy, 2015

TELANGANA SOLAR POWER POLICY 2015

all that you want to know About Rajasthan Solar Energy

Energy Efficiency, Clean Power as Engine for Sustainable Growth

Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar

Total 5,926 24,514 66,355 97,042 68, ,

Solar for Businesses. Getting Started with Solar. Laura Williams, Renewables Project Manager. June 10, 2015

DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015

The Solar Power Specialists. Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House, Unit A19, 20 Heron Road, Belfast, BT3 9LE

Marketing Methodology of Solar PV Power Packs

The Energy Transition in Germany Past, Present and Future

Sustainable Schools Renewable Energy Technologies. Andrew Lyle RD Energy Solutions

Using the sun to generate electricity

NOTICE OF INTENT Department of Revenue Policy Services Division. Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I.

Solar Power Frequently Asked Questions

Performance Assessment of 100 kw Solar Power Plant Installed at Mar Baselios College of Engineering and Technology

Presenter: Bruce Clay Clay Energy Fiji

Solar power plants for residential, commercial, utility and off-grid applications Part 2

Solar Rooftop Policy/ Guidelines

KERALA STATE ELECTRICITY REGULATORY COMMISSION

Summary of Electric Power Research Institute (EPRI) Report on Residential Off-Grid System Economics

The Energy Saving Trust s community solar programme How your community can benefit from discounted solar panels and Feed-in Tariffs

e-factsheet Feed-in Tariffs what we have to offer

Success in Scaling-up Solar Energy in Rajasthan, India

Solar technology. A guide to solar power at utility scale. in Africa

SOLARIS ENERGY SOLUTIONS

Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading

Electricity from PV systems how does it work?

Technology Fact Sheet for Mitigation

Frequently Asked Questions SOLAR ENERGY:

KERALA STATE ELECTRICITY REGULATORY COMMISSION

SOLAR ENERGY IN INDIA

Solar systems provide a range of flexible heating

Alternative Energy Made in Florida. Solar Power Plants for Commercial, Government, and Utility

Solar energy is available as long as the sun shines, but its intensity depends on weather conditions and geographic

Explanation of Net Energy Metering and Annual Net Surplus Electricity Settlement Options

Techno-Economic Analysis of Solar PV Based FM Radio Broadcasting Stations

In Focus. India s Renewable Energy Certificate Market

Solar and Wind Energy for Greenhouses. A.J. Both 1 and Tom Manning 2

Self-consumption. that you need to purchase from your power company. Bosch Solar Energy recommends photovoltaic systems with self-consumption.

FEED-IN TARIFF (FiT) IN MALAYSIA

SOLAR PV-WIND HYBRID POWER GENERATION SYSTEM

How To Increase Private Consumption

2016 Santee Cooper Solar Home & Solar Share Home Program Manual

Telecom Energy Management

The Rising Sun Grid parity gets closer kpmg.com/in

Additional Solar System Information and Resources

RENEWABLE ENERGY INVESTMENTS

Format - 17 GUIDELINES FOR ON-GRID SOLAR RTPV PROGRAMME (ON NET- METERING BASIS) FOR BESCOM OFFICERS

Solar PV For Surrey Schools - Information Pack

Solar Interconnections

Solar Power HourSM. Solar educa on for your community.

KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore

Siemens and The Carbon Trust The Free Money Deal. Free Money. Money doesn t grow on trees. But it does now grow on roofs and in boiler houses.

Everything you wanted to know (in simple language) about

Solar PV Panels. A talk by Ham and Petersham Street Champions

Solar Irrigation in Bangladesh

Local Solar. bikeriderlondon / Shutterstock.com. Local Solar Power

Free electricity for your home, offices or factory with solar PV panels

WIND POWER IN INDIA: PROS AND CONS AN OVERVIEW

Renewable Energy Certificate Mechanism for India. ABPS Infrastructure Advisory. Background

ALL STAR ELECTRIC COMPANY 10,000 Trumbull SE, Suite #F Albuquerque, NM (505) voice & fax NM License

Solar PV Installations for Social Housing Providers

Transcription:

Rooftop Solar and Net Metering in India - A Detailed Analysis White Paper from EfficientCarbon

Introduction Energy demand in India both in urban and rural areas in continuously increasing, however the electricity utilities are unable to meet this rapidly increasing demand. This is the reason why most of the commercial buildings such as hospitals, offices, malls etc. as well as residential buildings in the country are opting for back-up power systems. These back-up power systems are usually diesel generators and sometimes more than one generator is installed to meet their electricity demand. With rising costs and environmental awareness, many of these buildings are opting for Solar Photo Voltaic (SPV) systems as back-up power in order to reduce their dependency on diesel generators. These SPV systems which convert sunlight into electricity, are usually installed on the existing roof-top space of buildings to meet the minimum load requirement. A typical roof-top SPV system consists of all or some of the following components depending on its type: Photovoltaic modules Charge controllers Inverters Module mounting structures Evacuation switchyard Wires Metering system Apart from these components, an important requirement is availability of shadow-free roof-top space. Minimum shadow free area required to install a typical 1kW system on rooftop is about 30 sq. m. There are two types are such roof-top SPV systems grid independent systems and grid connected systems. Grid independent systems come with either with or without battery back-up. Batteries are used to store the excess electricity generated during the day to be used at night or when insufficient solar power is generated due to cloud cover etc. Given below is a typical illustration of battery back-up solar roof-top system. Batteries are often not opted for as - they are expensive requiring high investment and also they need to be periodically replaced. Hence, depending on the size of the system and its requirement, a building opts for a battery back-up system or without battery backup. In the second case, the system is generally sized such that electricity generated during the day from this SPV is utilized to meet its power requirement and the night time or when there is insufficient power generated, electricity is drawn from the grid or diesel generator. In the grid connected systems, the DC power generated is converted into AC power and is then fed into the grid. Electricity generated in this case during sunshine hours is primarily consumed by the building and excess in fed into the grid. However during the hours of insufficient power generation, electricity is drawn from the grid. For such systems, the grid acts as its battery back-up. Settlement of the energy imported to or exported from the grid is done by mechanisms such as: Feed-in Tariff Net metering Signing a Power Purchase Agreement. Net Metering The concept of net metering involves recording the net energy between export of generated energy and import of energy from distribution licensee for a given period of time. This involves the usage of a bi-directional meter which has the facility to record both import and export values. Under the net metering system, the excess energy generated by the solar photovoltaic plant at a given point of time is exported to the grid instead of being stored using a battery. However when there is a deficit in the power generated by the solar panels either during the night or a cloudy day, energy is drawn from the grid. At the end of the billing period, 1

Solar Panels Inverter Transformer Electrical Load Standard Meter Grid Kerala Kerala launched its 10,000 roof-top power plants programme for 2012-13 targeting a capacity of 10 MW. Since the per capita limit is small, this programme targeted households and small cottage industries. Each applicant is eligible to apply for 1kW system. Also apart from MNRE subsidy of 30% project cost or Rs. 81,000 per system, the state offers a discount of Rs. 39,000 per system Typical Net Metering Grid Connection System if more energy is exported to the grid than imported, then the distribution licensee pays the consumer at a pre-determined price. On the other hand if more energy is imported from the grid than exported, then the consumer pays the distribution licensee at a predetermined price. These prices usually vary from state to state. Solar Rooftop Policies of Indian States Tamil Nadu Tamil Nadu in its State solar policy announced a target of 350 MW capacity to be set up through solar roof-top systems by 2015. Of this capacity, it envisions 50 MW to be set up via Generation Based Incentive (GBI) route. GBI is proposed to be provided for six years with the following break up for solar or solarwind hybrid rooftops installed before 31st March, 2014: First two years Rs. 2/unit Next two years Re. 1/unit Last two years Re. 0.5/unit Gujarat Gujarat thought its Gandhinagar Solar Photovoltaic Rooftop programme targets to set up 5 MW capacity grid interactive roof-top SPV systems. Under this pilot project, SPV systems of various sizes ranging from 500 kw, 100 kw, 50 kw, 20 kw, 10 kw, 5 kw, 1 kw or more are expected to be set up on rooftops. However the size of an individual SPV system would depend on the shadow-free rooftop space available. Total capacity is to be divided into two subprojects having 2.5 MW capacity each and out of 2.5 MW, 2 MW capacity SPV systems will be installed on Government Rooftops and 0.5 MW on private rooftops. The proposed metering system for these projects is the Feed-in metering system. As per solar tariff order, 2012, for solar PV rooftop projects levelized tariff for 25 years: Projects availing accelerated depreciation Rs. 10.36/kWh Projects not availing accelerated depreciation Rs. 11.57/kWh Consumers who wish to avail GBI are required to install separate meters to measure rooftop generation. Net metering mechanism has also been proposed to set up solar rooftop systems. Net metering will be allowed for commercial establishments and individual homes to feed excess power generated back to the grid with power credits accruing to the power producer. Suitable voltages are suggested below: Solar PV System Size Grid Connected <10 kwp 240 V 10 kwp to <15 kwp 240 V / 415 V 15 kwp to <50 kwp 415 V 50 kwp to <100 kwp 415 V >100 kwp 11 kv Photovoltaic Modules Protection Device Junction Box Inverter Isolation Transformer Manual Disconnect Export Meter Conventional Energy Meter To Grid 2

Implementing Structure of solar rooftops in Gujarat Karnataka Karnataka s released a tender this year in January targeting a capacity 1.3 MW to be set up through 0.5 1 kw household solar systems across 1943 houses in several cities. The total cost was specified as Rs. 34 crores. Tariff of Rs. 3.4/kWh along with net metering facility was proposed for such SPV systems. Rajasthan Rajasthan through its state Solar Policy announced in 2011 aims to promote the setting up of roof-top plants connected to LT/11 kv grid as per the MNRE guidelines under Rooftop PV & Small Solar Generation Programme (RPSSGP) of the National Solar Mission. Accordingly PPA shall be executed with the concerned Discom of Rajasthan with metering arrangements made as per the CERC regulations. Haryana Haryana s solar policy targets commercial and industrial entities and it has approved two pilot projects of 100 kw providing financial assistance of Rs. 75 lakhs each. Chhattisgarh Chhattisgarh in its solar policy (2012-17) mentioned that solar roof-top plants can be set up under supported types of power generation plants. Under this policy, the total grid connected capacity target is 500-1000MW by 2017 to be set up through grid connected plants including solar roof-top plants. Andhra Pradesh Following the AP Solar policy, the Government released an order for setting up net metering facility in the state. This was done to encourage setting up solar PV plants on rooftops. As per G.O.Ms.No.22 for excess energy imported from the DISCOM, the consumer is expected to pay the DISCOM as per applicable retail supply tariff decided by the regulator commission. This settlement is done on a monthly basis. For excess energy exported to the DISCOM by the consumer, no payment will be made by the DISCOM. The generator is also required to bear the entire cost of metering arrangement provided including its accessories. Changes were made to this order in G.O.Ms.No.27, wherein the state Government decided to make payment for the surplus energy injected into the grid by a generator. This payment will be made at pooled cost as may be decided by APERC for that year. This cost will be made effective for a period of 7 years from the date of establishment of such SPV plant and the settlement of this surplus energy will be carried out on a half yearly basis. Along with this the Government will provide 20% subsidy from the State budget to be paid for installation of rooftop system (up to 3 kw capacity) in domestic sector only. This subsidy will be provided in addition to the eligible Central subsidy. 3

A typical semi-urban/rural household with a off-grid solar inverter system in Anantapur, Andhra Pradesh. Scheme supported by NABARD, MNRE & NREDCAP 4 Photographs courtesy, Thrive Energy Technologies, Hyderabad

Payback Periods for a Typical Solar Rooftop - Net Metering System Since we have a clear-cut GO issued along with a tariff announced for Andhra Pradesh, we are taking this example for AP alone. Similar values, when they are announced, can be substituted for different states while calculating the payback periods for those states. In order to get maximum returns from a SPV - Net Metered system, sizing is very important. To illustrate this,the following cases have been worked on to calculate the payback period in each situation. This is done for a 3 kw system which generates 12 units/day. Such a system costs close to Rs. 3,00,000 and after MNRE and State subsidy is provided it s cost comes down to Rs. 1,50,000. Settlement of electricity is done as per the G.O. Additionally, we could factor Rs 10,000 as additional expenses. Please note that we have not taken any battery backup into consideration and hence the low costs for the system. The payback period Case 1: Monthly production is more than the monthly consumption Generation: Consumption: Units/month = 300 kwh Electricity Bill paid normally: 0-100 units = Rs. 2.60 / kwh 101-200 units = Rs. 3.60 / kwh 201-300 units = Rs. 5.75 / kwh So, total bill = Rs. 1195 Since the production is 360 units, net consumption is - 60 units. Hence the entire bill is waived off and the generator gets Rs. 3.50 / kwh. So, monthly net benefit for the generator: Waived off bill = Rs. 1195 Add payment for units generated = Rs. 210 Total benefit per month = Rs. 1405 Total benefit per year = Rs. 16,860 Payback period for the investment = 9.48 years Case 2: Monthly production is equal to the monthly consumption Generation: Consumption: Electricity Bill paid normally: 0-100 units = Rs. 2.60 / kwh 101-200 units = Rs. 3.60 / kwh 201-300 units = Rs. 5.75 / kwh 301-360 units = Rs. 6.75 / kwh So, total bill = Rs. 1600 Since the production is 360 units, net consumption is 0 units. Hence the entire bill is waived off and the generator gets no aditional benefit So, monthly net benefit for the generator: Waived off bill = Rs. 1600 Add payment for units generated = Rs. 0 Total benefit per month = Rs. 1600 Total benefit per year = Rs. 19,200 Payback period for the investment = 8.33 years Case 3: Monthly production is more than the monthly consumption Generation: Consumption: Units/month = 400 kwh Electricity Bill paid normally: 0-100 units = Rs. 2.60 / kwh 101-200 units = Rs. 3.60 / kwh 201-300 units = Rs. 5.75 / kwh 301-400 units = Rs. 6.75 / kwh So, total bill = Rs. 1870 Since the production is 360 units, net consumption is 40 units. Hence the entire bill is waived off and the generator gets no aditional benefit while he has to pay the bill for the additional 40 units consumed at Rs. 2.60 / kwh. 5

Actual bill = Rs. 104 So, monthly net benefit for the generator: Waived off bill = Rs. 1870 Subtract Actual bill paid = Rs. 104 Add payment for units generated = Rs. 0 Total benefit per month = Rs. 1766 Total benefit per year = Rs. 21,192 Payback period for the investment = 7.55 years Please note: Here, we are not Adding fixed demand charges Adding FSA charges & Adjusting for increase in electricity prices If we take all these factors into account, the approximate payback periods could be: For Case 1 = 7.5 years For Case 2 = 6-6.5 years For Case 3 = 5 years Looking at these payback periods, it would be worthwhile to invest in setting up a Solar PV power pack on rooftops with net metering facility. With a lifetime of more than 20 years and minimum maintenance, grid synchronised Solar Power plants are the way to go for the future. About Ef icientcarbon EfficientCarbon is a consulting firm focusing on providing specialist advisory solutions to companies in the areas of Sustainable Development, Climate Change strategy, Carbon Management and Renewable Energy. With integrity, efficiency and diligence, EfficientCarbon strives to help its clients companies manage their environmental and social impacts and become totally Sustainable organisations in the truest sense. For more information, please visit www..com Contact: Pradeep Palelli Managing Partner Ph: +91 9052224701 Mail: pradeep@.com Harini Challapally Consultant - Renewable Energy Mail: harini@.com Conclusion The purpose of this document was to give Solar PV system integrators, companies looking to enter the rooftop solar market and potential customers a low down on the policies and where the market is heading. Looking at the proactive approach being taken up by MNRE and various nodal agencies, grid synchronised, net metered or captive rooftop solar PV will see a major growth and will help our country in achieving energy independence from fossil fuel based electricity. Copyright EfficientCarbon. All rights reserved. 6