The Manitoba Water Services Board SECTION

Similar documents
SECTION EARTH MOVING

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

City of Shelbyville Site Inspection Checklist

Specification Guidelines: Allan Block Modular Retaining Wall Systems

MDWASD 8/1999 SECTION TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

Stormwater/Wetland Pond Construction Inspection Checklist

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

SECTION SHEETING, SHORING AND BRACING

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Section 2 Specification 2.18 Concrete and/or Corrugated Steel Storm Sewer TABLE OF CONTENTS

Storm Drain Inlet Protection

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

SECTION 5. Sediment Control Measures

SE-10 STORM DRAIN INLET PROTECTION. Objectives

Construction Site Inspection Checklist for OHC By making use of some simple Best Management Practices (BMPs) a construction site operator can

Storm Drain Inlet Protection for Construction Sites (1060)

No allowance will be made for classification of different types of material encountered.

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection - IP

Outlet stabilization structure

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

Appendix D.1. Testing Requirements for Infiltration, Bioretention and Sand Filter Subsoils

Block and Gravel Inlet Protection (BIP)

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

City of Beaumont, Texas Grading Permit Information

Section 2100-Trenching and Tunneling

SECTION EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction)

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

SECTION SITE PREPARATION

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Carlton Fields Memorandum

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Table 4.9 Storm Drain Inlet Protetion Applicable for

CONSTRUCTION PERMIT REQUIREMENTS

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER

UFGS (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

Storm Drain Inlet Protection

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

SeCTion TemPoRARy Soil erosion and WaTer pollution ConTrol sewpcp requirements

Riprap-lined Swale (RS)

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

SECTION 1 GENERAL REQUIREMENTS

DESCRIPTION OF WORK:

SECTION POLYVINYL CHLORIDE (PVC) PIPE

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Division 2 Section Section 02795

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

SC-07 STORM DRAIN INLET PROTECTION

Operations and Maintenance Guidelines for Coal Ash Landfills Coal Ash Landfills are NOT the Same as Subtitle D Solid Waste Landfills

Section EXCAVATION AND BACKFILL FOR UTILITIES

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

INDEX DESCRIPTION MATERIALS APPROVAL OF SUBBASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

UNIFIED FACILITIES GUIDE SPECIFICATIONS

BRIDGES ARE relatively expensive but often are

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS

Soils, Foundations & Moisture Control

Technical Manual - Section 1 Introduction to Lytag lightweight aggregate

Tobique Employment & Training

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,

C. Section TESTING LABORATORY SERVICE.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

Beacon Hill Sewer District Standard Specifications

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

4-02 Gravel Base Ballast and Crushed Surfacing

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Emergency Spillways (Sediment basins)

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

SECTION REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:

Transcription:

Page 1 of 10 Part 1 General 1.1 DESCRIPTION OF WORK.1 This work shall consist of the removal of all materials of whatever nature, necessary for the proper placement of structure foundations, the supply and placement of all backfill materials and the final disposal of surplus and unsuitable materials. It shall include the construction of all cofferdams, cribs, caissons, shoring or other protective works necessary for excavation and backfill of the structure, together with all the necessary drainage and dewatering of the site. It shall also include the removal of all falsework, piling, cofferdams, cribs, shoring or other protective work, unless otherwise specified on the plans or as directed by the Engineer. 1.2 CLASSIFICATION OF WORK.1 EXCAVATION A - Excavation A shall include general excavation for the structure to the grade or grades shown on the plans and the disposal of this excavated material..2 EXCAVATION B Excavation B shall be the excavation for the construction of cut-off walls, curtain walls, or footing keys as may be necessary for the structure e and this excavation shall be to the outlines of that portion of the structure as shown on the plans, and shall include disposal of all excavated material..3 BACKFILL - Backfill shall include the supply and placing of any or all of the materials listed hereunder:.1 Common Backfill.2 Compacted Common Backfill.3 Compacted Impervious Backfill.4 Compacted Select Granular Backfill.5 Filter Gravel.6 Filter Sand 1.3 STANDARDS The following organization publishes Standards which have been referred to in this section:

Page 2 of 10.1 A.S.T.M. American Society for Testing and Materials 100 Barr Harbor Drive West Conshohocken PA 19428-2959 USA.2 Manitoba Workplace Safety and Health Act and Regulations The standards referred to shall be the most recent edition. 1.4 SUBMITTALS.1 In the event that cofferdams are required, and when requested by the Engineer, the Contractor shall submit drawings showing the proposed method of cofferdam construction..2 The submittal of these drawings shall not in any way relieve the Contractor of his responsibility to provide a safe and satisfactory cofferdam. 1.5 JOB CONDITIONS.1 OVER EXCAVATION, EXCAVATION A - The Contractor shall excavate only such materials as shall be necessary for the construction of the structure and must not excavate outside the limits of excavation indicated on the plans or as set out in the field. Where excavation is beyond the lines and grades shown on the plan, the Contractor shall replace the excavated material with appropriate backfill material as directed by the Engineer at the Contractor's expense..2 OVER EXCAVATION, EXCAVATION B - Over excavation of excavation B and the use of inside wood forms shall only be permitted with the approval of the Engineer. The forms shall be removed prior to any backfilling taking place. Excavation beyond the neat outline of the structure as shown on the plans shall be backfilled with material approved by the Engineer. The work of forming, backfilling and tamping shall be at the Contractor's expense. This class of excavation shall not be commenced until Excavation A is completed..3 UNSUITABLE COMMON BACKFILL - In the event that the Engineer deems the excavated material to be unsuitable for Common Backfill or for Compacted Common Backfill, and if the excavated material is unsuitable through no action of the Contractor, the Owner will supply suitable backfill material or shall require the Contractor to supply suitable backfill material to the excavation site which shall be paid for in accordance with the General Conditions attached hereto. The unsuitable excavation material shall be designated as surplus material and shall be disposed of to a site designated by the Engineer.

Page 3 of 10.4 SITE ALTERATIONS - In the event that the Engineer shall permit the excavation of access ramps, trenches or borrow pits within the limits of construction to facilitate the execution of the work, the Contractor shall, on completion of the work and at the Contractors expense, backfill such access ramps, trenches or borrow pits to the elevation of the original ground surface existing prior to the excavation, or as directed by the Engineer..5 RIVER AND CHANNEL PRESERVATION - The Contractor shall execute construction excavation and backfill procedures in accordance with the requirements of Manitoba Conservation guidelines and as outlined below..1 OFF-CHANNEL STRUCTURES - Excavation spoil piles shall be placed above the high water mark of the river or channel and run off shall be controlled to reduce the volume of sediment entering the river or channel. The Contractor shall submit a sediment control plan to the Engineer, for approval, at least two weeks prior to construction. A sediment pond to limit sediment from washing into the river or channel may be required. All data with respect to anticipated discharge rates and sediment size shall be submitted to the Engineer with the proposed sediment pond sizing. Maintenance of the sediment pond shall include periodic excavation of trapped sediment from the pond and sediment removal from the site to a location approved by the Engineer. Sediment trapped along the excavation slopes of the river or channel shall also be removed. Discharge from the excavation shall be pumped to the sediment control pond. The sediment control pond shall be sized to settle sediment from the pump discharge and shall be based upon the anticipated discharge rate to the pond and the size of the sediment within the discharge. Table 1 below is to be used as a guideline for sizing the pond. Discharge at the inlet to the pond shall be protected by a rip rap scour pad to distribute flow and to ensure that the settling pond base does not erode. Following construction, all sediment control materials associated with the sediment pond shall be removed and the site restored to the original contour and vegetative cover. Collected sediment shall be removed and disposed of at an approved spoil site. Excavated river or channel slopes shall be revegetated and protected for long term stability against surface erosion. The Contractor shall be responsible for establishing short and long term erosion control on the excavated slopes. Acceptable short term procedures include, rip rap, silt

Page 4 of 10 fences, straw bales or brush filters. In the long term, the slope shall be rip rapped or revegetated to the satisfaction of the Engineer. TABLE 1 REQUIRED SURFACE AREA FOR DISCRETE PARTICLE SETTLING (m 2 POND AREA PER m 3 /sec OF FLOW TO POND) PARTICLE CLASSIFICATION PARTICLE DIAMETER (MICRONS) WATER TEMPERATURE 0 O C 5 O C 10 O C 15 O C 20 O C Coarse sand 1000 3 3 3 3 3 medium sand 500 8 7 6 5 5 fine sand 250 40 33 28 23 19 coarse silt 62 620 530 460 400 460 medium silt 31 2486 2111 1819 1583 1389 fine silt 16 9332 7924 6829 5943 5213 very fine silt 8 37327 31697 27318 23773 20853 coarse clay 4 149310 126788 109271 95091 83413 medium clay 2 597239 507153 437085 380364 333653 fine clay 1 2388956 2028611 1748342 1521458 1334612.2 IN-CHANNEL STRUCTURES - For in-channel structures, the natural stream bed adjacent to the structure shall not be disturbed without permission from the Engineer. If any excavation or dredging is made at the site of the structure before caissons, cribs, or cofferdams are placed, the Contractor shall, without extra charge, after the foundation base is in place, backfill all such excavation to the original ground surface of the channel, stream or river bed with material satisfactory to the Engineer. Material deposited within the stream area from foundation or other excavation or from the filling of cofferdams, shall be removed and the stream area freed from obstructions..3 MITIGATION MEASURES - The following measures shall be taken to mitigate environmental concerns:

Page 5 of 10 1.6 INSPECTION.1 The Contractor shall not permit wastewater containing toxic material such as cement, concrete, lime or other construction materials to enter the river or channel..2 Debris entering the river or channel from clearing and construction activity shall be removed immediately by the Contractor..3 The Contractor shall not permit refuelling or servicing of construction equipment within 100 metres of surface water bodies..4 The Contractor shall ensure the collection and disposal of waste oil products from construction equipment is in accordance with Manitoba Laws and Regulations..5 The Contractor shall not permit construction activity between April 1 and June 15 that would disturb fish habitat or migrations..6 The Contractor shall minimize the time and extent of bare ground exposure..7 The Contractor shall revegetate the river banks and disturbed areas..8 The Contractor shall use rock rip rap for shoreline erosion control where necessary..1 EXCAVATION - After each excavation is completed the Contractor shall notify the Engineer, and no further work shall be commenced until the Engineer has approved the depth of the excavation and the suitability of the foundation material..2 BACKFILL - Backfill material shall be tested by the Engineer at the Owner's expense, during placement, to ensure conformance with these Specifications. The Contractor shall supply the required samples for testing at no cost to the owner. Part 2 PRODUCTS 2.1 MATERIAL.1 EXCAVATION - Material to be excavated is the in situ material at the structure site.

Page 6 of 10.2 BACKFILL Unless noted otherwise on the drawings, backfill shall be Common Backfill. All material used for backfill shall be of a quality acceptable to the Engineer and shall be free from large or frozen lumps, roots, and rocks no greater than 75mm in diameter, sod, brush or metallic trash or other unsuitable materials. Unless specified otherwise in Section 01001, Special Provisions, backfill shall be one of the following six classes of material:.1 Common Backfill - shall consist of material obtained from the excavation or suitable borrow area without restriction as to soil type..2 Compacted Common Backfill - shall consist of material obtained from the excavation or suitable borrow areas without restriction as to soil type..3 Compacted Impervious Backfill - shall consist of clays, silty clays or sandy clays obtained from the excavation or suitable borrow areas..4 Compacted Select Granular Backfill - shall meet the following gradation: SIEVE 75mm % PASSING 100 25 mm 80-100 4.75mm 40-70 75um 0-15.5 Filter Gravel shall meet the requirements of concrete coarse aggregate: SIEVE 25mm % PASSING 100 19mm 90-100 12.50mm 30-75 9.50mm 20-55 4.75mm 0-10 2.36mm 0-5

Page 7 of 10.6 Filter Sand - shall meet the requirements of concrete fine aggregate: SIEVE 9.50mm % PASSING 100 4.75mm 95-100 2.36mm 80-100 1.18mm 50-85 600um 25-60 300um 10-30 150um 2-10 Part 3 EXECUTION 3.1 CLEARING AND GRUBBING.1 Where necessary, prior to commencing excavation operations, clearing and grubbing shall be undertaken as set forth in Section 021160, Clearing and Grubbing. 3.2 PLACING OF EXCAVATED MATERIAL.1 All excavated material shall be placed in disposal areas where shown on the plans or as directed by the Engineer. In no case shall the Contractor be permitted to place excavated material in the area adjacent to the top of any excavation..2 The disposal areas shall be trimmed and left in a neat, tidy, free draining condition with an evenly graded surface. 3.3 EXCAVATION DEPTH.1 The excavation shall be to the elevations shown on the plans, or to such other elevations as may be directed by the Engineer in order to provide firm, stable foundation support..2 The Contractor shall remove all unsuitable material from the excavation as directed by the Engineer. Unsuitable excavated material shall be replaced with

Page 8 of 10 material approved by the Engineer. The work involved for additional excavation and replacement of unsuitable material shall be paid as extra work unless otherwise shown on the Plans or indicated in Section 01001, Special Provisions..3 The width and length of the excavation and the angle of excavated side slopes shall take into consideration the stability of the material. No extra payment or scheduling will be allowed for improper excavation methods which result in material sliding back into the bottom of the excavation. 3.4 WINTER EXCAVATION.1 Under winter conditions and for concrete structures the Contractor must prevent frost from penetrating the base of the excavation and shall maintain the excavation in a satisfactory, frost-free condition. 3.5 SHORING.1 For structures where space constraints prohibit the use of sloped side walls for the excavation, and where the excavation is deeper than 1.8 m, the structure excavations shall be shored and braced. The interior dimensions of clearance shall allow for the construction of forms and the inspection of their exteriors, driving piles where applicable, and for water drainage collection and pumping outside of the forms..2 Unless otherwise provided, shoring and bracing shall be removed by the Contractor after the completion of the foundation sub-structure. The removal shall be undertaken in such a manner as not to disturb or damage the structure. 3.6 DEWATERING.1 The Contractor shall construct, supply, maintain and operate all necessary dykes, cofferdams, drains, sumps, well points and pumps and any other equipment that may be required to keep the work area free from all sources of water damage which may affect the work..2 The Contractor's method of removing water from foundation excavations shall be subject to the Engineer's approval. All dewatering shall be achieved in a manner which shall prevent the loss of fines from the foundation, shall maintain the stability of the excavated slopes and the bottom of the excavations, and shall result in all construction operations being performed in the dry. The cost of dewatering shall be considered incidental to excavation.

Page 9 of 10 3.7 COMPACTION OF BACKFILL.1 The six classes of backfill shall be placed and compacted in accordance with the following methods:.1 Common Backfill - shall be placed in 150 mm lifts and compacted with the wheels or tracks of construction equipment..2 Compacted Common Backfill - shall be placed in 150 mm lifts and mechanically compacted to 95% of maximum Standard Proctor dry density (ASTM D698) at moisture content between 0.9 and 1.2% of optimum..3 Compacted Impervious Backfill - shall be placed in 150 mm lifts and mechanically compacted to 95% of maximum Standard Proctor dry density (ASTM D698) at a moisture content between 0.9 and 1.2% optimum..4 Compacted Select Granular - shall be placed in 150 mm lifts and mechanically compacted to 100% of maximum Standard Proctor dry density (ASTM D698)..5 Filter Gravel - where filter gravel is located under a structure it shall be placed in 150 mm lifts and compacted with mechanical compaction equipment. Where filter gravel is located under backfill it may be placed without compaction..6 Filter sand - where filter sand is located under a structure it shall be placed in 150 mm lifts and compacted with mechanical compaction equipment. Where filter sand is located under backfill, it may be placed without compaction. 3.8 WINTER BACKFILLING.1 Unless otherwise stated in Section 01001, Special Provisions, the placing of frozen backfill of any type shall not be permitted. The placing of backfill on frozen ground shall not be permitted. All types of backfill, when placed, shall be kept from freezing until all backfill operations are complete. 3.9 BACKFILL PROCEDURES.1 Care shall be taken to avoid damage to pipes or portions of structures embedded in the backfill.

Page 10 of 10.2 All backfill within 600 mm of the surface of a structure shall be compacted by hand operated mechanical plate tampers to the density specified for the class of backfill involved..3 Upon completion of backfilling, the Contractor shall shape and trim the area in accordance with the lines and grades shown on the plans or as staked on the ground by the Engineer..4 Special precautions shall be taken to prevent wedging action against abutments and retaining walls. The slope bounding the excavation shall be altered by stepping or serrating to prevent wedge action..5 Fill placed around structures shall be brought up uniformly at approximately the same elevation on all sides of the structure.