CAST IN-SITU CONCRETE WORKS TECHNICAL SPECIFICATION

Similar documents
Construction Specification for Concrete Curb and Concrete Curb and Gutter

TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER

SPECIFICATION FOR CONSTRUCTION OF UNBOUND GRANULAR PAVEMENT LAYERS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Urban Vehicle Crossing Application To be completed and fees paid for prior to approval

Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors

C. Section TESTING LABORATORY SERVICE.

SECTION EARTH MOVING

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

DESCRIPTION OF WORK:

3. QUALITY ASSURANCE REQUIREMENTS

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

INDEX DESCRIPTION MATERIALS APPROVAL OF SUBBASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6

4-02 Gravel Base Ballast and Crushed Surfacing

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

SECTION 1 GENERAL REQUIREMENTS

ROAD OPENING LICENCE APPLICATION FORM PLEASE READ ALL PARTS AND SECTIONS OF THIS FORM IN ADVANCE OF COMPLETING THE APPLICATION

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

SECTION PRECAST CONCRETE UTILITY STRUCTURES

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

WATERPROOFING FOR CONCRETE STRUCTURES

INSTALLATION OF INSITUFORM LINER

SECTION PRECAST CONCRETE STRUCTURES

SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)

General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and guards.

Division 2 Section Section 02795

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

40-9 PERMEABLE INTERLOCKING CONCRETE PAVEMENT

Commonwealth of Pennsylvania PA Test Method No. 632 Department of Transportation October Pages LABORATORY TESTING SECTION. Method of Test for

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

SECTION GUARDRAILS

Design and Construction of Cantilevered Reinforced Concrete Structures

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS

A. This Section includes rubberized asphalt sheet membrane waterproofing systems.

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Specification Guidelines: Allan Block Modular Retaining Wall Systems

INTERIM ADVICE NOTE 96 /07 Revision 1 GUIDANCE ON IMPLEMENTING RESULTS OF RESEARCH ON BRIDGE DECK WATERPROOFING

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Example Specification for Concrete using Current Building Code Requirements

CHAPTER 7: SUBDIVISION CONSTRUCTION, INSPECTION AND BONDING Subdivision Improvement Performance Bond Requirements

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

GUIDELINES FOR POLISHED CONCRETE FLOORS A Guide for Integrally Colored, Dyed and Stained Polished Floors

cement Masonry Cement Engineered for quality and reliability, Lafarge cements for masonry deliver consistent performance. page 2 Lafarge Cement

FIBER-OPTIC CABLE PLAN CHECK

CONSTRUCTION PERMIT REQUIREMENTS

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

1.02 DESCRIPTION A. This Section specifies furnishing and installing Cast in Place Detectable/Tactile Warning Surface tiles where indicated.

SECTION PAVEMENT DESIGN

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

APPENDIX B. I. Background Information

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION SHEETING, SHORING AND BRACING

Chapter 2 Basis of design and materials

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12

Before applying for a Road Opening Licence, please read and understand the following information.

RIGHT OF WAY ACTIVITY APPLICATION FOR OUTDOOR PATIOS ON MUNICIPAL PROPERTY IN THE CITY CENTRE

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

Chapter 8 Design of Concrete Mixes

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 16 BRIDGE DECK WATERPROOFING General Materials Equipment...

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

Grinding equipment that causes raveling, aggregate fractures or disturbance to the joints shall not be permitted.

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

METHOD STATEMENT 006 TORCH APPLIED MEMBRANE TO BASEMENT WALLS

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT

Cold Weather Concrete Practices

Wastewater Capital Projects Management Standard Construction Specification

Construction Specifications for Keyhole Pavement Coring and Reinstatement

Section SEWER PIPE INSTALLATION AND TESTING

SECTION 4Aggegate Subbase

INSTALLATION SPECIFICATIONS FOR AQUAPERM TM PAVER

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON ROAD SURFACE REQUIREMENTS FOR EXPRESSWAYS AND HIGH SPEED ROADS

Permit No. Permit Fee: $ Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: Address:

SECTION SITE PREPARATION

1. It would create hazardous effects of storm water run-off. 3. It would increase hazardous driving conditions on the public road.

Federation of Piling Specialists

SECTION STORM DRAIN SYSTEM

Water and Sewer Service Line Policy

Item No. 432S Portland Cement Concrete Sidewalks. 432S.1 Description

TS 813 GROUNDING AND BONDING TTD TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD CONTROLLER CABINET GROUNDING

Construction Management Program

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

VEHICLE CROSSOVER INFORMATION PACK

Transcription:

CAST IN-SITU CONCRETE WORKS TECHNICAL SPECIFICATION

TABLE OF CONTENTS CAST IN-SITU CONCRETE WORKS - TECHNICAL SPECIFICATION 1. GENERAL CONDITIONS 1.1 Extent of Work 1.2 Working Days and Hours 1.3 Responsibility regarding Existing Services 1.4 Protection of Property 1.5 Authority of the City Project Engineer 1.6 Traffic Management and Barricades on work sight 1.7 Water 2. SPECIFIC CONDITIONS 2.1 Scope of Work 2.2 Excavation when carried out by Contractor 2.3 Compaction 2.4 Forming 2.5 Concrete 2.6 Placing and Finishing 2.7 Protection of Works 2.8 Joints 2.8.1 Transverse Contraction Joints 2.8.2 Transverse Expansion Joints 2.9 Stripping of Edge Forms 2.10 Construction Criteria 2.10.1 Tolerances 2.10.2 Test Specimen 2.10.3 Thickness LIST OF APPENDICES Appendix A - Application to work in Road Reserve Appendix B - Footpath, Dual Use Path and Public Access Ways Details

Appendix D CAST IN-SITU CONCRETE WORKS TECHNICAL SPECIFICATION 1. GENERAL SPECIFICATION 1.1 Extent of Work The works shall consist of cast in-situ concrete paths on Road Verges in Pedestrian Access ways and other areas within the City of Stirling in accordance with this Specification and as shown on plans or as directed by the City Engineer s representative. 1.2 Working Days and Hours Work hours on site during Monday to Saturday are to be restricted to the hours 7.00am and 6.00pm in accordance with the City of Stirling restrictions for work on Arterial roads. Should the Contractor considers it essential to work outside normal working hours or normal working days, he shall obtain prior approval from the City Project Engineer. All contractors and contract staff are to wear standard safety clothing (in accordance with the City of Stirling's Safety Policy). 1.3 Responsibility regarding Existing Services The Contractor shall be held responsible for any damage to existing services. All damage to such services shall be made good at the expense of the Contractor. The Contractor shall notify the Authority concerned immediately and damage is caused to services. 1.4 Protection of Property The Contractor shall be responsible for preserving all public and private property. He shall protect from disturbance or damage all land monuments and property marks until the City Project Engineer has witnessed or otherwise referenced their location.

1.5 Authority of the City Project Engineer The City Project Engineer shall decide all questions that may arise as to the quality and acceptability of materials furnished. Suspension of the work may be ordered by the City Project Engineer if deemed to be in the public interest. 1.6 Traffic Management and Barricades on work sight 1.7 Water The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs and other traffic control devices as directed by the City Project Engineer. He shall take all necessary precautions to protect the work, private property and to safeguard the public. Where work is in progress on or adjacent to the road pavement. The Contractor shall allow sufficient labour to direct and control traffic, including allowance for flagmen at each end of the works, to allow the proper completion of works and the safety of the traffic. Every endeavour must be made to allow reasonable access to properties during progress of the work. The Contractor shall provide and be solely responsible for the supply and use of traffic control in accordance with Australian Standard AS1742.3-2002, Manual of Uniform Traffic Control Devices, Part 3 The Contractor should submit a detailed Traffic Management Plan to the City for approval. Works should not proceed until the City has approved the plan. The Contractor shall make his own arrangements for the supply of water needed for the proper carrying out of the work, eg to obtain the compaction specified in Clause 2.3. Unauthorised use of property owners water supply will not be tolerated. 2. TECHNICAL SPECIFICATIONS 2.1 Scope of Work The Contractor is responsible for the supply, placing and finishing of concrete so as to form a cast in-situ path. Unless previously instructed, all boxing out, backfilling and reinstatement will be carried out by the Contractor to the satisfaction of the City's Project Engineer. The Contractor will take responsibility for damage caused by vandalism after final concrete finish is completed ie: graffiti etc. Back to top

2.2 Excavation when carried out by Contractor The excavation for paths shall be carried out to the levels, lines and grades as given for the site and all excavation shall be executed cleanly to produce a sound base, free of depressions or soft spots or any deleterious materials to give the minimum required dept of the path. The Contractor must repair damaged reticulation. When excavation is carried out through an existing bitumen crossover, the latter shall be neatly sawn to facilitate later bitumen reinstatement. 2.3 Compaction All excavation shall be thoroughly compacted to produce a Perth penetrometer reading of seven blows per 300mm. 2.4 Forming Forms shall be of such cross-section and strength and so secured as to resist the pressure of the concrete when placed, without springing or settlement. The method of connection between sections shall be such that the joints shall not move in any direction. The maximum deviation of the top surface of the form shall not exceed 4mm in 3 metres or the inside face not more than 4mm in 3 metres longitudinally. The form when set, will be uniformly supported for its entire length at the specified elevation. All forms shall be cleaned following use. 2.5 Concrete (a) Premixed concrete shall comply with Australian Standard 1379-1991. The Specification and Manufacture of Concrete, in all respects. (b) Concrete shall have a minimum compressive strength of 20 mpa at 28 days. (c) Maximum aggregate size shall be 20mm. (d) (e) Slump at the point of delivery shall be 75mm + 15mm. No admixtures shall be used in the concrete unless specifically approved by the City Project Engineer's representative. If required, high early strength additive shall be used to give rapid hardening as per AS 1478 and AS 1479, Chemical Admixtures for Concrete. Back to top

2.6 Placing and Finishing Concrete shall be thoroughly compacted against the faces of forms. The pavement shall be screeded by hand finishing methods. Final finishing shall not be commenced until bleed water has disappeared from the surface. The final finish shall be deep broom finish (approximately 2mm deep). Picture framing is to be applied to the satisfaction of the City Project Engineer. All work to be of high quality, uniform appearance and executed in a tradesman like manner. Any concrete slurry on Telecom boxes, etc, must be thoroughly cleaned off. 2.7 Protection of Works Along the length of work wooden stakes shall be placed at regular intervals by the Contractor and a top and bottom brightly coloured ribbon between. (a) (b) (c) Wet Weather - The contractor shall be responsible for wet weather damage. He shall always have available materials to protect the surface of new works (eg polythene sheeting). Vandalism - at the completion of concrete finishing and after erection of signs, barricades, ribbons, etc, the Contractor will place persons to guard the works against vandalism. Hot Weather - during hot weather when the air temperature exceeds 36 0 C precautions shall be taken to avoid premature stiffening of the fresh concrete mix and to reduce water absorption and evaporation losses. The subgrade shall be thoroughly moistened but not saturated immediately before concrete placement begins, to reduce water absorption. To reduce evaporation losses, the concrete shall be cured for at least three days after placement using a liquid membrane compound. Liquid membrane compounds shall comply with ASTM Standard Specification C309-74, "Liquid Membrane Forming Compounds for Curing Concrete". Compounds, which adversely affect the non-slip character of the concrete surface or decrease the quality of surface finish, shall not be used. The compound shall be applied to the concrete surface strictly in accordance with the manufacturer's instructions. 2.8 Joints 2.8.1 Transverse Contraction Joints Transverse contraction joints shall consist of grooves cut in the surface of the concrete prior to setting with an approved tool. They shall be a minimum depth of 10mm. Spacing of the joints shall not exceed two metres along the footpath and shall be placed at right angles to the centreline. Back to top

2.8.2 Transverse Expansion Joints Transverse expansion joints 12mm thick are to be constructed at 10 metre intervals or as shown on the drawings for the full depth of the path. They shall be placed at right angles to the centreline of the footpath. This requirement will be closely supervised. The expansion joint material shall be continuous from form to form and extend vertically the full depth of the slabs and shall be Meljoint or similar or a material approved by the City Project Engineer. The joint material shall at not point protrude above the surface of the path. 2.9 Stripping of Edge Forms Forms are not to be removed from the concrete within a time period of at least eight hours since placement of concrete. This time period may be reduced with the approval of the City Projects Engineer depending upon weather conditions. 2.10 Construction Criteria 2.10.1 Tolerances Works shall be undertaken to the following tolerances: a) Grade across path shall be 2% from property line. b) Path surface shall be true to line and not deviate more than 10mm under a three metre straight edge. c) Spacing of expansion joints shall be 10 metres + 100mm. d) Thickness of path to be 100mm; -Omm, +1 Omm. e) Width of path; -Omm, +20mm. f) Surface irregularities, including abutting to service authority manholes, etc, shall not exceed 3mm. 2.10.2 Test Specimen The City Project Engineer shall require evidence that the concrete supplied to the work meets the requirement of Clause 2.5. An independent NA.T A registered laboratory shall be employed by the City of Stirling to fabricate and test specimens and report results. The cost of such testing shall be the responsibility of the City of Stirling except in the event of failure when it will become the responsibility of the Contractor. Acceptance of concrete will be based on the provisions of AS 3600. Back to top

2.10.3 Thickness The City Project Engineer when in doubt as to the thickness of the completed footpath may require core tests for determining actual thickness and for outlining areas of deficient thickness. The cost of core testing shall be the Contractor's responsibility in the event of failure to comply with this Specification. All sections of footpath less than the nominated thickness shall be removed and replaced at the Contractor expense. Back to top

LIST OF APPENDICES

Appendix A PERMIT FOR EXCAVATION IN A ROAD RESERVE Contractor: Address: Contact Name: Location of Works: Purpose of Excavation: Inspection Fee (1.5%): Reinstatement Deposit (2.5% Total Contract): Street Sweeping @$300 or as Specified: Other (Specify): Bitumen Crossovers to be Replaced with Concrete: Telephone: Completion: REQUIREMENTS 1. The applicant shall make themselves aware of and comply with the City of Stirling Conditions for Approval for Contractors Working in Road Reserves and Parks Reserves standard procedure for reinstatement of reserves. 2. The Permit or Excavation shall be submitted at least fourteen (14) days in advance of commencement of works. 3. Reinstatement charges at current City of Stirling rates shall apply (Contractors are requested to prepay the City prior to commencement of works). Any variation to the estimated cost shall be charged or credited to the Contractor, whichever is applicable. I HAVE READ THE ABOVE REQUIREMENT AND ACCEPT FULL RESPONSIBILITY AND LIABILITY IN RESPECT THERETO. Signature of Applicant Date Referring Officer