Soft Ground Tunneling on a Mexico City Wastewater Project



Similar documents
Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

TBM CROSSING OF STATIONS

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

GOWANUS EXPRESSWAY TUNNEL PRIMER

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Sany Tunnel Boring Machines

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

by Morgan Anamoah & Martin Feeney

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Moving Small Mountains Vesuvius Dam Rehab

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

EXCAVATOR SAFETY TRAINING

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

METHOD OF STATEMENT FOR STATIC LOADING TEST

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

1300 MAXTRAK SPECIFICATION

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

High Capacity Helical Piles Limited Access Projects

SECTION 1 GENERAL REQUIREMENTS

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

TBMs for Norwegian Hydropower projects. Sindre Log The Robbins Company

SECTION ABANDONMENT OF SEWER MAINS

Raise boring equipment

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Flowtite Jacking Pipe

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Söderströmtunnel: immersion in downtown Stockholm, Sweden

Installation of Large Diameter Buried Pipes

Design and Construction of Auger Cast Piles

SECTION PRECAST CONCRETE STRUCTURES

SECTION SHEETING, SHORING AND BRACING

Section Installation of pipe and casing for sanitary sewer by methods of augering.

The Performance Prediction of a TBM in Tuzla - Dragos Sewerage Tunnel

Hydraulic Excavators

Cardok Sàrl CP37 CH-1295 Tannay Switzerland Phone:

Char-Lynn Hydraulic Motor. Repair Information Series. October, 1997

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

System. Stability. Security. Integrity. 150 Helical Anchor

Milan M5 metro extension the construction of Lotto station

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

Tunnelling & Underground. Specialists

Town House Center Highway North Huntingdon, PA 15642

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Maxi-Stamper. 200 to 1,000 Tons STAMPING OUT DOWNTIME

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

Safe & Sound Bridge Terminology

Section 2100-Trenching and Tunneling

Kuala Lumpur conquers the underground. Using pioneering tunnelling technology made in Germany.

Beacon Hill Sewer District Standard Specifications

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

PVE Piling and Drilling Rigs Powerful, Versatile and Efficient. PVE Piling and Drilling Rigs B.V. Worldwide supply of specialized foundation machines

Pipe Cutting and Beveling Clamshells

Unit 24: Applications of Pneumatics and Hydraulics

BUTE Department of Construction Management and Technology

Unit 24: Applications of Pneumatics and Hydraulics

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

Wastewater Capital Projects Management Standard Construction Specification

Belt Tensioning Methods for Small Package Conveyors What s the best solution?

Meeting the Challenge of Pipeline Emergency Repair

High Strain Dynamic Load Testing of Drilled Shafts

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Volkswagen Jetta, Golf, GTI 1999, Liter VR6 2V Engine Mechanical, Engine Code(s): AFP 17 Engine-Lubrication (Page GR-17)

Specification for tunnelling third edition. The British Tunnelling Society and The Institution of Civil Engineers

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Contractor of the Year

Indianapolis Midfield Terminal Thermal Utility Construction

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

GLOSSARY OF TERMINOLOGY

DUGARD. Machine Tools Since Dugard 700L Series Heavy Duty CNC Lathes.

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Guide to working on Public Sewers

Construction sites are dewatered for the following purposes:

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

SECTION STORM DRAIN SYSTEM

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

The International Workshop on Micropiles, 2007

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process

PART 2 FORKLIFT HYDRAULIC SYSTEM

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

Risk Management Applied to Mechanized Tunnelling in Urban Area Piergiorgio GRASSO - GEODATA, Italy

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

Transcription:

Soft Ground Tunneling on a Mexico City Wastewater Project Doug Harding The Robbins Company, Solon, Ohio Desiree Willis The Robbins Company, Kent, Washington ABSTRACT: Ground settlement in Mexico City has caused the existing gravity feed wastewater system, built in 1975, to lose its slope. In addition to infiltration and corrosion, the system is severely undersized. To remedy the problems, the Mexico National Water Commission released a contract for a 7.8m ID 62 km long pipeline known as the Emisor Oriente Wastewater Tunnel Project. To meet the demanding schedule, six Earth Pressure Balance (EPB) TBMs will be required. This paper will address the overall importance of the project to Mexico City as well as the unique design of the EPB TBMs needed for excavation of varying geology in pressures up to 10 bar. The current status of the project and any problems encountered to date will also be covered. PROJECT BACKGROUND Mexico City, a metropolis of over 22 million people, is sinking at the rate of 10 cm per year. The world s second largest city was founded by the Aztecs in the Valley of Mexico, on what was once an island in the middle of Lake Texcoco. Spanish conquistadors later drained the lake bed using a system of canals, but the soft lake clays remained underneath the city s infrastructure. A combination of booming population and compression on the city s main sewer lines has necessitated the construction of one of Mexico s largest infrastructure projects a 62 km long pipeline known as the Emisor Oriente, or Eastern Wastewater, tunnel. Mexico City s wastewater system is almost exclusively served by the Emisor Central, a 68 km long line built in 1975. Over the past three and a half decades, ground settlement has caused a decrease in slope in the gravity sewer line and a reduction in capacity. Severe corrosion and nearly continuous groundwater infiltration have also made it impossible for the Emisor Central to be inspected and maintained between 1995 and 2008. Once inspection was made possible, it was found that the overall system capacity had been reduced by 40% since 1975 from 280 m 3 /sec to just 165 m 3 /sec in 2008. Over the same time period the city s population more than doubled from 10 million to over 20 million inhabitants, increasing demand on the system. PROJECT DESCRIPTION AND LOCATION Mexico s National Water Commission (CONAGUA) recommended immediate construction of a new line to help supplement the struggling system. The Emisor Oriente, or Eastern Wastewater Tunnel, will increase the city s current sewer capacity by 150 m 3 / sec once complete in September 2012. The line will carry wastewater from Mexico City to several water treatment plants currently under construction in the state of Hidalgo (see Figure 1). Figure 1. Emisor Oriente pipeline layout 158

Figure 2. Detailed location of Emisor Oriente Tunnel. Main shafts shown as stars. Figure 3. Geological profile of the Emisor Oriente Tunnel The construction of the line was divided into six lots lots 1, 2, and 6 under Mexican contractor Ingenieros Civiles Asociados (ICA) S.A. de C.V, and lots 3, 4, and 5 under Carso Infraestructura y Construcción, S.A. de C.V. All six lots will be bored with EPB machines Robbins was awarded lots 3,4 and 5 which will be bored using three 8.93m diameter EPB TBMs (see Figure 2). GEOLOGICAL CONDITIONS The Robbins machines are set to bore in alternating sections of compacted sand, gravel and clay with basalt rock, and are designed accordingly. The geology of the Valley of Mexico is also unique in that large boulders up to 600 mm in diameter are predicted throughout the drives. The particular set of geologic characteristics is found only in Mexico and in certain areas of Japan. The varied conditions consist of sections of lake clays, alluvium, and lava with tuff and andesite (see Figures 3 4). PROJECT APPROACH The three Earth Pressure Balance Machines supplied by Robbins will be 8.93 m in diameter. All of the machines were optimally designed for mixed ground conditions (see Figure 5 and Table 1). Cutterhead Design The machines are utilizing mixed ground, back-loading cutterheads for the variable geology. The design allows for a change in cutting tools between sections of soft ground and rock. 159

The seven-piece spoke-type cutterheads will utilize six outer segments plus a hexagonal-shaped center section to maximize the opening ratio of the face. The machines were designed with the largest possible opening ratios to ensure a smooth flow of muck into the cutterhead chamber. Crews will switch out between carbide knifeedge bits and 17-inch, carbide disc cutters depending on the ground conditions. A number of small shafts, spaced every 3 km between the larger launch shafts, will be used to perform cutter inspection and changes. Specialized wear detection bits will lose pressure at specified wear points to notify crews a cutting tool change is needed. The knife edge bits are arranged at several different heights to allow for effective excavation at various levels of wear. The design also allows for bearing and seal removal from either the front or back of the cutterhead. Twenty-five injection ports spaced around the periphery of the machine will be used for injection of various additives depending on ground conditions, and for probe drilling (see Figure 6). Figure 4. Boulders taken from similar ground at the Sapporo Metro Project, Japan Screw Conveyor and Muck Removal Each machine will be fitted with a ribbon-type screw conveyor 900 mm in diameter. The screw conveyors allow boulders up to two-thirds the screw diameter (up to 600 mm) to travel up the shaft, where they are disposed of through a boulder collecting gate. Each of the three machines may encounter pressures of up to 10 bar, necessitating a two-screw setup with a ribbon screw and shaft-type screw in order to smoothly regulate pressure (see Figure 7). Muck will be deposited from the screw to a rubber belt conveyor mounted on the trailing gear, which transfers to a side-mounted continuous conveyor. The continuous conveyor carries the muck to a 150 m long vertical belt conveyor located at the Table 1. Specifications for Emisor Oriente EPB TBMs 8.93 m Diameter EPB TBMs Excavation Diameter Cutterhead for Soil Cutterhead for Rock Main Cutting Tools Cutterhead Drive Cutterhead Power Machine Thrust Stroke Max Torque Screw Conveyor #1 Screw Conveyor #2 Articulation 8,910 mm 8,930 mm Special knife-edge bit (soil) Single and Double-row Disc Cutters (rock) Electric, variable speed 1,900 kw 84,000 kn 2,300 mm 17,900 knm Ribbon type, 900 mm diameter Shaft type, 900 mm diameter Active Segments Reinforced concrete, 400 mm thick Back-filling System Two-Liquid Type Figure 5. EPB TBM general assembly 160

Figure 6. Cutterhead design with interchangeable cutting tools for soil and hard rock Figure 7. Example ribbon-type screw conveyor launch shaft. Once at the surface, a radial stacker will deposit muck in a kidney-shaped pile for temporary storage. This system will be used on all three lots. The three continuous conveyor systems, also provided by The Robbins Company, consist of 762 mm wide fabric belt at a 3,200 m length and 900 MTPH capacity. Approximately 22% of the conveyor systems will be traveling through curves, with a minimum 700 m curve radius. To better handle curves, the systems will utilize patented selfadjusting curve idlers. The idlers help by pivoting to accommodate changing load tensions around curves. The pivoting action is also favorable because it does not unnecessarily alter the carrying capacity of the conveyor or the belt tension. Articulation For accurate tunneling through curves, each machine will feature active articulation. Active articulation engages articulation cylinders between the front and Figure 8. Partial cutterhead assembly rear shields to steer the machine independently of the thrust cylinders. The process allows the thrust cylinders to react evenly against all sides of the segment ring during a TBM stroke in a curve. Typical configurations, which use flat joints to articulate the shield, are capable of making 2 to 3 degree curve adjustments over the length of the segment or stroke. Another reason active articulation was chose for this project was the risk of segment deformation, or racking. A common cause of project delays, deformation toccurs most commonly when the passive articulation system is used in curves. Passive articulation does not utilize articulation cylinders independent of the machine s thrust cylinders, so the TBM reacts against sides of the segments unevenly in curves. Segments and Back-filling System The machines will line the tunnels with reinforced concrete segments 400 mm thick, in a 7+1 161

Figure 9. Forward shield assembly arrangement. Each segment is 1,500 mm in length and weighs approximately 60 kn. The finished tunnel diameter will be 7,800 mm. To back-fill any voids behind the segments and minimize ground settlement, the machines are utilizing two-liquid back-filling. Two-component backfill, made up of cement plus an accelerant, is used to harden ground rapidly. Grout is injected and the two separate components are mixed where the completed rings exit the tail shield. The mixture fills the annulus between the completed segment rings and surrounding soil. Volume and pressure of the backfill grout injection are constantly monitored and controlled to minimize surface subsidence, a concern in tunnels with low cover and in urban areas. After each injection, water is forced through the pipes to prevent clogging. PROJECT SPECIFICATIONS Current Status of Machines The machines were designed by Robbins with manufacturing done in various Robbins manufacturing plants worldwide. Various components were subassembled and shipped for full workshop assembly in a Robbins workshop located in Corpus Christi, Texas, USA. The Corpus Christi workshop in Texas was selected due to its close proximity to the jobsite. Large assemblies will be loaded onto a barge and shipped directly to a Mexican port for ease of transportation to the jobsite. As of November 2009, partial cutterhead assembly for the Lot 4 machine had been completed, as well as assembly of the Lot 3 forward shield and back-up system (see Figures 8 10). Shaft Construction The three 16 m diameter launch shafts are 80 m, 100 m, and 150 m deep. Machine launch and breakthrough will be as follows: Figure 10. Back-up system assembly Figure 11. Slurry wall construction, Shaft 20, November 2009 Lot 3 EPB TBM starting from shaft 13 and boring upwards to shaft 10. Lot 4 EPB TBM starting from shaft 17 and boring upwards to shaft 13. Lot 5 EPB TBM starting from shaft 20 and boring upwards to shaft 17. Shaft construction is currently underway. At the surface, shaft construction begins by building slurry walls. Several of the slurry walls for the excavation support, including shaft 20, are being excavated using a hydromill (see Figures 11 12). Once the slurry walls are constructed, most of the shafts are being excavated conventionally using a backhoe. Stable ground below the slurry walls is supported using wire mesh and shotcrete. Material is removed from the bottom of a shaft using a crawler crane (see Figure 13). To excavate each shaft dewatering is also needed. Outside each shaft are four installed pumping stations that operate during the course of excavation. Volumes of water being pumped are as follows: Shaft 13 5 liters per second Shaft 17 2 to 3 liters per second Shaft 20 2 to 3 liters per second 162

Figure 13. Shaft 13, November 2009 Figure 12. Hydro excavator machine, shaft 20 CURRENT SCHEDULE After assembly is completed, the machines will be shipped to the jobsites in Spring 2010 where they will be lowered into separate deep shafts using mobile boom cranes. Each machine will start from a different 16 m diameter shaft at either 80 m, 100 m, or 150 m deep. Current schedule milestones are documented in Table 2. Partially assembled machine components weighing as much as 120 metric tons will be lowered down the shafts to reduce assembly time underground. The 14.5 m long ribbon screw must be altered since its length exceeds available space in the shaft. The screw will be lowered in two halves and welded together through an inspection hatch on the casing. Once the ribbon screw has been installed the machine will be pushed a minimum of 30 m into a pre-excavated starting chamber. This arrangement will make space for installation of the machine s Table 2. Current scheduling milestones for Emisor Oriente project Lot 3 Lot 4 Lot 5 Forward shield assembly Nov-09 Dec-09 Jan-10 Rear shield assembly Dec-09 Jan-10 Feb-10 Main drive assembly Dec-09 Dec-09 Jan-10 Back-up system assembly Dec-09 Dec-09 Jan-10 Conveyor system Dec-09 Jan-10 Feb-10 Cutterhead assembly Jan-10 Dec-09 Feb-10 Final testing Jan-10 Feb-10 Mar-10 Delivery to jobsite Feb-10 Mar-10 Mar-10 rear shield, bridge section, and the shaft-type screw conveyor. A shortened back-up system, including electrical cabinets, transformers, and the hydraulic system will also be assembled. Upon completion the TBM will bore forward approximately 50 m with a temporary mucking system until the remaining 65 m of back-up equipment can be installed. REFERENCES Willis, D. (2009). Robbins Trio dig deep in Mexico. World Tunnelling, April, 12. 163