Adverse Physical Conditions & The Experienced Contractor



Similar documents
Profile. Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different. Dredging and Marine Contractors

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction

REMODELING CONTRACT., remodeling contractor, whose address is, to on the property located at.

CONSTRUCTION SOLUTIONS

CORPORATE INSOLVENCY & DEBT RESTRUCTURING

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

A Contract for Just Digging a Hole

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION

Measured development Construction and Engineering Training Supplement Guide

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No M (Supersedes Report No.

UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE

Checklist 26: How Owners Can Avoid Litigation on Construction Projects

The FIDIC Suite of Contracts

QBE Professional Indemnity Proposal Form Single Project Professional Indemnity

A/CN.9/WG.III/XXXII/CRP.3

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts

P&SM: Writing Contracts

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee

CONTRACT MANAGEMENT POLICY

Risks in International Consultancy Appointments: The FIDIC White Book

A Guide to the Design Build Process

London STOCK EXCHANGE

Dispute Resolution. White Paper. This document on Dispute Resolution outlines the four main approaches to resolving contractual disputes.

Natural Gas Supply Agreement ( Agreement )

Guidance Notes for the NEC Engineering and Construction Contract

NATIONAL COMPETENCY STANDARDS FOR QUANTITY SURVEYORS - CONSTRUCTION ECONOMISTS

Part E: Contract management

NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard

Appendix D. Minimum Requirements For Developmental Resources. For

Precision Hydrographic Services. Company Profile. Company Profile. We do it once, we do it right.

TERMS AND CONDITIONS FOR BUSINESS PARTNERS:

Contents. 1. PROFILE p2. 2. SERVICES 2.1 Offshore Support Services p 4 Offshore support p 6 ROV operations p 8

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E

Appendix 18 NEC3 Options

I would like to thank the Honourable Chief Justice Ma for. his insightful remarks on the important role of lawyers in

CHARTERER S LEGAL LIABILITY

Introduction to the ISO/IEC Series

ReDBox SUPPORT AGREEMENT

ENERGY PERFORMANCE CONTRACT

Fourth Generation Modular Construction

Proposal Form. Construction Industry Consultants Professional Indemnity

Rating Consultancy RICS/IRRV/RSA Code of Practice. 3rd edition

Engineering Council of South Africa

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

ICC UNIFORM RULES FOR CONTRACT BONDS

This document must be read in conjunction with Beacon Consulting s Fee Proposal. Together they form the Rules and Conditions of Service Delivery.

Family law a guide for legal consumers

How to Become a Clinical Psychologist

Customer Responsiveness Strategy

IBA Business and Human Rights Guidance for Bar Associations. Adopted by the IBA Council on 8 October 2015

Securing Information in an Outsourcing Environment (Guidance for Critical Infrastructure Providers) Executive Overview Supplement.

Issued by the Association FME-CWM, P.O. Box 190, 2700 AD ZOETERMEER

Financial Services Guidance Note Outsourcing

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.

Construction and Demolition Waste

HP Laptop & Apple ipads

QBE Professional Indemnity Proposal Form Construction Consultants

Taking Action. Dispute resolution, legal action and claims for negligence

Project manager services

APPROVAL OF COMPUTERIZED MAINTENANCE MANAGEMENT SYSTEM USED ON BOARD SHIPS

(1) risks should be allocated to the party that is in the position to control them and

Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 ARRANGEMENT OF SECTIONS. 6. Right to refer payment disputes to adjudication.

CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components

General Terms and Conditions of Sale and Delivery of Federatie Aandrijven en Automatiseren (Trading Companies)

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

Application of Accounting Standards to Financial Year Accounts and Consolidated Accounts of Disclosing Entities other than Companies

How to Select an Environmental Consultant

NEC3: Early Warning and Compensation Events

Australian Standard. General conditions of contract for design and construct. AS (Incorporating Amendment No. 1)

An Introduction to Risk Management. For Event Holders in Western Australia. May 2014

Capital Works Management Framework

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

WAVELENGTH PORTS AND TERMINALS CONSORTIUM SECTION 1 - LIABILITY WORDING

Description of Selected Services under the UN CPC system in which the EC made Market Access Commitments in the EPA

Single Project Professional Indemnity Insurance Proposal Form. Note: This is a proposal form for a claims made policy

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP

Defects liability period an introduction

How To Understand A Rent Review Clause

ORDERED, ADJUDGED AND DECREED,

Private Health Insurance Code of Conduct

Sample Arbitration Clauses with Comments

CIB Regulatory Change Management:

BILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL. Tel: METHOD STATEMENT

Alternative Dispute Resolution (ADR) Procedures

The New Standard Construction Contracts: NZS3910, 3916 and 3917

Appendix 25. Content of a Competent Person s Report for Petroleum Reserves and Resources

FIDIC S GREEN BOOK CLAUSES 6, 13 & 14

Contents. Finding A Builder...9. Subcontractors...9 Quotes And Estimates Owner Builders...11 Once Decided On A Builder...11

SECTION 106 CLAWBACK MAJOR 1. means the actual additional pre-tax profit of the Development Proposal to be calculated in accordance with paragraph B10

Transcription:

Adverse Physical Conditions & The Experienced Contractor David Kinlan Delft Academic Press

adverse physical conditions David Kinlan First edition 2014 Published by Delft Academic Press Leeghwaterstraat 42, 2628 CA Delft, The Netherlands tel. +31 15 27 82124, e-mail: hlf@vssd.nl Publishers website: http://www.vssd.nl/hlf About this book: http://www.vssd.nl/hlf/b032.htm All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. ISBN: 97890-6562-327-0 Key words: adverse physical conditions, claims, civil engineering, contracts, dredging, FIDIC, tenders, unforeseen conditions

Contents About the Author ix Foreword xi Acknowledgements xiii CHAPTER 1 Introduction 1 Differing Site or Latent Conditions 1 Get out of Jail Free Card 1 Unforeseeability or ambush 2 The Abrahamson principles 3 Risk allocation in Australia 4 Risk allocation in the US 5 The UK situation: NEC 6 International Infrastructure Contracts 7 CHAPTER 2 Site Investigation & Inspection 10 Finding hidden conditions 10 Site Investigation and decisions to be made 11 Geophysical surveys 12 FIDIC Site Data to be made available 13 A note of caution 15 Site Data provided by Employer 16 Breach of warranty 17 Recommendations 18 Type, Quantity and Location of Materials 20 Geological History of a Project Site 20 Drilling, Blasting, Boreholes 20 Using A Competent Soil Investigation Company is a Must 21 Good Site Investigations Cost Money 21 Basic Parameters required to be investigated 22 v

adverse physical conditions Main Objectives of a Subsurface Investigation 22 Status of information provided 24 Factual vs Interpreted Data 25 The Spacing of Boreholes is Critical 25 Disclosure of Limitations 27 FIDIC Principle of Fact vs Interpretation 28 Standard Classification of Soil and Rock 28 Site Information as defined in Contracts 29 Preparing a Geotechnical Model 30 Software for Analyzing Subsurface Data 30 Identifying Potential Issues 32 Trial Excavation or Early Works Contract 32 Additional Investigations Post Contract 34 Future developments 35 OpenEarth Data Source 35 Disclaimers 36 Australian Case Histories 36 Misleading & Deceptive Conduct in Australian law 38 CHAPTER 3 What is Reasonably Foreseeable by an Experienced Contractor 40 The Notion of Foreseeability in a Legal Context 40 Legal Cases dealing with Foreseeability 41 NEC 3 in the United Kingdom 46 The NEC 3 Contract, the identification of risk in the form of a Risk Register 47 Practical Examples of Impacts of Varying Physical Conditions 48 CHAPTER 4 Types of Adverse Physical Conditions and Contract Clauses 54 Types of Adverse Physical Conditions 54 Adverse Physical Conditions Clauses in Contracts 56 Risk Transfer in FIDIC Contracts 57 FIDIC Silver Book 58 FIDIC Dredging Form of Contract 2006 59 USACE Federal Acquisition Regulations 60 Type 1 60 Type II 62 CHAPTER 5 Notification of Claims Time Bars and What to do 65 vi

Notices under the Contract 65 BMD Case History 66 What should a Claim Notice Contain 66 FIDIC 1999, Clause 20.1: Claim Notification 67 When to notify the Employer 68 NEC 3 Clause 16, Binding Obligation 70 Impact of the Time-bar and Legal Issues Arising 70 Submit Short, Simple Claim Notices 72 CHAPTER 6 Essential Elements of an Adverse Physical Conditions Claim 74 Contemporary Records 74 Detailed claim submission 78 CHAPTER 7 Presentation of Claims 79 Introduction 79 Section 1- Executive Summary 80 Section 2 -Status of the Tender Soils Information 81 Section 3 - Statement of Contractor s Claim 82 Section 4 -Statement of Contractor s Claim 86 Section 5 - Contract versus Actual Soil Conditions 87 A. Contract Soil Conditions (refer to Appendix 1) 87 B. Post Contract Soil Conditions (refer to Appendix 2) 87 Section 6 -Trenching Programme Analysis 89 Section 7 - Analysis Pick Points 90 Section 8 -Wear & Tear on Pipelines 92 Section 9 - Additional Fuel Consumption 93 Section 10 - Site Investigation Costs 94 Section 11 Summary of Costs 94 CHAPTER 8 Establishing the Costs 95 Introduction 95 Establishing the Costs 97 CHAPTER 9 How to Avoid or Minimise Claims 100 Introduction 100 The Use and application of Reference Conditions 101 What to include in Geotechnical Reference Conditions 102 The future for Reference Conditions 104 vii

adverse physical conditions The use of Dispute Review Board or Dispute Adjudication Boards 105 Real Time Dispute Resolution 108 Risk Register 109 Percolation process 109 Expert Appraisal or Expert Determination 110 Dispute Resolution Advisor 110 Concluding Remarks 111 CHAPTER 10 Summary 112 APPENDIX Reference Material and Information Sources 116 viii

About the Author David Kinlan is a freelance Chartered Quantity Surveyor and Queensland Registered Adjudicator with 25 years of professional experience in the marine infrastructure industry. He was for many years employed by Ballast Nedam Dredging as a contracts manager and has been involved in many of the major and iconic dredging projects of the past twenty five years. In 1994 David Kinlan participated in the tender negotiations and eventual contract award of the Oresund Fixed Link Project. This project was groundbreaking for the dredging industry not just in that it had strict environmental monitoring of turbidity in the pristine waters of the Oresund Sound but the manner in which the project dealt with adverse physical conditions and contract disputes. Whilst still active with many global marine infrastructure tenders and contracts David has increasingly has become involved in tenders and contracts supporting the recent expansion of the resource sector in Queensland and Western Australia both for Clients and Contractors. David is based in Brisbane and offers all-round, proactive support for all stages of a project be it tender, contract, claim and project management services. David has published a number of articles in the International Association of Dredging Contractor s publication - Terra et Aqua dealing with vesting of plant, escalation and adverse physical conditions. The subject of adverse physical conditions continues to occupy the attention of the many marine infrastructure practitioners around the world and the lack of concise and precise knowledge on the subject spured David to further develop his original Terra et Aqua article with more in-depth study and to share his experience and insights on the subject by means of this publication. ix

Foreword From the perspective of the major international dredging contractors, the dire consequences of encountering adverse physical conditions during a dredging project have long been obvious. Also obvious has been the lack of literature examining the unforeseeability of these conditions from an engineering and contractual perspective. In this regard the present book by David Kinlan is warmly welcomed. When port authorities or other clients issue a request for tender for a major maritime infrastructure development project, it is done in good faith based on the available knowledge. The tenders that contractors offer are equally done in good faith based on their assessments of site conditions as experienced contractors. In both cases, these actions are done to the best of each party s knowledge and skills. But clearly, since dredging occurs below the water s surface, not everything is knowable or foreseeable before a project commences. A few things are knowable however: First, the major dredging contractors have a broad range of expertise in-house. They have experienced engineers and scientists and invest extensively in the latest research and development to ensure that they can offer the most cost-efficient, accurately implemented solutions. Second, all parties recognise that detailed and accurate geotechnical information is essential. Consequently, thorough site investigations are the backbone of maritime projects. Experienced clients realise that spending time, money and energy to discover the specific characteristics of the area to be dredged is invaluable. And yet: Not all physical conditions of the site will be discovered until the operations are actually underway. And once they are encountered, these adverse physical conditions can be the source of costly conflicts. Even though, with hindsight, most are found to be unforeseeable and unavoidable. How can we best deal with these unforeseeable conditions? How can contractors and clients avoid lawyers, claims and recourse to the courts to solve disputes? All these subjects are touched upon in David Kinlan s book. David also takes a critical look at how to escape the worst pitfalls of site investigations and when an adverse physical condition is discovered how to make the best of a bad situation. This best means: using early contractor involvement and the insights of experienced contractors at the site investigation stage; trying xi

adverse physical conditions to avoid the risks of unforeseen conditions which lead to claims by conducting sufficient site investigations; implementing a risk register and using best practice contract clauses that clearly address adverse conditions. In these ways, disputes can be nipped in the bud before cooperation turns into disagreement and before partners become adversaries. David offers numerous insights, based on his own hands-on experiences with major dredging contracts, his examination of the FIDIC contracts and PIANC workgroup studies. All in all, Adverse Physical Conditions & The Experienced Contractor provides a much-needed reference work for those in the dredging industry both contractors and clients alike who must cope with the reality of adverse physical conditions. Peter de Ridder President International Association of Dredging Companies xii

Acknowledgements This publication was inspired by the tales of my father Frank Kinlan, a diesel mechanic who together with the crew of scousers worked on the cutter suction dredger Port Sunlight and who valiantly battled to dredge caprock under difficult conditions in Manama Harbour, Bahrain in 1975 (see photo). I would like to acknowledge the following people for their assistance : Tim Maddock for reviewing the draft and Jim Anderson for providing many valid and insightful comments and reminding me of the developments of the NEC 3 Contract in the United Kingdom. Peter de Ridder for writing the Foreword to this book. Marsha Cohen who has guided me through a number of Terra et Aqua articles which ultimately led me to take on this publication. xiii

adverse physical conditions Van Oord NV for providing me with a large number of photos for illustration in this book. The Delft Academic Press who agreed to be my publisher and bring it to a wider readership. I would like to thank François Baillon from the Fédération Internationale des Ingénieurs-Conseils (FIDIC) for allowing me to reproduce sections of the FIDIC website as well as quote from the Rainbow Suite of Contracts. Lastly I would like to thank my wife Inge for putting up with the many hours I locked myself away in my office pouring over the many drafts it took before I arrived at something under which I was willing to put my name. xiv

CHAPTER 1 Introduction This book aims to assist those practitioners who have to formulate, manage or otherwise wish to avoid claims for adverse physical conditions on marine infrastructure projects. It is not meant as a definitive legal review of the status of adverse physical conditions as they may be dealt with under a particular infrastructure contract but is meant more as a general overview by bringing together the essential elements and development both technically and contractually that have led to the adverse physical conditions provisions we see in use in contracts today. Differing Site or Latent Conditions Adverse physical conditions, in the USA referred to as differing site conditions or in Australia also referred to as latent conditions, can come in many forms. These may include sub-surface and geotechnical conditions, environmental and hydrological conditions such as the influence of wind, wave and tide to artificial obstructions such as debris, munitions, wrecks and even polluted material. There is no definitive list as to what constitutes an adverse physical condition. In recent years however standard contracts such as the FIDIC Rainbow Contracts have made inroads into defining what is unforeseeable and defining what is an adverse physical condition. The allocation of the risk for adverse physical conditions has a long pedigree going back many years. It was originally founded in the major railway expansions both in the United Kingdom and around the world in the 19th Century when although contracts were undertaken little or no detailed geotechnical investigations were conducted. Thankfully in the modern era that situation has changed. Nowadays any project instigator is well advised to invest in a comprehensive geotechnical survey to adequately assess the project location s sub-surface conditions. Get out of Jail Free Card The concept of how adverse physical conditions are dealt with between Employer and Contractor verges on the holy grail of marine infrastructure. It represents 1

adverse physical conditions CHAPTER 2 Site Investigation & Inspection Site investigation and inspection is an essential step in all land and marine construction projects. It consists of planning, deploying and reviewing all the resultant site specific information which is required to design, plan and realize a construction project. In general, it encompasses meteorological, oceanic, hydrographical, sea bed and sub-surface data. The Contractor is generally under an obligation to have inspected the Site to evaluate the influence the local conditions will have on the work to be carried out before tender submission, although this should always subject to what is practical. This may be specifically required under a provision of the contract or may be an implied obligation given that the Contractor will need to assess for himself the conditions at the Site and any constraints which may need to be considered. Finding hidden conditions Usually the contract documents will require tenderers to make a site inspection and investigate the site conditions. Even so, this does not require a contractor to find all hidden conditions at the site. Rather, the contractor is under a duty to discover only those conditions which would be ascertainable by a reasonable investigation. What is reasonable will depend upon the circumstances, and if a physical condition occurs which could have been observed by a realistic and visual site site inspection, in all likelihood the contractor will be denied relief under the clause. Whilst site inspection and investigation is easily undertaken for land based projects how is this feasibly carried out when the Site consists of an expanse of water and a sub-surface many metres below it? Generally speaking, a Contractor s only chance to do his own inspection and investigation will be on the site visit when all he can do is a visual inspection of the surrounding geology and geomorphologic aspects surrounding the site and perform a desk study of all publically available information and that information provided by the Employer as part of the tender documents. 10

adverse physical conditions Is a claim excluded only if an experienced contractor could have foreseen that the conditions or obstructions must occur, or is it sufficient that there was a possibility, however remote, that the conditions might occur?... It is suggested that a claim is barred only if an experienced contractor could have foreseen a substantial risk. (Abrahamson s Engineering Law and the I.C.E. Contracts, 4th Edition) An adverse physical condition or obstruction can be said to have been foreseen only if an experienced contractor considers there could be a substantial risk of such condition or obstruction arising. Contractors are thus put on notice that based on the information available at time of tender, a reasonable thorough investigation could have brought to light the particular adverse physical condition which is causing the delay. Whilst the contract clauses remained largely unchanged for decades a radical overhaul finally occurred with the issue of the Rainbow suite of FIDIC Contracts in 1999. The FIDIC Contracts Committee sensed the need to guide practitioners, Engineers and arbitrators as to some of the meanings in clause 12 and definitions were provided in the FIDIC Contracts. Site Inspection of marine projects will generally be limited to examination of shoreline outcrops which may or may not be representative of the actual sub-surface conditions. 44