A Guide to the Design Build Process

Size: px
Start display at page:

Download "A Guide to the Design Build Process"

Transcription

1 A Guide to the Design Build Process Essential reading for anyone considering or undertaking building work We are an affiliation of Chartered Architects and Chartered Building Surveyors who together provide an integrated seamless Professional Service for anyone considering residential building work

2

3 THE DESIGN BUILD PROCESS There are a number of advantages in employing an experienced Architect or Building Surveyor to assist in your project. Besides the obvious design expertise and knowledge of the planning and regulatory systems, Architects and Building Surveyors will be able to select suitable and recommended contractors that you might like to consider for the build. To a certain extent contractors rely on the Architect or Building surveyor to refer future work for them and so have an incentive to do a good job. Secondly, a contractor may well price an estimate for work considerably more competitively if there are a set of well thought out, accurate and detailed drawings to use with less need to add on extra amounts for areas where assumptions are required. Money invested at the design stage may well save a client much greater amounts later on as competing estimates often vary considerably. In our experience the process of working with an Architect or Building Surveyor when undergoing any kind of building work can best be described as a series of stages. You may want involvement with all, or just some of these. In most cases they are sequential and we would usually advise completion of one stage before moving to the next. This is a useful way of controlling costs. The different stages are covered in brief on the next few pages and are headed as follows: Stage 1 - Feasibility Study Stage 2 - Measured Building / Topographical Survey Stage 3 - Formal Planning Application and Listed Building Application (where necessary) Stage 4 - Building Regulations Application Stage 5 - Selection of Building Contractor, preparing Construction Information /Tender Procedure Stage 6 - Contract Administration and Cost Control Services Stage 7 - Post Build Services

4 Stage 1 - The Feasibility Study What are my requirements, what do I want to build? What are the options and possibilities? How much will it cost? Will I need Planning Permission or any other consents? What will the planners allow me to do? What effect will the proposals have on the value of my property? The feasibility study is an informal meeting and sketch based process where we work with you to answer the above questions quickly and efficiently without incurring any significant costs. What does this usually involve? Meetings and a site visit with you to discuss your requirements and explore possibilities. Help you put together a wish list or brief. You may already have a detailed brief to take forward, or you may just have an idea of what you would like and an open mind to alternatives that we suggest. Preparation of sketch alternatives, usually hand drawn at this stage to keep costs down. Informal discussions with the relevant Planning Authority to assess whether Planning or other permissions (Listed Building Consent, for example) would be required and their likely reaction to a formal application. Example of a sketch impression (sometimes then used for informal discussion with the planners if necessary)

5 Depending on the nature of the work and degree of involvement you require a more accurate estimation of all costs can be assessed at this stage. Example of a sketch proposal scheme

6 We can also build virtual and physical models to help convey ideas and aid communication to planners and others of the potential possibilities. Interior of a physical model Example of a virtual model

7 Stage 2 - Measured Building / Topographical Survey A measured building survey is an accurate and detailed record of the current building, using sophisticated electronic equipment for speed, and carried out by one of our in-house surveyors. A topographical plan is a similar process used to pick up surrounding ground levels and features. The feasibility stage may well not need an accurate and detailed survey, it is a sketch based and discussion process and you may well have some old plans or rough estate agents details which can work just as well. However, assuming that the feasibility stage has produced a plan that you would like to proceed with, accurate survey data will usually be invaluable when proceeding to the next stages where detailed drawings are produced. You will get a set of floor plans, elevations and section drawings of the current building (if there is one) and a topographical landscape plan (if required) picking up ground levels and surrounding features (trees, paths etc.) Stage 3 - Formal Planning Application and Listed Building Application (where necessary) Assuming the feasibility stage has provided the right answers the next stage is a detailed planning application. Planning permission is the Council s way of saying, yes, you can proceed with the development. What do the planners need to know? Planning departments do not require any high level of technical information; they just really want to know information like: What the proposed building will look like What the current building looks like (if it exists) The purpose to which the building will be put What the parking arrangements are. What information do the planners require in order to make a decision? The Planners make a recommendation in respect of an application based on a set of regional and national policies. To demonstrate that a proposal complies with all the relevant polices a planning application will usually require: Preparation of more detailed floor plans and elevations to show how the building will work and what it will look like. These will usually be CAD

8 (computer drawn) drawings, accurate information that can be altered efficiently and based off the survey drawings. Preparation of accompanying written documentation demonstrating how the proposal complies with the relevant planning policies and information such as how energy efficient the completed building will be. Depending on the nature of the proposal we will discuss with the planners to determine whether any other information is required, such as: o An Archaeological Investigation/Report o A Daylight/Sunlight Assessment o An Environmental Impact Assessment (unlikely for domestic extensions) o A tree survey (performed by a qualified Aborculturist, likely if there are significant numbers of trees on the site) o A bat, owl or newt survey (often applicable in older buildings or buildings near water) o A pollution assessment (if the site has, or is suspected to have any polluted ground or materials) o An ecological walk over / desk top study. If any of these are necessary we can arrange everything on your behalf. How long does the formal planning process take? Planning permission usually takes 6 8 weeks from the time the application is submitted. In order to save costs, we normally advise clients not to proceed with any further detailed construction information or building regulations until planning permission has been granted. How does the planning process actually work? The whole process essentially works via the planners (Planning Officers) making a recommendation to a Planning Committee of lay people (Local Councillors) based on whether the proposal complies with their policies. In most cases, as long as a proposal is in compliance with the relevant policies and the Planning Officer makes a positive recommendation the chances are this will be endorsed by the Planning Committee, but a decision can be political and the Committee can always overturn a Planning Officer s recommendation; this is where lobbying local Councillors can be useful if done in a sensible way.

9 What if planning permission is refused? One of the advantages of employing an experienced Architect is their knowledge of local planning policies and procedures, however in some cases planning permission may be refused. In this case we will advise you on further options which might include an Appeal. Appeals are made either by written representations or through an informal hearing. Although planning permission usually takes 6 8 weeks from the time the application is submitted an Appeal is currently taking somewhere between 4 and 6 months from the time a refusal notice has been issued. You can only appeal if you receive a planning refusal. For how long is planning permission valid? Usually 3 years from the date of the approval. This time soon goes and it s worth making a diary note for a year after the event so you can review a way forward. Once you have started the development (starting implies a serious undertaking such as digging foundations or undertaking substantial demolition) work can be deemed to be valid indefinitely, i.e. the permission doesn t require renewing after 3 years. Renewing an application is more complex as one has to re-apply for planning permission providing an update of all the previous information. There is no easy way of renewing an existing application. Can I still make changes once permission has been granted? Yes, in some cases. the Council now have a system of allowing planning amendments provided a form is filled in and a fee (usually 25) is paid. If the amendments involve anything other than simple window or door changes, it is likely that a fresh application will be required which stresses the importance of getting the initial application right in as much detail as possible.

10 An example of a planning application drawing (one of a number that would be required - in this case, some elevations)

11 Stage 4 - Building Regulations Application This is a compulsory application to the Local Authority Building Control Department (a quite separate department), and it is designed to demonstrate that the proposed building will be constructed in accordance with national minimum standards (the Building Regulations). We only normally recommend applying for building regulation approval provided planning permission is in place. What are the Building Regulations? What information is required for an application? The Building Regulations are primarily to do with Health and Safety. They cover a large number of issues, such as ensuring that the building will be structurally sound, ensuring that there are protections against fire with clear means of escape in the event of fire, that the building is well insulated and thermally efficient and so on. What information does Building Control require? Ensuring that the building is structurally sound is performed by a separate Structural Engineer who will provide Building Control with a set of calculations. In our experience a close working relationship with the Engineer is extremely beneficial. We share premises with a firm of Structural Engineers and therefore usually involve them informally from the very start of a project to provide suggested designs that not only meet your requirements but are structurally efficient and sound. This can save time and therefore cost. Most applications these days also require quite a complex thermal calculation to show they are energy efficient. This is called a SAP calculation and we will often quote separately for doing this. It is worth noting that there is an alternative option of using a (private sector) Approved Inspector at this stage, which may in certain cases be more suitable. We can always advise when this may be the case.

12 An example of a building regulations application drawing (again, just one of a number that would be required - in this case, some building sections)

13 When can I start work? We always recommend that approval is obtained prior to commencement of work on site if possible. This usually takes around 6 weeks from the time of submission until approval. You are entitled to start the work before full approval is granted once a building regulation application has been submitted and acknowledged but this must be at your own risk. The Council retains the right to come back and request more information or changes, which could be difficult if the work has been started. Our quotations for obtaining building regulation approval are for just that, at this stage we do not get actively involved on site or provide any further information other than that which is necessary to obtain building regulation approval. Stage 5 - Selection of Building Contractor, preparing Construction Information /Tender Procedure How do I find a builder? We work with a number of contractors both small and large and have relationships going back many years. We monitor trends in prices and tend to know what a particular builder is good at doing. Builders with whom we work regularly tend to look after our clients for obvious reasons! We will be able to recommend a list of reputable and efficient builders that would be suitable for your job. How will builders price the work? We can work with you in detail to produce a set of tender documents suitable for builders to prepare estimates. These would comprise a detailed set of drawings and a written specification of work, with approximate quantities where required. Provided one approaches builders of appropriate experience, generally 4 or 5 on a job of an average size, the prices received will be typically wide ranging, perhaps varying by up to 25%. The strength of providing a comprehensive and accurate tender package is that it lessens the amount of information that the builder has to assume, it should allow the builder to price with more certainty and therefore more competitively. Time spent at the design stage will usually be more than offset by savings in the actual construction. We normally check priced documents on receipt of tenders and prepare a tender analysis advising on tenders received.

14 Stage 6 - Contract Administration and Cost Control Services We also provide Contract Administration and Cost Control Services. Typically the following will be included as part of these services: Attending pre-contract site meeting with chosen contractor to discuss programme organisation. Preparation of contract documentation. Arranging for signing of contract documents by both parties. Supplying all necessary information to contractor. Setting up project page on website with private password for access to drawings, cost schedules and minutes. Checking contract programme of works. Monitoring the process and the quality of work by periodic site visits. Preparing monthly reports to you on progress and actual contract expenditure. Administering the terms of the building contract during progress of the works. Preparing Rolling Final Account Cost Control documentation to reflect progress. Assessing valuation application submitted by the building contractor, issuing valuation certificates based upon the value of work actually completed (rather than the contractor s rule of thumb ). Preparing and updating a draft final account. Agreeing a final account with contractor and handing over record drawings. Stage 7 - Post Build Services What happens beyond completion of the project? We can help you set up a building maintenance manual to cover not only the new work but the existing building. This will include general advice on maintenance and instruction manuals for building services. We can also do an as built energy audit, as in most cases we will already have done calculations in relation to the new work. If this is an extension to an existing building, we can look at the whole building complex and advise on energy consumptions and ways in which these consumptions could be reduced.

15 Total services available include: Feasibility Assessments Planning and Listed Building Consents Measured Building Surveys Topographical and Specialist Surveys Building Regulations Approvals Tender Specifications for Builders Contract Administration Sustainability & Energy Saving Advice Reinstatement Cost Assessments Party Walls Boundary Disputes Building Condition Surveys Residential Valuations Maintenance Programmes Rights of Light/Daylight Assessments Schedules of Dilapidations THE DESIGN STUDIO 94 HIGH STREET STEYNING WEST SUSSEX BN44 3RD TEL: (01903) FAX: (01903) VAT REG NO Suite 2, Grosvenor Hall Bolnore Road Haywards Heath West Sussex RH16 4BX Tel: Fax: Gould and Company Chartered Surveyors is the trading name of Gould Property Consultants LLP, a Limited Liability Partnership TEL: (01903) FAX: (01273) [email protected]

16

Menu of Architecture Services 2009

Menu of Architecture Services 2009 Menu of Architecture Services 2009 We deliver architecture and interior design services in an accessible, easy to use format. We help you to select services that suit your project, budget and level of

More information

A Guide to Small Works. A brief explanation

A Guide to Small Works. A brief explanation A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here

More information

0 - Initial Services

0 - Initial Services Overview At All Australian Architecture we consider each project in terms of self contained stages (see below). Each stage is independent and does not tie you into completing every stage of your project

More information

PROPERTY MANAGEMENT AGREEMENT [HEREINAFTER REFERRED TO AS. hereby appoint QUADRANT PROPERTY MANAGEMENT LTD

PROPERTY MANAGEMENT AGREEMENT [HEREINAFTER REFERRED TO AS. hereby appoint QUADRANT PROPERTY MANAGEMENT LTD Quadrant PROPERTY MANAGEMENT LTD Kennedy House 115 Hammersmith Road London W14 0QH Telephone 020-7386 8800 Facsimile 020-7386 0440 e-mail: [email protected] website: www.quadrantpm.co.uk Your Ref

More information

WIN. Factoring Services News. Factoring Services News. Common repairs what happens! page 6. worth of vouchers

WIN. Factoring Services News. Factoring Services News. Common repairs what happens! page 6. worth of vouchers Factoring news for homeowners in mixed tenure blocks in East Renfrewshire www.eastrenfrewshire.gov.uk/housing Winter 2015 Factoring Services News Complete our customer satisfaction survey inside this edition

More information

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE

South East Region Leakage Code of Practice. Affinity Water Limited CODE OF PRACTICE ON LEAKAGE 1 of 13 Affinity Water Limited CODE OF PRACTICE ON LEAKAGE LEAKAGE FROM DOMESTIC CUSTOMERS WATER SUPPLY PIPES Dated: 10 July 2014 1 INTRODUCTION 2 of 13 The Company is committed to a policy of water efficiency

More information

A Guide to... Home Renovation Incentive (HRI)

A Guide to... Home Renovation Incentive (HRI) A Guide to... Home Renovation Incentive (HRI) About this guide This guide will tell you what you need to know if you are organising to have construction work done on your house and would like to avail

More information

Project and Building Consultancy. Capabilities and track record Enhancing the physical and economic potential of built assets

Project and Building Consultancy. Capabilities and track record Enhancing the physical and economic potential of built assets Project and Building Consultancy Capabilities and track record Enhancing the physical and economic potential of built assets Introduction Cavendish Maxwell 2205 Marina Plaza Dubai Marina P.O. Box 118624

More information

LETTING & PROPERTY MANAGEMENT

LETTING & PROPERTY MANAGEMENT LETTING & PROPERTY MANAGEMENT A GUIDE TO OUR SERVICES 25 Carfax, Horsham West Sussex RH12 1EE Tel: 01403 252200 Fax: 01403 218062 E-mail: [email protected] Web site: www.courtneygreen.co.uk

More information

Self Build: A Guide to Building your Own Home. Are you, or a member of your family, disabled and thinking about building a home?

Self Build: A Guide to Building your Own Home. Are you, or a member of your family, disabled and thinking about building a home? Self Build: A Guide to Building your Own Home Are you, or a member of your family, disabled and thinking about building a home? Introduction As a disabled person or a family with a disabled family member,

More information

DESIGN IS GOOD BUSINESS

DESIGN IS GOOD BUSINESS COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

How To Apply For Land Division In Australia

How To Apply For Land Division In Australia Development Act 1993 GUIDE FOR APPLICANTS Land Division Guide GUIDE FOR APPLICANTS Land Division Guide Planning SA Primary Industries and Resources SA 136 North Terrace Adelaide GPO Box 1815 South Australia

More information

HALIFAX INTERMEDIARIES

HALIFAX INTERMEDIARIES FOR THE USE OF MORTGAGE INTERMEDIARIES AND OTHER PROFESSIONALS ONLY HALIFAX INTERMEDIARIES SELF BUILD GUIDE Helping to make your plans reality About 12,000 people build their own homes in the UK each year,

More information

One Call Away. www.factor8ltd.co.uk

One Call Away. www.factor8ltd.co.uk One Call Away www.factor8ltd.co.uk Who We Are Factor 8 Ltd is a young, dynamic and reliable property management company which brings years of varied knowledge and experience together to produce a dedicated,

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

A guide to appointing an architect

A guide to appointing an architect A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the

More information

FENCING LAW IN VICTORIA: WHAT ARE MY RESPONSIBILITIES?

FENCING LAW IN VICTORIA: WHAT ARE MY RESPONSIBILITIES? FENCING LAW IN VICTORIA: WHAT ARE MY RESPONSIBILITIES? If you are a property owner, new changes to the Fences Act 1 mean that you and your neighbour have equal responsibility for the dividing fence on

More information

The Complete Guide to Renting a Commercial Property

The Complete Guide to Renting a Commercial Property The Complete Guide to Renting a Commercial Property Contents Contents 2 Introduction 3 Picking out a Commercial Property What Questions to Ask 4 What is a Business Lease? 5 Lease Negotiations 5 Rental

More information

Pre-Application Planning Advice

Pre-Application Planning Advice Pre-Application Planning Advice Guidance Note and Schedule of Fees Regeneration and Planning (Development Management) December 2014 The Development Management Service is responsible for the determination

More information

LANDSCAPE ESIGN. Plan, Design & Create the landscape of your dreams. How to... 253-922-7075 olympiclandscape.com

LANDSCAPE ESIGN. Plan, Design & Create the landscape of your dreams. How to... 253-922-7075 olympiclandscape.com 1 LANDSCAPE ESIGN How to... Plan, Design & Create the landscape of your dreams 253-922-7075 olympiclandscape.com C ontents What is landscape design?...4 Why is proper planning a good investment?...6 What

More information

APPLICATION FOR BUILDING WARRANT

APPLICATION FOR BUILDING WARRANT THE BUILDING (SCOTLAND) ACT 2003 Application Under Section 9 for a Building Warrant to Construct, Demolish or Convert a Building, or to Provide Services, Fittings or Equipment in or in connection with

More information

Head of Lease Terms - Ten Steps to a Successful negotiation

Head of Lease Terms - Ten Steps to a Successful negotiation Imperial College ThinkSpace Leasing Terminology Head of lease terms The principal terms upon which the lease will be drafted are detailed within a single document, entitles the Heads of Lease Terms. These

More information

PROJECT BRIEF Version (insert number)

PROJECT BRIEF Version (insert number) PROJECT BRIEF Version (insert number) 1 Project Name ------------------------------------------------------------------- 1.1 The Project Project Address Nature of Work Location 1.2 DCC Client for Project

More information

Conveyancing Guide Making your Home yours..

Conveyancing Guide Making your Home yours.. Conveyancing Guide Making your Home yours.. Introduction to Conveyancing Buying your new home can be a long and difficult process and the final step, the legal one, often seems the biggest. Buying a house

More information

Moving Home Guide. A simple step by step guide to buying & selling

Moving Home Guide. A simple step by step guide to buying & selling RESIDENTIAL PROPERTY BUYING & SELLING Moving Home Guide A simple step by step guide to buying & selling 2 Turn to page 11 of this Guide where there is a useful checklist that details all the things you

More information

Regulations for the 25% State Commercial Tax Credit Program Prepared by the Division of Historic Preservation

Regulations for the 25% State Commercial Tax Credit Program Prepared by the Division of Historic Preservation Regulations for the 25% State Commercial Tax Credit Program Prepared by the Division of Historic Preservation A. DEFINITIONS These Regulations provide guidelines for the application process and the Administration

More information

SECTION 4: CLAIMS MANAGEMENT

SECTION 4: CLAIMS MANAGEMENT SECTION 4 INDEX SECTION 4: CLAIMS MANAGEMENT PART 1 Adjusters Reports: (all perils) B. All reports; front page format; B. Full reports: i. Main body format; ii. Explanatory notes. C. Abbreviated reports

More information

Building Permit Information House Relocation

Building Permit Information House Relocation Building Permit Information House Relocation About private Building Surveyors Until about 1992 all building permits were issued by Councils. This function was then privatised, and while many Councils still

More information

Guide to Procedure for Competitive Tendering March 2003

Guide to Procedure for Competitive Tendering March 2003 Guide to Procedure for Competitive Tendering March 2003 The Landscape Institute 33 Great Portland Street London W1W 8QG Tel: +44 (0)20 7299 4500 Fax: +44 (0)20 72994501 Email: [email protected]

More information

The Amendment of the Loan Agreement (for Business)/ Overdraft Facility Agreement (for Consumption)/ Money Mortgage Agreement*

The Amendment of the Loan Agreement (for Business)/ Overdraft Facility Agreement (for Consumption)/ Money Mortgage Agreement* The Amendment of the Loan Agreement (for Business)/ Overdraft Facility Agreement (for Consumption)/ Money Mortgage Agreement* No. Clause Reference Amendment Sanctions 1. Important notice Standard Chartered

More information

03 Your tenancy explained

03 Your tenancy explained 03 Your tenancy explained Written Statement of Services Factored Owners Written Statement of Services under the Property Factors (Scotland) Act 2011 Revised version: April 2015 What is the Written Statement

More information

Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 ARRANGEMENT OF SECTIONS. 6. Right to refer payment disputes to adjudication.

Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 ARRANGEMENT OF SECTIONS. 6. Right to refer payment disputes to adjudication. Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 Section 1. Interpretation. ARRANGEMENT OF SECTIONS 2. Construction contracts: exceptions, etc. 3. Payments under construction contracts. 4. Payment claim

More information

Charging for Pre-application Advice

Charging for Pre-application Advice Charging for Pre-application Advice Guidance Note - London Borough of Islington April 2016 1 Introduction The London Borough of Islington has a rich built heritage, a diverse community and high land values.

More information

Description of the RICS Building Survey Service

Description of the RICS Building Survey Service Description of the RICS Building Survey Service 1 The service The RICS Service includes: a thorough inspection of the property (see The inspection ); and a detailed report based on the inspection (see

More information

Residential mortgages general information

Residential mortgages general information Residential mortgages general information Residential mortgages general information 2 Contents Who we are and what we do 2 Forms of security 2 Representative Example 2 Indication of possible further costs

More information

Please staple bank deposit here NOTES ON DONATION APPLICATIONS (AND PAYMENT OF)

Please staple bank deposit here NOTES ON DONATION APPLICATIONS (AND PAYMENT OF) PART 1 Please staple bank deposit here THE HEART OF COMMUNITY FUNDING NOTES ON DONATION APPLICATIONS (AND PAYMENT OF) 1. You can t apply for things you will have bought, or events which will have passed,

More information

There are other sections that may be used to detain the patient without consent, which are described in later sections of this booklet.

There are other sections that may be used to detain the patient without consent, which are described in later sections of this booklet. L12 Understanding the Mental Health Act Information for Patients/Relatives and Carers What happens when a patient is detained in hospital? Usually two doctors will examine and assess the patient not necessarily

More information

Doug Kerr Insurance Consultants P/L ABN AFSL Tel: Fax:

Doug Kerr Insurance Consultants P/L ABN AFSL Tel: Fax: PRIVACY POLICY Doug Kerr Insurance Consultants P/L ABN 67 078 679 071 AFSL 246366 Shop33/ 1 st Floor, 15-23 Langhorne Street DANDENONG VIC 3175 P.O Box 7031 DANDENONG VIC 3175 Tel: (03) 9791 6688 Fax:

More information

DEVELOPMENT MANAGEMENT

DEVELOPMENT MANAGEMENT DEVELOPMENT MANAGEMENT Sub Heading Sub Heading 2 march 2012 PRE APPLICATION ADVICE SERVICE FOR PLANNING APPLICATIONS Introduction CONTACT DETAILS Telephone 0191 433 3416 / 0191 433 3426 Fax 0191 477 8422

More information

OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993

OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993 AS AN OWNER BUILDER building work? What records should I keep? Is insurance required? W I need approval for? What do I need approval for? How do I obtain building work? How do I obtain approval? What records

More information

Project Management Handbook 2014. "To Understand the Causes of Things"

Project Management Handbook 2014. To Understand the Causes of Things Management Handbook 2014 "To Understand the Causes of Things" AMENDMENT RECORD This document has been issued and amended as follows: - Isu. Rev. Reason for Issue / revision Date Issued to Team Stakeholders

More information

CSENSE LTD. Block Management Agreement

CSENSE LTD. Block Management Agreement CSENSE LTD Block Management Agreement For Guidance in this agreement The singular includes the plural and the plural includes the singular. Any obligation undertaken by more than one person is a joint

More information

International Construction Warranties Limited. Terms & Conditions. Version UK1

International Construction Warranties Limited. Terms & Conditions. Version UK1 International Construction Warranties Limited Terms & Conditions Version UK1 Rules of Registration Version 5 All Companies applying for or taking out a Warranty on a New Development with ICW shall comply

More information

North Yorkshire Building Control Partnership

North Yorkshire Building Control Partnership North Yorkshire Building Control Partnership Providing Building Control for Hambleton, Richmondshire, Ryedale, Scarborough and Selby Councils Choosing a building you can trust The information contained

More information

Terms of Business and Important Information We Must Disclose to You

Terms of Business and Important Information We Must Disclose to You 1. Terms of Business ( Terms ) In these Terms references to we or us are to the firm whose details are set out in the covering letter that accompanies these Terms. We recommend that for your own benefit

More information

Asbestos at work guide

Asbestos at work guide Asbestos at work guide Contents Introduction.... 2 Frequently asked questions.... 4 The Control of Asbestos Regulations 2006... 5 Types of asbestos survey.... 7 1 Introduction This document provides a

More information

1 The Role of Accounting

1 The Role of Accounting 5 1 The Role of Accounting Accounting Information Accounting provides financial information for a variety of entities to enable them to make informed judgements and decisions. It is important that you

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Your guide to the residential architectural process. A step-by-step guide from Context Architects

Your guide to the residential architectural process. A step-by-step guide from Context Architects Your guide to the residential architectural process A step-by-step guide from Context Architects We know that building a new house or renovating your home can seem daunting and complicated. So we ve produced

More information

Check. They re Chartered. Chartered Project Managers

Check. They re Chartered. Chartered Project Managers Check. They re Chartered. Chartered Project Managers The Society of Chartered Surveyors Ireland is the leading organisation of its kind in Ireland for professionals working in the property, land and construction

More information

Home Warranty Insurance Claim Form

Home Warranty Insurance Claim Form Home Warranty Insurance Claim Form General WFI Insurance Limited (ABN 24 000 036 279) trading as Lumley Insurance offers Builders Home Warranty Insurance to owner Builders and Licensed Builders in the

More information

Block Management Brochure

Block Management Brochure BLOCK MANAGEMENT BROCHURE Block Management Brochure 4 Englands Lane London NW3 4TG T 020 7586 8550 F 020 7586 8582 [email protected] www.kernahans.net YOUR PROPERTY IN SAFE HANDS 4 Englands Lane, London

More information

Pre-Application Planning Advice: Guidance Note

Pre-Application Planning Advice: Guidance Note Pre-Application Planning Advice: Guidance Note Introduction Eastleigh Borough welcomes and encourages discussion before a developer or landowner submits a planning application and is committed to providing

More information

Consumer Code. for Home Builders

Consumer Code. for Home Builders Consumer Code for Home Builders This document contains the Consumer Code requirements together with non-mandatory good practice guidance for Home Builders Second Edition January 2010 Contents Meaning of

More information

Office Contact Number 01803 611030. 13, Hyde Road, Paignton, Devon. TQ4 5BW. www.targetpropertyservices.com

Office Contact Number 01803 611030. 13, Hyde Road, Paignton, Devon. TQ4 5BW. www.targetpropertyservices.com Office Contact Number 01803 611030 13, Hyde Road, Paignton, Devon. TQ4 5BW. www.targetpropertyservices.com TARGET PROPERTY RENTALS RENTALS & MANAGEMENT AGENCY AGREEMENT This agreement is made between the

More information

ISLINGTON & SHOREDITCH HOUSING ASSOCIATION JOB DESCRIPTION. Operations. Operations Director

ISLINGTON & SHOREDITCH HOUSING ASSOCIATION JOB DESCRIPTION. Operations. Operations Director ISLINGTON & SHOREDITCH HOUSING ASSOCIATION JOB DESCRIPTION Title of Post Section/department To whom immediately responsible For whom immediately responsible Job Purpose Partnering Contacts Manager Operations

More information

The Purchase Price in M&A Deals

The Purchase Price in M&A Deals The Purchase Price in M&A Deals Question that came in the other day In an M&A deal, does the buyer pay the Equity Value or the Enterprise Value to acquire the seller? What does it mean in press releases

More information

Scandinavian Airlines (SAS) Regulations of the SAS Credits Program

Scandinavian Airlines (SAS) Regulations of the SAS Credits Program Scandinavian Airlines (SAS) Regulations of the SAS Credits Program 1 1. Part One. Regulations of the SAS Credits Program.... 3 1.1 The Content and Scope of the Regulations.... 3 1.2 General Information

More information

CONTRACTORS: IT S YOUR BUSINESS TO UNDERSTAND THE NEW CONSUMER PROTECTION MEASURES.

CONTRACTORS: IT S YOUR BUSINESS TO UNDERSTAND THE NEW CONSUMER PROTECTION MEASURES. CONTRACTORS: IT S YOUR BUSINESS TO UNDERSTAND THE NEW CONSUMER PROTECTION MEASURES. Licensed Building Practitioners skills maintenance If you are a Licensed Building Practitioner (LBP) you can gain skills

More information

CONTRACT CONDITIONS FOR LOGISTICS (2014)

CONTRACT CONDITIONS FOR LOGISTICS (2014) CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member

More information

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company Ref: Quality Manual.ind Issue: June 2009 INDEX 1 Amendment Status 2 Controlled Distribution

More information

Internal Audit Report. Chief Executive s Unit. Review of Contract Management

Internal Audit Report. Chief Executive s Unit. Review of Contract Management Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Employment Practices Liability Insurance Proposal Form

Employment Practices Liability Insurance Proposal Form Employment Practices Liability Insurance Proposal Form Important Notice 1. This is a proposal for a contract of insurance, in which 'proposer' or 'you/your' means the individual, company, partnership,

More information

Appendix 1. This appendix is a proposed new module of the DFSA Rulebook. Therefore, the text is not underlined as it is all new text.

Appendix 1. This appendix is a proposed new module of the DFSA Rulebook. Therefore, the text is not underlined as it is all new text. Appendix 1 This appendix is a proposed new module of the DFSA Rulebook. Therefore, the text is not underlined as it is all new text. The DFSA Rulebook Auditor Module (AUD) PART 1 INTRODUCTION 1 APPLICATION

More information

Part of the Holyhead 2020 Regeneration Programme Working in Partnership with Welsh Government

Part of the Holyhead 2020 Regeneration Programme Working in Partnership with Welsh Government Holyhead Investment Fund Part of the Holyhead 2020 Regeneration Programme Working in Partnership with Welsh Government !!!!!!!!!!!"#$%"&'(!)*+,'-.!'-(!)*'+$&!/$'0&1!,&2&-&,'.*#-!/,#2,'33&! 45-(&(!+%!."&!6&$1"!2#)&,-3&-.7!'(3*-*1.&,&(!+%!*1$&!#4!'-2$&1&%!0#5-.%!

More information

Before beginning your journey there are a number of things you will need to consider, with the most important being finance.

Before beginning your journey there are a number of things you will need to consider, with the most important being finance. Whether you have just started your own small businesses, or you are a budding entrepreneur with big aspirations, there has never been a better time to work for yourself. With the economy going from strength

More information

Occupational pension scheme governance

Occupational pension scheme governance GfK. Growth from Knowledge Occupational pension scheme governance A report on the 2014 (eighth) scheme governance survey Prepared for: The Pensions Regulator By: GfK Financial, May 2014 1 P a g e Contents

More information

SPECIALIST 24 HR CRIMINAL DEFENCE

SPECIALIST 24 HR CRIMINAL DEFENCE SPECIALIST 24 HR CRIMINAL DEFENCE What happens at the Police Station? Often the most important stage in any case is what happens in the police station. In most cases you will be under arrest and it may

More information

Conveyancing Guide. We welcome you as a client of Tyndallwoods and thank you for your instructions. Conveyancing has two basic stages

Conveyancing Guide. We welcome you as a client of Tyndallwoods and thank you for your instructions. Conveyancing has two basic stages Conveyancing Guide We welcome you as a client of Tyndallwoods and thank you for your instructions. This guide is part of the Tyndallwoods commitment to quality of service. We are well aware that moving

More information

Social Return on Investment

Social Return on Investment Social Return on Investment Valuing what you do Guidance on understanding and completing the Social Return on Investment toolkit for your organisation 60838 SROI v2.indd 1 07/03/2013 16:50 60838 SROI v2.indd

More information

Empty Dwelling Management Orders Guidance for residential property owners. housing

Empty Dwelling Management Orders Guidance for residential property owners. housing Empty Dwelling Management Orders Guidance for residential property owners housing Contents Introduction 2 Summary 3 Key facts for property owners 4 Making of Empty Dwelling Management Orders 5 Money Matters

More information

Property Management Service Level Agreement

Property Management Service Level Agreement Property Management Service Level Agreement 2014 comms:3292 www.lancashire.gov.uk 2 Contents 3 Welcome Mission Statement 4 Customer Charter 5 Introduction 6 Responsibilities and Choices 7 Service Level

More information

Terms of Business. The Detective Agency

Terms of Business. The Detective Agency Terms of Business Terms of Business following Terms and Conditions of Service apply to all products and services provided by Limited (hereinafter referred to as ). All work is carried out by on the understanding

More information

EXPLANATORY NOTES & CONDITIONS

EXPLANATORY NOTES & CONDITIONS ON FARM SCHEME OF GRANT AID FOR THE DEVELOPMENT OF THE ORGANIC SECTOR EXPLANATORY NOTES & CONDITIONS It is important to read the Explanatory Notes and Conditions before making application under this Scheme

More information

Pre Application Advice Charging Scheme and Post Application Service Introduction (1 st February 2014)

Pre Application Advice Charging Scheme and Post Application Service Introduction (1 st February 2014) Pre Application Advice Charging Scheme and Post Application Service Introduction (1 st February 2014) The Development Control Service is responsible for providing planning advice, processing planning applications

More information