A SMALL-SCALE ARSENIC AND IRON REMOVAL PLANT



Similar documents
PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

LOW-COST MEDICAL WASTE INCINERATOR

STATE BANK OF INDIA.

USING A BIOGAS DIGESTER

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

LAYING BLOCK AND BRICK

Chapter. Restoration of Damaged Structures

CHAPTER NO. 27 QUANTITIES OF MATERIALS

SECTION STORM DRAIN SYSTEM

Treatment options for hydrogen sulfide. Testing for hydrogen sulfide

SECTION STORM DRAINAGE SYSTEM

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs

SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS. Prepared by Risi Stone Systems Used by permission.

Free-Form Concrete Pool

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

BOQ for Plumbing, Sanitary Works

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

Guide to working on Public Sewers

How To Retaining Wall Guide

RESIDENTIAL MASONRY A BEST PRACTICES GUIDE

Tender schedule. Rate in

Subject: Technical Letter 22 April 1977 Removal of Water Supply Contaminants -- Copper and Zinc

DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

HOUSE BUILDING DIGEST

SEE HOW TO MAKE LIME PLASTER WHY USE LIME? PATTI STOUTER, BUILD SIMPLE INC. FEBRUARY 2013

Gravity-fed schemes. Technical brief. Introduction

KALPANA INDUSTRIES LTD. TECHNICAL DATA SHEET

Fact sheet 6: for farmers

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Complete. Water Solutions. for Rural India

How to build raised beds page

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

ELECTRIC PERISTALTIC MORTAR POINTING PUMP

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

How to build a Pizza Oven in 4 days

Aggregates for Path Construction

Prepare a drainage system layout and specification notes for a low- rise building.

TECHNICAL BULLETIN. Location of the system. Percolation tests for drainage fields. Cesspool sizing. Suggested Information notices

TECHNOLOGIES FOR ARSENIC MITIGATION

Water Treatment & Purification Chemicals

SANITARY SEWER SPECIFICATIONS

Permeable Pavement Construction Guide

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

septic systems What is a Septic System? How does a Septic System Work?

Septic Tank to Cistern Conversions. Saving Water & Saving Money

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

LANDSCAPING AQUA SPORT. Rainwater treatment using filter substrate channel. DIBt approval applied for

DRAFT OF CDN S DEFLUORIDATION EXPERIENCES ON A COMMUNITY SCALE

Iron and manganese are two similar elements

GRADATION OF AGGREGATE FOR CONCRETE BLOCK

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

Batching and Mixing Plants

Septic Records and Maintenance Guidelines

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)

31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE

TYPICAL ESTIMATE OF A RAINWATER COLLECTION UNIT (110 mm / 150 mm dia PVC Pipelines)

Development of Low-cost Technologies for Removal of Arsenic from Groundwater

R E S I D E N T I A L H O U S I N G

Fiberstars Lighted Laminar Flow Fountain Installation Manual

Innovation and Progress in Water Treatment Technology

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Onsite Wastewater Concepts, Materials, Regulations & The Application Process Part I

Fact sheet 6: for farmers

Domestic heating Fuel storage tanks

SEPTIC TANKS FOR THE COLLECTION & SETTLEMENT OF DOMESTIC SEWAGE

Power consumption (kw)

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

Iron and Manganese BACTERIA AND IRON AND MANGANESE

Section 2100-Trenching and Tunneling

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

International Greenhouse Company

SECTION PRECAST CONCRETE STRUCTURES

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"

oil care Looking after your heating oil in the south east

Stormwater/Wetland Pond Construction Inspection Checklist

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

1 yard per sq. 2 Depth. Color is a personal choice. Dye fades due to sunlight. Although color remains, fading begins to occur

Section 402. STORM SEWERS

MASONRY RESTORATION Lime Putty Mortar Repointing Guide

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Resurfacing Concrete. Page 1 of 5

Fabricated Drainage Products

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

VOLUME AND SURFACE AREAS OF SOLIDS

PROJECT PROFILE ON CEMENT CONCRETE HOLLOW BLOCKS

Corrosivity of Water Supplies

Homeowners and Home Buyers Guide to Wells and Private Sewage Systems

K2 STONE NATURAL VENEER

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems

Transcription:

A SMALL-SCALE ARSENIC AND IRON REMOVAL PLANT Introduction Groundwater is the main source of water supply in Bangladesh. Groundwater abstracted from tubewells was considered to be the best option for water supply in rural and peri-urban areas. Unfortunately, arsenic in excess of the acceptable limit has been found in tubewell water in many parts of the world and particularly in Bangladesh. Alternative options for arsenic-safe water are urgently needed to mitigate arsenic toxicity and protect public health and there has been considerable research into a range of technologies. Some of the common arsenic mitigation technologies include: Co-precipitation of arsenic and iron Adsorption of arsenic onto coagulated flocs Lime treatment Adsorption onto sorptive media Ion exchange Filtering by special membrane Microbial process One low-cost option based on the coprecipitation principle that is showing promises is the arsenic and iron removal plant (AIRP) that has been tested in Bangladesh. This approach to arsenic mitigation is described in this Technical Brief. How does the AIRP system work? Figure 1: AIRP Design. The basic structure of the 4 chamber plant is shown in Figure 1. Water contaminated with arsenic and iron from the source tubewell is introduced to chamber C1. The water spreads through the perforations of the inlet pipe. This action aerates the water. In the aeration process, oxygen from the air reacts with iron and arsenic in the water. This transforms the soluble arsenic and iron into insoluble compounds. The insoluble arsenic and iron, The Schumacher Centre, Bourton on Dunsmore, Rugby, Warwickshire, CV23 9QZ, UK T +44 (0)1926 634400 F +44 (0)1926 634401 E infoserv@practicalaction.org.uk W www.practicalaction.org is a registered charity and company limited by guarantee. Company Reg. No. 871954, England Reg. Charity No.247257 VAT No. 880 9924 76 Patron HRH The Prince of Wales, KG, KT, GCB

precipitates out. Water then passes through chambers C2 and C3. These chambers are filled with different types and size of filter media that arrest the arsenic and iron particles by adsorption and filtration. Finally, water free from arsenic and iron arrives in the last chamber C4. In this process a 70 to 75 percent reduction in arsenic can be achieved. Therefore, water that has 100 150 ppb (parts per billion) of arsenic could be treated to an acceptable level by the AIRP technology. [Bangladesh standard for allowable arsenic contamination is 50ppb.] AIRP construction The following criteria should be used in selecting the site for an AIRP. The site for the AIRP should be near the tubewell yielding water contaminated with arsenic and iron The plant should be located on flood-free high land There should be proper drainage facilities/opportunities The plant should be located in a place easily accessible by the community Materials required for constructing an AIRP are listed in Table 1. Sl Name of Quantity Units Usages/placement Remarks # construction and media materials Construction materials 01 Filling sand 0.75 02 Bricks (Size: 240 mm x 115mm x 70mm) 350-450 Cubic m Nos. Foundation bed of the plant Structure of the plant Based on the site condition Depends on site condition, drainage facilities Cubic Masonry and casting 03 Medium Sand 2.0 m works 04 Cement 3-4 Bag Cement additive To make the plant water 05 0.5 Kg Plaster works (Padlu) proof 38 mm dia steel Outlets and intra In between walls of chamber 06 1.6 m pipes chamber connection C1-C2 and C2-C3 07 End cap (38 mm) 04 Nos. Outlet pipe One with each chambers PVC Pipe (100mm 1.0 to Feeding water to Distance from the source 08 m dia) 1.5 chamber C1 (tubewell) To protect passing of media 09 Plastic net 1.0 Sq. m Wear GI pipes materials during cleaning To pass water slowly to the Strainer pipe (38mm In between walls of 10 1.0 m chamber C4 resting media dia) chamber C3-C4 materials 11 Tap/Bib-Cock 01 Nos. 12 Steel sheet 2.5 Sq. m As cover of the plant 25 mm Flat bar 12 15 m (5mm thick) Media/filling materials and operation instruments 12mm down graded 14 0.25 Sq. m Chamber C1 For one time brick chips 6mm down graded 15 stone chips/pea 0.25 Sq. m Chamber C2 gravels Course sand (FM- 16 0.25 Sq. m Chamber C3 2.0 to 2.5) 200- (If iron contamination is low 17 Iron nails gm Chamber C1 400 in raw water) 18 Pipe wrench 01 No. To open/close outlets Table 1: Construction materials and filter media required for an AIRP suitable for 10 households Outer side of the Fit at a convenient height for chamber C4 users to draw water easily 2

Steps for preparing the site Clean the site (2.0 m x 2.0 m) close to the contaminated water source Water source (tubewell) should be at the left side (first corner) of the plant If the soil condition of the bed of the plant has been found loose/slushy, then additional earth should be excavated and filled with compact sand as per site condition 3 inches thick cement concrete (CC) or Reinforced Cement Concrete (RCC) with proportion of 1:2:4 (cement:sand:brick chips) over Brick Flat Soling (BFS) platform should be constructed. Note that the foundation bed of the plant should be constructed considering the level of nearby drainage network so that wastewater could pass easily from the plant; If necessary, the bed of the plant may be raised by additional brick work on the periphery (outer wall) of the plant Steps for constructing the superstructure Start the 5 inch (127mm) thick brick masonry work of the outer and inner walls after completing the CC/RCC bed (at least 24 hours delay is required). The height of the walls should be up to 600mm. Each chamber should be equal in size (600mm x 600 mm x 600 mm). After the brick works, plaster the walls with neat cement finishing (NCF) with 1:4 mortar (cement:sand) ratio. Water resistant additive (padlu) may be used during plaster works to keep the chambers impermeable. About 0.5 kg of padlu should be mixed with one bag of cement (50 kg) for making the plaster mortar. Side drain should be constructed with proper slope and connected to nearby drainage networks. Steps for adding fittings and fixtures: One outlet pipe for each chamber should be placed about 10 mm above the plant bed. The outlet should have an end cap at the outside and a plastic net placed on the inner side. The outlet pipe should be put in place during the brickwork stage. These outlets will drain wastewater while cleaning the chambers. Better drainage of wastewater and other settings of the plant should be considered while placing the outlet pipes. A perforated PVC pipe (100mm diameter) should be placed at chamber C1 as the inlet to introduce raw water from the contaminated tubewell into the plant. The perforated portion of the pipe should be fully within chamber C1. Pipes should be placed for circulating water between chambers as well. Between chambers C1 and C2, two galvanized iron (GI) pipes (38mm diameter and 150 mm long) covered with plastic net at both ends should be placed at the top level of the finished plant bed. Between chambers C2 and C3, two similar pipes should be placed at the middle height from the bed. Between chambers C3 and C4, two PVC strainers (38mm in diameter and 450 mm in length) should be placed between chambers C3 and C4 at the top level of the finished plant bed. The strainers should have end caps at chamber C3 and open ends at chamber C4. About 300mm length of the strainers should be within chamber C3. An outlet with a stopcock (tap) should be placed at chamber C4 about 150 mm above the finished bed of the plant. This will let users collect purified water. The outlet should be located so that the users could easily collect water by commonly used pots. 3

A cover made of corrugated iron (CI) sheet should be used to keep the plant (chamber materials and water) safe and free from dust and other contaminates. The cover could be hinged on one end so that it may be lifted for inspection and cleaning and put back in place afterwards. If the height of the existing tube well (water sources contaminated with arsenic and iron) is too low then it should be raised up to the level that water can be easily flow into chamber C1 through a perforated PVC pipe. Fill chambers C1, C2 and C3 with filter media as described in Table 1. Note: Proper and timely curing should be maintained during construction for strength and durability of the plant. Figure 2: Construction of AIRP. Photo: Moin/DRIK. Figure 3: Typical Chamber of a plant. Photo: Moin/DRIK. AIRP operation and maintenance Steps for operation set up: Close end caps of all outlet pipes at first Pump water from the contaminated tubewell to flow though the inlet pipe into chamber C1 Continue pumping to fill chambers C1, C2 and C3. When the water level in chamber C4 rises to the same level as other chambers, then the end caps of the outlets should be opened to flush out water from all chambers. This should be repeated at least three times After the initial three flushing cycles, the plant should be ready for operation. Water may be collected from the pure water outlet in chamber C4 for drinking and cooking Performance monitoring of the plant: For a quick check, collect a glass of water from chamber C4 and put some green pieces of plucked guava leaves in it and observe the water If no changes occur in the water, the performance of the plant is satisfactory and the user could use water for drinking and other cooking If the colour of the water in the glass darkens within 30 to 60 seconds, the performance of the plant is not satisfactory. In this case, renew the filter media and repeat the set up process For a more confirmatory test, use an arsenic field kit to test the treated water 4

Maintenance Regularly clean the outer sides/periphery of the plant and ensure it is free from water logging Keep the plant covered with the CI/plastic sheet Keep the outlet pipes closed After a 7 days interval flush out the water (opening the outlets) 2 or 3 times and clean the chambers After one month or if the performance of the plant is found to be unsatisfactory (test with the green guava leaves), take out all the media/filter materials separately then clean and wash with hot water mixed with bleaching powder (10 gm per liter of water), dry in sunlight and refill. After one year or if the performance of the plant is found unsatisfactory then all filter/media materials should be replaced by new materials Water containing a lot of iron contamination quickly reduces the adsorption and filtration capacity of the filter/media materials. In this case, the filter materials need to be cleaned more regularly to keep the plant functional. But if the iron concentration in the raw water is low, then iron can be added (iron pins/nails could be added with brick chips) to chamber C4 Figure 4: Demonstration of AIRP operation. Photo: Moin/DRIK. Figure 5: Arsenic removal monitoring with guava leaves. Photo: Moin/DRIK. 5

Box 1: Facts about arsenic What is arsenic? Arsenic is a metal that is soluble in water. It has no taste, colour or smell. It is highly poisonous. Where does it come from? It naturally occurs in groundwater in many parts of the world. What happens if one intakes arsenic? At high dose, a person may die instantly. At low dose, arsenic may cause chronic diseases such as skin lesions, cancer, gangrene, etc. The safe limit in water according to Bangladesh standard is 50 parts per billion (50 micrograms per litre). How do you detect arsenic in water? There are field kits available. Water may be tested by the field kits and compared against colour charts to indicate approximate arsenic concentration. How to cope with arsenic in water? The best option is to stop drinking arsenic contaminated water. One should switch to an arsenic-safe source or treat the raw water to reduce the arsenic concentration before drinking. Bangladesh House 12/B, Road 4 Dhanmondi Dhaka- 1205, Bangladesh Tel: +880 (0) 2-8650439, 9675236, 9675243 Fax: +8802 9674340 Email: practicalaction@practicalaction.org.bd Website: http://practicalaction.org/practicalanswers/ This Technical Brief was written by Shafiul Azam Ahmed for based on information from Bangladesh. October 2008. is a development charity with a difference. We know the simplest ideas can have the most profound, life-changing effect on poor people across the world. For over 40 years, we have been working closely with some of the world s poorest people - using simple technology to fight poverty and transform their lives for the better. We currently work in 15 countries in Africa, South Asia and Latin America. 6