GRID CONNECTION OF POWER GENERATING FACILITIES. FEBEG POSITION Elia WG Belgian Grid (16.09.2011)



Similar documents
Visions for the energy future. Thierry Van Craenenbroeck VREG

European Distribution System Operators for Smart Grids

Harmonisation of electricity generation transmission tariffs. A EURELECTRIC contribution to ACER s scoping exercise

Specific amendments to the Capacity Allocation and Congestion Management Network Code

European Distribution System Operators for Smart Grids

How To Integrate Renewable Energy With Smart Grids

The Legal Helpdesk. Rules on grid access and priority dispatch for renewable energy in Europe

Priority Dispatch in Real Time Operation. Marie Hayden

Competition in EU Electricity Markets The Role of Antitrust Policy

ASSET MANAGEMENT PLANNING PROCESS

JASPERS Networking Platform. Training on general State Aid issues in infrastructure projects CASE STUDY

The Status of the Wind Power Market in Egypt. Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA)

Operational Security Network Code

National Fund for Environmental Protection and Water Management. activities in climate protection

EURELECTRIC presentation. EURELECTRIC contribution to a reference model for European capacity markets. DG COMP workshop 30 June 2015

Reliability and security of electricity supply: the Italian blackout

Electricity in Egypt

PV GRID. Efficient Grid Integration of European PV: Project Results. Jörg Mayer, Managing Director German Solar Industry Association (BSW-Solar)

market design policy paper

DATA, THE GATE TO A SMART ENERGY SYSTEM - views from the electricity industry

LAW ON ELECTRICITY MARKET

Overview of the IESO-Administered Markets. IESO Training. Updated: January, Public

Legal Opinion. by EMLA

EU initiative on the Access to the EU Public Procurement markets

ECCO International, Inc. 268 Bush Street, Suite 3633 San Francisco, CA 94104

CAPACITY MECHANISMS IN EU POWER MARKETS

Mark Pearce National Grid Interconnectors Business National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA 23 June 2006

Business Plan in 2015 of Organization for Cross-regional Coordination of Transmission Operators, Japan

Code of practice for employers Avoiding unlawful discrimination while preventing illegal working

APPENDIX D MOTOR VEHICLE TRADE UNITED STATES. Appendix Party means either Japan or the United States, as the case may be;

The pivotal role of TSOs in European energy market integration

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

The participation of non-generation activities in the GB Capacity Market. Department for Energy & Climate Change

Standard conditions of the Electricity Distribution Licence

A new energy market design

OPINION OF THE EUROPEAN CENTRAL BANK. of 24 October 2008

Forward Risk-Hedging Products PC_2012_E_13

A new electricity market for Northern Ireland and Ireland from Integrated Single Electricity Market (I-SEM)

Transmission Pricing. Donald Hertzmark July 2008

Introduction to Ontario's Physical Markets

Alternative regulation and DSO business DG-GRID workshop, The Hague, 15 Nov 2006 Jaap C. Jansen models

Policy on Safety, Security, Health and Environmental Protection (SHE) in the Roche Group Edition

How To Decide If There Is A Need For Regulatory Intervention In Relation To End To End-To-End Competition In The Postal Sector

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009

Overview of points that must be included to get a useful Guidelines for. Good TPA Practice

A system for congestion management in the

4-column document Net neutrality provisions (including recitals)

European Distribution System Operators for Smart Grids. Flexibility: The role of DSOs in tomorrow s electricity market

TAHOE REGIONAL PLANNING AGENCY REQUEST FOR PROPOSAL FOR SOFTWARE CONSULTANT

Industry Example: The European Market for Electricity

European Commission Public Consultation on GENERATION ADEQUACY, CAPACITY MECHANISMS AND THE INTERNAL MARKET IN ELECTRICITY

Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium

Market Coupling: a method with implicit advantages. B. Den Ouden CEO, Amsterdam Power Exchange Spotmarket BV (APX)

European Distribution System Operators for Smart Grids. Position paper on Electric Vehicles Charging Infrastructure

COMMISSION STAFF WORKING PAPER EXECUTIVE SUMMARY OF THE IMPACT ASSESSMENT. Accompanying the document

Estate Planning and Patients' Rights in Cross-Border Healthcare

Prepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at

POLITICAL DECLARATION OF THE PENTALATERAL ENERGY FORUM

Investing in the Infrastructure for Energy Markets

FIXED-TERM AND TEMPORARY CONTRACTS

OF WESTERN BALKAN 6 ON REGIONAL ELECTRICITY MARKET DEVELOPMENT AND ESTABLISHING A FRAMEWORK FOR OTHER FUTURE COLLABORATION

COMPETITIVE ELECTRIC ENERGY MARKET IN GREECE

ENTSO-E Working Draft Network Code on Emergency and Restoration

process is usually performed with an additional SCUC and has been the natural fit for the use of wind power forecasts. Currently, however, since this

ENTSO-E Network Code on Emergency and Restoration

Potential cross-border balancing cooperation between the Belgian, Dutch and German electricity Transmission System Operators

Main variations of business models for Flexible Industrial Demand combined with Variable Renewable Energy

AGCS Gas Clearing and Settlement AG

Trade in Services Agreement Annex on Road Freight Transport

An introduction to the Sustainable Biomass Partnership

Your Power. Traction energy

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

SmartGrids SRA Summary of Priorities for SmartGrids Research Topics

REDUCTION OF BUREAUCRATIC BARRIERS FOR SUCCESSFUL PV DEPLOYMENT IN THE EU KEY RECOMMENDATIONS

Guidance produced jointly by BIS, the UK Association of Notified Bodies and. March 2014

THE ITALIAN ELECTRICITY MARKET

MSD Supply Chain Programme Strategy Workshop

Transcription:

GRID CONNECTION OF POWER GENERATING FACILITIES FEBEG POSITION Elia WG Belgian Grid ()

FEBEG 2

CONTENT Current developments General principles Integrating new power plants in the grid Grid connection procedure Firm capacity for injection Congestion management Derogations Conclusions

CURRENT DEVELOPMENTS Proposals Elia (WG Belgian Grid) for new capacity reservation procedure Proposals Elia (WG Belgian Grid) for new connection procedure Proposals in Policy Platforms VREG and CWaPE (REDI) regarding flexible access (= conditional connection)

GENERAL PRINCIPLES (1) Need for transparent and efficient procedures for nondiscriminatory connection of new power plants to the grid (art. 23,1 of EU Electricity market directive) All new generation capacity should be timely connected to the grid (art. 23,2): connection cannot be refused on the grounds of possible future limitations to available network capacities current situation in BE is not compliant connection cannot be refused on the ground that it will lead to additional costs linked with necessary capacity increase of system elements Power generators need firm commitment and predictable conditions at the moment of their investment decision

GENERAL PRINCIPLES (2) Grid operators should employ all reasonable means to timely connect all new generation capacity: at a reasonable cost at the most appropriate connection point (location, voltage, ) without imposing disproportionate or discriminatory technical or operational constraints to power generators Grid operators should proactively invest with a long term vision in order to reach this objective 1 ensure the long-term ability of the system to meet demands for transmission of electricity in a secure, reliable and efficient way contribute to security of supply through adequate transmission capacity and system reliability Solidarity and coordination between TSO and DSOs regarding grid investments and choice of most appropriate connection point for power plants 1 Art. 12 of EU Electricity Market Directive

INTEGRATING NEW POWER PLANTS IN THE GRID Investment decision Power generation development Firm grid capacity available Strategy Project planning Development Phase Specs, Licensing, RFI, RFP, Engineering Build First Firing Consultation Request Request Commitment for firm capacity Connection Agreement Connection Procedure Orienting study Detailed study Engineering Realization Connection (Congestion Management) Grid development TYND Investment planning Engineering Permitting Grid reinforcements Grid reinforcements

CONNECTION PROCURE Capacity reservation TSO should treat all applications for grid connection on a transparent and non-discriminatory manner At the moment of its investment decision (financial closing) the applicant needs firm commitment that grid capacity will be firmly available at the commissioning date Objective is to avoid grid capacity hoarding for non realistic projects and reduce interdependencies and administrative overhead for Elia and applicant: frequent in between checks based on permitting status or confirmations of requests should be avoided ad hoc intervention of Minister in individual procedures is not appropriate

CONNECTION PROCEDURE Principles Connection procedure should be transparent and efficient and based on non-discriminatory criteria: objective criteria to assess request for connection informative orienting study formal request for detailed study (leading to connection options, including conditions, timing and costs) formal & mutual acceptance of one option signing of the connection agreement start realization according to planning and payment scheme Signing of the connection agreement: firmly allocates the capacity to the applicant fixes all terms and conditions between applicant and grid operator, including arrangements if grid operator is unable to timely realize grid connection (reinforcement) or if power plant project is delayed or definitely stopped

CONNECTION PROCEDURE Agreement General terms and conditions Specific terms and conditions In case of timely realization of connection Payment In case of withdrawal connection request Possible compensation depending on phase of realization In case of untimely realization of connection Compensation In case of untimely realization grid reinforcements Congestion management

FIRM CAPACITY FOR INJECTION Flexible connection is unacceptable lack of incentives for grid investments discourages investments in generation capacity discriminatory competition distortion additional uncertainty and missed revenues for power generator NMA1: flexible connections are discriminatory because they make a distinction between existing and new connections If grid infrastructure is not sufficient to guarantee firm connection capacity: market based congestion management as temporary solution pending urgent grid investments 1 NMA decision of the 20th of May, 2009 (102690/87)

CONGESTION MANAGEMENT (1) Objective criteria to measure/predict actual/future congestion proactive investment program Structural congestion is unacceptable Occasional congestion: should also be prevented by timely investments market based congestion management can offer temporary solution Market based congestion management system with fair compensation ensures: grid operators can assess whether they compensate grid users to ramp up/down or invest in grid reinforcements a correct price which reflects scarcity or oversupply of flexibility a fair compensation incentivizes market operators to invest in flexible generation capacity or flexible demand

CONGESTION MANAGEMENT (2) System redispatch with up- and downward regulation can be implemented according to the Dutch Model: clear identification of congested zones on TSO and DSO grid voluntary and, if necessary, mandatory bidding applicable on all grid users (both generators and end users), including already connected parties no discrimination biddings for different categories of units to prioritize renewables and cogeneration fair and market based compensation net cost of congestion management system is socialized in grid fee

DEROGATIONS Derogations of these principles should be avoided: except for system security reasons existing derogations such as mutually agreed upon grid access constraints for specific connections during a limited number of hours for the maintenance of grid components, should not be considered as a precedent

CONCLUSIONS Grid operators should employ all necessary means to timely connect all new generation capacity Complexity and uncertainty in the connection procedure and agreement should be reduced Grid capacity for injection needs to be firm Structural congestion must be avoided by timely investments Occasional congestion should also be prevented by grid reinforcements or managed with a market based congestion management system with fair compensation