1 TRANSLATION Narodne novine Official Gazette of the Republic of Croatia issue no. 68 of 27 July 2001 page 2179 Pursuant to Article 88 of the Constitution of the Republic of Croatia, herewith I pass the D E C I S I O N ON PROMULGATION OF THE LAW ON ELECTRICITY MARKET I promulgate the Law on Electricity Market passed by the Croatian Parliament on its session held on 19 July Ref. No /2 Zagreb, 24 July 2001 President of the Republic of Croatia Stjepan Mesi (signed) LAW ON ELECTRICITY MARKET I. GENERAL PROVISIONS Article 1 This Law shall regulate the following activities of the energy sector: power generation, transmission, distribution, retail supply, operation and control of the electricity system and organization of the electricity market. Article 2 (1) The terms used in this Law shall have the meaning stipulated in the Energy Law. (2) Other terms used in this Law shall have the following meaning: 1. System Operator - the energy undertaking that operates and controls the electricity system 2. Market Operator the energy undertaking that carries out activities related to organization of the electricity market. 1
2 Article 3 (1) Energy activities: power generation and supply of electricity to eligible customers shall be carried out in compliance with the rules that regulate market relations and according to which energy undertakings negotiate freely the quantity and price of delivered electricity by concluding short-term or long-term contracts or directly within the organized market. (2) Energy activities: power generation for tariff (captive) customers, power transmission and distribution, supply of electricity to tariff customers, operation and control of the electricity system and organization of the electricity market shall be carried out as public services. II. CARRYING OUT ENERGY ACTIVITIES Article 4 (1) Plants, facilities and networks used for power generation, transmission and distribution can be constructed by energy undertakings that have licences for carrying out energy activities, under conditions prescribed by the Law on Construction and special technical and safety criteria and criteria related to environmental protection, that are stipulated in special regulations. (2) Energy undertakings produce electricity in facilities that are constructed and put into operation pursuant to the provisions of the Energy Law, the Law on Construction and other regulations. Article 5 (1) Costs of connection of new energy undertakings and customers to the network as well as costs related to the transmission or distribution network that may arise as a result of such connection, shall be borne by the applicant for connection to network and by other network users that may benefit from such connection, in accordance with Grid Code. (2) Conditions and the manner of calculating connecting costs and their distribution on users that benefit from such connection shall be regulated by the Rules to be passed by the Minister. (3) Cadastral data for the electricity network needed for the connection of a new user shall be made available to energy undertakings and customers upon request. Article 6 The Market Operator, System Operator, the energy undertaking engaged in power transmission and the energy undertaking engaged in power distribution shall be obliged to keep confidential data and information received from other energy undertakings if such data are private and confidential, unless they are not entitled or obliged to make them public or to submit them to the relevant government bodies. 2
3 A. Power generation Article 7 (1) A power generator is entitled to: - use energy sources it finds most convenient for the production of required electricity, provided it complies with technical requirements and criteria related to environmental protection as they are stipulated in the licence and relevant regulations, - conclude contracts for the sale of electricity under conditions prescribed by this Law and other regulations, - have access to transmission and distribution network. (2) A power generator is obliged to: - comply with conditions stipulated in the licence for carrying out energy activity, - possess adequate measuring devices for the measurement of electricity that enters the respective network, - comply with the rules prescribed by the Market Operator, - comply with the regulations related to environmental protection. (3) Power generation plants must meet prescribed environmental protection criteria and ensure permanent control of impact on environment. (4) Power generators, owners of power generation plants, shall pay effective dues to local government on whose territory the plant is located. The Croatian Government shall prescribe the amount of such dues and the manner of their allocation. Article 8 (1) Energy co-generators that produce electricity and heat in a single plant and that use waste or renewable energy resources in an economically viable way and in compliance with environmental protection measures, can gain the status of eligible (preferential) producer. (2) Energy co-generators from point (1) above shall gain the status of eligible producer on the basis of a decision to be issued by the Energy Regulatory Council in accordance with criteria prescribed by the Minister. Article 9 (1) An energy undertaking may make the decision on the construction of plants for power generation for eligible customers at its own discretion, provided it has a licence for carrying out power generation activities. (2) An energy undertaking may construct plants for power generation for tariff customers upon public tendering and approval issued by the Energy Regulatory Council. 3
4 (3) The Terms of Reference for the tenders from point (2) above shall contain the following: - the location where the plant is to be constructed, - the type of primary energy source to be used for power generation, - the manner and conditions of power generation and taking, - conditions to be met after cessation of plant s operation, - conditions related to environmental protection and health and safety of citizens, - the required energy efficiency level, - conditions for the use of common and public goods. (4) The Energy Regulatory Council shall issue the approval for the construction of power generation plant that will supply electricity to tariff customers, to a power generator who meets the requirements prescribed in the tender and who offers the lowest price of produced electricity. (5) The Energy Regulatory Council shall inform in writing the undertakings whose tender was not accepted about the reasons of refusal and shall furnish them a copy of the licence issued to the most successful tenderer. (6) Energy operators from point (5) above can form an appeal against the Energy Regulatory Council s decision before the Ministry. B. Transmission and distribution of electricity Article 10 (1) The energy undertaking carrying out transmission of electricity shall be responsible for the construction, operation and maintenance of the transmission network, and the generation of a portion of reactive power. (2) The energy undertaking carrying out transmission of electricity shall ensure third party access to the transmission system in compliance with the Rules as laid out in Article 5, point (2) hereof. Article 11 (1) The energy undertaking carrying out distribution of electricity shall be responsible for the development, construction, operation and maintenance of the distribution network. (2) The energy undertaking carrying out distribution of electricity shall: - guarantee reliability of the operation of distribution network and shall maintain electricity quality parameters at the prescribed level, - coordinate operation of the distribution network with operation of the transmission network, interconnection lines and users facilities, - submit information to System Operator and Market Operator about its future electricity needs, - ensure third party access to distribution network in accordance with prescribed criteria. 4
5 Article 12 (1) The System Operator shall prepare plans for the development and construction of transmission network for a 3-year period, in cooperation with the energy operator carrying out electricity transmission and subject to the prior approval of the Energy Regulatory Council. (2) The energy undertaking carrying out distribution of electricity shall prepare plans for the development and construction of the distribution network for a 3-year period subject to prior approval of the Energy Regulatory Council. (3) Plans from points (1) and (2) above shall comply with the Energy Strategy and the Energy Strategy Implementation Program. (4) The Energy Regulatory Council shall set electricity transmission fees and distribution fees upon the proposal of the energy undertaking carrying out transmission or distribution of electricity, respectively. (5) The energy undertaking carrying out distribution of electricity shall not disclose to any third party any confidential information of energy undertakings and customers, unless specific regulations prescribe that certain data should be made public or should be disclosed to the relevant government bodies. (6) The electricity transmission fee and distribution fee will be set on the basis of network development and construction plans from points (1) and (2) of this Article. Article 13 (1) The System Operator and/or energy undertaking carrying out electricity distribution shall be obliged to allow access to the distribution network to power generators and eligible customers on non-discriminatory basis, based on the principle of regulated third party access. (2) Prior to submitting an application for access to the network, a power generator must make sure that it complies with the technical requirements specified in Article 16, point (2) hereof. (3) An eligible customer shall obtain approval for access to the network from the System Operator. (4) The data on availability of access to and use of electricity transmission and distribution networks shall be public. Article 14 (1) The System Operator and/or energy undertaking carrying out electricity distribution may refuse access to the distribution network due to technical or operational constraints. The 5
6 refused power generators or eligible customers shall be informed about the reasons of refusal, which must be substantiated and submitted in written form. (2) Power generators or eligible customers who have been refused access to the network or have objections concerning terms and conditions of access, may appeal to the Energy Regulatory Council. The award of the Energy Regulatory Council shall be final. After that the party may appeal against such final award before the Administrative Court. Article 15 When a power generator and a customer intend to conclude a contract on electricity delivery and/or supply, and cannot obtain access to the network, they can construct a direct line, subject to the Energy Regulatory Council s approval. Article 16 (1) Operation and management of the electricity transmission and distribution networks shall be regulated by the Grid Code. (2) The Grid Code shall specifically regulate: - technical and other criteria for access to the network, - technical and other criteria for safe operation of the electric energy system that can ensure reliable supply of the market with quality electricity, - procedures to be applied for system operation in emergency situations, - technical and other criteria for interconnection and operation of networks. (3) Grid Code shall be drafted by the System Operator in cooperation with energy operators carrying out electricity transmission and distribution. The Grid Code shall be passed by the Minister subject to the prior opinion of the Energy Regulatory Council. C. Retail supply of electricity Article 17 (1) Retail supply of electricity is the energy activity of electricity delivery and/or sale and it is an independent activity in respect to electricity transmission and distribution, and it refers to processing of billing elements related to delivery of electricity, billing of consumed electricity, billing of customers and collecting payments for each consumption site. (2) Every energy undertaking can carry out retail supply of electricity to eligible customers provided it obtains a licence for carrying out electricity supply services. (3) An energy undertaking holding a licence for carrying out public services may provide electricity retail supply services to tariff customers upon obtaining the relevant licence for carrying out this activity. 6
7 (4) The Croatian Government shall prescribe the minimum share of renewable energy resources, excluding large hydro plants (exceeding 5 MW), to be used by an energy undertaking carrying out electricity supply activities as a public service. Article 18 (1) Supply of electricity to eligible customers is the activity where eligible customers and electricity suppliers freely negotiate the quantity and price of electricity that is the subject of delivery. (2) Electricity suppliers and eligible customers shall submit the contracts from point (1) of this Article, as well as the contracts concluded with the electricity transmission undertaking and/or distributor to the Market Operator. D. Operation and control of electricity system Article 19 (1) The System Operator shall guarantee regular and reliable supply of electricity and proper coordination of the power generation, transmission and distribution systems. (2) The System Operator shall ensure proper coordination of transmission network operation with the operation of neighbouring transmission networks. (3) The System Operator must be independent in consideration to power generation and supply, and must carry out its function in cooperation with Market Operator based on the principles of transparency and non-discrimination. (4) The System Operator may not be engaged in electricity trading activities. (5) The System Operator may dispatch power generation plants intended for temporary use only in following cases: - in case of serious disturbances or failures of the system, - in case of crises as defined in Energy Law. Article 20 (1) The System Operator shall be responsible for: - operation and control of the electricity system, - ensuring access to third parties on the basis of regulated access - cooperation with energy undertakings carrying out transmission and distribution of electricity concerning determination and allocation of transmission costs, - providing services of the electricity system, - balancing supply and demand for electricity with respect to contracted quantities on the organized market, and issuing approvals for feasibility of short-term and long-term schedules, 7
8 - providing information on electricity demand movements in cooperation with the Market Operator and other information required by the Energy Regulatory Council, - providing necessary instructions for proper operation of power generation and transmission systems in compliance with the criteria related to reliability and security in line with Grid Code, and management of ancillary services market, - providing information to power generators on generation scheduling and dispatch and available capacity requirements for each period. (2) The System Operator shall inform the Energy Regulatory Council about the complaints referring to its operation and about the resolution of such complaints. E. Organization of electricity market Article 21 (1) The Market Operator shall be responsible for the organization of the electricity market. (2) The Market Operator shall be responsible for the economic viability of the electricity system and the management of purchasing and sale of electricity in accordance with the conditions determined by the law. (3) The Market Operator shall carry out its assignments by respecting the principles of transparency, objectivity and non-discrimination, under the supervision of the Energy Regulatory Council. Article 22 (1) The Market Operator shall be responsible for: - recording all contract obligations among energy undertakings active in the energy market, - collecting tenders and selecting the most successful tenders for meeting the demand for electricity in a specific period up to the moment when the demand is met, by ranking the tenders according to offered prices, - submitting reports to energy undertakings and the System Operator about the results of evaluation of received tenders, planning of access to the network on the basis of tender evaluation and prices of the remaining portion of offered electricity, - receiving feedback from the System Operator regarding necessary harmonization in consideration of technical possibilities and in cases of extraordinary situations in the transmission or distribution network, - fixing final prices of electricity for specific time periods and informing energy undertakings participating in the market accordingly, - establishing the billing system for electricity according to the determined final price, - making public prices of electricity for the time period to be determined by the Energy Regulatory Council, - keeping records on eligible customers. (2) In selecting the most successful tenders, the System Operator shall give preference to: 8
9 - eligible producers, - producers that use domestically produced feedstock for power generation in an amount not exceeding 15% of total feedstock consumption within a calendar year, according to the Croatian Energy Balance. (3) The Marker Operator shall ensure the purchase of total produced electricity volumes from eligible producers under at least equal conditions currently effective on the organized market. (4) The Market Operator shall publish the Rules of Electricity Market Organization subject to prior approval by the Energy Regulatory Council. III. ELIGIBLE CUSTOMER Article 23 (1) An eligible customer can freely choose its electricity supplier. (2) Supply of electricity for eligible customers can be ensured from import by mediation of a market agent or broker or from domestic sources. (3) On the date of this Law coming into effect all customers with annual consumption exceeding 40 GWh shall gain the status of eligible customer. (4) The Croatian Government may prescribe a lower consumption level from point (3) above for gaining the status of eligible customer. (5) Eligible customer shall not lose the status of eligible customer until it maintains its consumption at the level upon which it was granted the status of eligible customer. IV. TARIFF CUSTOMERS Article 24 (1 ) Tariff customers shall have electricity supplied under the provision of public service obligation according to prices set in the electricity tariff system. (2) The Market Operator shall ensure supply of electricity to tariff customers from: - eligible producers - generation plants that have contracts for the supply of electricity pursuant to public service obligation, and - the electricity market. (3) The Croatian Government may, within the scope of a special economic or social program, set discounted electricity prices, in the area of generation, for specific categories of tariff customers. 9
10 V. RECIPROCITY PRINCIPLE Article 25 The System Operator may, upon the proposal of a power generator or the Ministry, refuse access to the electricity system to a power generator from a State where the level of opening of electricity market is lower than in the Republic of Croatia. VI. TRANSIT Article 26 (1) When international agreements signed by the Republic of Croatia impose a commitment, the System Operator is obliged to carry out the transit of electricity through the transmission network under terms and conditions stipulated in these agreements. (2) Access to the transmission system for carrying out the transit of electricity shall be regulated by provisions referring to access to eligible customers. VII. SUPERVISION Article 27 (1) The administrative control over implementation of this Law and regulations passed on the basis of this Law shall be carried out by the Ministry. (2) The inspection control over implementation of this Law shall be carried out by the State Inspectorate. VIII. PENALTY PROVISIONS Article 28 (1) A cash fine ranging from HRK 10, to 50, shall be imposed on an energy undertaking that: - fails to maintain the transmission network (Article 10, point (1)), - fails to proceed in accordance with Article 10, point (2) hereof, - fails to maintain the distribution network (Article 11, point (1)), - fails to proceed according to Article 11, point (2) hereof, - fails to prepare plans for development and construction (Article 12, point (1)), - does not prepare development and construction plans in compliance with the Energy Strategy and Strategy Implementation Program (Article 12, point (3)), - refuses access to the network contrary to Article 13 or Article 14 hereof, - starts construction of direct line without prior approval of the Energy Regulatory Council (Article 15), - does not apply the Grid Code (Article 16), - provides electricity to eligible customers without prior approval of the Energy Regulatory Council (Article 17, point (2)), 10
11 - fails to submit contracts on electricity supply to the Market Operator (Article 18, point (2)), - dispatches power generation plants contrary to Article 19, point (5) hereof, - fails to submit reports about complaints on its work and their resolution to the Energy Regulatory Council (Article 20, point (2)), - during selection of tenders fails to proceed in compliance with Article 22, point (2) hereof, - fails to ensure purchase of electricity generated by eligible producers under equal terms (Article 22, point (3)), - publishes the Rules of Electricity Market Organization without approval issued by Energy Regulatory Council. (2) A cash fine ranging from HRK 2, to 10, shall be imposed on a responsible official of energy undertaking for offences laid out in point (1) above. (4) In addition to a fine penalty, in case of several breaches or repeated offences as laid out in point (1) of this Article within one year, the energy undertaking may be sanctioned by suspension from carrying out the same activities up to one year, and the responsible person may be barred from carrying out the same activities for a period up to one year. IX. TRANSITIONAL AND FINAL PROVISIONS Article 29 (1) From the date of the application of this Law, Hrvatska Elektroprivreda d.d. (Croatian Electricity Company) shall continue with carrying out its activities as public services, i.e. as the electricity utility in the Republic of Croatia. (2) Pursuant to the provision from point (1) above, Hrvatska Elektroprivreda d.d. shall carry out the following activities: - generation of electricity for tariff customers, - transmission of electricity, - distribution of electricity, - supply of electricity to tariff customers, - operation and control of the electricity system, - organization of the electricity market. (3) Hrvatska elektroprivreda d.d. is obliged to bring its organizational structure in compliance with the provisions of Energy Law and provisions of this Law in the way that individual activities are carried out by related legally independent companies (HEP Group) within 6 months from the date of the application of this Law. (4) The legal entities within HEP Group shall obtain licences for carrying out their respective activities from the Energy Regulatory Council within the period stipulated in point (3) above. (5) Hrvatska elektroprivreda d.d. shall found the share-based company that will operate the Croatian electricity system and organization of electricity market up to the date of this Law application, pending the approval of the Croatian Government. 11
12 (6) Hrvatska elektroprivreda d.d. shall within 12 months from the date of founding of the company pursuant to point (5) of this Article, transfer the shares, i.e. interests in this company to the Republic of Croatia. Article 30 The Law on Electricity Company (Zakon o elektroprivredi) published in Official Gazette issues 31/90, 47/90, 61/91, 26/93, 78/94, 105/99, 111/99 and 51/01 shall cease to be in effect beginning with the date of application of this Law. Article 31 This Law shall come into effect on the eighth day from its publication in Narodne novine and its implementation shall start from 1 January Class: /01-01/02 Zagreb, 19 July CROATIAN PARLIAMENT Chairman of the Parliament Zlatko Tomi (signed) 12
REPORT On the work of the Croatian Energy Regulatory Agency For the year 2005
Republic of Croatia Croatian Energy Regulatory Agency REPORT On the work of the Croatian Energy Regulatory Agency For the year 2005 Zagreb, July 2006 Croatian Energy Regulatory Agency CONTENT A. REPORT
NATIONAL PAYMENT SYSTEM ACT
(official gazette Narodne novine, No. 117/2001) NATIONAL PAYMENT SYSTEM ACT I GENERAL PROVISIONS Article 1 This Act shall regulate the functioning of the national payment system. Article 2 "Payment system"
CROATIAN PARLIAMENT 1364
CROATIAN PARLIAMENT 1364 Pursuant to Article 88 of the Constitution of the Republic of Croatia, I hereby pass the DECISION PROMULGATING THE ACT ON PERSONAL DATA PROTECTION I hereby promulgate the Act on
2 SUMMARY AND MORE SIGNIFICANT EVENTS IN
Table of contents 1 INTRODUCTION 5 2 SUMMARY AND MORE SIGNIFICANT EVENTS IN 2009 6 2.1 An overview of the basic organizational scheme and authorities in the Agency 7 2.2 More significant events on the
CROATIAN PARLIAMENT 242
Important Disclaimer The English language text below has been provided by the Translation Centre of the Ministry for European Integration for information only; it confers no rights and imposes no obligations
DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT. No. Dated: October, 2009 NOTIFICATION (DRAFT)
DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT No. Dated: October, 2009 NOTIFICATION (DRAFT) In exercise of powers conferred under sections 61, 66,
L A W ОN FOREIGN EXCHANGE OPERATIONS
L A W ОN FOREIGN EXCHANGE OPERATIONS This Law shall govern: I GENERAL PROVISIONS Article 1 1) payments, collections and transfers between residents and nonresidents in foreign means of payment and dinars;
LEGISLATION COMMITTEE OF THE CROATIAN PARLIAMENT
LEGISLATION COMMITTEE OF THE CROATIAN PARLIAMENT 2300 Pursuant to its authority from Article 59 of the Rules of Procedure of the Croatian Parliament, the Legislation Committee determined the revised text
DELHI ELECTRICITY REGULATORY COMMISSION
DELHI ELECTRICITY REGULATORY COMMISSION DELHI ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION AND RENEWABLE ENERGY CERTIFICATE FRAMEWORK IMPLEMENTATION) REGULATIONS, 2011 No. Dated:. NOTIFICATION
LAW ON PROVIDING FAST MONEY TRANSFER SERVICES (unofficial fair copy) 1 I. GENERAL PROVISIONS
LAW ON PROVIDING FAST MONEY TRANSFER SERVICES (unofficial fair copy) 1 I. GENERAL PROVISIONS Article 1 This Law shall regulate the manner and the terms and conditions for providing fast money transfer
RULE ON LICENSING OF ENERGY ACTIVITIES IN KOSOVO
ZYRA E RREGULLATORIT PËR ENERGJI ENERGY REGULATORY OFFICE REGULATORNI URED ZA ENERGIJU RULE ON LICENSING OF ENERGY ACTIVITIES IN KOSOVO Prishtinë, 29 August 2011 _ Tel: 038 247 615 lok.. 101, Fax: 038
UNMIK REGULATION NO. 2003/37 ON THE PROMULGATION OF THE LAW ON POSTAL SERVICES ADOPTED BY THE ASSEMBLY OF KOSOVO
UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/REG/2003/37 17 December 2003 REGULATION
Japan. Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi
Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi 1 Policy and law What is the government policy and legislative framework for the electricity sector? The electricity sector in is governed by the
Merchants and Trade - Act No 28/2001 on electronic signatures
This is an official translation. The original Icelandic text published in the Law Gazette is the authoritative text. Merchants and Trade - Act No 28/2001 on electronic signatures Chapter I Objectives and
CREDIT REPORTING BILL EXPLANATORY NOTES
CREDIT REPORTING BILL EXPLANATORY NOTES INTRODUCTION These explanatory notes are intended as a guide to the proposed new Act. They are not meant as a substitute for a careful reading of the Bill itself.
ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S
Hamdi Mramori Street, No 1 Prishtina 10000 Kosovo Tel: +381 (0) 38 247 615 ext. 103 Fax: +381 (0) 38 247 620 e-mail: [email protected] www.ero-ks.org ELECTRICITY SUPPLY/ TRADE LICENSE GRANTED TO: KORLEA
Arrangement of Clauses
REGULATION NO: NERC-R-0108 NIGERIAN ELECTRICITY REGULATORY COMMISSION In exercise of the Powers to make Regulations conferred by Section 96(1) of the Electric Power Sector Reform Act 2005 (Act No.6 of
The Electronic Transactions Law Chapter I Title and Definition
The Union of Myanmar The State Peace and Development Council The Electronic Transactions Law ( The State Peace and Development Council Law No. 5/2004 ) The 12th Waxing of Kason 1366 M.E. (30th April, 2004)
DECISION on the Croatian Large Value Payment System and on the Settlement in Bank Accounts Held with the Croatian National Bank.
Pursuant to Article 38 paragraph 3 under m) of the Croatian National Bank Act (official gazette Narodne novine, No. 36/2001) and Article 44 paragraph 1 items 7 and 8 of the National Payment System Act
Consolidated Insurance Mediation Act 1
Consolidated Insurance Mediation Act 1 Act no. 930 of 18 September 2008 This is an Act to consolidate the Insurance Meditation Act, cf. Consolidated Act no. 401 of 25 April 2007, as amended by section
CONTENT OF THE AUDIT LAW
CONTENT OF THE AUDIT LAW I. GENERAL PROVISIONS Article 1 This Law shall regulate the conditions for conducting an audit of legal entities which perform activities, seated in the Republic of Macedonia.
LAW FOR THE ELECTRONIC DOCUMENT AND ELECTRONIC SIGNATURE. Chapter two. ELECTRONIC DOCUMENT AND ELECTRONIC SIGNATURE
LAW FOR THE ELECTRONIC DOCUMENT AND ELECTRONIC SIGNATURE Prom. SG. 34/6 Apr 2001, amend. SG. 112/29 Dec 2001, amend. SG. 30/11 Apr 2006, amend. SG. 34/25 Apr 2006, amend. SG. 38/11 May 2007 Chapter one.
ACT ON LIABILITY FOR NUCLEAR DAMAGE
ACT ON LIABILITY FOR NUCLEAR DAMAGE Published in the Official Gazette of the Republic of Slovenia - International Treaties, No. 77/2010 UNOFFICIAL TRANSLATION I. GENERAL PROVISIONS Article 1 (Contents)
It is hereby notified that the President has assented to the following Act which is hereby published for general information:-
PRESIDENT'S OFFICE No. 967. 14 June 1996 NO. 29 OF 1996: MINE HEALTH AND SAFETY ACT, 1996. It is hereby notified that the President has assented to the following Act which is hereby published for general
DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT NOTIFICATION
DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT No. Dated: -12-2011 NOTIFICATION In exercise of powers conferred under sections 61, 66, 86(1)(e)
LAW FOR THE ELECTRONIC DOCUMENT AND ELECTRONIC SIGNATURE
LAW FOR THE ELECTRONIC DOCUMENT AND ELECTRONIC SIGNATURE Prom. SG. 34/6 Apr 2001, amend. SG. 112/29 Dec 2001, amend. SG. 30/11 Apr 2006, amend. SG. 34/25 Apr 2006, amend. SG. 38/11 May 2007, amend. SG.
Act on the Supervision of Financial Institutions etc. (Financial Supervision Act)
FINANSTILSYNET Norway Translation update January 2013 This translation is for information purposes only. Legal authenticity remains with the official Norwegian version as published in Norsk Lovtidend.
(28 February 2014 to date) CREDIT RATING SERVICES ACT 24 OF 2012
(28 February 2014 to date) [This is the current version and applies as from 28 February 2014, i.e. the date of commencement of the Financial Services Laws General Amendment Act 45 of 2013 to date] CREDIT
Players Agent Registration Regulations
Players Agent Registration Regulations 1 Definitions 1.1 In these, the following terms shall have the following meanings: Agency Activity means acting in any way and at any time in the capacity of agent,
ARTICLES OF INCORPORATION OF RAIFFEISEN VOLUNTARY PENSION FUND
In accordance with the Mandatory Pension Funds Act (Official gazette no. 19/2014, hereinafter: Act), the Management of Raiffeisen društvo za upravljanje obveznim i dobrovoljnim mirovinskim fondovima d.d.,
2. Definitions of Terms
PUBLIC DEBT LAW I. GENERAL PROVISIONS 1. Subject of the Law Article 1 This Law regulates conditions, manner and procedure under which the Republic of Serbia (hereinafter referred to as: the Republic) may
Act on the Supervision of Credit Institutions, Insurance Companies and Securities Trading etc. (Financial Supervision Act)
KREDITTILSYNET Norway Translation updated August 2003 Translated by Government Authorised Translator Peter Thomas This translation is for information purposes only. Legal authenticity remains with the
7. LAW ON LOCAL SELF-GOVERNMENT FINANCING. Pursuant to Article 88 item 2 of the Constitution of the Republic of Montenegro, I hereby issue the
Pursuant to Article 88 item 2 of the Constitution of the Republic of Montenegro, I hereby issue the Decree Promulgating the Law on Local Self-Government Financing (Official Gazette of the Republic of Montenegro
GUIDELINES FOR THE ADMINISTRATION OF INSURANCE AGENTS - 2010
GUIDELINES FOR THE ADMINISTRATION OF INSURANCE AGENTS - 2010 PART I - PRELIMINARY Purpose and Authorisation 1. These Guidelines are intended to provide the framework and procedure for the licencing and
LAW ON FOREIGN CURRENT AND CAPITAL OPERATIONS I BASIC PROVISIONS
Law on Foreign Current and Capital Operations In accordance with Article 88 Item 2 of the Constitution of the Republic of Montenegro I hereby pass the ENACTMENT ON PROCLAMATION OF THE LAW ON FOREIGN CURRENT
1.2 This license shall be subject to the provisions herein stated, the Telecommunications Law and any regulations issued thereunder.
FORM OF INDIVIDUAL LICENSE FOR INTERNATIONAL TELECOMMUNICATIONS SERVICES TO BE GRANTED TO THE BAHRAIN TELECOMMUNICATIONS COMPANY B.S.C. BY THE TELECOMMUNICATIONS REGULATORY AUTHORITY 1. GRANT OF LICENSE
Pursuant to Article 88 item 2 of the Constitution of the Republic of Montenegro I hereby issue the
Pursuant to Article 88 item 2 of the Constitution of the Republic of Montenegro I hereby issue the DECREE PROMULGATING THE LAW ON FOREIGN CURRENT AND CAPITAL TRANSACTIONS (Official Gazette of Montenegro
Financial Services (Collective Investment Schemes) FINANCIAL SERVICES (EXPERIENCED INVESTOR FUNDS) REGULATIONS 2012
Financial Services (Collective Investment Schemes) 2005-48 Legislation made under s. 52. FINANCIAL SERVICES (EXPERIENCED INVESTOR FUNDS) (LN. ) Commencement 12.4.2012 Amending enactments Relevant current
ORDER to promulgate the Act on Prevention of Late Payment (ZPreZP)
Legal notice All effort has been made to ensure the accuracy of this translation, which is based on the original Slovenian text. All translations of this kind may, nevertheless, be subject to a certain
BERMUDA PRIVATE INVESTIGATORS AND SECURITY GUARDS ACT 1974 1974 : 78
QUO FA T A F U E R N T BERMUDA PRIVATE INVESTIGATORS AND SECURITY GUARDS ACT 1974 1974 : 78 TABLE OF CONTENTS 1 2 3 4 4A 5 6 6A 7 8 9 9A 10 11 12 13 14 15 16 17 18 Interpretation Application of the Act
English Translation of Finance Companies Control Law
English Translation of Finance Companies Control Law Article 1 Introductory Chapter Definitions The following terms and phrases wherever mentioned in this Law shall have the meanings assigned thereto unless
Electricity in Egypt
T: (+20) 2 3760 4592 F: (+20) 2 3760 4593 A: 16 Hussein Wassef Street, Messaha Square Dokki, Giza, Egypt 12311 www.ide.com.eg Electricity in Egypt Policy and Regulatory Reform November 2015 Electricity
The Electricity Supply Bill 1
Bill no. 234 Folketinget (Danish Parliament) 1998-99 Unauthorised translation 30 June 1999 Submitted on 29 April 1999 by the Minister for Environment and Energy (Svend Auken) Adopted by Folketinget on
Reform of the Grenada Electricity Sector
Reform of the Grenada Electricity Sector Presentation of the Draft Electricity Supply Act, 2015 Bill and the Draft Public Utilities Regulatory Commission Act Bill By: Janis H. Brennan, Consultant Reform
LAW OF UKRAINE On the natural gas market This Law defines legal fundamentals of the functioning of the natural gas market in Ukraine founded on
LAW OF UKRAINE On the natural gas market This Law defines legal fundamentals of the functioning of the natural gas market in Ukraine founded on principles of free competition, due protection of consumers
ELECTRICITY MARKET ACT
1 NB: Unofficial translation Ministry of Trade and Industry, Finland ELECTRICITY MARKET ACT (386/1995; amendments up to 1172/2004 included) In accordance with a decision by Parliament, the following is
LAW ON FOREIGN EXCHANGE OPERATIONS OF FEDERATION OF BOSNIA AND HERZEGOVINA
The translation of BiH legislation has no legal force and should be used solely for informational purposes. Only legislation published in the Official Gazettes in BiH is legally binding. LAW ON FOREIGN
European best practice regarding to the licensing in the energy sector
99333 EU- INOGATE programme, project Support to Energy Market Integration and Sustainable Energy in the NIS (SEMISE) European best practice regarding to the licensing in the energy sector The content of
ON FIRE PROTECTION LAW ON FIRE PROTECTION CHAPTER I GENERAL PROVISIONS
Republika e Kosovës Republika Kosovo - Republic of Kosovo Kuvendi - Skupština - Assembly Law No. 04/L-012 ON FIRE PROTECTION Assembly of Republic of Kosovo; Based on Article 65 (1) of the Constitution
CREDIT RATING SERVICES BILL
REPUBLIC OF SOUTH AFRICA CREDIT RATING SERVICES BILL (As introduced in the National Assembly (proposed section 7); explanatory summary of Bill published in Government Gazette No. 22 of 7 February 12) (The
The Mortgage Brokerages and Mortgage Administrators Regulations
1 AND MORTGAGE ADMINISTRATORS M-20.1 REG 1 The Mortgage Brokerages and Mortgage Administrators Regulations being Chapter M-20.1 Reg 1 (effective October 1, 2010) as amended by Saskatchewan Regulations,
GEORGIAN LAW ON ELECTRICITY AND NATURAL GAS
GEORGIAN LAW ON ELECTRICITY AND NATURAL GAS CHAPTER 1. GENERAL PROVISIONS Article 1. Objectives and Purposes of the Law 1. This law shall regulate relations and activities of Sole entrepreneurs, Physical
ACT ON THE CHAMBER OF ARCHITECTS AND CHAMBERS OF ENGINEERS IN CONSTRCUTION AND PHYSICAL PLANNING I. GENERAL PROVISIONS
ACT ON THE CHAMBER OF ARCHITECTS AND CHAMBERS OF ENGINEERS IN CONSTRCUTION AND PHYSICAL PLANNING I. GENERAL PROVISIONS Article 1 (1) This Act regulates the basic structure, area of competence, public authorities
Personal Data Protection Bill
Bill No. /12. Personal Data Protection Bill Read the first time on 12. Section PERSONAL DATA PROTECTION ACT 12 1. Short title and commencement 2. Interpretation 3. Purpose 4. Application of Act (No. 12)
GOVERNMENT NOTICE NO. 416 published on 28/12/2012 ARRANGEMENT OF SECTIONS THE BANK OF TANZANIA (CREDIT REFERENCE BUREAU) REGULATIONS, 2012
GOVERNMENT NOTICE NO. 416 published on 28/12/2012 THE BANK OF TANZANIA (CREDIT REFERENCE BUREAU) REGULATIONS, 2012 ARRANGEMENT OF SECTIONS PART I PRELIMINARY PROVISIONS Section Title 1.Citation 2. Application
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY / RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012
Guide for Authorised Taxi-cab. Network Providers and Taxi-cab. Network Services Standards for the. Sydney Metropolitan, Newcastle
Guide for Authorised Taxi-cab Network Providers and Taxi-cab Network Services Standards for the Sydney Metropolitan, Newcastle and Wollongong Transport Districts and the Local Government Areas of Gosford
THE TURKISH RENEWABLE ENERGY LAW: STILL HUNGRY I. INTRODUCTION
THE TURKISH RENEWABLE ENERGY LAW: STILL HUNGRY By Mehtap Yildirim Öztürk and Çagdas Evrim Ergün ε Turkey has recently enacted its first renewable energy law, namely Law No. 5346 Concerning the Use of Renewable
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under
Personal Data Protection LAWS OF MALAYSIA. Act 709 PERSONAL DATA PROTECTION ACT 2010
1 LAWS OF MALAYSIA Act 709 PERSONAL DATA PROTECTION ACT 2010 2 Laws of Malaysia ACT 709 Date of Royal Assent...... 2 June 2010 Date of publication in the Gazette......... 10 June 2010 Publisher s Copyright
MONEY TRANSFER AGENCIES (LICENSING) ACT 2009
I,.j ACT No. 20 of 2009 MONEY TRANSFER AGENCIES (LICENSING) ACT 2009 ARRANGEMENT OF SECTIONS SECTION 1. Short title and commencement. 2. Interpretation. 3. Application for licence. 4. Grant of licence.
THE PRIVATE SECURITY SERVICE BILL (No. VI of 2004) Explanatory Memorandum
THE PRIVATE SECURITY SERVICE BILL (No. VI of 2004) Explanatory Memorandum The object of this Bill is to provide for the licensing of private security services, the registration of security guards, the
THIRD SUPPLEMENT TO THE GIBRALTAR GAZETTE No. 4,167 of 7th May, 2015
THIRD SUPPLEMENT TO THE GIBRALTAR GAZETTE No. 4,167 of 7th May, 2015 B. 13/15 Clause PRIVATE TRUST COMPANIES BILL 2015 1. Short title and commencement. 2. Interpretation. 3. Registration of Private Trust
Law on the Deposit Insurance Agency (Official Gazette of the Republic of Serbia, No. 14/2015) (Unofficial Translation)
Law on the Deposit Insurance Agency (Official Gazette of the Republic of Serbia, No. 14/2015) (Unofficial Translation) I. GENERAL PROVISIONS Article 1 This Law governs the status, organization, powers
THE CROATIAN PARLIAMENT. Pursuant to Article 88 of the Constitution of the Republic of Croatia, I hereby issue the DECISION
THE CROATIAN PARLIAMENT Pursuant to Article 88 of the Constitution of the Republic of Croatia, I hereby issue the 2729 DECISION ON PROMULGATING THE SECURITY VETTING ACT I hereby promulgate the Security
REPUBLIC OF TRINIDAD AND TOBAGO. Act No. 16 of 2004
Legal Supplement Part A to the Trinidad and Tobago Gazette, Vol. 43, No. 102, 17th June, 2004 Legal Supplement Part A to the Trinidad and Tobago Second Session Eighth Parliament Republic of Trinidad and
NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE
NORTHERN TERRITORY ELECTRICITY RING-FENCING CODE JULY 2001 Table of Provisions Clause Page 1. Authority...2 2. Application...2 3. Objectives...2 4. Ring-Fencing Minimum Obligations...2 5. Compliance with
LAW ON FOREIGN CURRENCY TRANSACTIONS. ( Official Herald of the Republic of Serbia, Nos. 62/2006 and 31/2011) I GENERAL PROVISIONS
LAW ON FOREIGN CURRENCY TRANSACTIONS ( Official Herald of the Republic of Serbia, Nos. 62/2006 and 31/2011) The present Law shall govern: I GENERAL PROVISIONS Article 1 1) payments, collections and transfers
How To Regulate The Gas Sector
LAW N 2002/013 OF 30 DECEMBER 2002 TO INSTITUTE PART I : GENERAL PROVISIONS Section 1 : This law and its application instruments shall govern the downstream gas sector comprising transportation, distribution,
L A W ON AMENDMENTS TO THE LAW ON PENSION AND DISABILITY INSURANCE. Article 1
L A W ON AMENDMENTS TO THE LAW ON PENSION AND DISABILITY INSURANCE Article 1 In the Law on Pension and Disability Insurance (RS Official Gazette, nos. 34/03, 64/04 and 84/04), in Article 9, the words:
DECISION PROMULGATING THE ACT ON AMENDMENTS TO THE ACT ON PENSION INSURANCE COMPANIES AND PAYMENT OF PENSIONS BASED ON INDIVIDUAL CAPITALISED SAVINGS
Pursuant to Article 89 of the Constitution of the Republic of Croatia, I hereby issue the DECISION PROMULGATING THE ACT ON AMENDMENTS TO THE ACT ON PENSION INSURANCE COMPANIES AND PAYMENT OF PENSIONS BASED
Directive 2009/72/EC of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC
Directive 2009/72/EC of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC Incorporated and adapted by Ministerial Council Decision 2011/02/MC-EnC
CROATIAN PARLIAMENT Pursuant to Article 88 of the Constitution of the Republic of Croatia, I hereby pass the
CROATIAN PARLIAMENT Pursuant to Article 88 of the Constitution of the Republic of Croatia, I hereby pass the DECISION PROMULGATING THE ACT ON THE SECURITY INTELLIGENCE SYSTEM OF THE REPUBLIC OF CROATIA
I. BASIC PROVISIONS. Subject of regulation
LAW ON ENVIRONMENTAL IMPACT ASSESSMENT Published in the Official Gazette of the Republic of Serbia, No. 135/2004 ( Službeni glasnik Republike Srbije, br. 135/04) I. BASIC PROVISIONS Subject of regulation
KINGDOM OF SAUDI ARABIA. Capital Market Authority CREDIT RATING AGENCIES REGULATIONS
KINGDOM OF SAUDI ARABIA Capital Market Authority CREDIT RATING AGENCIES REGULATIONS English Translation of the Official Arabic Text Issued by the Board of the Capital Market Authority Pursuant to its Resolution
TMF Group Croatia Amendments of the General Tax Act are now in force
TMF Group Croatia Amendments of the General Tax Act are now in force The General Tax Act amendments came into effect on 17 March 2015. Please find below the most important changes: The definition of a
The Hearing Aid Sales and Service Act
1 HEARING AID SALES AND SERVICE c. H-2.01 The Hearing Aid Sales and Service Act being Chapter H-2.01 of The Statutes of Saskatchewan, 2001 (effective March 10, 2006) as amended by the Statutes of Saskatchewan,
Meşrutiyet Cad. No. 98 D. 10 Beyoğlu, Istanbul / Turkey Tel: +90 212 251 15 00 Fax: +90 212 251 15 01 A REGULATORY UPDATE. New Electricity Market Law
Meşrutiyet Cad. No. 98 D. 10 Beyoğlu, Istanbul / Turkey Tel: +90 212 251 15 00 Fax: +90 212 251 15 01 http://boden-law.com A REGULATORY UPDATE New Electricity Market Law ELECTRICITY MARKET LAW PASSED BY
The Mortgage Brokerages and Mortgage Administrators Act
MORTGAGE BROKERAGES AND 1 The Mortgage Brokerages and Mortgage Administrators Act being Chapter M-20.1* of The Statutes of Saskatchewan, 2007 (effective October 1, 2010), as amended by the Statutes of
THE CROATIAN PARLIAMENT DECISION PROMULGATING THE ACT ON INVESTMENT FUNDS WITH A PUBLIC OFFERING
THE CROATIAN PARLIAMENT Pursuant to Article 89 of the Constitution of the Republic of Croatia, I hereby pass the DECISION PROMULGATING THE ACT ON INVESTMENT FUNDS WITH A PUBLIC OFFERING I hereby promulgate
CONSULTATION PAPER NO 2. 2004
CONSULTATION PAPER NO 2. 2004 REGULATION OF GENERAL INSURANCE MEDIATION BUSINESS This consultation paper explains the need for the Island to regulate general insurance mediation business and examines the
Measures on Administration of Health Insurance
Measures on Administration of Health Insurance 健 康 保 险 管 理 办 法 No.8 [2006] Reviewed and adopted at the Chairmen Meeting of the China Insurance Regulatory Commission on June 12, 2006, Measures on Administration
LAW ON THE PROTECTOR OF HUMAN RIGHTS AND FREEDOMS
LAW ON THE PROTECTOR OF HUMAN RIGHTS AND FREEDOMS Podgorica, July 2003 LAW ON THE PROTECTOR OF HUMAN RIGHTS AND FREEDOMS I BASIC PROVISIONS Article 1 Establishing the Protector of Human Rights and Freedoms
REPUBLIC OF SOUTH AFRICA CREDIT RATING SERVICES BILL. Draft for public comment As approved by Cabinet on 26 July 2011
REPUBLIC OF SOUTH AFRICA CREDIT RATING SERVICES BILL Draft for public comment As approved by Cabinet on 26 July 2011 -------------------------------- (As introduced in the National Assembly (proposed section
THE CROATIAN PARLIAMENT. Pursuant to Article 89 of the Constitution of the Republic of Croatia, I hereby issue the DECISION
THE CROATIAN PARLIAMENT 1456 Pursuant to Article 89 of the Constitution of the Republic of Croatia, I hereby issue the DECISION PROMULGATING THE ACT ON SETTLEMENT FINALITY IN PAYMENT AND FINANCIAL INSTRUMENTS
DEPARTMENT OF TRANSPORT
DEPARTMENT OF TRANSPORT No. R.. Date ROAD ACCIDENT FUND ACT, 1996 ROAD ACCIDENT FUND REGULATIONS, 2008 The Minister of Transport has, under section 26 of the Road Accident Fund Act, 1996 (Act No. 56 of
INTERNATIONAL COLLECTIVE INVESTMENT SCHEMES LAW
REPUBLIC OF CYPRUS INTERNATIONAL COLLECTIVE INVESTMENT SCHEMES LAW (No 47(I) of 1999) English translation prepared by The Central Bank of Cyprus ARRANGEMENT OF SECTIONS PART I PRELIMINARY AND GENERAL Section
Foreign Exchange Act, 2006 Act 723
Foreign Exchange Act, 2006 Act 723 Section ARRANGEMENT OF SECTIONS Authority of Bank of Ghana and licensing 1. Authority of Bank of Ghana 2. Responsibility of Bank of Ghana 3. Requirement of licence 4.
Insurance Authority Board of Directors Resolution No. 15 of 2013. Concerning Insurance Brokerage Regulations
UNITED ARAB EMIRATES INSURANCE AUTHORITY CHAIRMAN Insurance Authority Board of Directors Resolution No. 15 of 2013 Concerning Insurance Brokerage Regulations The Chairman of the Insurance Authority, Having