Commissioning of 87,000-kW Kaplan Turbine and Generator for Otori Power Station



Similar documents
Performance Improvement of Pump-turbine for Large Capacity Pumped Storage Power Plant in USA

MICRO HYDRO POWER GENERATING EQUIPMENT

525-MVA Generator-motor and Thyristor Starter Put into Service at the Tokyo Electric Power Co., Inc. s Kannagawa Hydroelectric Power Station

Mini & Micro Hydro Power Generation. EBARA Hatakeyama Memorial Fund Tokyo, Japan

Application of a Large Hybrid Turbocharger for Marine Electric-power Generation

HYDROPOWER SYSTEMS BY APPOINTMENT TO H.M. THE QUEEN WATER TURBINE ENGINEERS, GILBERT GILKES & GORDON LTD, KENDAL

HYDROMATRIX Jebel Aulia - Sudan

Oil Injection Rotary Screw Compressors Contributing to Environmental Protection and Energy Conservation

Power Recovery Turbines

What are the Benefits?

Generators TEM. for small hydroelectric power stations. Electric Machines

TYPE APPROVAL CERTIFICATION SCHEME MASS PRODUCED DIESEL ENGINES

1.3 Turbochargers are categorised in three groups depending on served power by cylinder groups with:

SYNCHRONOUS MACHINES

EC medium pressure axial fans. The effi cient system solution.

Pump Specifications 2448LSG, 2448LSGX Series Omnivore 2HP Simplex Grinder Packages

Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes

Design and manufacturing of Crossflow, Pelton, Kaplan and Francis turbines

Characteristics of Centrifugal Blower and Its Effective Use in High Static Pressure Area

CDX. EBARA PUMPS EUROPE S.p.A. CENTRIFUGAL PUMPS. Page - CONTENTS 100

Development of Power Supply System with Hybrid Turbocharger for Marine Application

KEYWORDS Micro hydro turbine, Turbine testing, Cross flow turbine

Ergo-Pro Single Line Solar Station Installation and Operating Instructions

Development Of High Efficiency Brushless DC Motor With New Manufacturing Method Of Stator For Compressors

Rules for Classification and Construction Additional Rules and Guidelines

DIRECT CURRENT GENERATORS

Pico Power: A Boon for Rural Electrification

SUNON SPECIFICATION FOR APPROVAL DESCRIPTION : DC BRUSHLESS FAN. DIMENSIONS : 60X60X15 mm M O D E L : KD0506PHS2

DESIGN OF SMALL HYDRO ELECTRIC PROJECT USING TAILRACE EXTENSION SCHEME

Motors and Inverters for Environmentally Friendly Industrial Equipment

Design and Test Operation Performance of 1,500 C Class Gas Turbine Combined-Cycle Power Plant:

The original OSSBERGER Crossflow Turbine

Pump Specifications 405 Series Commercial Drain Pump (High-Temp) 2 Solids handling

Vehicle Design Summit Electric Hub Motor (V2) Eric Conner Harvey Tang Matthew Peddie

Manual piston sampler...m 11

AC Electric Motors best practice

SUNON SPECIFICATION FOR APPROVAL

Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling

Radial piston pumps type R and RG

Micro-Hydro. Module Introduction. Tokyo Electric Power Co. (TEPCO)

FIXED DISPLACEMENT HYDRAULIC VANE PUMPS BQ SERIES

MEMBRANE VACUUM MINI PUMPS

WIND TURBINE TECHNOLOGY

Turbo generators Best quality for thermal power plants

Unit 24: Applications of Pneumatics and Hydraulics

Wet Stator Units for Oil and Gas Upgrade and support services

Availability Assessment of Generating Units of Balimela Hydro Electric Power Station (510 MW) A Markovian Approach

Performance of Gangrel Hydroelectric Power Plant A Case Study

Japan s Largest Photovoltaic Power Plant

Single-Phase AC Synchronous Generator

Application Example: Quality Control. Turbines: 3D Measurement of Water Turbines

Development of Tandem-Compound 1,000-MW Steam Turbine and Generator

Permanent Magnetic Generator Construction Manual

HORIZONTAL PUMPING SYSTEM

VERTICAL TURBINE AND PROPELLER PUMPS

Unit 24: Applications of Pneumatics and Hydraulics

SYNCHRONOUS MACHINE TESTING WITH MOTOR CIRCUIT ANALYSIS INSTRUMENTATION

Small-Micro Hydro Facilitation & Innovative Technologies in Japan

Raising the waters. Lift irrigation is getting a boost from ABB s synchronous motors

Energy Savings through Electric-assist Turbocharger for Marine Diesel Engines

ELECTROPUTERE ROTATING ELECTRICAL MACHINES DIVISION

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P Turbidity Monitoring Plan

PI734D - Technical Data Sheet

PI734B - Technical Data Sheet

NO-BREAK KS 7e. Concentrated Energy kva (50Hz) 3000 kva (60Hz) DIESEL ROTARY UNINTERRUPTIBLE POWER SUPPLY SYSTEM

Development of 5-MW Offshore Wind Turbine and 2-MW Floating Offshore Wind Turbine Technology

FIXED DISPLACEMENT HYDRAULIC VANE PUMPS BQ SERIES

FIXED DISPLACEMENT HYDRAULIC VANE PUMPS BQ SERIES

Vertical Pumps for the Oil & Gas Industry

Design and Analysis of Switched Reluctance Motors

Your Service Partner Avonmouth and Bristol Service Centres

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2

Fixed displacement vane pumps

Project Layout & Design Features of the Project

Completion of High-efficiency Coal-fired Power Plant

Design and Modeling of Fluid Power Systems ME 597/ABE 591 Lecture 5

Shaft grounding. Carbon brushes for shaft grounding are used in turbo-generators, in distinct AC- and DC motors and as a special application in Ships.

Correct use of air tool technology.

Principles of Adjustable Frequency Drives

Approval Standard for Water Motor Gong

Bearing Stiffness Determination through Vibration Analysis of Shaft Line of Bieudron Hydro Powerplant

Lab 8: DC generators: shunt, series, and compounded.

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

In-Wheel Motor System

WIND POWER GENERATION TECHNOLOGY Mrs. N.V. Vader Mrs. V.A. Joshi

Roller Chain Coupling

Wolf Creek Hydropower Rehabilitation Analysis Report

DET SIGMA PUMPY HRANICE PUMP TURBINES

CHAPTER 4 DESIGN OF INTEGRAL SLOT AND FRACTIONAL SLOT BRUSHLESS DC MOTOR

Measurement Types in Machinery Monitoring

UNIT 3 AUTOMOBILE ELECTRICAL SYSTEMS

- CONSTRUCTIONS 300 SECTIONAL VIEW 300 MECHANICAL SEAL DIMENSIONS AND WEIGHT 400 PUMP 400 PACKING 401

Annex-A TECHNICAL SPECIFICATION

CENTRIFUGAL PUMP OVERVIEW Presented by Matt Prosoli Of Pumps Plus Inc.

Technical Specification. Generating Set with Waukesha engine burning natural gas

Verification of Short Circuit Test Results of Salient Poles Synchronous Generator

AXIAL TURBINE FOR DOUBLE EFFECT TIDAL POWER PLANTS: A CFD ANALYSIS.

Pump Vibration Analysis

Installation and maintenance instructions. Danfoss Vent

S Y N C H R O N O U S G E N E R A T O R S

Transcription:

Commissioning of 87,000-kW Kaplan Turbine and Generator for Otori Power Station 126 Commissioning of 87,000-kW Kaplan Turbine and Generator for Otori Power Station Asami Sato Keiichi Goto OVERVIEW: The surrounding environment needs to be considered in the planning, design and construction of hydroelectric power stations, from the perspective of environmental conservation. of the Otori Power Station, which was installed by J-POWER (Electric Power Development Co., Ltd.) began operating in June 2003. The power station is located on the existing Otori Dam, which is in far upstream on the Agano River. The dam is used as an upper reservoir, and an additional 87,000-kW Kaplan turbine-generator was installed next to the existing 95,000-kW Kaplan turbine-generator. The Otori Power Station is located in the Echigo Sanzan Tadami Quasi-National Park, which is surrounded by a rich natural environment. As the construction area is close to an area that is a breeding ground for rare raptorial birds, construction was carried out to mitigate its impact on the environment as follows: (1) Locating the main structures underground to minimize changes to the above-ground environment; (2) Stopping above-ground construction work during the nesting period for local predatory birds; (3) Effectively utilizing waste products emitted from the construction work. The attention paid to this project indicates new directions in the construction of future hydroelectric power stations. INTRODUCTION ENVIRONMENTAL conservation has recently become a topic of interest throughout the world, and hydroelectric-power generation attracted more attention as a result. Hydroelectric-power generation offers excellent performance when assessed in terms of carbon dioxide emissions because it is natural energy to create electricity. Power stations using reservoirs are able to respond promptly to changes in demand for power during the day and at night, and are used effectively as a peak power source. At the same time, the construction of hydroelectric- Tadami River Outlet for Power Station Pipeline for Otori Regulating Pond Tailrace for Unit No. 1 Power Station Intake for Otori Dam Fig. 1 Bird s Eye View of Underground Power Station (a), Kaplan Turbine Runner Being Installed (b), and Overall View of Generator (c). (a) (b) (c)

Hitachi Review Vol. 53 (2004), No. 3 127 power stations requires enormous building work, and poses significant challenges to mitigating the environmental impact. Many environmental factors had to be considered during the construction and planning of of the Otori Power Station, because it is located in the Echigo Sanzan Tadami Quasi-National Park, and is surrounded by a rich natural environment. The construction area was also very close to an area that is a breeding ground for rare raptorial birds. For this reason, the existing dam and tailrace were utilized and much of the main structure was installed underground to minimize changes to the above-ground environment. As a result, we achieved increased power output and reduced the impact on the environment. The following explains the main features of Unit No. 2 of the Otori Power Station owned by J-POWER (see Fig. 1). OUTLINE OF OTORI POWER STATION of the Otori Power Station is equipped with a large Kaplan hydro-turbine, whose output is only surpassed by the existing Unit No. 1 whose output is the largest in Japan. Through a process of international bidding, Hitachi, Ltd. won the tender to supply the hydro turbine-generator being a major manufacturer. As a result, Hitachi s turbine-generators were installed in both No. 1 and No. 2 units. After was constructed, the power output increased from 95,000 kw to a total of 182,000 kw. Fig. 2 is a cross-section of the assembly of a turbine-generator, and Table. 1 lists the specifications for Units No. 1 and No. 2. Construction on began in 1999 followed by a field-operation test in February 2003, concluding with formal operations in June 2003. KAPLAN TURBINE Table 2 lists the main specifications for the Kaplan turbine for the Otori Power Station. Runner The Kaplan turbine can operate at its most efficient point by changing the angle of the runner vanes in line with the head and output, and is superior in terms of effective utilization of energy. First, we developed performance by utilizing CFD (computational fluid dynamics), and drafted manufacturing plans of a model runner with 3D-CAD (computer-aided design). We then manufactured the model parts, checked the dimensions and verified Fig. 2 Cross-section of Kaplan Turbine-Generator for Unit No. 2. The turbine, which has a 5,100-mm diameter runner with movable blades, is a vertical axis spiral-type Kaplan turbine. The generator has an umbrella structure, without an upper guide bearing. TABLE 1. Specifications for Otori Power Station The main specifications for Units No. 1 and No. 2 are listed. Specifications Unit No. 1 Max. output Max. discharge Normal net head Commissioned year 95,000 kw 220 m 3 /s 50.8 m 1964 87,000 kw 207 m 3 /s 48.1 m 2003 TABLE 2. Specifications of Kaplan Turbine at Otori Power Station Hydro-turbine specifications for Units No. 1 and No. 2 are listed. No.1 has the largest output in Japan, and No. 2 the second largest. Specifications Unit No. 1 Type Max. net head Max. output Rotation speed Runner diameter VK-1RS 51.0 m 100,000 kw 125 min -1 6,100 mm VK-1RS 48.1 m 89,500 kw 167 min -1 5,100 mm

Commissioning of 87,000-kW Kaplan Turbine and Generator for Otori Power Station 128 performance through model tests. The design, manufacture, and inspection of the prototype runner were consolidated based on the 3D-CAD data, which made quality control during each process easier, and also increased the quality of the manufactured products. The outer diameter of the runner is 5,100 mm and it has six vanes. Fig. 3 shows the runner during the final test in shop assembly. From the perspective of environmental conservation, we adopted a hub, which kept pure water inside so that oil would not leak into the river. Casing and Stay-ring The casing was spiralled and large scale, with a diameter of 6,800 mm at the inlet, and a maximum outer diameter of approximately 20 m. Due to restrictions in transportation for the carry-in route to the power station, the casing was divided into several parts and welded together on site. Fig. 4 shows the process of assembly in the shop. Despite the restricted working conditions on site, we installed this large-scale casing in only three months. We adopted ultrasonic automatic-recording as a nondestructive way to test the casing weld lines. Fig. 5 shows the process for installing the stay-ring on site. To improve turbine efficiency, the stay-vanes were located at unequal intervals. The flow guides were attached to the inlets of the main plates of the stayring to reduce loss in water flow. Fig. 3 Final Test to Confirm Assembly of Runner for in Workshop. The runner was assembled into a single unit and a static balance test was conducted. Main Unit of Kaplan Turbine The strength of the main unit was calculated with 3D finite element analyses. As a result, we adopted a single thick-plate structure for the head cover. Selflubricated bearings were used in the sliding areas of the wicket gates. Fig. 4 Shop Assembly of Casing for. Large-scale casing the inlet diameter of 6,800 mm, with a maximum outer diameter of approximate 20 m. The casing was divided into several parts and welded together on site. Fig. 5 Site Assembly of Stay-ring for. This shows the casing plates being attached to the stay-ring, which was assembled into a single unit on site. The stay-vanes were placed at unequal intervals.

Hitachi Review Vol. 53 (2004), No. 3 129 Results of Field Tests During commissioning, we observed water pressure pulsations inside the tailrace, which occurred after load rejection. Resonance by stationary waves inside the tailrace was considered to be the cause. To prevent rotating parts from vibrating due to water pressure pulsations, we changed the shutdown sequence. As a result, we have had no problems with operation to date. GENERATOR Table 3 lists the main specifications of the generator. The rotor being hung in the power station is shown in Fig. 6. The design and manufacturing processes for the generator are described below. Shaft Construction and Bearings We used Hitachi s pivot spring thrust bearings as they have had a great deal of application records. We adopted a semi-umbrella construction with guide bearings in the upper rotor shaft for Unit No. 1. However, for, we built a rotating silicon rectifier into the spider part of the rotor center, and shortened the length of the rotor. This umbrella construction, without upper guide bearings, allowed capacity of the upper oil tank and number of related pipes to be reduced. We also adopted a double oil seal in the clearance between the oil dam for the thrust bearing oil reservoir and the rotating parts, and prevented oil leaks from occurring from the shaft side. Through the use of an umbrella structure, we simplified the generator and the oil system, which made this equipment much more environmentallyfriendly. AC-exciter and Rotating Silicon Rectifier To make maintenance-free, we adopted brushless excitation using an AC (alternating current)- exciter and a rotating silicon rectifier. Of all of Hitachi s generators with brushless excitation, the No. 2 generator has the second largest capacity surpassed only by the No.1, which has already been upgraded to this method. Stator Based on transportation restrictions, the stator for the generator was shipped in six parts, and delivered to the power station after the performance test had been conducted at our workshop. After that, the generator was assembled. TABLE 3. Specifications for Generator for Otori Power Station The main specifications for Units No. 1 and No. 2 are listed. Specifications Unit No. 1 Type Rated capacity Rotation speed Rated voltage Rated current Power factor Number of poles Excitation method DC: direct current VEFK 3 W-RD 100,000 kva 125 min -1 13,200 V 4,380 A 0.9 48 DC excitation Brushless excitation VTFKW-RD 97,000 kva 167 min -1 11,000 V 5,091 A Brushless excitation Fig. 6 Site Assembly of Rotor for. This shows the process for hanging the rotor of the generator. The rotating silicon rectifier is contained within the rotor. The stator coil using F-class pre-impregnated insulation, offered durability as well as reducing the quantity of varnish used during manufacture. The slots consisted of top-ripple springs and side-ripple springs to ensure a long life for the coil support inside the slots. CONCLUSIONS This report described the main features of Otori Power Station s owned by J-POWER (Electric Power Development Co., Ltd.). Despite various restrictions related to reducing the environmental impact, the development and construction of this project was completed and Unit No. 2 successfully began operations in June 2003. 0.9 36

Commissioning of 87,000-kW Kaplan Turbine and Generator for Otori Power Station 130 In the recent situation where global warming is posing a significant challenge, Hitachi, Ltd. intends to develop and design more efficient installations and also sustainable turbine-generators for hydroelectric power. ACKNOWLEDGMENTS We would like to offer our sincere thanks to the personnel of J-POWER for their tremendous support and cooperation during the planning, design, manufacture, construction and operation of the Otori Power Station. ABOUT THE AUTHORS Asami Sato Joined Hitachi, Ltd. in 1972, and now works at the Hydro Turbine Department, the Power Systems. He is currently engaged in the design of turbine equipment for hydroelectric power stations. Mr. Sato can be reached by e-mail at asami_satou@pis.hitachi.co.jp. Keiichi Goto Joined Hitachi, Ltd. in 2000, and now works at the Generator QA & Inspection Section, the Electric Power System & Equipment QA Department, the Power Systems. He is currently engaged in the testing and inspecting of generators and motors. Mr. Goto can be reached by e-mail at keiichi-a_gotou@pis.hitachi.co.jp.