DEVELOPING THE PROJECT PORTFOLIO MANAGEMENT PROCESS AND MATURITY STEP BY STEP



Similar documents
Maturity Levels of Project Portfolio Management (PPM) and how to set your Own Target Level 1

Project Management Office Charter

White Paper. Making the case for PPM

The Standard for Portfolio Management. Paul E. Shaltry, PMP Deputy PM PPMS ( ) BNS02

Sound Transit Internal Audit Report - No

project portfolio management

Driving PPM Adoption Through Effective Change Management

Project, Portfolio Management (PPM) for the Enterprise Whose System is it Anyway?

Project Management Office (PMO) Added value instead of administration

Frank P.Saladis PMP, PMI Fellow

PMP 2013 Exam Prep. Course Overview

SAP PPM Capacity Planning and the Organization Maturity Model #1567. John Hoover VER 1.1

Introduction to OpenPPM

Configuring Microsoft Project Server

MGMT 4135 Project Management. Chapter-16. Project Oversight

Introduction to project management and concepts

Process Governance: Definitions and Framework, Part 1

ISO 21500: Did we need it? A Consultant's Point of View after a first experience. Session EM13TLD04

Key Leadership Behaviors Necessary to Advance in Project Management

INCREASING THE STRATEGIC VALUE OF PPM THE KEY TO BUSINESS-DRIVEN PPM SUCCESS BUSINESS-DRIVEN WHITE PAPER SERIES

project management community? Are you getting the best from your Project Management Learning Consultancy At a glance

15 Most Typically Used Interview Questions and Answers

Agile Programme Management

Enterprise Release Management

10 Reasons Why Project Managers Need Project Portfolio Management (PPM)

TD Bank N.A. s Enterprise-Wide PMO Monitors Projects and Maintains Focus on Strategic Goals

Project Management Excellence Enabling Quality In Project Execution

Partner selection: A source of alliance success. Danielle Twardy

How To Adopt Rup In Your Project

Creating a project management office (PMO)

What Every Project Manager Should Know Trends in Project Governance

WHITE PAPER CHANGE MANAGEMENT

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International

PM Competency Mapping Dhananjay Gokhale, PMP Vice-President, Project Excellence Learning & Consulting Center Compulink Systems Limited.

Leading and Managing Innovation

STANDARD FOR AUDITING PROJECTS DEFINITIONS AND RULES

Project Governance. Version: June 3, 2010 By: Dr Ralf Müller PM Concepts AB

IPMA Advanced Courses 2015

Integrating Project Schedule & Resources Whitepaper By Ted Barth, Managing Partner BNW Manufacturing Associates LLC

Project Management. Project management basic concepts

Getting started as a self investor. Your guide to self investing

Portfolio Management 101:

Software Process Improvement Software Business. Casper Lassenius

Research Report. The Impact of Implementing a Project Management Office Report on the Results of the On-Line Survey

A Comparison of Project, Program & Portfolio Management Responsibilities and who should be responsible for what. By R. Max Wideman

Project Management Framework

PM Services. Portfolio Strategy, Design and Build

A PM SOLUTIONS RESEARCH REPORT. The State of Project Portfolio Management (PPM) Media Partner

Creating a Project Management Office (PMO)

Building an Effective Business Architecture & Metrics Capability

Leveraging Sarbanes-Oxley (SOX) to Build Better Practices

PORTFOLIO & PROJECT MANAGEMENT

Name Chapter 1: Introduction to Project Management Description Instructions

Agile project portfolio manageme nt

Principles and standards in Independent Advocacy organisations and groups

Small Start-up Business Project Management

Portfolio Management Professional (PfMP) SM Credential FAQs

Ten Critical Steps. for Successful Project Portfolio Management. RG Perspective

Setting up and operationalisation of Enterprise PMOs

RISK BASED INTERNAL AUDIT

Project Management. On-Site Training and Facilitation Services. For more information, visit

Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition

Reading Sample. Integration Scenarios with Other Project Management Tools. Contents. Index. The Author. Project Management with SAP Project System

Report on the Survey The Reality on Project Management Offices

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland

Topic Duration Why Enterprise Change Heat Maps?? History / Background Business Case Discussion Mitigating the Perfect Storm: How to Implement??

What is Human Resource Management?

CA PA for CA Clarity PPM 14.2: Project and Investment Management 200

Finding The PPM Sweet Spot

The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA

The Viking Approach to Project Management

Delivering Corporate Social Responsibility through Project Portfolio Management

Incorporating Risk Assessment into Project Forecasting

Creating High Performance Project Teams

HOW TO GET THE MOST OUT OF YOUR ACCOUNTANT

2007 & 2008 Dennis L. Bolles and Darrel G. Hubbard 1

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

ROI Building The Business Case For Professional Services Automation

Integrating Scrum with the Process Framework at Yahoo! Europe

15 Most Typically Used Interview Questions and Answers

Project Time Management

WBS Templates for IT/Software Projects, AIPM IRC Bibliography, 2 nd February, 2005

Scrum in a Large Project Theory and Practice

When being a good lawyer is not enough: Understanding how In-house lawyers really create value

Transcription:

1 (7) DEVELOPING THE PROJECT PORTFOLIO MANAGEMENT PROCESS AND MATURITY STEP BY STEP IPMA World Congress 2009-06-11 Seminar 1: Strategy Creation and Project Portfolios Tuesday, June 16, 2009, 10:30-11.00 a.m. Conference room Mr. Matti Haukka Senior Project Management consultant Project Institute Finland Ltd matti.haukka@projekti-instituutti.fi www.projekti-instituutti.fi/en 1 ABSTRACT This paper describes five PPM maturity levels and the general prerequisites each of these levels. The main point is to describe the different PM roles and their significance when it comes to achieving each of these maturity levels. The paper emphasizes specially the roles of project owner and Project Management Office. Paper gives some ideas how to develop these roles and how to manage the change towards a Project Oriented Organisation. 2 RECOGNIZE THE VALUE OF YOUR PROJECT PORTFOLIO The value of projects to the company should be estimated and management should really be aware of it. This is important to awake the management and start to develop any new models. In a company that is delivering projects to its external customers (delivery projects) the value is well considered. But in the case of internal project portfolio, it usually isn t. First the value can be measured by estimating the significance of strategic change, need of developing new products and processes etc. Practically the value of projects can be measured by dividing all working processes to project work and non-project work and estimating the amount of resource allocation to both processes. Figure 1. shows what a typical situation is. In most companies the amount of resources allocated to project work but not managed in a proper way is surprisingly big and this should be better noticed by management. Depending on the value of projects, the management should set the development objectives and estimate the amount of development effort. 1

2 (7) Tasks and endeavors that should be managed using PM and PPM processes: No harmonized models: Projects Small unique assignments recurring processes Projects Small and medium sized projects Small unique assignments normaalit recurring processes prosessit Problem area! A B Projects C Small unique assignments recurring normaalit processes prosessit The blocks describe the distribution of worktime of personnel in a company that has many projects Project Institue Finland ltd. Figure 1: Typical situation in the middle. Management attention is focused into the big projects only and a huge amount of medium and small size projects are leaving without. Solution on the right is based on the use of project complexity classification, which is setting a right level of management effort when it comes to a single project. However PPM system should consider all projects. 3 DEVELOPING THE PPM MODEL AND METHODOLOGIES A method of keeping a database of all on-going projects creates the foundation for PPM. This alone brings a challenge. Many line managers would have to start a two-week investigation when being asked which projects are going on in their organisation. The first level of portfolio management maturity is reached when this aspect is in order. Many would possibly have to start a new investigation when being asked: What is the status of these projects? or Is our portfolio in balance when it comes to strategic objectives and risks? The second level of maturity is reached when the reporting is working on regular basis. There is still a long way to go to the stage where projects are systematically evaluated, visible decisions are taken in gates, attention is paid to resources and the strategically most important projects are carried out without delay. When the reporting also covers forecasts of projects real benefits and their evaluation continues till the projects are finished, only then can we start talking about advanced PPM (See Figure 2). 2

3 (7) The basic prerequisites to achieve each of these levels are the following (without emphasizing roles yet): Level 1 Decision point model (stage gate model) Clear definition of a project Level 2 Harmonized Project Model and complexity classification of projects Quality of status reporting should be good enough Level 3 High quality planning procedures and competence. PM and PPM software tools Hour reporting Level 4 Owner s responsibility on achieving the business benefits and total success of the project should be emphasized PPM Board and strategic level PMO should be established Level 5 Measuring the final business benefits of projects Reward systems should be based on final business benefits of projects, too Five steps and PPM maturity model Project selections and prioritization is done transparently and through systematic procedures Resource needs are planned for all projects (eg. Procedures to solve resource conflicts) Awareness of the status and balance of all projects (Reporting System) Awareness of Ongoing Projects (Project Database) The business benefits of all projects are evalueted afterwards and this causes continuous development Effectiviness of project business Faster implementation of strategies Figure 2: Maturity levels and steps to develop PPM based on ABC Project Model. Knowing the development steps and key elements of a PPM system helps management to set objectives and time schedule for development work 3

4 (7) 4 THE MOST IMPORTANT PM ROLES LEVEL BY LEVEL Level 1 Project Owner Project owner is the most critical PM role when an organization starts to develop its PM culture. Our experiences with our customers has shown, that if nothing else is happening but the project owners has been clearly recognized and these owners understand their role and responsibilities, it is already causing a clear improvement when it comes to effectiveness of project work and business results. If the owners exist, the basic information of all projects is available and there is always somebody who is responsible and aware about the go/no go decisions of any project. This only can make the stage-gate model to function. To get the owner role to work, effective training is needed. Training should emphasize mainly changing attitudes and giving a basic knowledge of PM principles. Level 2 Project Management Office (PMO) In order to get reliable information (see an example in figure 3) about the project portfolio a harmonized PM Model is needed. Developing and updating this model is one of the most important responsibilities of a PMO. Another important responsibility is of course to administrate the portfolio. If nobody is doing this it is impossible to give current and reliable information to management. Many organizations have withdrawn or delayed to establish a PMO. One reason has been the cost of extra resources. In this case the business case of PMO should be pointed out better. In most cases the reason has just been the lack of competent resources. PMO manager and personnel should have a real good competence of PM. This means, that PMO personnel should participate a PM Master (=advanced) level training course. Of course it is important that they have experience in project work, too. Planned Strategic report autonomous growth, 10% building travel brand, 20% development.com, 20% low cost, high productivity, 20% compliance, 5% business continuity, 15% HRM, employee development, 10% Actual autonomous growth, 12% building travel brand, 7% development.com, 38% low cost, high productivity, 14% compliance, 17% business continuity, 7% HRM, employee development, 5% Figure 3: The important role of PMO is to provide information about the planned and actual portfolio to the management 4

5 (7) Level 3 Project Manager It may be a surprise for most of the readers that project manager role doesn t appear before this level. Of course Project Manager is perhaps the most critical role from the single project point of view, but when it comes to PPM the order is not the same. Achieving the level 3 means, that the allocation of resources is continuously known. This cannot happen if the organization doesn t have enough competent project managers with good skills of making WBS, time scheduling, work amount estimations, rolling wave planning or using PM software etc. However the use of project complexity classification helps here. Small non complex projects are not requiring the same level of planning as the complex one. But still the predefined procedures are needed and all Project Managers should work according to these procedures. Level 4 PPM Board You need the role of PPM Board already on the lower levels. However achieving the level 4 requires much more work effort by management. In case that PPM board is the same as Management Group, PPM issues should be clearly separated in the agenda or these should be handled in separate meetings. The most important task of the PPM board is to select the right projects and make prioritization. To do this, they must be aware of available resources (level 3 needed!). The critical competence of PPM Board members is just a normal business competence. Of course they should know well the PM and PPM model of the company and definitions and terminology of PM. Actually the training should again emphasize changing attitudes. We recommend that during the deployment of new PM and PPM model in the organization the PPM Board Members should participate the same trainings as other personnel. Level 5 New organization model No special role is named here anymore. In the future the best effectiveness will be achieved if all these roles have been merged as a part of the whole organizational structure. In this case we can talk about real Project Oriented Company. Figure 4 shows how the PM Culture is developing towards a Project Oriented Company. Developing PM Culture PPM Program/project oriented organisation Program Management PBO PBO PMO Corporate Portfolio Managing single Programs PMO Single PM Source: The Portfolio Management Standard, PMI, 2006 and Valense Ltd. & Michel Thiery, 2007 (Adjusted) Figure 4: Development of PM Culture 5

6 (7) 5 CONCLUSIONS The main prerequisites for each maturity level of PPM are the following. Companies should take care of these necessary actions before dreaming of any remarkable improvements to PPM itself: Step1: Implement a harmonized project management model with necessary and transparent decision points (gates, toll gates). At the same time make sure that each project has an owner (sponsor) who is carrying the ultimate responsibility for the project success. Step2: Establish a Project Management Office (PMO) with necessary resources and ensure that each project is managed and reported according to the same main framework. Step 3: Ensure that each project is planned and their resource plans are updated and of proper quality. Develop the competence of project managers accordingly. Step 4: Organize a Project Portfolio Management Board, which is putting enough management effort on PPM, emphasizing mostly the initial decision points of projects and using systematic and transparent procedures. PMO should be organized as a strategic level unit, too. Step 5: Organize the PMO so, that it has enough resources to support post-project appraisals and to develop both the strategic and PPM processes further to ensure continuous organizational learning. When implementing a PPM system, the question is actually of the need for changes in an organisation s management culture. The time allocated to management should be reconsidered, in middle management in particular. This will not happen unless the evaluation and reward systems in organisations are changed in order to pay attention to the successes in project work as well. The more important strategic change and development are to organisations, the more crucial these issues will become. This requires that a strong project culture is developed at all levels of the organisation. When developing the PM culture, the PPM maturity levels may help the organisation to progress step by step. But before developing PPM, the organisational competence and processes of individual projects should be on a certain level. A generic project model for individual projects should be implemented and clear classification criteria for project types and complexity levels should be defined. 6

7 (7) REFERENCES [1] Gerard Geurtjens and Matti Haukka, IPMA Advanced training course H : Managing Corporate Project Portfolios, Copenhagen March 2006, 2007 and 2008 and Shanghai 18-20 October 2007 [2] Matti Haukka, Towards visible and systematic Project Portfolio Management, IPMA World Congress on Project Management, Budapest 19-20 June 2004 [3] Matti Haukka, Harmonizing the Project Management practices across the boarders experiences with the merged companies in Nordic Countries, IPMA World Congress on Project Management, Budapest 19-20 June 2004. [4] Matti Haukka, Towards transparent project portfolio management, NORDNET Symposium, Copenhagen, October 2005. [5] Matti Haukka, The prerequisites of functioning Project Portfolio Management, IPMA World Congress, Shanghai, October 2006 [6] Matti Haukka, The prerequisites and steps to develop corporate Project Portfolio Management, IPMA World Congress, Krakow, June 2007 [7] Michel Thiery, Program Management Seminar, PMI Chapter Finland 2007 [8] PMI, A Guide to the Project Management Body of Knowledge, Third Edition [9] PMI, The Standard for Project Portfolio Management [10] Project Institute Finland ltd, ABC Project Model ver. 2.0 7